+ All Categories
Home > Documents > PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES...

PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES...

Date post: 21-Mar-2020
Category:
Upload: others
View: 5 times
Download: 1 times
Share this document with a friend
18
PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES BASED DISTILLERY PLANT BY M/S. SHREE MAROLI VIBHAG KHAND UDYOG SAHAKARI MANDLI LTD. SURVEY NO.: 71, 72 & 80 AT-KOLASARA (KALYAN NAGAR) P.O- MAROLI BAZAR, TALUKA JALALPORE, DISTRICT NAVSARI-396436 GUJARAT
Transcript
Page 1: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

PRE - FEASIBILITY REPORT

FOR

PROPOSED 35 KLPD MOLASSES

BASED DISTILLERY PLANT

BY

M/S. SHREE MAROLI VIBHAG KHAND UDYOG

SAHAKARI MANDLI LTD.

SURVEY NO.: 71, 72 & 80 AT-KOLASARA

(KALYAN NAGAR) P.O- MAROLI BAZAR,

TALUKA JALALPORE,

DISTRICT NAVSARI-396436

GUJARAT

Page 2: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

SUMMARY

M/s. Shree Maroli Vibhag Khand Udyog Sahakari Mandli Ltd is an existing sugar mill located, at

Survey No. 71, 72 & 80 At-Kolasara (Kalyan Nagar) P.O- Maroli Bazar, Taluka Jalalpore, District Navsari,

Gujarat. Capacity of the existing Sugar Industry is 3000 TCD producing 11200 MT/Month of White Crystal

Sugar. Now Shree Maroli Vibhag Khand Udyog Sahakari Mandli Ltd has proposed 35 KLPD Molasses

based distillery unit within existing company premises.

PROJECT COST The total cost of the project will be around Rs. 30.0 crores. Total capital cost of pollution control measures

will be Rs. 3.0 crores & recurring cost per annum will be 1.0 crores.

DETAILS OF PRODUCTS Details of existing and proposed products are given in following table.

LIST OF EXISTING AND PROPOSED PRODUCTS AND PRODUCTION CAPACITY

SR.

NO. NAME OF THE PRODUCTS

EXISTING

QUANTITY

ADDITIONAL

QUANTITY TOTAL

(A) PRODUCTS

1 White Crystal Sugar 11200 MT/Month -- 11200 MT/Month

2 Captive Power Plant (In

House During Crushing Season) 5.85 Mw/Hr. -- 5.85 Mw/Hr.

3 Rectified Spirit/Anhydrous

Alcohol -- 35 KLPD 35 KLPD

(B) BY PRODUCTS

4 Molasses 5,200 MT/Month -- 5,200 MT/Month

5 Bagasse 33,500 MT/Month -- 33,500 MT/Month

6 Press Mud 4,200 MT/Month -- 4,200 MT/Month

7 Bio Compost 4,200 MT/Month -- 4,200 MT/Month

REQUIREMENTS FOR THE PROJECT

LAND

No new land will be acquired for the proposed project. Out of total land area (i.e. 1,53,262 m2) around

8,000 m2 open land area will be utilized for the proposed distillery unit.

WATER

For the proposed project additional 506 m3/Day water will be required. Existing water required of the sugar

plant is 428.7m3/Day, after proposed project total water required will be 934.7m

3/Day. Source of water for

existing unit is Borewell/ Canal and for the proposed distillery unit surface water (i.e canal water) will be

utilized.

ELECTRICAL ENERGY For proposed project additional power requirement will be 400 KW/Hr. Existing connected Power load is

299.10 KWH/MT. Power supply shall be full-filled by Dakshin Gujarat Vij Company Limited.

MANPOWER

At present, 237 personnel are working in the sugar industry. For proposed project additional 24 personnel

will be employed who will come from local area. Total manpower after proposed project will be 261

personnel.

FUEL

For the proposed project, energy requirement will be met from existing boiler (2 Nos.) having capacity of

50 and 30 TPH, for the proposed project Baggase (1.9 MT/Hr) will be used as fuel in existing boiler.

Page 3: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

SOURCES OF AIR POLLUTION AND CONTROL MEASURES

EMISSIONS FROM COMBUSTION OF FOSSIL FUELS FROM STATIONARY OR MOBILE

SOURCES

Sr.

No. Stack Attached To

Stack Height

In Meter

Air Pollution Control

Devices Parameter

EXISTING

1. Boiler No. 1

(Bidrum Water Tube 50t/Hr) 45.0 (common

stack)

Ventury Type Wet

Scrubber

PM < 150 Mg/Nm3

SO2 < 100 ppm

NO2 < 50 ppm

2. Boiler No. 2

(Bidrum Water Tube 30t/Hr)

Ventury Type Wet

Scrubber

PM < 150 Mg/Nm3

SO2 < 100 ppm

NO2 < 50 ppm

3. D. G. Set

(500 KVA – Stand By) 11.0 --

PM < 150 Mg/Nm3

SO2 < 100 ppm

NO2 < 50 ppm

PROPOSED: No any additional utilities are required for the proposed project.

WASTE WATER GENERATION AND IT’S TREATMENT: Wastewater generated from the sugar factory is being treated in existing ETP unit and treated water is being

used in bio-composting.

Waste water generated from the proposed distillery unit in the form of spent wash will be concentrating in

multi effective evaporator and then sent for bio-composting. Condensate from MEE will be recycled back

to the process, while spent less and other waste water will be treated in ETP units and treated water will be

used for the bio-composting. Thus achieve the’ Zero Liquid Discharge’.

NOISE POLLUTION AND CONTROL MEASURES: From the existing and proposed manufacturing unit noise pollution will generate which will be controlled

by adopting different types of noise pollution control measures. Main sources of the noise pollution are

machineries, Electric motors, etc.

Following noise control measures to be adopted in the existing and proposed project,

� Encasement of noise generating equipment.

� Greenbelt all around the plant boundary.

� In addition personnel, working near high noise level generating sources, will be provided with ear

muffs.

� Proper and suitable acoustic barrier will also be provided around, areas generating high noise.

� Effective preventive maintenance and vibration measurement of all rotating equipment will help in the

improvement of plant life and also noise reduction.

SOLID WASTE GENERATION AND ITS DISPOSAL METHOD The details of solid/Hazardous waste generation and its management are given in the following table.

Sr.

No.

Name of the

Waste

Cat

No.

Existing

(MT/Year)

Additional

(MT/Year)

Total

(MT/Year) Method of Storage & Disposal

1. ETP Waste 34.3 58

(MT/Year) --

58

(MT/Year)

Collection, Storage and used as

Manure.

2.

Used Oil

5.1 1.45

(MT/Year)

0.55

MT/Year

2.0

(MT/Year)

Collection, Storage, transportation

and disposal by selling to GPCB

approved registered recyclers /

reuse.

3.

Discarded

Container/Barrel

s/ Linear

33.3 150

Nos./Year --

150

Nos./Year

Collection, Storage and disposal by

selling to GPCB approved

registered recyclers.

GREEN BELT DEVELOPMENT Company is having total 1,53,262 m

2 land area is available. The company has green belt area with Lawn,

plants and flowers spread across about 33% of the total area. Further it will be developed at plant boundary.

Page 4: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

INDEX

CHAPTER

NO. CONTENT

1 Introduction of the Project

2 Project Description

3 Site Analysis

4 Planning Brief

5 Proposed Infrastructure

6 Rehabilitation and Resettlement (R & R) Plan

7 Project Schedule & Cost Estimates

8 Analysis of Proposal

Page 5: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

1

CHAPTER-1

INTRODUCTION OF THE PROJECT

1.1 IDENTIFICATION OF PROJECT

M/s. Shree Maroli Vibhag Khand Udyog Sahakari Mandli Ltd. is a sugar industry located at Survey No. 71,

72 & 80 At-Kolasara (Kalyan Nagar) P.O-Maroli Bazar, Taluka Jalalpore, District Navsari, Gujarat. Molasses

is produced as a by-product during manufacturing of sugar. Maroli sugar industry is planning to set up 35

KLPD distillery plant within existing premises using molasses as a basic raw material.

1.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT

M/s. Shree Maroli Vibhag Khand Udyog Sahakari Mandli Ltd is planning for installation of the molasses

based distillery unit at Survey No. 71, 72 & 80 At-Kolasara (Kalyan Nagar) P.O-Maroli Bazar, Taluka

Jalalpore, District Navsari, Gujarat.

LIST OF PRODUCTS AND PRODUCTION CAPACITY

Sr.

No. Name of the Products

Existing

Quantity

Additional

Quantity Total

(a) Products

1 White Crystal Sugar 11,200 MT/Month -- 11,200 MT/Month

2 Captive Power Plant (In House

During Crushing Season) 5.85 Mw/Hr. -- 5.85 Mw/Hr.

3 Rectified Spirit / Anhydrous

Ethanol -- 35 KLPD 35 KLPD

(b) By Products

4 Molasses 5,200 MT/Month -- 5,200 MT/Month

5 Bagasse 33,500 MT/Month -- 33,500 MT/Month

6 Press Mud 4,200 MT/Month -- 4,200 MT/Month

7 Bio Compost 4,200 MT/Month -- 4,200 MT/Month

1.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR REGION.

In India economy many industries are dependent over agriculture produce for production of luxury and need

based committees. Alcohol is used in chemical industry as well as for preparation of beverages. The use of

alcohol for the purpose of potable liquor is as high as its use for industrial purpose. As a source of income to

the government, the potable liquor units get assured quota of alcohol. This trend is continuing and will

continue in view of the fact that potable liquor has larger revenue generating potential. Denatured sprits are

Rectified Sprit made unfit for drinking by addition of chemicals which have strong disagreeable odor and

which cannot be easily separated from sprit. Ethyl alcohol is important feedstock for manufacture for basic

carbon base products like Acetic Acid, Butanol, Butadiene, Acetic anhydride, Vinyl acetate, PVC etc. which

are needed in pharmaceuticals, paints and other important industries as they are value added products. Ethyl

alcohol has been a source of large amount of revenue by way of excise duty levied by Government on

alcoholic liquor. Fermented ethyl alcohol has also great demand in countries like Japan, United state, Canada,

Sri Lanka etc. as synthetic alcohol produced by these countries from Naphtha of Petroleum Crude is not

suitable for beverages. Ethylene, Ethylene oxide and mono-ethylene glycol can be manufactured from

petrochemical route. However, latest technological development and taking into account increasing cost of

petrochemical raw material the above mentioned chemicals can be easily manufactured from ethyl alcohol.

1.4 DEMANDS-SUPPLY GAP The gap between the availability of alcohol and the requirement by the industry has been widening. The

existing requirement of alcohol by the industries is around 600 million liters annually. In 1992-93, alcohol

consumed for industrial purpose was 450 million liters and utilization for potable purpose was 434 million

liters. The trend is expected to continue over last 9-10 years.

1.5 EMPLOYMENT GENERATION: For the proposed project additional 24 nos. of personnel (existing 237 nos.) will be employed.

Page 6: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

2

CHAPTER-2

PROJECT DESCRIPTION

2.1 TYPE OF PROJECT

M/s. Shree Maroli Vibhag Khand Udyog Sahakari Mandli Ltd is an existing sugar mill located, at Survey

No. 71, 72 & 80 At-Kolasara (Kalyan Nagar) P.O-Maroli Bazar, Taluka Jalalpore, District Navsari, Gujarat.

Molasses is produced as a by-product during manufacturing of sugar. Maroli sugar factory is planning to set

up distillery plant within existing premises of sugar plant to manufacture 35 KLPD Rectified Spirit and/or 35

KLPD Anhydrous Alcohol using molasses as a basic raw material.

2.2 LOCATION

M/s. Shree Maroli Vibhag Khand Udyog Sahakari Mandli Ltd located at Survey No. 71, 72 & 80 At-Kolasara

(Kalyan Nagar) P.O- Maroli Bazar, Taluka Jalalpore, District Navsari Gujarat. It is situated at 21°01'.18.24"

North latitude and 73°54'59.47" East longitude. A map showing location of the presentated in figure-1and

detailed plan layout in shown in figure- 2.

FIGURE- 1 LOCATION MAP

Page 7: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

3

FIGURE-2 PLAN LAYOUT

Page 8: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

4

2.3 PROCESS DESCRIPTION

MANUFACTURING PROCESS OF DISTILLERY UNIT

The manufacturing process of rectified spirit/ anhydrous alcohol involves two major steps. Molasses is the

basic raw material. Generally sulphuric acid is not required, nutrients like yeast, anti-foam agent etc, will be

used.

Following steps are required for the Ethanol Production.

1) Fermentation Section

Molasses handling: Molasses from the own sugar factory will be utilized for the proposed production.

Molasses is then after weighted, sent for storage or to the process diluter tank.

Yeast Propagation: Best strain of yeast is required for the production of alcohol, yeast is bought from nearby

vendor and is developed further in propagation section and maintain the viable cell population of about 300

million cells/ml by yeast recycling and continuous aeration of the fermenter.

Fermentation: When Yeast is added in container, yeast works on sugar present in molasses, break down the

sugar into alcohol and carbon-dioxide, required temperature controlled to be 30-32°C (by circulating cooling

water). From Fermenter CO2 collected and directed to scrubber. Remaining content is “wash”.

2) Distillation Section

The “wash” from the fermentation enters into distillation section. The hardware contains columns basically

for two functions, namely Stripping and Rectification. Thus, 1) Analyser column – Operated under vacuum

and 2) Rectifier cum Exhaust Column – operated under pressure. (Additional columns only for refinement).

The “wash” from fermentation is first preheated in heater and fed to analyser column. Alcohol from the wash

in form of vapour from the analyser column is fed to pre-rectifier column (under vaccum). The impure spirit

drawn from the top of column were collected at bottom which is fed into the rectified cum exhaust column

(under pressure). Alcohol is enriched towards the top and drawn out as Rectified Spirit about 95% v/v

concentrations. Fusel oil generated is drawn out to tank, washed with water, decanted, layers separated and

alcohol layer returned as recovery.

3) Molecular Sieve Dehydration

Molecular sieve dehydration is to produce anhydrous alcohol from rectified spirit. Water molecules are

absorbed on the pore surface and the larger alcohol molecules are excluded and exit from the sieve unit. The

absorption is a vapour phase process and hence, rectified spirit, vaporized and super heated in a

vaporizer/column is passed through sieve unit. Generally there are two sieve units. One is under adsorption

while the other is under regeneration. The cycle time for adsorption and regeneration varies from 5 to 10

minutes. Thus forms Absolute Alcohol of desired 99.8% v/v purity. There is alternate Sieve Bed 2 ready for

next operation.

4) Multi-Effect Evaporation

Spent wash from the process is fed into bio-digester thus result in recovery of bio-gas and also reduce the

COD and BOD. Then after spent wash will be sent in multi effective evaporator. Whole process is under

vacuum and vapor generated are compressed and used as steam. Condensate water generated from

evaporation will be recycled back into the process.

Page 9: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

5

PROCESS FLOW DIAGRAM OF MOLASSES BASED DISTILLERY AFTER PROPOSED

Water requirement and waste water generation for 35 KLPD molasses distillery

WATER CONSUMPTION KLD WASTE WATER GENERATION KLD

For Fermentation 263 Drift + Evaporation + pure from

cooling from tower 93

For Dilution 21 Spent Lees 4

For Cooling Tower 187 Spent Wash 373

For Boiler 28 Steam condensate Evaporation Losses 28

Miscellaneous 5 Miscellaneous 5

Domestic 2 Domestic 2

TOTAL 506* TOTAL 506

*Above table represents maximum fresh water requirement.

2.4 RAW MATERIALS REQUIREMENT

Details of raw material consumption are given in following table.

LIST OF RAW MATERIALS

Sr.

No.

Name of the Raw

Material

Existing Quantity

(MT/Month)

Additional Quantity

(MT/Month)

Total

(MT/Month)

1. Sugar Cane 93,000 -- 93,000

2. Lime 205 -- 205

Molasses Storage

and Handling

Fermentation

Multi-Pressure

Distillation

Spent wash

Rectified spirit/ Anhydrous

Alcohol

Bio -

Methanation

Multi-Effect Evaporator

Condensate

Process/Cooling

Sent for Bio -

composting

Bio-gas

recovered

Page 10: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

6

Sr.

No.

Name of the Raw

Material

Existing Quantity

(MT/Month)

Additional Quantity

(MT/Month)

Total

(MT/Month)

3. Sulphur 47 -- 47

4. Phosphoric Acid 4.5 -- 4.5

5. Hydrochloric Acid 0.01 -- 0.01

6. Caustic Soda (Sodium

Hydroxide) 1.11 10.5 11.61

7. Urea -- 0.8 0.8

8. Antifoam Agent -- 1.74 1.74

9. Molasses (From own

Sugar factory) -- 4,200 4,200

10. Yeast (Active Dry

Yeast/Distiller’s Yeast) -- Own Propagation

2.5 RESOURCE OPTIMIZATION / RECYCLING AND REUSE IN THE PROJECT

Water as a resource is recycled at each possible step of the process and latest technology and methodology

will be adopted to conserve and reuse the resources. Waste water generated from the process goes to ETP and

treated water after pH corrections is used back again into the various processes and remaining is used for the

horticulture purposes.

2.6 AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT AND

SOURCE

2.6.1 WATER REQUIREMENT

For the proposed project additional 506 m3/Day water will be required. Existing water required of the sugar

plant is 428.7m3/Day, after proposed project total water required will be 934.7m

3/Day. Source of water for

existing unit is Borewell/ Canal and for the proposed distillery unit surface water (i.e canal water) will be

utilized.

2.6.2 POWER REQUIREMENT

For proposed project additional power requirement will be 400 KW/Hr. Existing connected Power load is

299.10 KWH/MT. Power supply shall be full-filled by Dakshin Gujarat Vij Company Limited.

2.6.3 FUEL REQUIREMENT

SR.

NO. FUEL

DAILY FUEL CONSUMPTION SOURCE & MODE OF

TRANSPORTATION EXISTING PROPOSED TOTAL

1. Diesel 15 Lit / Hr -- 15 Lit / Hr From Nearest Petrol Pump

2. Baggase 40 MT / Hr 1.9 MT/Hr 41.9 MT/Hr Within own sugar factory

premises

2.7 QUANTITY OF WASTES TO BE GENERATED (LIQUID, AIR AND SOLID) AND THEIR

MANAGEMENT / DISPOSAL

2.7.1 WASTE WATER GENERATION

For the proposed project additional 506 m3/day water will be generated. Existing waste water generation of

the sugar plant is 563.71m3/day, after proposed project total waste water generation will be 1069.71m

3/Day.

Waste water generated from the proposed distillery unit in the form of spent wash will be concentrating in

multi effective evaporator and then sent for bio-composting. Condensate from MEE will be recycled back to

the process, while spent less and other waste water will be treated in ETP units and treated water will be used

for the bio-composting. Thus achieve the’ Zero Liquid Discharge’.

Page 11: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

7

2.7.2 AIR POLLUTION

EMISSIONS FROM COMBUSTION OF FOSSIL FUELS FROM STATIONARY OR MOBILE

SOURCES

SR.

NO. STACK ATTACHED TO

STACK

HEIGHT IN

METER

AIR POLLUTION

CONTROL

DEVICES

PARAMETER

EXISTING

1. Boiler No. 1

(Bidrum Water Tube 50t/Hr) 45.0 (common

stack)

Ventury Type Wet

Scrubber

PM < 150 mg/nm3

SO2 < 100 ppm

NO2 < 50 ppm

2. Boiler No. 2

(Bidrum Water Tube 30t/Hr)

Ventury Type Wet

Scrubber

PM < 150 mg/nM3

SO2 < 100 ppm

NO2 < 50 ppm

3. D. G. Set

(500 KVA – Stand By) 11.0 --

PM < 150 mg/nM3

SO2 < 100 ppm

NO2 < 50 ppm

PROPOSED: No any additional utilities are required for proposed project.

2.7.3 SOLID WASTE GENERATION AND THEIR DISPOSAL

The sources of solid wastes, generation and its management are as given in the following table.

SR.

NO. WASTE

EXISTING

QUANTITY

(MT/M)

PROPOSED

QUANTITY

(MT/M)

TOTAL

QUANTITY

(MT/M)

DISPOSAL

1. ETP Waste 58.0

(MT/Year) --

58.0

(MT/Year)

Collection, Storage and used as

Manure.

2.

Used Oil

1.45

(MT/Year)

0.55

MT/Year

2.0

(MT/Year)

Collection, Storage, transportation

and disposal by selling to GPCB

approved registered recyclers.

3.

Discarded

Container/Barrels/

Linear

150.0

Nos./Year --

150.0

Nos./Year

Collection, Storage and disposal

by selling to GPCB approved

registered recyclers.

Page 12: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

8

CHAPTER-3 SITE ANALYSIS

3.1 CONNECTIVITY

3.1.1 RAIL

The nearest railway station is Maroli Railway station, which is around 2 km in west direction from the project

site.

3.1.2 ROAD

The site is well connected by road network to all the key places. The major highway passing near the project

site is NH - 8 which is approximately 6 km East direction from the project site.

3.1.3 AIR

The nearest airport from the project site is Surat Airport. The distance of airport from project site is around 21

km in North West.

3.1.4 COMMUNICATION

Project Site is well connected with telephone, telefax etc. all the communications facilities are well developed

in the district.

3.2 TOPOGRAPHY

Topography of the land is plane.

3.3 EXISTING LAND USE PATTERN

There is no Forest, National park; Wild life sanctuary within a radius of 10 Km. For the proposed project

existing infrastructure land will be utilized.

3.4 EXISTING SOCIAL STRUCTURE

Project site is located at a distance of around 9 km from Navsari city. All the infrastructures are available

within city like Schools, Hospitals & community facilities.

Page 13: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

9

CHAPTER – 4 PLANNING BRIEF

4.1 PLANNING CONCEPT

Molasses is the by-product in processing sugar cane for production of sugar. In general the molasses

production is about 4.5% on cane crushed. The Carbohydrates in Molasses are already in the form of Sugars.

Hence molasses does not need any pretreatment for production of Alcohol. Repeated evaporation and

Centrifugation decreases the sugar content of molasses and increases the viscosity and concentration of salts

and other impurities. The residual syrup thus becomes thick, viscous and brown in colour and is very heavy.

The concentration of molasses is normally measured in Brix.

Molasses Scenario of India

Details of Molasses Production in India (Source-Indian Sugar Mills Association)

Season 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14

Molasses

Production 6.542 8.40 10.97 11.824 11.744 10.881

4.2 LAND USE PLANNING

The plant general layout has been planned considering production facilities, auxiliary and ancillary facilities

and plant utilities & services. Out of the total plot area (1,53,262 m2) around 8000 m

2 of open area from the

existing unit will be utilized for the distillery plant.

4.3 AMENTIES / FACILITIES

Adequate storage facility for chemicals, machinery spares and consumables shall be provided. A small

mechanical and electrical/ instrument workshop facilities for repairs and maintenance shall be provided. Time

and security offices shall be provided in the plant. To avoid fire hazard, internal fire hydrants system unit will

be provided.

Page 14: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

10

CHAPTER – 5 PROPOSED INFRASTRUCTURE

5.1 INDUSTRIAL AREA

No new land will be acquired for the proposed project. Out of total land area (i.e. 1,53,262 m2) around 8,000

m2 open land area will be utilized for the proposed distillery unit.

5.2 RESIDENTIAL AREA

There is no provision of housing for the employees at site.

5.3 GREEN BELT

The main objective of the green belt is to provide a barrier between the source of pollution and the

surrounding areas. The green belt helps to capture the fugitive emission and to attenuate the noise generated

apart from improving the aesthetics. Development of green belt and other forms of greenery shall also prevent

soil erosion and washing away of topsoil besides helping in stabilizing the functional ecosystem and further to

make the climate more conducive and to restore water balance. The company has green belt area with Lawn,

plants and flowers spread across about 33% of the total area. Further it will be developed at plant boundary,

road side, around offices & buildings and Stretch of open land.

The selection of tree species suitable for plantation at the industry are governed by guiding factors as stated

below:

• The trees should be tolerant to air pollutants present in the area

• The trees should be able to grow and thrive on soil of the area, be evergreen, inhabitant, having

minimum of leaf fall.

• The trees should be tall in peripheral curtain plantation and with large and spreading canopy in

primary and secondary attenuation zone.

• The trees should posses extensive foliar area to provide maximum impinging surface for continued

efficient adsorption and absorption of pollutants.

• The trees should be fast growing and indigenous and should maintain ecological, land and

hydrological balance of the region.

• It is also recommended to plant few trees, which are sensitive to air pollution, as air pollution

indicator.

• It is also recommended to carry out extensive plantation within premises.

Keeping in view the climatic conditions, status of soils and vegetation types in and around the project area the

species shall be selected for proposed green belt development.

5.4 SOCIAL INFRASTRUCTURE

Drinking water facility, proper sanitation, etc. will be provided to the workers working in plant.

5.5 CONNECTIVITY

As discussed earlier, proposed location of the plant is already well connected with the network of road & rail.

So there is no need to construct any new road or rail for the transportation.

5.6 WASTE WATER MANGAMENT

Waste water generated from the proposed distillery unit in the form of spent wash will be concentrating in

multi effective evaporator and then sent for bio-composting. Condensate from MEE will be recycled back to

the process, while spent less and other waste water will be treated in ETP units and treated water will be used

for the bio-composting. Thus achieve the’ Zero Liquid Discharge’.

Page 15: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

11

5.7 INDUSTRIAL SOLID WASTE MANAGEMENT

From the proposed project activity detail for the solid/hazardous waste generation are given in below table.

DETAILS OF SOLID & HAZARDOUS WASTE GENERATION DURING OPERATION

SR.

NO.

NAME OF

THE

WASTE

CAT

NO.

EXISTING

(MT/YEAR)

ADDITIONAL

(MT/YEAR)

TOTAL

(MT/YEAR

)

METHOD OF

STORAGE &

DISPOSAL

1. ETP Waste 34.3 58.0

(MT/Year) --

58.0

(MT/Year)

Collection, Storage

and used as Manure.

2.

Used Oil

5.1 1.45

(MT/Year) 0.55

MT/Year

2.0

(MT/Year)

Collection, Storage,

transportation and

disposal by selling to

GPCB approved

registered recyclers /

reuse.

3.

Discarded

Container/Ba

rrels/ Linear

33.3 150.0

Nos./Year --

150.0

Nos./Year

Collection, Storage

and disposal by selling

to GPCB approved

registered recyclers.

Page 16: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

12

CHAPTER – 6

REHABILITATION AND RESETTLEMENT (R & R) PLAN

The project is located on private land, which is already acquired and there is no habitat. So the project

proposal does not involve any Rehabilitation & Resettlement.

Page 17: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

13

CHAPTER – 7

PROJECT SCHEDULE & COST ESTIMATES

7.1 TIME SCHEDULE FOR THE PROJECT

The implementation of the project will involve major activities like preparation of specification / drawings,

issue of tenders, receipt of quotations, scrutiny of tenders, placing of orders, civil & structural construction,

delivery & erection of equipment, test trial runs of various items of equipment and commissioning of the plant

& equipment and completion of the project will take about 6 months after the necessary clearances are

available, and the funding for the project has been tied up.

7.2 ESTIMATED PROJECT COST

The total cost of the project after proposed project will be around Rs. 30 crores. Total capital cost of pollution

control measures will be Rs. 3 crores & recurring cost per annum will be 1 crores.

7.3 BUDGETORY PROVISIONS FOR EMP

Adequate budgetary provisions have been made by the management for execution of environmental

management plans. The details of capital and recurring (per annum) budget earmarked for pollution

control / monitoring equipment; operation and maintenance of pollution control facilities, for greenbelt

development and maintenance.

COST OF ENVIRONMENTAL PROTECTION MEASURES

SR.

NO. PARTICULATES RS. IN CRORE

1. Capital Expenditure 3.0

2. Recurring expenditure on environmental management cell and on

pollution control systems per annum. 1.0

Page 18: PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD MOLASSES ...environmentclearance.nic.in/writereaddata/Online/TOR/0_0_27_Jan_2016... · PRE - FEASIBILITY REPORT FOR PROPOSED 35 KLPD

14

CHAPTER – 8

ANALYSIS OF PROPOSAL

8.1 FINANCIAL AND SOCIAL BENEFITS

The capital cost of the distillery unit in existing premises is estimated about Rs. 30.0 Crores for the

installation of plants & machinery along with required auxiliary and balancing facilities for the production.

For the coming of this project surrounding area will get developed due to this project and through the

Corporate Social Responsibility (CSR) activities, socio-economic status of the region will also get developed.


Recommended