PRC-005-2 Workshop July 29-30 2014
Salt Lake City Utah Updated for final posting August 12, 2014
Phil O’Donnell, WECC Manager Operations & Planning Audits
Roger Cummins, WECC Senior Compliance Auditor Joe Veltri, WECC Compliance Auditor
Fred Johnson, WECC Consultant Jim Terpening, WECC Consultant
John (Rob) Robertson, Manager of Electric Regulatory Compliance First Wind Rick Ashton, Tri-State G&T Substation Maintenance Supervisor
WECC PRC-005-2 Workshop Agenda
Day 1 Subject 1:00 -1:15 PM Welcome and Introductions 1:15-1:35 PM Overview and Definitions of Standard PRC-005 1:35 – 1:45 PM Upcoming Changes 1:45 - 2:00 PM Break 2:00 – 4:00 PM Applicability and BES Examples 4:00 – 4:30 PM Questions
Day 2 Subject 8:00 – 10:00 AM PRC-005-2 Requirements and WECC audit
Approach 10:00 – 10:30 AM Break 10:30 – 11:00 AM PRC-005-2 Implementation Plan 11:00 – 11:30 AM Questions and Wrap-Up
3
• The Standard – Background • Applicability • Definitions and Terms • Tables and Attachments • Data and Evidence Retention • Future Changes to PRC-005
Introduction and Definitions
4
Top 10 Violated Standards in WECC
0
50
100
150
200
250
300
350
CIP
-007
PR
C-0
05C
IP-0
01C
IP-0
04C
IP-0
06C
IP-0
05V
AR
-002
CIP
-003
CIP
-002
TOP
-002
Standard Totals
LargestRequirement
5
• FERC Order 693 • Direction to modify PRC-005-1 o Include maximum allowable intervals o Combine PRC-005, PRC-008, PRC-011 and
PRC-017
Background
6
Order Date Modification Implementing Version 3/16/2007 Order 693 Original PRC-005-1 PRC-005-1 9/26/2011 Order Approving Interpretation for
Radially Connected Transformers (1a)
PRC-005-1a
2/3/2012 Order 758 Interpretation of Protection System Definition (1b)
PRC-005-1b
2/3/2012 Order Approving Modification to Definition of Protection System. (to include battery chargers)
NERC Glossary
9/19/2013 Order 785 Generation Req. at Transmission Interface
PRC-005-1.1b
12/19/2013 Order 793 – Combine Standards and Performance Based Programs
PRC-005-2
7
Name and Change in Purpose
PRC-005-1 Transmission and Generation Protection System Maintenance and Testing Purpose: To ensure all transmission and generation Protection Systems affecting the reliability of the Bulk Electric System (BES) are maintained and tested.
PRC-005-2 Protection System Maintenance Purpose: To document and implement programs for the maintenance of all Protection Systems affecting the reliability of the Bulk Electric System (BES) so that these Protection Systems are kept in working order.
8
• PRC-005-1 Transmission and Generation Protection System Maintenance and Testing
• PRC-008-0 Implementation and Documentation of Underfrequency Load Shedding Equipment Maintenance Program
• PRC-011-0 Undervoltage Load Shedding System Maintenance and Testing
• PRC-017-0 Special Protection System Maintenance and Testing
Combines Existing Standards
PRC-005-1 PRC-008-0 PRC-011-0 PRC-017-0
PRC-005-2
9
• Transmission Owner • Generator Owner • Distribution Provider
• BES Applicability Addressed Later
Applicable To…
10
• Protection Systems that are installed for the purpose of detecting Faults on BES Elements (lines, buses, transformers, etc.)
• Protection Systems used for underfrequency load-shedding systems installed per ERO underfrequency load-shedding requirements.
• Protection Systems used for undervoltage load-shedding systems installed to prevent system voltage collapse or voltage instability for BES reliability.
• Protection Systems installed as a Special Protection System (SPS) for BES reliability.
Facilities (TO, DP)
11
• Protection Systems that act to trip the generator either directly or via lockout or auxiliary tripping relays.
• Protection Systems for generator step-up transformers for generators that are part of the BES.
• Protection Systems for transformers connecting aggregated generation, where the aggregated generation is part of the BES (e.g., transformers connecting facilities such as wind-farms to the BES).
• Protection Systems for station service or excitation transformers connected to the generator bus of generators which are part of the BES, that act to trip the generator either directly or via lockout or tripping auxiliary relays.
Protection Systems for generator Facilities that are part of the BES
12
• Protective relays which respond to electrical quantities, • Communications systems necessary for correct operation of protective
functions • Voltage and current sensing devices providing inputs to protective
relays, • Station dc supply associated with protective functions (including
batteries, battery chargers, and non-battery based dc supply), and • Control circuitry associated with protective functions through the trip
coil(s) of the circuit breakers or other interrupting devices.
Definitions:
Protection System –
13
Any one of the five specific elements of the Protection System Definition.
o Relays o Sensing Devices o Communications o DC Control Circuitry o Batteries & Supply
Definitions:
Component Type
14
A component is any individual discrete piece of equipment included in a Protection System, including but not limited to a protective relay or current sensing device. The designation of what constitutes a control circuit component is very dependent upon how an entity performs and tracks the testing of the control circuitry. Some entities test their control circuits on a breaker basis whereas others test their circuitry on a local zone of protection basis.
Definitions: Component
15
Thus, entities are allowed the latitude to designate their own definitions of control circuit components. Another example of where the entity has some discretion on determining what constitutes a single component is the voltage and current sensing devices, where the entity may choose either to designate a full three-phase set of such devices or a single device as a single component.
Definitions: Component (cont.)
16
• An ongoing program by which Protection System components are kept in working order and proper operation of malfunctioning components is restored. A maintenance program for a specific component includes one or more of the following activities:
• Verify — Determine that the component is functioning correctly. • Monitor — Observe the routine in-service operation of the component. • Test — Apply signals to a component to observe functional performance or
output behavior, or to diagnose problems. • Inspect — Examine for signs of component failure, reduced performance or
degradation. • Calibrate — Adjust the operating threshold or measurement accuracy of a
measuring element to meet the intended performance requirement.
Definitions: Protection System Maintenance Program (PSMP)
17
A deficiency identified during a maintenance activity that causes the component to not meet the intended performance, cannot be corrected during the maintenance interval, and requires follow-up corrective action.
Definitions: Unresolved Maintenance Issue
18
• Protection Systems or components of a consistent design standard, or a particular model or type from a single manufacturer that typically share other common elements. Consistent performance is expected across the entire population of a Segment.
• A Segment must contain at least sixty (60) individual components
Definitions: Segment
19
PRC-005-2 Workshop Protection Systems
o A Misoperation ‐ a false operation of a Protection System or a failure of the Protection System to operate, as designed, when needed ‐ can result in equipment damage, personnel hazards, and wide‐area Disturbances or unnecessary customer outages.
o Maintenance or testing programs are used to determine the performance and availability of Protection Systems.
20
A failure of a component requiring repair or replacement, any condition discovered during the maintenance activities in Tables 1-1 through 1-5 and Table 3 which requires corrective action, or a Misoperation attributed to hardware failure or calibration failure.
o Misoperations due to product design errors, o software errors, o relay settings different from specified settings, o Protection System component configuration errors, o or Protection System application errors are
Are not included in Countable Events.
Definitions: Countable Event
21
Tables & Attachments
Table or Att. Description Table 1-1 Protective Relay’s Table 1-2 Communications Systems Table 1-3 Sensing Devices Table 1-4a DC Supply (VLA Batteries) Table 1-4b DC Supply (VRLA Batteries) Table 1-4c DC Supply (NiCad Batteries) Table 1-4d DC Supply (non- Battery Table 1-4e Exclusions for monitoring Table 1-5 Control Circuitry Table 2 Alarming Paths Table 3 Distributed UFLS and UVLS Systems Attachment A Criteria for a Performance Based Protection
System Maintenance Program.
22
• The following evidence retention periods identify the period of time an entity is required to retain specific evidence to demonstrate compliance.
• For instances where the evidence retention period
specified is shorter than the time since the last audit, the Compliance Enforcement Authority may ask an entity to provide other evidence to show that it was compliant for the full time period since the last audit.
Data and Evidence Retention
23
• Current dated Protection System Maintenance Program, as well as any superseded versions since the preceding compliance audit, including the documentation that specifies the type of maintenance program applied for each Protection System Component Type.
• Documentation of legacy programs also required.
Data and Evidence Retention Requirement 1
24
• Documentation of the two most recent performances of each distinct maintenance activity for the Protection System Component, or
• All performances of each distinct maintenance activity for the Protection System Component since the previous scheduled audit date, whichever is longer.
Data and Evidence Retention Requirements 2-5
Project 2007-17.3 (PRC-005-X)
Protection System Maintenance and Testing – Phase 3 (Sudden Pressure
Relays)
High Level PRC-005-X Draft 2 Changes • Removed Requirement R6 (BA Requirement) • Modified Table 5 to provide clarity • Revised Section 4.2.6.1 to address situations where
Balancing Authorities participate in a Reserve Sharing Group
• Modified Facilities Section 4.2.5.3 by adding Sudden Pressure Relaying
• Modified the Supplementary Reference and FAQ Document to reflect the changes in the Standard
PRC-005-X Key Dates
• July 25, 2014: Standard posted for 45-day comment and ballot
• September 2014: Final Ballot • November 2014: NERC Board of Trustees adoption • December 2014: File with FERC
PRC-005-X NERC Contact
• Jordan Mallory, NERC Standards Developer Specialist
Phone: 404.446.9733 Email: [email protected] Project Page Link • Please call or email with any questions or concerns
regarding Project 2007-17.3 (PRC-005-X)
Project 2014-01 Dispersed Generation Resources
Standard Drafting Team (DGR SDT)
Overview of PRC-005-X(X) DGR SDT Recommended Changes • DGR SDT scope limited to recommendations on
Standards applicability to DGRs • Changes made in tandem with Project 2007-17.3
(Sudden Pressure Relays) • Changes clarify the applicability of PRC-005-X to DGRs
• The DGR SDT made no substantive changes to the Standard • Section 4.2.5 separated into two sections (4.2.5 and
4.2.6) • Differentiates between typical Bulk Electric System generator
Facilities and BES generators • The applicability to DGR Facilities has been modified and
relocated from 4.2.5 to 4.2.6.
Applicability PRC-005-2/3/X
• 4.2.6 Protection Systems for the following BES generator Facilities for dispersed power producing resources identified through Inclusion I4 of the BES definition:
• 4.2.6.1 Protection Systems for Facilities used in aggregating dispersed BES generation from the point where those resources aggregate to greater than 75 MVA to a common point of connection at 100 kV or above.
• Rationale for 4.2.6: The Facilities listed that are applicable to dispersed power
producing facilities are covered within 4.2.6. The intent is to NOT include the individual generating resources in the Protection System Maintenance Program, and as such the Protection Systems within the individual generating resources would not be within the scope of PRC-005. Only Protection Systems on equipment used in aggregating the dispersed BES generation from the point where those resources aggregate to greater than 75MVA to a common point of connection at 100kV would be included in the Protection System Maintenance Program, including the Protection Systems for those transformers used in aggregating generation.
PRC-005-X(X) Key Dates
• June 12, 2014: Standard posted for 45-day comment and ballot
• July 18-28, 2014: Initial ballot period • September 2014: Second ballot (if necessary) • November 2014: Target date for NERC Board
adoption
PRC-005-X(X) NERC Contact
• Sean Cavote, NERC Standards Developer Phone: 404.446.9697 Email: [email protected] Project Page: http://www.nerc.com/pa/Stand/Pages/Project-2014-01-Standards-Applicability-for-Dispersed-Generation-Resources.aspx
• Please call or email with any questions or concerns
regarding Project 2014-01 (PRC-005-X(X))
Fred Johnson & Jim Terpening WECC Compliance Auditor Consultants
Applicability of PRC-005-2 & Examples of New BES Definition
35
• During the past 20 years, major functional advances are primarily due to the introduction of microprocessor technology for power system devices, such as primary measuring relays, monitoring devices, control Systems, and telecommunications equipment.
PRC-005-2 Workshop Protection Systems
Protection and control systems have seen dramatic technological changes spanning several generations.
36
Self monitoring capability Ability to capture Fault records Ability to meter currents and voltages Data communications via ports Ability to trip or close circuit breakers and switches Construction from electronic components
PRC-005-2 Workshop Protection Systems
Modern microprocessor‐based relays have six significant traits that impact a Maintenance strategy:
37
Acting as a Digital Fault Recorder (DFR) Allowing Protection Engineers to study the fault(s)
and the clearing time of the fault.
PRC-005-2 Workshop Protection Systems
Modern microprocessor‐based relays
o Fault record(s) showing how the Protection System responded to a Fault in its zone of protection, or to a nearby Fault
38
• Meter currents and voltages, as well as status
of connected circuit breakers, continuously during non‐Fault times.
• Can compute values, such as MW and MVAR line flows, that are sometimes used for operational purposes, such as SCADA.
PRC-005-2 Workshop Protection Systems
Modern microprocessor‐based relays
39
Modern microprocessor‐based relays • Provide remote access to all of the results of
Protection System monitoring, recording and measurement.
PRC-005-2 Workshop Protection Systems
40
Modern microprocessor‐based relays • Trip or close circuit breakers and switches
through the Protection System outputs o On command from remote data communications
messages • From relay front panel button requests.
PRC-005-2 Workshop Protection Systems
41
Modern microprocessor‐based relays
• Significant advances in the technology behind the other components of the Protection Systems, Microprocessors are now a part of: Battery chargers Associated communications equipment Voltage and current‐measuring devices Control circuitry (in the form of software‐latches
replacing lock‐out relays, etc.)
PRC-005-2 Workshop Protection Systems
42
NERC Definition of a Protection System: o Protective relays which respond to electrical
quantities
o Communications Systems necessary for correct operation of protective functions
o Voltage and current sensing devices providing inputs to protective relays
PRC-005-2 Workshop Protection Systems
43
NERC Definition of a Protection System: o Station dc supply associated with protective
functions (including station batteries, battery chargers, and non‐battery‐based dc supply)
o Control circuitry associated with protective functions through the trip coil(s) of the circuit breakers or other interrupting devices.
PRC-005-2 Workshop Protection Systems
44
PRC-005-2 Workshop Protection Systems
Applicable Relays The NERC Glossary definition of a Protection System includes relays, dc supply, current and voltage sensing devices, dc control circuitry and associated communications circuits. The relays to which this standard applies are those protective relays that respond to electrical quantities and provide a trip output to trip coils, dc control circuitry or associated communications equipment. This definition extends to IEEE Device No. 86 (lockout relay) and IEEE Device No. 94 (tripping or trip‐free relay), as these devices are tripping relays that respond to the trip signal of the protective relay that processed the signals from the current and voltage‐sensing devices. Relays that respond to non‐electrical inputs or impulses (such as, but not limited to, vibration, pressure, seismic, thermal or gas accumulation) are not included.
45
PRC-005-2 Workshop Protection Systems
• This standard does not cover circuit breaker maintenance or transformer maintenance.
• The standard also does not presently cover testing of
devices, such as sudden pressure relays (63), temperature relays (49), and other relays which respond to mechanical parameters, rather than electrical parameters.
Mechanical Devices that do not operate electrically with no calibration settings
46
• An auxiliary relay, IEEE Device No.# 94, is described in IEEE Standard C37.2‐2008 as: “A device that functions to trip a circuit breaker, contactor, or equipment; to permit immediate tripping by other devices; or to prevent immediate reclosing of a circuit interrupter if it should open automatically, even though its closing circuit is maintained closed.”
PRC-005-2 Workshop Protection Systems
Auxiliary Relays
47
• A lock‐out relay, IEEE Device No.# 86, is described in IEEE Standard C37.2 as: “A device that trips and maintains the associated equipment or devices inoperative until it is reset by an operator, either locally or remotely.”
• Software‐latch 86 that replaces an electromechanical 86 does not require routine trip testing
• Any trip circuitry associated with the “soft 86” would still need applicable verification activities performed, but the actual “86” does not have to be “electrically operated” or even toggled
P 13 – Supplementary Reference and FAQ dated October 2012
PRC-005-2 Workshop Protection Systems
Lock-out Relay
48
New Bulk Electric System Definition Application to PRC-005-2
PRC-005-2 Workshop Protection Systems
49
Unless modified by the lists of Inclusions or exclusions, all Transmission Elements operated at 100 kV or higher and Real Power and Reactive Power resources connected at 100 kV or higher. This does not include facilities used in the local distribution of electric energy.
Bulk Electric System (BES) Definition
50
Compliance obligations for newly identified Elements (Phase 2): o Twenty‐four months after the applicable
effective date of the definition: July 1, 2014 + 24 mo. = July 1, 2016
or o If a longer timeframe is needed…the
appropriate timeframe may be determined on a case‐by‐case basis by agreement between the RRO and Element owner/operator.
BES Definition – Newly Defined Elements- Compliance Obligation
51
Compliance obligations for newly identified Elements: o New Elements to be commissioned after July 1,
2014 must be compliant prior to being placed into service.
BES Definition – Newly Defined Elements
52
Any electrical device with terminals that may be connected to other electrical devices such as a generator, transformer, circuit breaker, bus section, or transmission line. An element may be comprised of one or more components.
Transmission Element
53
• Step 1- Apply core definition o Is the device operated at 100kV or higher? o Is the power or reactive resource connected at
100kV or greater? • Step 2- Apply specific inclusions o Do any of the inclusions result in additional
devices to be considered a “BES element”?
Process to determine if a element is BES
54
• Step 3- Apply specific exclusions o Are there specific situations for potential
exclusion from the BES?
RESULT: The protection systems associated with the resultant BES elements are subject to PRC-005-2
Process to determine if a element is BES (continued)
55
I1. Transformers with the primary terminal and at least one secondary terminal operated at 100 kV or higher unless excluded under Exclusion E1 [radial] or E3 [local network].
BES Inclusion I1- Transformers
56
A B Typical Two winding Transformer Question: Which Transformer is a BES element?
BES Inclusion I1- Transformers
> 100 kV > 100 kV > 100 kV < 100kV
57
A B
Typical Three winding Transformer
Question: Which Transformer is a BES element?
BES Inclusion I1- Transformers
Load Load
58
I2. Generating resource(s) including the generator terminals through the high‐side of the step‐up transformer(s) connected at a voltage of 100 kV or above with: • Gross individual nameplate rating greater than 20
MVA. Or, • Gross plant/facility aggregate nameplate rating
greater than 75 MVA.
BES Inclusions I2- Generating Resources
59
A B > 20 MVA 19 MVA
Question: Which Power Resource is a BES element?
BES Inclusions I2- Generating Resources
60
A Multiple Generators Examples B
BES Inclusions I2- Generating Resources
61
Multiple Generators with an Aggregate Resources of 79 MVA
BES Inclusions I2- Generating Resources
62
Multiple Generators with an Aggregate Resources of 79 MVA with one Generator serving load
BES Inclusions I2- Generating Resources
63
I3. Blackstart Resources identified in the Transmission Operator’s restoration plan. Resources are included in the BES regardless of configuration or location.
BES Inclusions I3- Blackstart Resources
64
I4. Dispersed power producing resources that aggregate to a total capacity greater than 75 MVA (gross nameplate rating), and that are connected through a system designed primarily for delivering such capacity to a common point of connection at a voltage of 100 kV or above. Thus, the facilities designated as BES are: • The individual resources, and • The system designed primarily for delivering capacity from the point
where those resources aggregate to greater than 75 MVA to a common point of connection at a voltage of 100 kV or above.
BES Inclusions I4- Dispersed Power Resources
65
BES Inclusions I4- Dispersed Power Resources – Wind Farm 80 MVA
<100 kV/≥100 kV
≥100 kV
Wind Farm – 80 MVA individual units 2 MVA
The Common Point of connection is where the individual transmission Element(s) of the collector system is connected to the 100kV or higher
Transmission system. (Note: This point is typically specified in the respective Transmission Owner and Generator Operator Interconnection Agreements.)
The point of aggregation is where
the individual generator name plate
ratings of the dispersed generation total > 75 MVA (actual 80 MVA) and a failure would result in loss of 75 of MVA capacity or
greater to the BES.
66
<100 kV/≥100 kV
≥100 kV
Photovoltaic System – 80 MVA individual units 20 MVA
Photovoltaic Cells & Inverters (Banks)
The Common Point of connection is where the individual transmission
Element(s) of the collector system is connected to the 100kV or higher Transmission system. (Note: This
point is typically specified in the respective Transmission Owner and Generator Operator Interconnection
Agreements.)
BES Inclusions I4- Dispersed Power Resources- 80MVA Photovoltaic System
The point of aggregation is where the individual generator name plate ratings of the
dispersed generation total > 75 MVA (actual 80 MVA) and a failure would result in loss of 75 of
MVA capacity or greater to the BES.
67
Photovoltaic System – 80 MVA individual units 20 MVA aggregated below 100kV.
BES Inclusions I4- Dispersed Power Resources- 80 MVA Photovoltaic System
The point of aggregation is where the individual generator name plate ratings of the dispersed
generation total > 75 MVA (actual 80 MVA) and a failure would result in loss of 75 of MVA
capacity or greater to the BES.
The Common Point of connection is where the individual transmission Element(s) of the
collector system is connected to the 100kV or higher Transmission system. (Note: This point is typically specified in the respective Transmission Owner and Generator Operator Interconnection
Agreements.)
≥100 kV
≥100 kV
<100 kV <100 kV
<100 kV
Photovoltaic Cells & Inverters (Banks)
68
I5. Static or dynamic devices (excluding generators) dedicated to supplying or absorbing Reactive Power that are connected at 100 kV or higher, or through a dedicated transformer with a high‐side voltage of 100 kV or higher, or through a transformer that is designated in Inclusion I1.
BES Inclusions I5- Static or Dynamic Devices
69
BES Inclusions I5- Reactive Resources Reactive Resource “2” is connected directly to the station bus (≥100 kV) and is therefore considered to be a BES Element
Reactive Resource “1” is connected through the tertiary winding of a transformer that meets the inclusion criteria established by Inclusion I5 (i.e., through a transformer that is designated in Inclusion I1) and is therefore considered to be a BES Element
Reactive Resource “3” is connected through a dedicated transformer with a high-side voltage of ≥ 100 kV and is therefore considered to be a BES Element. The dedicated transformer does not meet the inclusion criteria established by Inclusion I1 and is therefore not considered to be a BES Element
Reactive Resource “4” is connected directly to the station bus (≥100 kV) and is not connected through a dedicated transformer with a high-side voltage of 100 kV or higher or through a transformer that is designated in Inclusion I1, and is therefore not considered to be a BES Element
1 2
3
4 Load
> 100 kV
<100 kV <100 kV
>100 kV /<100 kV >100 kV
>100 kV >100 kV
70
E1. Radial systems: A group of contiguous transmission Elements that emanates from a single point of connection of 100 kV or higher and: a.) Only serves Load. Or, b.) Only includes generation resources, not identified in Inclusions I2, I3, or I4, with an aggregate capacity less than or equal to 75 MVA (gross nameplate rating). Or, c.) Where the radial system serves Load and includes generation resources, not identified in Inclusions I2, I3, or I4, with an aggregate capacity of non‐retail generation less than or equal to 75 MVA (gross nameplate rating).
BES Exclusion E1- Radial Systems
71
“Single Point of Connection of 100 kV or higher” is where the radial system will begin if it meets the criteria of Exclusion E1, including parts a, b, or c. For example, the start of the radial system may be a hard tap of the Transmission line, or could be the tap point within a ring or breaker and a half bus configuration. The connection to the radial system must be from only one point at 100 kV or higher. Any group of contiguous transmission elements that have multiple connections at 100 kV or higher do not qualify for Exclusion E1. Normally open switching devices between radial systems, will not disqualify a radial system from this exclusion.
E1- Definition “Single Point of Connection”
72
BES Exclusion E1- Radial System: Serving only load
Radial System: Serving only load
≥100 kV
Load
Substation Boundary
≥100 kV
Load
Substation Boundary
≥100 kV <100 kV
≥100 kV <100 kV
Green identifies non-BES (excluded radial system
The single Point of connection is where the radial system (group of
contiguous transmission Elements) emanates at a
voltage of 100 kV or higher from the Transmission
system.
73
BES Exclusion E1a- Multiple radial systems with underlying loop at ≤ 50 kV
Multiple Radial Systems (Underlying Loop Facilities ≤ 50 kV)
The single Point of connection is where the radial system (group of contiguous transmission Elements) emanates at a voltage of
100 kV or higher from the Transmission system.
A B C
D E F
Green identifies non-BES (excluded radial system
≥100 kV
Load
Substation Boundary
≥100 kV < 50 kV
Load
≥100 kV < 50 kV
< 50 kV Sub-100 kV Loop
74
BES Exclusion E1b- Radial System: Single Generation Resource
Radial System: Single Generation Resource ≥100 kV
The single Point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a voltage
of 100 kV or higher from the Transmission
system.
≥100 kV
≥100 kV <100 kV
≥100 kV <100 kV
≥100 kV ≥100 kV
15 MVA 25 MVA
75
BES Exclusion E1b- Radial System: Multiple Generation Resources less than 75 MVA
Radial System: Multiple Generators
≥100 kV
18 MVA
<100 kV / ≥100 kV
15 MVA
≥100 kV / <100 kV
The single Point of connection is where the radial system (group of
contiguous transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system.
The non-retail generators have gross individual nameplate
ratings ≤ 20 MVA (actual 18 MVA, 15 MVA, 14 MVA, 12 MVA, & 10 MVA. By application of Inclusion I2 these units are not considered
a BES Element
12 MVA
14 MVA
<100 kV / ≥100 kV
<100 kV / ≥100 kV
≥100 kV <100 kV
10 MVA
Generator Site Boundary
76
BES Exclusion E1c- Radial System: Generation Resources & Serving Load
Radial System: Generation Resources & Serving load ≥100 kV The single Point of connection is where the
radial system (group of contiguous transmission Elements) emanates at a voltage of 100 kV or higher from the
Transmission system.
The generator has a gross individual nameplate rating >
20 MVVA (actual 25 MVA) and is connected through the high-side of the step-up transformer
at a voltage of 100 kV or above. By application of
Inclusion I2 this unit is a BES Element
The substation transformers are not part
of the BES since both (primary and secondary
terminals are not operated at ≥ 100 kV as
per Inclusion I1
≥100 kV <100 kV
25 MVA
≥100 kV <100 kV
≥100 kV <100 kV
Load
Load
77
BES Exclusion E1c- Radial System: Generation Resources & Serving Load
Radial System: Generation Resources & Serving load
≥100 kV The single Point of connection is where the radial system (group of contiguous
transmission Elements) emanates at a voltage of 100 kV or higher from the
Transmission system.
Green identifies non-BES (excluded) radial system. The excluded radial system serves Load and has <20 MVA gross aggregate nameplate rating of
connected non-retail generation (actual 15 MVA)
and therefore meets the criteria of Exclusion E1c.
The substation transformers are not part
of the BES since both (primary and secondary
terminals are not operated at ≥ 100 kV as
per Inclusion I1
≥100 kV <100 kV
15 MVA
≥100 kV <100 kV
≥100 kV <100 kV
Load
Load
78
BES Exclusion E1- Radial System: Normally Open Switching Device
Two Radial Systems separated by an open switch
≥100 kV ≥100 kV
The single Point of connection is where the radial system (group of contiguous transmission Elements) emanates at a voltage of 100 kV or
higher from the Transmission system.
To Load
Substation Boundary
To Load
Substation Boundary
≥100 kV <100 kV
≥100 kV <100 kV
The normally open (N.O.) device between the radial systems does
not affect this exclusion
N.O.
<100 kV
The normally open (N.O.) device between the radial systems does not
affect this exclusion
N.O.
<100 kV
79
E2. A generating unit or multiple generating units on the customer’s side of the retail meter that serve all or part of the retail customer Load with electric energy on the customer’s side of the retail meter if:
BES Exclusion E2- Generation Resources on the customer side of a retail meter
80
(i) the net capacity provided to the BES does not exceed 75 MVA, and
(ii) standby, back‐up, and maintenance power services are provided to the generating unit or multiple generating units or to the retail Load by a Balancing Authority, or provided pursuant to a binding obligation with a Generator Owner or Generator Operator, or under terms approved by the applicable regulatory authority.
BES Exclusion E2- Generation Resources on the customer side of a retail meter
81
Net capacity: The net capacity determination for Exclusion E2 is the net flow to the BES as measured by integrated hourly revenue metering for the most recent 12 month period. Periods of net capacity to the BES that exceed the threshold value when directed by the applicable Balancing Authority do not preclude the ability to utilize this exclusion.
BES Exclusion E2- Generation Resources on the customer side of a retail meter
82
BES Exclusion E2- Generation Resources on the customer side of a retail meter
Behind‐the‐Meter Generation: Net Capacity to the BES less than 75 MVA
≥100 kV The single Point of connection is where the customer owned equipment is connected to the 100 kV or higher Transmission System. (Note:
This point is specified in the respective Interconnection Agreements.)
50 MVA to BES
100 MVA to Industrial Process
Customer owned generation behind the customer's meter is excluded from the BES by application of Exclusion E2: • Net capacity to the BES is less than 75 MVA
(Actual 50 MVA, and • Standby power has been secured in
accordance with the language of Exclusion E2.
≥100 kV/<100 kV
≥100 kV <100 kV
150 MVA
83
BES Exclusion E2- Generation Resources on the customer side of a retail meter
Behind‐the‐Meter Generation: Net Capacity to the BES greater than 75 MVA
≥100 kV The single Point of connection is where the
customer owned equipment is connected to the 100 kV or higher Transmission System. (Note:
This point is specified in the respective Interconnection Agreements.)
100 MVA to BES
50 MVA to Industrial Process
Customer owned generation resource behind the customer's meter is included in the BES: • By application of Inclusion I2, because the
generator’s gross individual nameplate rating is > 20 MVA (actual 150 MVA, and
• The net capacity to the BES is > 75 MVA (Actual 100 MVA, therefore Exclusion E2 does not apply.
≥100 kV/<100 kV
≥100 kV <100 kV
150 MVA
84
E3. Local networks (LN): A group of contiguous transmission Elements operated at less than 300 kV that distribute power to Load rather than transfer bulk power across the interconnected system. LN’s emanate from multiple points of connection at 100 kV or higher to improve the level of service to retail customers, and not to accommodate bulk power transfer across the interconnected system. The LN is characterized by all of the following:
BES Exclusion E3 - Local Networks
85
Limits on connected generation: The LN and its underlying Elements do not include generation resources identified in Inclusions I2, I3, or I4, and do not have an aggregate capacity of non‐retail generation greater than 75 MVA (gross nameplate rating);
Real Power flows only into the LN and the LN does not transfer energy originating outside the LN for delivery through the LN; and
Not part of a Flowgate or transfer path: The LN does not contain any part of a permanent Flowgate in the Eastern Interconnection, a major transfer path within the Western Interconnection, or a comparable monitored Facility in the ERCOT or Quebec Interconnections, and is not a monitored Facility included in an Interconnection Reliability Operating Limit (IROL).
BES Exclusion E3 - Local Networks
86
BES Exclusion E3- Local Network with aggregate generation less than 75 MVA LN operated at 138 kV with aggregate generation < 75 MVA with power
flow into network.
<300kV
230kV
The multiple points of connection are where the local network (group of contiguous transmission Elements) emanates at a voltage of 100 kV or higher from the Transmission system.
Power Flow
<100 kV 138 kV
The substation transformers are not part of the BES since both (primary and secondary) terminals are not operated at ≥100 kV as per Inclusion I1.
Load Load
<100 kV 138 kV
15 MVA
Power Flow
138 kV 230 kV
<300 kV 138 kV
15 MVA 10 MVA
Generation Site
Boundary
<300 kV 230 kV
<300 kV 230 kV
Power Flow
Load <100 kV/138 kV
25 MVA
1
2
3
4
87
BES Exclusion E3- Local Network with aggregate generation less than 75 MVA
LN operated at 138 kV with a BES generator.
<300 kV
230 kV
The multiple points of connection are where the local network (group of contiguous transmission Elements) emanates at a voltage of 100 kV or higher from the Transmission system.
Power Flow
<100 kV 138 kV
The substation transformers are not part of the BES since both (primary and secondary) terminals are not operated at ≥100 kV as per Inclusion I1. Except for the transformer on generation > 20 MVA.
Load Load
<100 kV 138 kV
30 MVA
Power Flow
138 kV 230 kV
<300 kV 138 kV
15 MVA 10 MVA
Generation Site
Boundary
<300 kV 230 kV
<300 kV 230 kV
Power Flow
Load <100 kV/138 kV
25 MVA
1
2
3
4
88
BES Exclusion E3- Sub 100kV loop power flowing out of network
Sub 100kV loop with Power flowing out of network
The presence of the sub-100 kV loop establishes multiple points of connection at a voltage level
of 100 kV or higher to the Transmission System
Load
Substation Boundary
<300 kV <100 kV/>50 kV
Load
Sub-100 kV Loop
A B C
D E F
<300 kV
Power Flow
The network does not meet the exclusion criteria established in Exclusion E3 due to power flowing out of the networked system (E3b)
<300 kV <100 kV/>50 kV
<100 kV/>50 kV
The substation transformers are not part of the BES since both (primary and secondary) terminals are not operated at ≥100 kV as per Inclusion I1.
Power Flow
89
E4. Reactive Power devices installed for the sole benefit of a retail customer(s). Reactive Power devices installed for the sole benefit of a retail customer(s) supersedes the more general Inclusion I5 (Static or Dynamic Reactive Power Devices). Reactive Power devices installed for the sole benefit of a retail customer are, by definition, not required for operation of the interconnected transmission system.
BES Exclusion E4- Reactive Power Devices
90
• Step 1- Apply core definition o Is the device operated at 100 kV or higher? o Is the power or reactive resource connected at
100kV or greater? • Step 2- Apply specific inclusions o Do any of the inclusions result in additional
devices to be considered a “BES element”?
Hierarchical Application of the Definition
91
• Step 3 - Exclusions should be applied in the following sequence: o Exclusion E2 - Behind‐the‐Meter Generation o Exclusion E4 - Reactive Power Devices o Exclusion E3 - Local Networks o Exclusion E1 - Radial Systems
RESULT: The protection systems associated with the resultant BES elements are subject to PRC-005-2
Hierarchical Application of the Definition
Joe Veltri Compliance Auditor, WECC
PRC-005-2 Workshop
Requirement R1
July 29th – 30th, 2014 Salt Lake City, UT
93
Establish a Protection System Maintenance Program for
Protection Systems
Requirement R1
94
Requirement R1.1
Identify which maintenance method (time-based, performance-based per PRC-005 Attachment A, or a combination) is used to address each Protection System Component Type. All batteries associated with the station dc supply Component Type of a Protection System shall be included in a time-based program as described in Table 1-4 and Table 3.
95
Include the applicable monitored Component attributes applied to each Protection System Component Type consistent with the maintenance intervals specified in Tables 1-1 through 1-5, Table 2, and Table 3 where monitoring is used to extend the maintenance intervals beyond those specified for unmonitored Protection System Components.
Requirement R1.2
96
Determine Maintenance Method • Time Based Condition Based (extending the interval)
• Performance Based
Requirement R1
97
TBM – time‐based maintenance – externally prescribed maximum maintenance or testing intervals are applied for components or groups of components.
Time Based Maintenance
98
• Select Appropriate Component Type Table • Determine Degree of Monitoring • Find Minimum Maintenance Activity • Determine Maximum Interval
Tables and Monitoring
99
• The Maintenance Activity(ies) is the minimum maintenance that must be performed and documented
• Under TBM, entities are responsible only for performing Minimum Maintenance Activities within the defined (or extended) interval.
Maintenance Activity
100
• Four Calendar Months Add four months from the last time the activity was performed.
• A battery bank is inspected in month no.1
then it is due again before the end of the month number 5.
Interval Definitions
101
Calendar Year ‐ January 1 through December 31 of any year. As an example, if an event occurred on June 17, 2009 and is on a “One Calendar Year Interval,” the next event would have to occur on or before December 31, 2010.
Interval Definitions
102
The Component Types
Sensing Devices Table 1-3
DC Supply Table 1-4a through 4f
Protective Relay Table 1-1
Communication Systems Table 1-2
Control Circuitry Table 1-5
103
• Table 1-1 Protective Relays • Table 1-2 Associated Communications • Table 1-3 Instrument Transformers • Table 1-4 Station DC Supply • Table 1-5 Control Circuits
Tables Associated with your Component
104
• Table 2 Alarming & Paths • Table 3 Distributed UFLS & UVLS • A DISTRIBUTED UFLS or UVLS scheme
contains individual relays which make independent load shed decisions based on applied settings and localized voltage and/or current inputs
Tables Associated with your Component
105
Protective Relay
Table 1-1 Component Type - Protective Relay
Excluding distributed UFLS and distributed UVLS (see Table 3) Component Attributes Maximum Maintenance Maintenance Activities Interval1
Any unmonitored protective relay not having all the monitoring attributes of a category below
6 calendar years
For all unmonitored relays: • Verify that settings are as specified
For non-Microprocessor relays: • Test and, if necessary calibrate
For Microprocessor relays: • Verify operation of the relay inputs
and outputs that are essential to proper functioning of the Protection System
• Verify acceptable measurement of
power system input values
Protective Relay (con’t)
Table 1-1 Component Type - Protective Relay
Excluding distributed UFLS and distributed UVLS (see Table 3) Component Attributes Maximum Maintenance Maintenance Activities Interval1 Monitored microprocessor protective relay with the following: • Internal self-diagnosis and alarming
(see Table 2)
• Voltage and/or current waveform sampling three or more times per power cycle, and conversion of samples to numeric values for measurement calculations by microprocessor electronics.
• Alarming for power supply failure (see
Table 2)
12 calendar years
Verify:
• Settings are as specified.
• Operation of the relay inputs and outputs that are essential to proper functioning of the Protection System.
• Acceptable measurement of power
system input values
Protective Relay (con’t)
Table 1-1 Component Type - Protective Relay
Excluding distributed UFLS and distributed UVLS (see Table 3) Component Attributes Maximum Maintenance Maintenance Activities Interval1 Monitored microprocessor protective relay with preceding row attributes and the following: • AC measurements are continuously verified
by comparison to an independent ac measurement source, with alarming for excessive error (see Table 2)
• Some or all binary or status inputs and control outputs are monitored by a process that continuously demonstrates ability to perform as designed, with alarming for failure (See Table 2)
• Alarming for change of settings (see Table 2).
12 calendar years
Verify only the unmonitored relay inputs and outputs that are essential to proper functioning of the Protection System.
DC Supply VLA
Table 1-4(a) Component Type – Protection System dc Supply Using Vented Lead Acid
(VLA) Batteries Excluding distributed UFLS and distributed UVLS (see Table 3)
Protection System Station dc supply used only for non-BES interrupting devices for SPS, non-distributed UFLS Systems
or non-distributed UVLS systems excluded (See Table 1-4(e))
Component Attributes Maximum Maintenance Maintenance Activities Interval
• Protection System Station dc supply using
Vented Lead-Acid (VLA) batteries not having monitored attributes of Table 1-4(f).
4 Calendar Months
Verify: • Station dc supply voltage Inspect: • Electrolyte level
• For unintentional grounds
DC Supply VLA
Table 1-4(a) Component Type – Protection System dc Supply Using Vented Lead Acid
(VLA) Batteries Excluding distributed UFLS and distributed UVLS (see Table 3)
Protection System Station dc supply used only for non-BES interrupting devices for SPS, non-distributed UFLS Systems
or non-distributed UVLS systems excluded (See Table 1-4(e))
Component Attributes Maximum Maintenance Maintenance Activities Interval
• Protection System Station dc supply using
Vented Lead-Acid (VLA) batteries not having monitored attributes of Table 1-4(f).
18 Calendar Months
Verify:
• Float voltage of battery charger • Battery continuity • Battery terminal connection resistance • Battery intercell or unit-to-unit connection
resistance
Inspect:
• Cell condition of all individual battery cells where cells are visible or measure battery cell/unit internal ohmic values where the cells are not visible.
• Physical condition of battery rack.
DC Supply VLA
Table 1-4(a) Component Type – Protection System dc Supply Using Vented Lead Acid
(VLA) Batteries Excluding distributed UFLS and distributed UVLS (see Table 3)
Protection System Station dc supply used only for non-BES interrupting devices for SPS, non-distributed UFLS Systems
or non-distributed UVLS systems excluded (See Table 1-4(e))
Component Attributes Maximum Maintenance Maintenance Activities Interval
• Protection System Station dc supply using Vented
Lead-Acid (VLA) batteries not having monitored attributes of Table 1-4(f).
18 Calendar Months
-or-
6 Calendar
Years
Verify that the station battery can perform as manufactured by evaluating cell/unit measurements indicative of battery performance ( e.g. internal ohmic values or float current) against the station battery baseline.
-or-
Verify that the station battery can perform as manufactured by conducting a performance of modified performance capacity test of the entire battery bank.
112
• Table 1-4(b) Valve regulated Lead Acid • Table 1-4(c) Nickel Cadmium (NICAD) • Table 1-4(d) Non Battery Based Energy
Storage Each Table defines Maximum Maintenance Interval and Maintenance Activities
DC Supply Tables
113
• Any unmonitored communication system necessary for correct operation of protective functions
• Continuous monitoring or periodic automated testing and alarm for loss of function
• Continuous monitoring or automated testing (signal level. Reflected power, data error rates)
• Binary inputs and control outputs monitored by process continuously demonstrating ability to perform as designed with alarming for failure.
Communication Systems Table 1-2
114
• Trip Coils • Electromechanical lockout devices • Unmonitored control circuitry associated with
SPS • Unmonitored control circuitry inclusive of all
auxiliary relays • Monitored & alarmed control circuitry
associated with protective functions and /or SPS
Control Circuitry Associated with Protective Functions
Instrument Transformers
Table 1-3 Component Type – Voltage and Current Sensing Devices providing inputs
to Protective Relays Excluding distributed UFLS and distributed UVLS Table 3) Component Attributes Maximum Maintenance
Maintenance Activities Interval1
12 calendar years
Any voltage and current sensing devices not having monitoring attributes of the category below
Verify that current & voltage signal values are provided to the protective relays
Instrument Transformers
Table 1-3 Component Type – Voltage and Current Sensing Devices providing inputs
to Protective Relays Excluding distributed UFLS and distributed UVLS Table 3) Component Attributes Maximum Maintenance
Maintenance Activities Interval1
No Periodic Maintenance
specified
Voltage and current sensing devices connected to microprocessor relays with AC measurements are continuously verified by comparison of sensing input value as measured by the MP relay to independent measuring source with alarming for unacceptable error failure (See table 2)
None
Extension for DC Supply Monitoring Table 1-4 (f)
Alarming Paths & Monitoring
119
• Unmonitored Protective Relays • Monitored Microprocessor Relays • Instrument Transformers • Protection System DC Supply • Control Circuits o Relay to Lockout o Lockout to tripping device Excludes Trip Coils of Non- BES interrupting devices
UFLS / UVLS Table 3
Roger Cummins Sr. Compliance Auditor, WECC
PRC-005-2 Workshop Requirement R2
July 29th – 30th, 2014
Salt Lake City, UT
121
Establishing a Performance-based Plan
Requirement R2
122
Establishing a Performance-based Plan
Requirement R2
123
R2. Each Transmission Owner, Generator Owner, and Distribution Provider that uses performance-based maintenance intervals in its PSMP shall follow the procedure established in PRC-005 Attachment A to establish and maintain its performance-based intervals.
Requirement R2
124
• There is a requirement to develop a PSMP
• There is no requirement to develop a Performance-based PSMP
• A PBM PSMP must be followed, even if more stringent (activities, intervals)
R2 Applicability
125
Maintain components per the
Maintenance Program (R4)
R2 – The Process
Establish a Maintenance
Program (R1)
Choose TBM or PBM
for each Component
Type (R1)
Follow Attachment A criteria to establish and maintain PBM
(R2)
Maintain components per the
Tables (R3)
Maintain components per the Maintenance
Program (R4) Take action to
correct Unresolved Maintenance Issues
(R5)
Start
End
PBM TBM
PRC-005-2 Requirements
Flowchart
Follow Attachment A criteria to
establish and maintain PBM (R2)
126
Segment o At least 60 components. oComponents of a consistent design standard,
particular model or type, single manufacturer, share other common elements.
oConsistent performance is expected across the population of a Segment.
R2 – Definitions
127
Segment Considerations oManufacturer oModel oDesign Standard o Failure Mode o Environment o Vintage o…
R2 – Definitions
128
Countable Events o a failure of a component requiring repair or
replacement o any condition discovered during the
maintenance activities which requires corrective action
o a Misoperation attributed to hardware or calibration failure.
R2 – Definitions
129
The solution with the fewest assumptions should be selected
o in the absence of certainty, embrace simplicity o trade simplicity only for greater explanatory power o explanatory power shifts the burden of proof
Occam’s Razor
130
R2 – Follow Attachment A to establish and maintain performance-based intervals
R2 – Attachment A Criteria
131
Establish per Attachment A 1. Develop Segments 2. Maintain Components 3. Document Maintenance Activities 4. Analyze Maintenance Activities 5. Determine Maximum Intervals
R2 – Attachment A Criteria
132
1. Develop a list of Segments with a description of Components included in each designated Segment.
2. Maintain the Components in each Segment according to the time-based intervals in the Tables until results are available for a minimum of 30 individual Components.
Establish Technical Justification
133
3. Document the program activities and results for each Segment, including dates and Countable Events for each Component.
4. Analyze the activities and results for each
Segment to determine the overall performance of the Segment.
Establish Technical Justification
134
5. Determine the maximum allowable maintenance interval for each Segment
• such that the Segment experiences Countable Events on no more than 4% of the Components within the Segment,
• for the greater of either the last 30 Components maintained or all Components maintained in the previous year.
Establish Technical Justification
135
…such that the Segment experiences Countable Events on no more than 4% of the Components within the Segment…
• Population of greater last 30 components maintained, or, all components maintained within the last year.
• Must do 30 or the greater of the 2 • Count # of events in the segment (and maintenance) population • Calculate Countable Events %:
Countable Events
# CEs in Segment + Maintenance Population Countable Events % = ──────────────────────── X 100 Segment Population
136
If you have 4% or more...? o Develop, document, and implement an action plan to
reduce the Countable Events to less than 4% of the Segment population within 3 years. • Increase maintenance activities • Reduce Segment interval • Accelerate maintenance to maintain all
components in the Segment within the reduced interval.
Countable Events
200 Devices
Phil O’Donnell WECC Manager Operations & Planning Audits
Requirement 3- Implementation of Time based programs
139
R3. Each Transmission Owner, Generator Owner, and Distribution Provider that utilizes timebased maintenance program(s) shall maintain its Protection System Components that are included within the time-based maintenance program in accordance with the minimum maintenance activities and maximum maintenance intervals prescribed within Tables 1-1 through 1-5, Table 2, and Table 3.
WECC Auditor’s Approach to Auditing the PRC Standards PRC-005-2 – Requirement 3
140
Very similar to the current PRC Standards except… ● Required Maintenance Activities are
specified ● Maximum Interval is Specified
WECC Auditor’s Approach to Auditing the PRC Standards
PRC-005-2 – Requirement 3
141
142
A comprehensive list of all of the entity’s Protection System Components (and Alarm Paths) being maintained under PRC-005-2 time-based maintenance programs providing:
● Will be requested prior to audit (when RSAW and initial documentation is due)
● This will provide the basis for a sample records for additional review
● This will be communicated by completing the Attachment G Supplemental spreadsheet.
Evidence for Assessment Per Draft RSAW
143
Tracking and Providing Additional Data
Attachment G Supplement
144
● Type of Program: TBM (or PBM or Combination for R4) ● Applicable Standard: PRC-005-2 (or Legacy Program) ● The Component Identification
o (Device Name and Device Description, Protection Type)
● Physical location o (Bus or Generator)
● Component Type o (Relay, Sensing Device, Com, DC Control Circuity, Battery/DC Supply)
● The dates of the last two performances of all maintenance activities, or all performances of maintenances activities since the last audit, whichever is greater.
● The maintenance interval(s) pertaining to the Component or Path in each year since the last audit. (There may be more than one).
● The applicable PRC-005-2 Table being used for required maintenance.
Evidence for Assessment Attachment G Supplement Info
145
• Expand the Attachment G Supplement to include the required data.
• Provide options for organization of data.
Attachment G Supplement
146
Option 1: Legacy tabs will be provided. o Input data as before, additional data required.
Attachment G Supplement
147
• Use the Legacy tabs – (PRC-005-1, 008, 011, 017) • Input as before;
Option 1 - Legacy
Gen/Substation Name
Device Name
Device Description
Date Last Tested
Prior Test Date
Interval
148
Additional data is required.
Option 1 – Legacy
Interval Maintenance Method
Maintenance Program Version (Last)
Maintenance Program Version (Prior)
Monitoring (Y/N)
Segment Identifier
12 yrs TBM v2 v1 Yes 8 yrs TBM v1 v1 Yes 20 yrs PBM v2 v1 Yes B
Use other Legacy tabs as applicable to list UFLS, SPS
149
Option 2: PRC-005 All Components o List all devices in this single tab
Attachment G Supplement
150
Additional data required
Option 2 – One Big Pile
Protection Type (UFLS,
SPS) Table
UFLS Table 3
SPS
UVLS
151
Option 3: Segment tabs o List Segments o List all PBM Components by Segment. o TBM components use either Option 1 or 2.
Attachment G Supplement
152
Option 3 – By Segment
Segment Identifier
Segment Description
Segment Interval Countable
Events (%)
Date of Most
Recent Analysis
General Notes
1 2 3 4 1 2 3 4
A Line Package 12 12 18 16 0 0 1
B SEL MP Relay 20 20 20 20 1 0 0 0
C GE BDD EM Relay 10 8 8 6 2 2 3 2
… … … …
Segments tab o List each defined Segment
153
Segment Components tab o List the Components within each Segment.
Option 3
Segment Identifier
Component Location
Component Name/ Description
Last Test Date
Program Version (Last)
Prior Test Date
Program Version (Prior)
A Elroy Sub LL Package V2 V1 A Astro Sub LL Package V2 v1 B Jane #1 JJ-KK Line SEL-321 V1 v1 B George #2 JJ-KK Line SEL-321 V1 v1
154
NERC Sampling Guidelines
155
NERC Sampling Guidelines
156
● Samples will be requested which satisfy NERC sampling guidelines.
● Detailed Documentation for each Component required if selected for sample.
● Documentation that the maintenance specified by the Tables was performed on the dates required. o The evidence may include but is not limited to dated maintenance records, dated maintenance
summaries, dated check-off lists, dated inspection records, or dated work orders.
Evidence for Assessment
New Documentation that that each component or Path being maintained under PRC-005-2 has the attributes specified by the PRC-005-2 Tables which justifying the use of the maintenance interval and/or minimum maintenance activities being performed.
157
Legacy Programs
158
● More info in discussion on Implementation of PRC-005-2
● Single Attachment G Supplement ● Samples will include some from old
programs ● Will be held to requirements of previous
standards ● Will be looking for Progress on Transition.
Legacy Programs
Fred Johnson- WECC Consultant
Requirement 4 -Implementation of Performance
Based Maintenance Programs
160
PRC-005-2, R4 Each Transmission Owner, Generator Owner, and Distribution Provider that utilizes performance-based maintenance program(s) in accordance with Requirement R2 shall implement and follow its PSMP for its Protection System Components that are included within the performance-based program(s).
PRC-005-2 Workshop R4- Implementation of Performance Based Maintenance Program
161
Requirement 2 states: Each Transmission Owner, Generator Owner, and Distribution Provider that uses performance-based maintenance intervals in its PSMP shall follow the procedure established in PRC-005-2, Attachment A to establish and maintain its performance-based intervals.
PRC-005-2 Workshop R4- Implementation of Performance Based Maintenance Program
162
This requirement is to verify that the entity has implemented its program in accordance with Attachment A and that the components within the segments has been maintained within their established intervals and the minimum maintenance activities have been performed in accordance with Tables 1-1 through 1-5, Table 2, and Table 3
PRC-005-2 Workshop R4- Implementation of Performance Based Maintenance Program
163
RSAW Evidence o In order to verify maintenance intervals have
been properly established and maintained by following is required: A list of all segments established or maintained
since last audit. List is to include: • Segment identification • Segment Description ( SEL 421, Control circuitry, ASEA
PT’s, Protection System Package) • Maximum Maintenance interval • Countable events • Countable Events %
PRC-005-2 Workshop R4- Implementation of Performance Based Maintenance Program
164
RSAW Evidence o Complete list of all segments since last audit List is to include
• Individual segment identification • Identification of each component and its location within
each segment. • Segment population. • Maximum Maintenance Interval. • Last and previous maintenance dates. • Program version used for prior maintenance
PRC-005-2 Workshop R4- Implementation of Performance Based Maintenance Program
Jim Terpening WECC Consultant
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
July 29 – 30, 2014 Salt Lake City, UT
166
PRC-005-2, R5 o Each Transmission Owner, Generator Owner,
and Distribution Provider shall demonstrate efforts to correct identified Unresolved Maintenance Issues. Compliance Date is April 1, 2015
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
167
Definition – Unresolved Maintenance Issue o A deficiency identified during a maintenance
activity that causes the component to not meet the intended performance, cannot be corrected during the maintenance interval, and requires follow-up action.
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
168
Application o Transmission and Generation Protection
Systems (PRC-005) o Under-frequency Load Shedding Equipment (PRC-008)
o Undervoltage Load Shedding Equipment (PRC-011)
o Special Protection Systems (PRC-017)
o These standards have now been incorporated into our PRC-005-2
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
169
• The Maintenance Activities specified in the Tables do not present any requirements related to Restoration; R5 of the standard does require that the entity “shall demonstrate efforts to correct any identified Unresolved Maintenance Issues.”
• The type of corrective activity is not stated; however it could include repairs or replacements.
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
170
Example Correction of Unresolved Maintenance issues o Include but not limited to: Replacement of capacitors in distance relays Replacement of relay(s) Other Protection System Components Upgrade of electromechanical relay(s) Upgrade of Solid State Protective relay(s) to
Microprocessor based devices
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
171
RSAW Evidence o Complete list of all Unresolved Maintenance
Issues Since last audit April 1, 2015
• Any UMI on this date will be reviewed back to 2014 • Tracking from April 1, 2014 for UMI will be needed
List is to include • Resolved Maintenance Issues • Remaining Unresolved Maintenance Issues
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
172
RSAW Evidence o Complete list of all Unresolved Maintenance
Issues List is to include (con’t)
• Date encountered • Local Zone of Protection • Protected Element • Substation • Other Location(s) • Specific Components • Function • Manufacture
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
173
RSAW Evidence o Unresolved Maintenance Issues Evidence demonstrating efforts to correct the
Identified Unresolved Maintenance Issue. • Evidence – Documentation should be but not limited to:
• Copies of component orders • Invoices • Project schedules with completed milestones • Return Material authorizations • Purchase orders
PRC-005-2 Workshop R5 Unresolved Maintenance Issues
Roger Cummins Sr. Compliance Auditor, WECC
PRC-005-2 Workshop Implementation and Transition
July 29th – 30th, 2014
Salt Lake City, UT
175
Implementation And
Transition
PRC-005-2
176
Implementation What To Do
And When To Do It
PRC-005-2
177
For purposes of calculating the time periods in the implementation plan, the regulatory approval date in the U.S. is February 24, 2014.
Implementation
178
PRC-005-2 was effective April 1, 2014. o The first compliance date is April 1, 2015. o Must have a PSMP (TBM, PBM or both). o Current plan may be used to become compliant
with PRC-005-2.
Implementation
179
Current intervals and activities may be used to maintain compliance, but o the implementation plan compliance dates must
be met o only maintenance performed according to the
PRC-005-2 Standard is compliant with v2 o The legacy standards retire 2027
Implementation
180
• Entities shall be 100% compliant on the first day of the first calendar quarter twelve (12) months following applicable regulatory approvals.
• April 1, 2015.
Implementation
181
• R1 – Establish a plan • R2 – Follow Att. A to establish PBM • R5 – Unresolved Maintenance Issues o Entities should be tracking UMI as of April 1,
2014. o Evidence of efforts to correct the UMI may be
requested for those outstanding on April 1, 2015.
Implementation
182
• Phased implementation, based on Maximum Allowable Interval.
• R3 and R4 refer to components in both TBM and in PBM.
Implementation
183
Implementation
Maximum Interval <1 calendar year Compliance Months Compliance Date
100% 18 October 1, 2015
Maximum Interval ≥1 / <2 calendar years Compliance Months Compliance Date
100% 36 April 1, 2017
184
Implementation
Maximum Interval 3 calendar years Compliance Months* Compliance Date
30% 24 April 1, 2016 60% 36 April 1, 2017
100% 48 April , 2018
*For generating plants with scheduled outage intervals exceeding two years, at the conclusion of the first succeeding maintenance outage.
185
Implementation
Maximum Interval 6 calendar years Compliance Months* Compliance Date
30% 36 April 1, 2017 60% 60 April 1, 2019
100% 84 April 1, 2021
*For generating plants with scheduled outage intervals exceeding three years, at the conclusion of the first succeeding maintenance outage.
186
Implementation
Maximum Interval 12 calendar years Compliance Months Compliance Date
30% 60 April 1, 2019 60% 108 April 1, 2023
100% 156 April 1, 2027
187
Transition Things We Need To Know
and Stating The Obvious
PRC-005-2
188
• While in transition, be prepared to identify: o All applicable Protection System components. o The plan under which they were last
maintained; PRC-005-2 or the applicable Legacy plan.
Transition
189
Added maintenance activities: o For activities being added to an entity’s
program, evidence may be available to show only a single performance.
Transition
190
The Legacy Standards: o Remain active throughout the phased
implementation; o Applicable to an entity’s Protection System
component maintenance not yet transitioned to PRC-005-2.
Transition
191
The Legacy Standards o “retired” by the entity as Component Types
become compliant with PRC-005-2… All of a type described in the Component Attributes
or defined in a Segment; A Maximum Allowable Interval must be determined.
Transition
192
Maintain Protection System components: o According to the maintenance program already
in place for the legacy standards or the maintenance program for PRC-005-2.
But not both.
Transition
193
Choose the version of your plan that will be used to come into compliance with PRC-005-2. o May apply individually to specific Components o May apply to all Components o If using Legacy plan, the intervals and activities
in the legacy plan may be used. To maintain compliance with Legacy standards
Transition
194
Once an entity has designated PRC-005-2 as its maintenance program for specific Protection System components, it cannot revert to the original program for those components. • You get to make the call but you can’t take it
back.
Transition
195
Maintain Components according to the Tables: o Staying with TBM? Test according to the
Tables. o Moving to PBM? Test 30 according to Tables. Or, verify maintenance activities for 30 are available Perform analysis and implement that Segment.
Transition
196
Maintain documentation to demonstrate compliance with the Legacy Standards o until the entity meets the requirements of
PRC-005-2 in accordance with this implementation plan.
Transition
197
“…meets the requirements of PRC-005-2…” o Once an individual component has been
maintained according to the Tables Last test demonstrates performance of the Minimum
Maintenance Activities.
Transition
198
“…meets the requirements of PRC-005-2…” Or, o The Component is in an established Segment. Consistent performance expectation Sampled annually (≥ 5%) Reasonable assurance of consistent performance
across the population.
Transition
199
Formally transitioning Component Type(s) to PRC-005-2. o Once a Last and Prior test demonstrate
performance according to the tables, that specific Component is compliant with PRC-005-2. (an EM relay)
o Once a group of components, or Component Type is compliant, that Component Type may be transitioned to PRC-005-2. (All EM relays)
Transition
200
TBM to TBM Transition
Last Tested Due Date
2013 2021
Legacy Plan Defined 8 year Interval
201
TBM to TBM Transition
Last Tested 100%
2013 2021
30%
2017 2019
60%
2015
Compliance Date
PRC-005-2 TBM Maximum 6 year Interval
Includes past maintenance, if compliant
202
TBM to PBM Transition
Last Tested
2013
Test 30
Components
2015
Compliance Date
PRC-005-2 PBM Segment A
Max Interval for this
Segment
Each Year
Test ≥5%
Test ≥5%
Test ≥5%
Time-Based Performance-Based (R2) (R4)
100%
203
TBM to TBM Transition
Last Tested Due Date
2013 2019
Legacy Plan Defined 3 year Interval
Due Date
2016
Due Date
2022
204
TBM to TBM Transition
Last Tested 100%
2013 2021
PRC-005-2 TBM Maximum 6 year Interval
2019 2016
30% 60%
2017
Thank you
206
• PRC-005-2 Standard http://www.nerc.com/pa/Stand/Reliability%20Standards/PRC-005-2.pdf
• PRC-005 Implementation Plan http://www.nerc.com/pa/Stand/PRC0052RD/Project_2007-17_Implementation_Plan_Clean_errata.pdf
• Supplementary Reference and FAC http://www.nerc.com/pa/Stand/PRC0052RD/Project_200717_Protection_System_Maintenance_and%20T_Supplementary_Reference_clean_10-2012_2.pdf
• PRC-005-X Project Page http://www.nerc.com/pa/Stand/Pages/Project-2007-17_3-Protection-System-Maintenance-and-Testing-Phase-3.aspx
• BES Definition, Notification and Exception Process http://www.nerc.com/pa/RAPA/Pages/BES.aspx
Workshop References Links to NERC’s website as of August 2014
207
• Phil O’Donnell, WECC Manager Operations & Planning Audits [email protected]
• Roger Cummins, WECC Senior Compliance Auditor [email protected]
• Joe Veltri, WECC Compliance Auditor [email protected]
For questions on Project 2007-17.3 • Jordan Mallory, NERC Standards Developer Specialist
For questions on Project 2014-01 • Sean Cavote, NERC Standards Developer
Workshop Contact Information