+ All Categories
Home > Documents > Power System Planning and Investment

Power System Planning and Investment

Date post: 10-Feb-2016
Category:
Upload: eben
View: 38 times
Download: 0 times
Share this document with a friend
Description:
Power System Planning and Investment. Richard Sedano and Richard Cowart NEDRI March 26, 2003. Demand Side Solutions Have Value. But there are barriers Solving Structural Barriers to Demand Response: Involves addressing planning and investment practices - PowerPoint PPT Presentation
Popular Tags:
23
The Regulatory Assistance Project 177 Water St. Gardiner, Maine USA 04345 Tel: 207.582.1135 Fax: 207.582.1176 50 State Street, Suite 3 Montpelier, Vermont USA 05602 Tel: 802.223.8199 Fax: 802.223.8172 Power System Planning and Investment Richard Sedano and Richard Cowart NEDRI March 26, 2003
Transcript
Page 1: Power System Planning and Investment

The Regulatory Assistance Project177 Water St.

Gardiner, Maine USA 04345Tel: 207.582.1135

Fax: 207.582.1176

50 State Street, Suite 3Montpelier, Vermont USA 05602Tel: 802.223.8199Fax: 802.223.8172

Power SystemPlanning and Investment

Richard Sedano and Richard CowartNEDRI

March 26, 2003

Page 2: Power System Planning and Investment

Demand Side Solutions Have Value

But there are barriersSolving Structural Barriers to Demand

Response:Involves addressing planning and investment

practicesAlso removes some barriers affecting energy

efficiency and distributed generation

Page 3: Power System Planning and Investment

Priorities and Realities

Electric Market is RegionalPublic Policy Involved, Just a Matter of

WhenPotential to improve investment decisions

or slow them downResource Parity Assures Least CostPrinciples apply throughout power system

Page 4: Power System Planning and Investment

Objectives

Market oriented decisions with competitive forces at work

Cost causation has meritSocialization granted only after passing a

testCost recover mechanisms comparable for

all resource solutions

Page 5: Power System Planning and Investment

Demand Resources in Grid Planning and Investment

Demand resources have a role in three areas:Regional System PlanningRegional Grid Investment PolicyDistribution Utility Planning

Page 6: Power System Planning and Investment

(A) Symptoms of Regional Electric Market Problems

Lack of timely transmission line proposalsGeneration construction that causes congestionLack of connection between electricity

investment decisions and environmental implications

Lack of consideration of customer resources to solve grid problems

Lack of co-ordination of investment plans by monopoly and competitive companies

Page 7: Power System Planning and Investment

System Planning Recommendations

Regional cooperation by statesContinuing regional planning process

Driven by system needsAll solutions available

Page 8: Power System Planning and Investment

Multi-StateCoordination

Recommendation 1: Increase coordination among the states and between states and the ISO

Efficiency to regulatory decision-makingCertainty to the marketplaceGuide ISO toward more efficient planningAvoid duplication of effortSupport authority, independence of states

How far will States Go?

Page 9: Power System Planning and Investment

Regional Power System Planning Process

Recommendation 2: Conduct a continuing regional power system planning process to identify system needs and alternative strategies to meet them.

Cyclical Transparent System needs treated over time Maximum planning horizon Maintain responsiveness to emergent conditions Improve public confidence

Page 10: Power System Planning and Investment

Regional Power System Planning Process

Formal Role for State Governments if states want it

Focus on areas of interestInvolve more stakeholdersAttract all solutions

Page 11: Power System Planning and Investment

ComprehensiveSolution Set

Recommendation 3: The outcome of a regional power system planning process should be an evaluation on an even-handed basis of a wide range of feasible solutions to emerging problems, including investments in generation, transmission, and demand-side options.

Regardless of the planning process, all reasonable solutions should be considered and evaluated similarly

Candidate solutions come from competitive and regulated entities State regulation would have to support solutions coming from

regulated entities Implementing a solution affects the economics of the others

Page 12: Power System Planning and Investment

System Investment Recommendations

Market oriented investments preferred State authority remains Cost causation is appropriate Socialization is appropriate for some reliability-

oriented investments Efficient Reliability Standard should apply

Resource parityLeast cost standard

Cost recovery comparability

Page 13: Power System Planning and Investment

(B) Grid Investment Policies Recommendation 4: Leave investment and siting decisions in the

hands of market participants and state regulators wherever possible, assigning cost responsibility to those who create the need for system upgrades, and those who benefit from them.

After grid problems and potential solutions are identified in the system planning process, these results should be posted publicly so that market participants can consider what actions they might take within the existing market structure to meet emerging needs. Wherever possible, RSAC should permit market-based and state-based responses to emerge.

Public, regional intervention to promote or pay for grid solutions should be taken only where it is evident that adequate resolution is not forthcoming in the market, or that the investment in question is one that, as a matter of equity, ought to be undertaken by grid managers with cost recovery imposed through tariffs.

Page 14: Power System Planning and Investment

(5) Efficient Reliability Test

Recommendation 5: ISO-New England, NEPOOL, and FERC

should apply an Efficient Reliability test, based on principles of least-cost analysis and resource parity, when considering proposals to socialize the costs of system improvements through wholesale rules and transmission tariffs.

Page 15: Power System Planning and Investment

(5a)Two principles Resource parity: Energy efficiency, load management,

demand-side bidding, and distributed resources – in addition to traditional generation and transmission resources -- are all potentially cost-effective means of meeting reliability needs identified by system operators and power pool managers. NEDRI recommends that when socialized cost recovery is sought, that demand-side resources be treated comparably to supply-side and wires options both in analysis and in access to funding.

Least-cost standard: A principal criterion for selecting a solution that is qualified to receive socialized support should be whether it is the lowest-cost, reasonably available solution to an unmet system need, considered on a total cost basis.

Page 16: Power System Planning and Investment

(5b) Screening proposals to socialize grid costs

NEDRI recommends that NEPOOL, ISO-New England, and FERC adopt the following standard as a means of screening proposals to socialize grid enhancements:

Before “socializing” the costs of a proposed reliability-enhancing investment through tariff, uplift, or other cost-sharing requirement, ISO-NE (and FERC) should require the applicant to demonstrate: (1) That the relevant market is fully open to demand-side as well

as supply-side resources; (2) That the proposed investment is the lowest cost, reasonably-

available means to correct a remaining market failure; and (3) That benefits from the investment will be widespread, and thus

appropriate for support through broad-based funding.

Page 17: Power System Planning and Investment

(6) Comparable cost recovery opportunities

Recommendation 6: Ensure comparable cost recovery opportunities for transmission and non-transmission resource solutions

Whether a grid problem is resolved through a transmission or non-transmission solution, or a combination of them, the solution should qualify for cost recovery through transmission tariffs or wholesale uplift charges on the same basis.

Page 18: Power System Planning and Investment

(C) Distribution System Planning and Demand Resources

Recommendation 7: Distribution companies can and should apply recommendations 1-6

Distribution needs distinct from regional system needs

Many circuits, shorter horizons Practices focus on traditional solutions Demand opportunities significant All resource planning focus requires a new

perspective

Page 19: Power System Planning and Investment

Distribution needs distinct from regional system needs

LocalizedDistinct performance of individual circuits

Timing driven by specific events or customers

Shorter time horizons

Page 20: Power System Planning and Investment

Redefinition of Distribution Planning

Focus on wire solutions to address growth-related challengesChallenge to distribution planners

A distinct source of value from customer resources: avoided distribution costsConstructionLosses, voltage support

Full menu of customer resources

Page 21: Power System Planning and Investment

Distributed Utility PlanningFocus on circuitsFactor in cost of incremental customer

resources (societal test)Regulatory Policy matters

Expect DUP to consider customer resourcesPricingBreak link between net income and sales

StaffingPilot

Page 22: Power System Planning and Investment

Possible Roles of the Multi-State Entity

Transmission Siting Advice

Regional Resource Adequacy

Congestion Monitoring Market Power

Monitoring Gas Supply Co-

ordination

Environmental Issue Integration

Technical Potential Assessments

Innovative Solutions Advice

Public Benefits Co-ordination

Page 23: Power System Planning and Investment

Need longer horizon

Meetings throughout region are good

Public Policy input is inconsistent, not reliable

Non-transmission alternatives not permitted to compete (planning, cost recovery) here; unclear how any distributed resource options are considered

Unequal treatment for cost recovery among resources is too large a barrier to get best choices

Opportunity to engage more “rings” of interested people

RTEP Process Flow with observations

Declaration of appropriate projects lacks weight

Queueing remains a problem

No effect on state decision-making on pricing, metering, siting, distributed resources


Recommended