    POST-EARTHQUAKE REPAIR AND

    IMPROVEMENTS, SAN VICENTE, CHILEJohn Bardi, P.E., M. ASCE

  • 8/13/2019 PORTS13 SanVicente

    2/21

    USGS Shake Map, M 8.8 Offshore Maule

    San Vicente

    Epicenter

    Very Strong to Severe

    Shaking in San Vicente Liquefaction and Lateral

    Spreading at Terminal

    Wharf Deformation upto 600 mm

  • 8/13/2019 PORTS13 SanVicente

    3/21

  • 8/13/2019 PORTS13 SanVicente

    4/21

    Liquefaction and Lateral Spreading

  • 8/13/2019 PORTS13 SanVicente

    5/21

    Wharf DeformationBerth 1

  • 8/13/2019 PORTS13 SanVicente

    6/21

    Pile DeformationBerth 1-2 Transition

    Pile Inclination

  • 8/13/2019 PORTS13 SanVicente

    7/21

    Berth 2 & 3 Deformation

  • 8/13/2019 PORTS13 SanVicente

    8/21

    Typical Pile DamageBerths 2 & 3

  • 8/13/2019 PORTS13 SanVicente

    9/21

    Repair and Reconstruction Strategy

    Damage Assessment and Load Rating

    P-Delta Analyses

    Structural Investigation & Local Repairs

    Temporary Operation and Load Restrictions

    Short Term Repairs (Access Bridges)

    Develop ShortTerm Operating Live Load Criteria

    Long Term Repairs

    Ground Improvement Program

    New Lateral-Force Resisting Systems9

  • 8/13/2019 PORTS13 SanVicente

    10/21

    Repair and Reconstruction Strategy

    1

    0

  • 8/13/2019 PORTS13 SanVicente

    11/21

    Existing Berths 2 & 3

    11

  • 8/13/2019 PORTS13 SanVicente

    12/21

    Berth 2/3 Reconstruction Strategy

    Eliminate Fusible Transition Span

    Stabilize Ground Behind Wharf

    Provide Landside Link Structure with New

    Lateral-Force Resisting System

    Provide New Waterside Apron Structure with

    provision for New Container Crane Loading

    Integrate Existing Structure with Link and

    Apron Structures via new structural deck

    overlay12

  • 8/13/2019 PORTS13 SanVicente

    13/21

    Berths 2 & 3 Reconstruction

    21.75 Future Crane Gauge

    13

  • 8/13/2019 PORTS13 SanVicente

    14/21

    0

    1000

    2000

    3000

    4000

    5000

    6000

    0.00 0.20 0.40 0.60 0.80 1.00 1.20

    Force

    (kN)

    Displacement (m)

    Existing

    Retrofitted

    Berths 2 & 3 Typical Pushover Plots

    14

  • 8/13/2019 PORTS13 SanVicente

    15/21

    Existing Berth 1

    15

  • 8/13/2019 PORTS13 SanVicente

    16/21

    Berth 1 Replacement Strategy

    Eliminate Fusible Transition Span

    Stabilize Ground Behind Wharf

    Provide New Structure with Comparable

    Lateral-Force Resisting System

    Match Provision for Container Crane Loading to

    Reconstructed Berths 2/3

    Use Existing Structure as Work Platform

    16

  • 8/13/2019 PORTS13 SanVicente

    17/21

    Berth 1 Inclinometer data

    -1200

    -1000

    -800

    -600

    -400

    -200

    0

    0 50 100 150

    Depth(i

    n)

    Deflection (in)

    Deflection

    Data

    Best Fit

    Deflection Relative

    to Pile Tip-1200

    -1000

    -800

    -600

    -400

    -200

    0

    -200000 0 200000 400000

    Depth(

    in)

    Moment (kip-in)

    Moment

    Data

    Best Fit

    Yielding

    Along Length

    of Pile

  • 8/13/2019 PORTS13 SanVicente

    18/21

    Berth 1 Replacement

    18

    21.75 Future Crane Gauge

  • 8/13/2019 PORTS13 SanVicente

    19/21

    Berth 4 Extension Strategy

    Provide for extension of new craneway

    Deeper draft capability

    Provide a new berth to prior to starting

    construction on Berths 2 & 3

    Provide 5thberth for smaller vessels

    19

  • 8/13/2019 PORTS13 SanVicente

    20/21

    Berth 4 Extension

    20

  • 8/13/2019 PORTS13 SanVicente

    21/21

    Acknowledgements

    Pares & Alvarez, Concepcion, Chile

    Ing. Paola Pineda

    Ing. Marcelo Steffen

    Co-Authors

    J. Paul Smith-Pardo, PhD, PE, MASCE, Seattle Univ.

    Jyotirmoy Sircar, PE, MASCE, BergerABAM

    Geotechnical

    William M. Camp, III, PE, D.GE, S&ME, Inc.

    Aaron D. Goldberg, PE, D.GE21