+ All Categories
Home > Documents > PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

Date post: 28-Apr-2015
Category:
Upload: uhrin-imre
View: 94 times
Download: 7 times
Share this document with a friend
Description:
SIEMENS
19
Energy Sector © Siemens AG 2012 SGT-8000H Product Line Actual Update PowerGen Europe, Cologne 12. – 14. June, 2012 Willibald J. Fischer Director, GT Product Management Siemens AG Energy Sector
Transcript
Page 1: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

Energy Sector© Siemens AG 2012

SGT-8000H Product Line Actual Update

PowerGen Europe, Cologne12. – 14. June, 2012

Willibald J. FischerDirector, GT Product ManagementSiemens AG Energy Sector

Page 2: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 2© Siemens AG 2012

Energy Sector

Agenda

Introduction

SGT5-8000H / Irsching 4

SGT6-8000H / Berlin Test Bed

Update on Further Projects

Conclusion

Page 3: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 3© Siemens AG 2012

Energy Sector

SGT5-2000E

SGT6-5000F

SGT6-2000E

SGT6-4000F

292 MW

206 MW

187 MW

168 MW

113 MW

375 MW

Large-scale Siemens Gas Turbine Portfolio for 50 and 60 Hz

SGT5-4000F

SGT5-8000H

274 MW SGT6-8000H

SGT5-8000H04/2007

SGT6-8000H01/2011

Direct scale(50 / 60 Hz)

Page 4: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 4© Siemens AG 2012

Energy Sector

SGT5/6-8000H Product LinePerformance and Configuration Overview

50 Hz 60 Hz

SGT-PAC 8000H 375 MW 274 MW40 % 40 %

SCC-PAC 8000H 1S 570 MW 410 MW> 60 % > 60 %

SCC-PAC 8000H 2x1 1.140 MW 820 MW> 60 % > 60 %

SCC-PAC 8000H 3x1 t.b.d. 1.230MWt.b.d. > 60 %

net values at ISO conditions

SGT5/6-8000H

SCC5/6-8000H 1S

SCC5/6-8000H 2x1

Page 5: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 5© Siemens AG 2012

Energy Sector

Agenda

Introduction

SGT5-8000H / Irsching 4

SGT6-8000H / Berlin Test Bed

Update on Further Projects

Conclusion

Page 6: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 6© Siemens AG 2012

Energy Sector

Irsching Units 1 – 5owned by E.ON Kraftwerke

Unit 4SCC5-8000H 1S

KW Ulrich Hartmann

Unit 5SCC5-4000F 2x1

Unit 1 – 3convent.

Gas Fired Units

Page 7: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 7© Siemens AG 2012

Energy Sector

Irsching 4, Project Overview

Open Cycle

Validation 8000H

Phase 1SGT5-8000Hopen cycle

Reference PlantSCC5-8000H 1S

Phase 2Combined Cycleextension

Field ValidationSGT5-8000H18 months

2011201020092008200720062005Q4Q3Q2Q1Q4Q3Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1 Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4

Combined Cycle

Commercial Operation

22. July 2011

Page 8: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 8© Siemens AG 2012

Energy Sector

Irsching 4, as of June 2012Nearly 1 Year of successful Commercial Operation

22.07.2011 PAC/Commercial Operation

01.-03.10.2011 6.000 EOH Visual Inspection

06.-08.01.2012 8.000 EOH Visual Inspection

Decision: defer CI to 12.000 EOH

17.-21.03.2012 10.000 EOH Visual Inspection

05.-16.05.2012 12.000 EOH Comb. Inspection

Operational Summary:

• Daily start / stop and load following per load dispatchrequirements

• more than 350 starts and 15.000 EOH in total, incl. GT validation

• High operational Availability and Reliability confirmedin commercial operation

Page 9: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 9© Siemens AG 2012

Energy Sector

SGT5-8000H / Irsching 4Operational Status, as of 28.05.2012

Phase I Phase IIGT Validation Combined Cycle

Starts 85 289 / 8Operating hrs (OH) 1525 5666Dynamic hrs 1990 2488

Sub Total (EOH) 4.365 11.125

Grand Total 7.191 OH / 15.490 EOH

Page 10: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 10© Siemens AG 2012

Energy Sector

Agenda

Introduction

SGT5-8000H / Irsching 4

SGT6-8000H / Berlin Test Bed

Update on Further Projects

Conclusion

Page 11: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 11© Siemens AG 2012

Energy Sector

SGT6-8000HValidation at Berlin Test Facility (BTF)

Page 12: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 12© Siemens AG 2012

Energy Sector

First fire of SGT6-8000H Sep 7th, 2011

100% load achieved, unheated gas Oct 21st, 2011

100% load achieved, heated gas Dec 13th, 2011

75% load achieved, fuel oil Jan 19tth, 2012

Gas & oil, LLCO testing Apr-May 2012

Sub-25 ppm combustion testing June-July 2012

SGT6-8000H at Berlin Test Facility Update and Current Status

SGT6-8000H at Berlin test facility

Schedule:

Current Status:FSFL and part load Operation and tuning on cold & hot fuel gasFSFL and part load operation on fuel oil, fuel transfer tuningNOx / CO emissions at base and part load confirmedLLCO (Low Load CO) testingNext Steps: Installation of sub-25 ppm combustion hardwareOptimization and fine tuning on gas and oil

Page 13: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 13© Siemens AG 2012

Energy Sector

Agenda

Introduction

SGT5-8000H / Irsching 4

SGT6-8000H / Berlin Test Bed

Update on Further Projects

Conclusion

Page 14: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 14© Siemens AG 2012

Energy Sector

SGT-8000H References

1xSCC5-8000H 1SGermanyIrsching 4COD 07/2011

> 15.000 EOH

2x3xSGT6-8000HUSA, FLCanaveralCOD 05/2013,

RivieraCOD 05/2014

1xSCC6-8000H 1S Bugok III (GS EPS)South Korea

COD 08/2013

SCC6-8000H 2x1 Ansan (Posco E & C)South Korea

COD 10/2014

1xSCC6-8000H 1S Andong (KOSPO)South KoreaCOD 03/2014

3xSCC6-8000H 1S

N.N., South KoreaCOD 05/2014

08/201411/2014

total: 16 units sold or under final negotiation

Cape CanaveralEnergy Center, FL

Riviera BeachEnergy Center, FL

Bugok 3GS EPS, Korea

Page 15: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 15© Siemens AG 2012

Energy Sector

Agenda

Introduction

SGT5-8000H / Irsching 4

SGT6-8000H / Berlin Test Bed

Update on Further Projects

Conclusion

Page 16: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 16© Siemens AG 2012

Energy Sector

H Class PerformanceSGT5-8000H: 375 MW / 40 %SCC5-8000H 1S: 570 MW / > 60%SCC5-8000H 2x1: 1.140 MW / > 60%

Reduced Emissions25 ppm NOx, 10 ppm CO,330 g/kWh CO2

Improved Operational Flexibilty15 and 35 MW/min. GT loading500 MW in < 30 min. plant hot start

Improved Part Load Capability Reduced Investment (less EUR/kW) High Reliability and Availability Resulting in Lower Life Cycle Costs

SGT5-8000H / SCC5-8000HThe answer to market and customer requirements

Up to 5-10% higher return on investment compared to F-class technology

Page 17: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 17© Siemens AG 2012

Energy Sector

Future

CCPP Killingholme (2x1)2 x 450 MW

CCPP Mainz (1x1)405 MW

CCPP Irsching 4 (1S)578 MW

1996 1991 20112008 2015SGT5-2000E SGT5-8000H:

(next steps)SGT5-4000F(latest upgrade)

SGT5-8000H(Intro)

10 % points increase in efficiency over approx. 20 years

Evolution of Siemens Combined Cycle Technology

CCPP Didcot B (2x1)2 x 705 MW

SGT5-4000F(Intro)

CCPP SCC5-8000H (1S) > 600 MW

> 50%CC efficiency*

> 56%CC efficiency*

> 58,5%CC efficiency*

> 60%CC efficiency*

> 61,5%CC efficiency*

525 °C / 80 bar2PR-non RH

t.b.d.565 °C / 125 bar3PR-RH

600°C / 170 bar3PR-RH, Benson

540 °C / 110 bar 3PR-RH

* at ISO conditions

Page 18: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 18© Siemens AG 2012

Energy Sector

Gala der Deutschen Wirtschaft

11.02.2012, FrankfurtThan

k you for yo

ur atten

tion!

Page 19: PowerGen Europe 2012 Cologne SGT-8000H Update Fischer.

PowerGen Europe 2012, ColognePage 19© Siemens AG 2012

Energy Sector

This document contains forward-looking statements and information – that is, statements related to future, not past, events. These statements may be identified either orally or in writing by words as “expects”, “anticipates”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “will” or words of similar meaning. Such statements are based on our current expectations and certain assumptions, and are, therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond Siemens’ control, affect its operations, performance, business strategy and results and could cause the actual results, performance or achievements of Siemens worldwide to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise, among others, from changes in general economic and business conditions, changes in currency exchange rates and interest rates, introduction of competing products or technologies by other companies, lack of acceptance of new products or services by customers targeted by Siemens worldwide, changes in business strategy and various other factors. More detailed information about certain of these factors is contained in Siemens’ filings with the SEC, which are available on the Siemens website, www.siemens.com and on the SEC’s website, www.sec.gov. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in the relevant forward-looking statement as anticipated, believed, estimated, expected, intended, planned or projected. Siemens does not intend or assume any obligation to update or revise these forward-looking statements in light of developments which differ from those anticipated.

Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or their respective owners.

Disclaimer


Recommended