1 29-11-2011 15:30 PPP in Practice I Foro Internacional Ferroviario BCNRail PPP in Practice High Speed Line Netherlands Infraspeed Maintenance Ruud Schellekens 29-11-2011 15:30 PPP in Practice I Foro Internacional Ferroviario BCNRail Goal HSL-line Facts & Figures The Parties • Two examples (problem/change)
Transcript
Page 1: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

1

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

PPP in PracticeHigh Speed Line Netherlands

Infraspeed Maintenance

Ruud Schellekens

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Goal• HSL-line Facts & Figures• The Parties• Two examples (problem/change)

Page 2: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

2

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Track Description

Shield-driven Tunnel “Groene Hart”

Noordelijk Holland

Barendrecht

Zuid Holland Zuid

BrabantZuid

Breda RAS

Rotterdam Lombardijen

Rotterdam West RAS

HoofddorpRAS

Zuid Holland Midden

BrabantNoord

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

HSL Facts & Figures

Shield-driven Tunnel “Groene Hart”

Noordelijk Holland

Barendrecht

Zuid Holland Zuid

BrabantZuid

Breda RAS

Rotterdam Lombardijen

Rotterdam West RAS

Hoofddorp RAS

Zuid Holland Midden

BrabantNoord

- Amsterdam - Schiphol: 17 kilometer- Schiphol - Hoofddorp: 5 kilometer- Hoofddorp - start High Speed Track: 2 kilometer- start High Speed Track - end High Speed Track : 42 kilometer- end High Speed Track - Rotterdam Station: 4 kilometer- Rotterdam Station - Rotterdam Lombardijen: 7 kilometer- Rotterdam Lombardijen - start High Speed Track : 5 kilometer

- start High Speed Track – Belgium Border: 43 kilometer.25% at surface level;75% HSL-Zuid-tracé 170 civil works

•viaducts, 4 tunnels,dive-unders•one aquaduct A few bridges

Investment•Civil works 6. Billion EURO•Otherworks 1. Billion EURO PPP

Page 3: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

3

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

First: The good news• Project delivered ON-TIME• First 5 years availability OK!• No serious safety incidents• …..• …..Conclusion:===PPP-works for all parties===

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

But…. Monthly Availability

94,00%

95,00%

96,00%

97,00%

98,00%

99,00%

100,00%

101,00%

jan-07

apr-07

jul-07

okt-0

7jan-0

8

apr-0

8jul

-08

okt-0

8jan

-09

apr-0

9jul-0

9

okt-0

9jan-1

0

apr-1

0jul

-10

okt-10

jan-11

apr-1

1jul-1

1

okt-1

1

Availability without Bonus minutes(%)

Availability with Bonus minutes(%)

Start Operation AMS-ROT 160Km/h

Start Operation AMS-PAR 300/160 Km/h

Full line 300 Km

Page 4: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

4

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

PPP Challenges• Many parties involved >20

– Different roles– Different Interests/Goals

• Risk allocation is Key• System integration• Partnership (Cooperation)

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail Parties

SPCInfraspeed

EPCMaintenance

Rai

lway

Man

ager

: PR

OR

AIL

Saf

ety

Auth

ority

: IVW

STA

TE

Sha

reho

lder

s

Institutionals

Industrials

Lend

ers

Advi

sors

•Rabobank •ING Bank•KBC Bank•KfW •Dexia Credit Local•HypoVereinsbank•BNG + •20 Syndicated Banks

Allen & Overy (Legal)Scott Wilson (Techno)Heath Lambert (InsurePKF (financial auditor)

Infraspeed Advisors

•Freshfields Bruckhaus Derringer (Legal)•Ernst & Young (Accounting, Fiscal)•Marsh UK (Insurance)•Delta Rail (Independent Safety Assessor)

PUBLIC PRIVATE

Page 5: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

5

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

• Risk mitigation: which party can best control the risks ?

• Fit for purpose Service Level Agreement – Functionality and Quality of the Systems

• Value for money (to the taxpayer) • Public Sector Comparator• PFI: Time is money• budget stability for the Public Sector

• Long term stability & contractual relationships• Private sector risk improves quality• Lump Sum, Turn Key, date certain contracts• Safety/environment

What does the State, look for?

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

• Risk aversion• Allocation : which party can best control the risks ?• Reflected in contracts and insurance

• Predictable• Investments• Revenues CASHFLOW• costs

• Reliable• contract parties• “Stick to the rules“ - no surprises !

What do Lenders look for?

Page 6: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

6

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

• Risk aversion• Allocation : which party can best control the risks ?• Reflected in contracts and insurance

• Predictable• Investments• Revenues CASHFLOW• costs

• Reliable• contract parties• “Stick to the rules“ - no surprises !

• Return on Investment• Profit

NB: view of Lenders and Institutional investors is alike!

What do Institutional investors look for?

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

• Manageable Risks• Allocation : which party can best control the risks ?• Reflected in contracts • Scope of work to different parties

• Return on Sales• Positive Cash flow• Margin/Profit

• Reliable• contract parties/partners

• Protect Reputation

What do Industrials look for?

Page 7: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

7

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

My view on PPP

PRIVATEINDUSTRIAL

PRIVATEINSTITUTIONALS

LENDERS

PUBLIC(STATE)

PROFITREPUTATION

RELIABILITYRETURN ON INVESTMENT

COMPETITIVEBEST IN CLASSAVAILABILITY

ADVISOR

ADVISOR

ContractsRisk

distribution

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Risk AllocationState – Infrastructure Provider

• General Principle: – IP takes all the risks subject to exceptions

• Exceptions:– Delay Events (time + money)– Non-Attributable Events (time + money)

eg civil defects <10 yrs – Relief Events (time) eg force majeure,

strikes > 48 hrs– Compensation Events (money)

eg change in law

PRIVATEINDUSTRIAL

PRIVATEINSTITUTIONALS

LENDERS

PUBLIC(STATE)

Page 8: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

8

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Risk AllocationInstitutionals/Lenders – Industrials

• General Principle: – Contractual risks/obligation towards the STATE are

forwarded (back to back) to the Industrials.– Industrials takes all the risks

subject to exceptions

• Exceptions:– Risks that belong to the STATE– Finance/Tax risks– Risks above CAPS

PRIVATEINDUSTRIAL

PRIVATEINSTITUTIONALS

LENDERS

PUBLIC(STATE)

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Allocation of risks

State Infraspeed EPC MCGround RiskCivils assetsOther interface risksConstruction cost overrunsDelay in completionConsentsTrafficDefects in system assetsPerformance DeductionsOperating cost overruns/renewalsDerailmentDiscriminatory change in law/taxesOther change in taxForce MajeureCaps insufficientInfraspeed is only responsible for limited residual risk

PRIVATEINDUSTRIAL

PRIVATEINSTITUTIONALS

LENDERS

PUBLIC(STATE)

Page 9: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

9

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Examples of Non-Attributable Events• State breach• Civils Assets / Connecting Systems Defects• Contamination• Sound emission levels• Train not compliant with requirements• Failing traction power supply (in-feed 150kV)• Failure by task organisations (Prorail VL, Infra)• Soil settlement

PUBLIC(STATE)

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

PPP Cash-flow model Infraspeed

100

0

100

200

Euro

(milli

ons)

2005 2010 2015 2020 2025 2030

Development Period Availability Period

Construction Costs

Performance Payments

Maintenance & Renewals Costs

Page 10: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

10

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Availability• Duration of trains on track = X• Delay of trains due to errors = Y• Availability = 1- Y/X %

Time table

Error

SimulationAccuracy < 2% Availablity

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Monthly Availability Penalty

€ 1.000.000

€ 2.000.000

€ 3.000.000

€ 4.000.000

€ 5.000.000

€ 6.000.000

€ 7.000.000

€ 8.000.000

€ 9.000.000

penalty

perfo

rman

ce p

aym

ent

Performance Fee

100 %99 %

98 %97 %

96 %95 %

94 %93 %

92 %91 %

90 %

Availability (%)

availability penalty

Tra

in D

elay

Pen

alty

(€)

Page 11: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

11

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

First Example: a planned changeor new requirement

PUBLIC(STATE)

COMPETITIVEBEST IN CLASSAVAILABILITY

POSITION OF THE STATE

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Response to a ChangeRELIABILITYRETURN ON INVESTMENT

Everything worksI do not want a ChangeThis changes the cashflowThe risk increasesRisk must be accepted by Industrials

The lenders must approveIt jeopardizes the Loan..price up

PRIVATELENDERS

PRIVATEINSTITUTIONALS

ApproveNecessary

Risk toIndustrials

Everything worksI do not want a ChangeThis changes the cashflowThe risk increasesRisk must be accepted by Industrials

The lenders must approveIt jeopardizes the Loan

Page 12: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

12

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Response to a Change

PRIVATEINDUSTRIAL

PROFITREPUTATION

Risk increases… need more profit

I am the only one that can execute the change ;-)

I will not take the magnitude of the risk (whole system)On a “small” change

Everything worksI do not want a ChangeThis changes the cashflowThe risk increasesRisk must be accepted by Industrials

The lenders must approveIt jeopardizes the Loan..price up

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Result

PRIVATEINDUSTRIAL

PRIVATEINSTITUTIONALS

LENDERS

PUBLIC(STATE)

Changes are:•Expensive (high risk no competition)•State needs to take the availability risk•Lenders need to approve•Process is complex and time consuming•Many advisors get involved•What to do with the financing?•…….•…….•…….

Changes do not benefit from PPP

Page 13: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

13

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

PRIVATEINDUSTRIAL

PRIVATEINSTITUTIONALS

LENDERS

PUBLIC(STATE)

Problem

Second Example: a problem

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Example ETCS Level 2Problem: Trains now and then loose connection to RBC and

come to a stop

Involved parties

• Train Operating Company (OBU)• GSM-r Operator• Infrastructure Provider (RBC)

Page 14: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

14

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

SolutionIt is Public Private PartnershipParties need each other to solve the problem

• Bring all involved parties together:– Suppliers OBU and RBC and GSM-r– Train Operating Company– Infrastructure Provider

• Share knowledge !CONTRACT! Is a forbidden word

• Define an approach to analyse and solve

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

ResultRBC communication Loss HSL-Z south section

WalClock STreinOverigGSM-RGrensTraxx én ThalysVL_lifesign

0

5

10

15

20

25

14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Week 2011

num

ber

Page 15: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

15

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

What is needed for Partnership• It all starts with TRUST• TRUST starts with Transparency• TRANSPARENCY starts with communication• COMMUNICATION starts with People

PEOPLE need to communicateThe goal is simple

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Did you ever do a communications training together with your -external- customer?If you are “married” for 30 years: Do It!

Page 16: PPP in Practice High Speed Line Netherlandsmedia.firabcn.es/.../Presentacions/29_salaA/Ruud_Schellekens_pres.… · - Amsterdam - Schiphol: 17 kilometer - Schiphol - Hoofddorp: 5

16

29-11-2011 15:30 PPP in Practice

I Foro Internacional Ferroviario BCNRail

Maybe it works different in Spain…

“There is unity now, in principle everybody here does what I ask them. Because they are not Dutch….as soon as you take a breath Dutch say: “yes but…..” “

Johan Cruijff about his work in Spain: