PPM-50: What's New At DCMA, DECM and Beyond... Carlos D Fagundo, DCMA
Transcript
Page 1: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

PPM-50:What's New At DCMA, DECM and Beyond...

Carlos D Fagundo, DCMA

Page 2: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

EVMS Center Organization – FY20

2

GD Group – PIXG Dean Nifakos

[email protected] 857.268.4561

- GD (MS, IT, LS, BIW, NASSCO) - Leidos

- GE Aviation - Rolls-Royce

- Eastern Shipbuilding - Dynetics

- Progeny Systems - VT Halter Marine

EVMS

Center

Northrop Grumman Group – PIXN John Christian Donna Holden (Acting)

[email protected] 804.416.9212

- NG - Cobham - ViaSat

Boeing Group – PIXB Erik Berg

[email protected] 952.259.5496

- Boeing - Fincantieri Marinette Marine

- L3 Harris

BAE Group – PIXDPaddy Gonzalez / Shad Kresta (Acting)

[email protected] 469.744.3279

- BAE - Textron (Bell, AAI, TMLS)

- Aerojet Rocketdyne - Bechtel - WDC

- Jacobs Technology - Battelle

- General Atomics - Al Salam Aerospace

Lockheed Martin Group – PIXLDaniel Goldsmith

[email protected] 407.228.5242

- LM - Ology Bioservices - Sikorsky

- CAE

Raytheon Group – PIXR Danielle Bemis

[email protected] 520.257.1129

- Raytheon (Pratt/Collins) - Ball Aerospace - CACI

- Honeywell - Vigor Works - ULA

Deputy Director: Donna [email protected] 804.416.9212

Director: James [email protected] 804.416.9153

Page 3: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

EVMS - Center Footprint

3

Page 4: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

EVMS Center Subject Matter Experts (SMEs)

4

Page 5: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

Policy Updates

5

• Policy Team will now own all Business Practices (BPs) and have responsibility for updating

them. (Policy Team Leads: Mr. Dean Nifakos and Ms. Danielle Bemis)

• The policy Integrated Product Team includes one representative from each DCMA Corporate group

• In addition to DCMA internal policy, the DCMA EVMS Policy IPT participates with other

Government, Department and Industry working groups involved in policy, regulation and process

updates as necessary

Examples:

• 1. updated writing of the Electronic Industries Alliance (EIA)-748 working group

• 2. providing comments on the new Integrated Program Management Report (IPMR) from Acquisition,

Analytics and Policy (AAP)

• 3. participating in the Planning and Scheduling Excellent Guide (PASEG) updates

• 4. participating in the Civilian Agencies-led EVMS maturity model study (3-year project with Industry and

Government partners)

• Policy changes outlined put DCMA on a stronger policy footprint & more flexible streamline

approach to execute our mission in the coming year

Page 6: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

EVMS Business Practices

6

Business Practices define internal processes for the EVMS Center

• BP 1: Pre-Award EVM System Plan Review

• BP 2: Post Award EVM System Description

• BP 3: Contract Initiation Support

• BP 4: EVMS Surveillance

• BP 5: EVMS Review for Cause

• BP 6: Compliance Review Execution

• BP 7: EVMS Compliance Metric Configuration Control

BPs are posted to the EVMS public site here: https://www.dcma.mil/HQ/EVMS/

Page 7: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

EVMS Business Practices (cont.)

7

Page 8: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

Business Practices Update

8

• Business Practice 1 - Pre-Award EVM System

Plan Review

• Business Practice 2 - System Description

Review

• Business Practice 3 - Contract Initiation Support

• Business Practice 4 - EVMS Surveillance

• Business Practice 5 - Review for Cause

• Business Practice 6 - Compliance Review

Process

• Business Practice 7 – Compliance Metric

Configuration Control

BP4 Update

• BP4 SSPs will run from 1 Jan to 30

Sept to get us back on the FY Cycle.

• BP4 Returning the focus to

compliance evaluation of 32

guidelines over a three year period

• EVMS Analyst risk rates sites visited,

contracts reviewed, data requested to best

fit the current environment

Page 9: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

Create and Issue SSP

9

Page 10: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

EVMS Metric Specification Templates CCB

10

• Effective 1 June 2018 – EVMS Compliance Test Metric Configuration

Management established

• IAW Business Practice 7 (BP7) – intent is to define uniform process of configuration

control and change management for test metric specifications utilized by EVMS Center

personnel to assess contractor compliance

• Configuration Control Board (CCB) meeting IAW BP7

• Semi-annual Quarterly meeting to review change requests submitted for DCMA EVMS

Compliance Metrics (DECM)

• Through internal DCMA 360 library:

• Internal Government Employees (DCMA)

• Through PIX Inbox:

• External Government Employees (Navy)

• DoD Government Contractors (Industry)

• Automated Software Developers

Page 11: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

Submission to CCB

11

• Submission eligibility

• Any EVMS Stakeholder

• Submission process

• Submit to inbox: [email protected]

• Submission requirements

• Red-line/track changes to Spec Sheet

• Specific, clearly identifiable update/change (commentary without such not considered for

incorporation)

• Externally submitted changes can be coordinated with appropriate Hub

Page 12: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

CCB Membership/Participation

12

• 5 Voting Members

• 3 EVMS Center Hub Leads (rotation between the 6 Hub Leads)

• BP7 Owner (Currently Donna Holden),

• Navy Representative

• Facilitator

• Configuration Control Manager

Page 13: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

CCB Timeline

13

Page 14: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

CCB History

14

• Five CCB meetings completed in FY 19

• Oct & Nov 2018 (Q1 – 2 parts)

• Introductory CCB in October to familiarize participants with the process and set ground rules

• Part 2 held in person at the DCMA River’s Bend office

• v3.1 metrics released – 7 new metrics

• Jan 2019 (Q2)

• Virtual CCB

• v3.2 metrics released – 4 new metrics, 2 metrics deleted, & 44 metrics updated

• Apr 2019 (Q3)

• Virtual CCB

• v3.3 metrics released – 6 new metrics, 1 metric deleted, & 43 metrics updated

• Jul 2019 (Q4)

• Virtual CCB

• v3.4 metrics released 3 Sep –1 new metric, 3 metrics deleted, & 49 metrics updated based on individual

change requests (CR); Total of 105 metrics updated due to CRs and additional EVMSIG admin changes

Page 15: PPM-50...- Progeny Systems - VT Halter Marine EVMS Center Northrop Grumman Group –PIXN John Christian Donna Holden (Acting) donna.g.holden2.civ@mail.mil 804.416.9212 - NG - Cobham

July 2019 CCB

15

• Voting Members

• CCB Lead – Donna Holden

• Navy – Tad Kelly

• 3 Hub Leads – Berg, Nifakos, Christian

• Summary of changes (1 new, 3 deleted, 49 updated)

• Deleted metric 19A301a but replaced it with new metric 19A401a due to EVMSIG update

admin change

• Deleted metric 06A203a; SF relationships are now checked as part of 06A212a (OOS

check)

• Deleted metric 06A206a; Leads are now checked as part of 06A212a (OOS check)

• Aside from the 49 impacted metrics, a significant number of metrics experienced some

admin change due to the 2018 EVMSIG updated language and track changes submitted

by the Dallas hub and verified by NAVY (Total QTY impacted = 105)