+ All Categories
Home > Documents > Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR ›...

Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR ›...

Date post: 26-Jun-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
38
Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in ML Area of 1751.92 ha (by Open Cast Mining) At Hasdeo Arand Coalfield, Korba District, Chhattisgarh Project Proponent Chhattisgarh State Power Generation Company Limited, Raipur, Chhattisgarh Submitted to Ministry of Environment Forest & Climate Change (MoEF&CC) New Delhi September, 2017
Transcript
Page 1: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Pre-Feasibility Report

For

Proposed Gidhmuri &Paturia Coal Mine

of 5.6 MTPA Capacity in ML Area of

1751.92 ha (by Open Cast Mining) At

Hasdeo Arand Coalfield, Korba District, Chhattisgarh

Project Proponent

Chhattisgarh State Power Generation Company Limited, Raipur, Chhattisgarh

Submitted to

Ministry of Environment Forest & Climate Change (MoEF&CC) New Delhi

September, 2017

Page 2: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

CONTENTS

Sr. No. Title Page no.

1 EXECUTIVE SUMMARY 1

2 INTRODUCTION OF THE PROJECT 1

3 PROJECT DESCRIPTION 3

4 SITE ANALYSIS 16

5 PLANNING BRIEF 25

6 PROPOSED INFRASTRUCTURE 31

7 REHABILITATION AND RESETTLEMENT (R&R) PLAN 33

8 PROJECT SCHEDULE & COST ESTIMATES 34

9 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) 35

Page 3: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

1.0 EXECUTIVE SUMMARY

Sr .No Description Details

1. Name of the Project Paturia & Gidmuri open cast coal mine

2. Total land requirement for the ML area of 1751.92 ha for 30 years project

3. Mineable reserves Open cast : 158.40 million tonnes

4. Total overburden generation 644.95 million m3

5. Quantity of external dump 25.65 million m3

6. Quantity of internal dump 619.30 million m3

7. Total External dump area 101.26 ha

8. Top soil thickness 5-60 m including overburden

9. Average stripping ratio (coal: 1: 4.25

overburden)

10. Method of mining Opencast mining by shovel-dumper

11. Ultimate depth 130 m bgl

12. Maximum production capacity 5.6 MTPA

13. Expected life of mine 30 years

14. Working hours 3 shift per day of 8 hrs in 330 days of operation in a year

15. Quarry floor area 1751.92 ha

16. Quarry surface area 1476.66 ha (Q1-360.24 +Q2 443.89 +Q3 596.05 + Q4 76.48 ha)

17. Number of seams/sections 5 coal seams

18. Average seam gradient 20 to 5

0

19. Maximum bench height 10-35 m

20. Bench width Coal : 60 m

21. Water requirement (Mine) 1281 m3/day

22. Power requirement & source 80 MVA of power is required for the mine and will be sourced from Chhattisgarh State Power Distribution Company Limited

23. Manpower requirement Option-1 Option-2

Manpower 991 nos 1088 nos

24. Colony area 1500 sq ft per family (1088)

25. Rehabilitation and Resettlement About 485 numbers of household involving about 2036 project person (as per census 2011) will be affected and suitable R & R package will be implemented as per norms of Government of Chhattisgarh.

2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

(i) Identification of project and project proponent.

Chhattisgarh State Power Generation Company Limited (CSPGCL) is proposing Gidhmuri & Paturia coal blocks opencast mining with capacity of 5.6 MTPA

at Hasdeo Arand Coalfield, Korba District, Chhattisgarh to meet requirement for the

thermal power plant of a capacity of 2 X 660 MW at Bhaiyathan in Chhattisgarh

State.

Chhattisgarh State is fortunate that it has immense possibilities of coal based

thermal power generation. At the national level one finds several States suffering

from serious power crisis. Looking to abundant availability of coal in the state,

1

Page 4: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Chhattisgarh would be developed as a 'Power Hub' of the nation from where power

would be exported to other needy States.

Chhattisgarh State Power Generation Company Limited (CSPGCL) is emerging as the

epicentre of “Power" of the nation it is constituted on 15th

November 2000. Ministry of Coal and Mines, Government of India has allotted Gidhmuri & Paturia coal blocks

to CSPGCL located in Hasdeo-Arand coalfield area on 13th

October 2015 (order no: 103/28/2015/NA) to meet the requirement of 5.6 MTPA coal for proposed coal based power plant at Bhaiyathan.

The Mining Plan (April, 2007) of Gidhmuri & Paturia coal blocks (Hasdeo Arand

Coalfield), (5.6 MTPA) has been approved by Ministry of Coal, Govt. of India vide its

letter No. 47011/1(22)/2002-CPAM/CA-1 Dtd 06-September-2007. The approval

conveyed under section 5(2) (b) of the Mines & Minerals (Development &

Regulation) Act, 1957.

(ii) Brief description of nature of the project.

The proposed Paturia Gidhmuri opencast mine of 5.6 MTPA capacity is a captive coal mine to supply the coal for proposed thermal power plant at Bhaiyathan, which will

fulfill the future power requirement of Chhattisgarh State and will accelerate the

economic development of the State.

The Gidhmuri & Paturia Block is in area of about 1751.92 ha and are situated in the western part of Hasdeo-Arand Coalfield. The total coal reserves by open cast coal

mining is 158.40 million tonnes.

(iii) Need for the project

The mineral wealth of a nation is an important feature in its economic progress, and mining in India has a vital role in the development. Chhattisgarh has a glorious

heritage in the field of natural resources, mines and minerals. The state is

geologically so endowed that it has become a veritable repository of minerals.

Detailed investigations were confined so far to major minerals only that are coal. For

the development of more and more coal based power plant and to cater the needs

of power plant emphasis is given on investigation of coal.

Search and exploration of coal in the State during last few years has resulted in the

discovery of several coal deposits in Hasdeo Arand coal field. These are large workable reserves and their mining has already been started. The State is in the

process of becoming power hub of the country because of abundant deposits of coal

have been reserved for power generation.

Electricity is the key for development. All sectors viz. industrial, agriculture and

social require electric power for their growth and development. There is a substantial gap between demand and availability of electricity in the nation. In the

direction to fulfil this gap, coal based Bhaiyathan power plant is being proposed to

setup at Chhattisgarh state. Proposed Paturia–Gidhmuri mine is an essential

component of the aforesaid project.

About 67% of the power plants in India are coal based. The proposed Paturia,

Gidhmuri opencast mine of 5.6 MTPA capacity which is a captive coal mine of

Chhattisgarh State Power Generation Company Limited (CSPGCL) will whole out the

coal to proposed thermal power plant at Bhaiyathan, which will fulfil the future power requirement of Chhattisgarh State and will bring the economic development

in the State.

2

Page 5: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

(iv) Demand-Supply Gap

The development is directly proportional to the increase in demand of basic facilities

like water and electricity. Presently 1694.35 MW of gross electricity is available and

restricted demand of electricity as on date is around 1965 MW and unrestricted

demand is 2208 MW. Out of gross capacity, 1410.05 MW power is generated by

CSPGCL. The details are given in Table–1 below.

TABLE-1

POWER STATION WISE INSTALLAED CAPACITY (As on 31.03.2017)

Installed Thermal Capacity 3280.00 MW

Installed Hydel Capacity 138.70 MW

CSEB's Gen. Capacity 3424.70 MW

(v) Import vs. Indigenous production

There will not be any import for the proposed open cast of Gidhmuri &

Paturia coal blocks.

(vi) Export Possibility

The Coal will not be exported from the proposed open cast of Gidhmuri & Paturia coal blocks.

(vii) Domestic / export Markets.

The proposed Paturia,

have been allotted to

(CSPGCL) by Ministry

mentioned above.

Gidhmuri opencast coal mine in Hasdeo Arand coal field

Chhattisgarh State Power Generation Company Limited of

Coal, Govt. of India for end use of their projects as

(viii) Employment Generation (Direct and Indirect) due to the project.

About 1088 persons will get direct employment in various services upto target

achieving year and about 5000 person will get indirect employment, which will

develop due to the project and the persons employed in the project.

3. PROJECT DESCRIPTION

3.1 Type of project including interlinked and interdependent projects, if any.

The proposed Paturia, Gidhmuri opencast mine of 5.6 MTPA of capacity which is a

captive coal mine of Chhattisgarh State Power Generation Company Limited (CSPGCL) will supply the coal to the proposed thermal power plant at Bhaiyathan

thermal power plant (2X660 MW).

3.2 Location

The Paturia-Gidmuri blocks is located at about 75 km from Ambikapur on Ambikapur-Bilaspur highway in Korba district of Chhattisgarh State. The location

map, study area map and goggle image are given in Figure-1, Figure-2 and Figure-3.

3

Page 6: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Paturia and Gidmuri Blocks Co-ordinates :

The Gidhmuri & Paturia blocks, are explored by M.E.C.L, occupies an area of

about 17.51 Sq km and is situated in the western part of the Hasdeo-Arand Coal field.

Latitude from: 22o45’28.252” N to 22

o47’24.111” (N)

Longitude from: 82o40’51.794” to 82

o45’57.913” (E)

3.3

Details of

selecting

environmental highlighted.

alternate sites the proposed

considerations

considered

site,

gone

and the basis

particularly

into should

of

the

be

No alternative site for this project could be envisaged. As mining in coal block area

is due to site specific location of deposition of coal deposit.

3.4 Size or magnitude of operation

Chhattisgarh State Power Generation Company Limited (CSPGCL) is

proposing Gidhmuri & Paturia coal blocks by opencast mining with capacity of 5.6

MTPA at Hasdeo Arand Coalfield, Korba District, Chhattisgarh to meet requirement

for the thermal power plant of capacity of 2 X 660 MW at Bhaiyathan in Chhattisgarh

State.

This output is prima facie considered technically feasible because of its favourable geo-mining conditions like:

Thickness of various seams; Their disposition & its splits; Comparatively long strike length; and Sufficient mineable coal reserves etc.

3.5 Project description with process details

3.5.1 Physiography

Mining of coal is carried out by opencast, which is approved by Ministry of Coal for Gidhmuri & Paturia block. Open cast mining is preferred where, there is no hard

cover or the extractable coal reserve is in economical stripping limits.

3.5.2 Regional Geology

Gidhmuri & Paturia blocks lie in western part of Hasdeo Arand coal field. Where the

coal blocks are broadly delineated by the Rehar river (known as Arand river) in the

east and Hasdeo river in the West thus the coal field has been named as Hasdeo Arand coal field.

Hasdeo-Arand Coalfield is bound by vast stretch of Talchir Precambrian formations in

the North-West is represented by gneisses in the East. Mand-Raigarh & Korba

coalfield in the west. Supra-Barakars (Kamthis) occur in the south eastern part of

the coalfield. Based on G.S.I report (1982-1985) geological formation of the Hasdeo-Arand Coalfield is given in Table-2.

4

Page 7: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE-1 LOCATION MAP OF GIDHMURI & PATURIA COAL BLOCKS

5

Page 8: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE-2 STUDY AREA MAP OF GIDHMURI & PATURIA COAL BLOCKS

6

Page 9: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE-3 GOOGLE IMAGE OF GIDHMURI & PATURIA COAL BLOCKS

7

Page 10: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

TABLE-2

GEOLOGICAL FORMATION OF HASDEO-ARAND COALFIELD

Age Formation Lithology

Recent Soil/Alluvium

Cretaceous Deccan Traps Basic flows and dykes

Upper Permian Kamthi formation Sandstone, Ferruginous shale, Buff

Sandstone and pebble beds

------------------------ Unconformity ----------------------

Barakars ( 300-400 m) Feldspathic sandstone, Carbonaceous Karharbari (100 m) shale, Coal seams, conglomerate at

Permian Talchir base.

Sandstone Shale, Coal seams Green & Khaki Green shale.

------------------------ Unconformity ----------------------

Pre-Cambrian Gneisses, Quartzites

3.5.3 Geo Mining Characteristics

Strike & Dip

Paturia

The general trend of the strike of the seams over larger part of the block is East-West to WNW-ESE. However, there is local variation in the strike of the central part

where it becomes NNE-SSW. The dip of the formation in general is 10 to 4

0 towards

south west.

Gidhmuri

The Gidhmuri block forms part of plunging anticline structure with its plunge axis in

NW-SE direction. However, this anticlinal structure has been dissected by fault. The

wide range of dip and strike vacation may be attached to the location of the block on

this anticline.

The general trend of the strike of the seams is East-West in the western and south western part. The strike swings to N-S in the eastern and southern part. The dip of

the formation in general is 20 to 5

0 easterly in the eastern, central and southern

part and almost southerly in the south western part.

3.5.4 Seam Description

Barakar formation occurs in Gidhmuri & Paturia blocks beneath the soil cover while

Talchir formation are not exposed they have been only intersected in some

boreholes.

Gidhmuri block has developed 5 coal seams viz I, II, III, IV & V seams in ascending

order Seam-I is a very thin seam (mostly <0.9 m) in entire Gidhmuri block and is

not suitable for mining. Seam II is thin seam (0.10 m-1.20 m) and lies with

substantial parting of around 60 m with seam III in Gidhmuri block. Seam III is most potential seam (7-8 m) in this block.

In Paturia block four coal seams have developed, seam-I, II, III, and IV is developed in ascending order. Seam-II occurs in split as well as composite seam.

The seam underlies seam-III (Bottom seam) with a parting ranging 13 to 21 m has

8

Page 11: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

only U/G potentiality. Seam-III splits into three sections over the entire Paturia

block designated as III Top III Middle & III Bottom sections. For opencast

consideration two sections of III TOP have been considered as composite seam (III

TOP-1 + III TOP-2 with intervening parting which on western side in Paturia block.

The seam extractable coal reserves are given in Table-3.

TABLE-3

SEAM EXTRACTABLE COAL RESERVES

Sr. Seam Total extractable Reserves (Mtes) for Gidhmuri & Paturia No Blocks

Quarry-1 Quarry-2 Quarry-3 Quarry-4 Total

a III Bottom 2.48 21.68 11.81 35.97

b III Top (Merged) 37.96 51.03 72.93 25.83 187.75

c IV 7.08 3.56 3.12 3.04 16.80

d V 1.96 0.84 -- -- 2.80

Total for 48 years

e Total 47.00 57.91 97.73 40.68 243.33

f Total OBR (Mm3) 185.89 229.23 443.77 309.81 1168.71

g S. Ratio (m3/te) 3.95 3.96 4.54 7.62 4.80

Total for 30 years

Total 36.95 45.05 72.45 3.95 158.40

Total OBR (Mm3) 141.73 168.15 297.71 37.35 644.95

S. Ratio (m3/te) 3.84 3.73 4.11 9.45 4.07

Quarry Parameters

h Dip of seams 2-5 1-5 2-4 2-5

(Degree)

i Strike length (km) 2.1 2.8 3.5 2.2

j Maximum depth 110 100 110 130

(m)

3.5.5 Production capacity & Calendar Programme

The production programme is proposed with two options i.e Option -1 and Option-2

are given in following Table-4.

Option-1 : Shovel and Dumper combination with dragline Option-2 : Shovel and Dumper combination without dragline

TABLE-4 PRODUCTION PROGRAMME

Year 1 2 3 4 5 6th

-30th

Total onwards

Option-I

Coal (MT) 1.00 2.20 4.00 5.60 5.60 140.00 158.40

OB (MCum) 2.60 4.13 7.88 11.21 12.45 606.68 644.95

SR (Cum/te) 2.60 1.88 1.97 2.0 2.22 4.33 4.07

Option-II

Coal (MT) 1.00 2.20 4.00 5.60 5.60 140.00 158.4

OB (MCum) 5.29 6.39 9.80 13.95 14.43 624.09 673.95

SR (Cum/te) 5.29 2.91 2.45 2.49 2.58 4.46 4.25

3.5.6 Geological & Mining Characteristics

The Geological & mining characteristics of Gidhmuri & Paturia open cast mine (5.6 MTPA) is given in Table-5 (A) and Table-5 (B). A total no of 5 coal seams is occurring within the above quarriable area. Out of these. Seam-III Top (Merged)

is the thickest and most prominent seams. The coal dipping at a gradient of 20-5

0

towards the south.

9

Page 12: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

TABLE-5(A) GEOLOGICAL & MINING CHARACTERISTICS

Option-1 Shovel & Dumper Combination with Dragline

Sr No Seam Extractable Reserves (Mtes) considered for proposed mining plan for 30 years

Quarry-1 Quarry-2 Quarry-3 Quarry-4 Total

a) III Bottom 2.48 16.65 1.05 20.18

b) III Top 31.35 41.14 53.92 2.77 129.18 (Merged)

c) IV 4.54 1.41 1.88 0.11 7.93

d) V 1.06 0.03 - - 1.09

e) Total 36.95 45.05 72.45 3.95 158.40

f) Total 141.73 168.15 297.71 37.35 644.95 OBR(Mm

3)

g) S.Ratio 3.84 3.73 4.11 9.45 4.07 (m3/te)

TABLE-5(B) GEOLOGICAL & MINING CHARACTERISTICS

Option-2 Shovel & Dumper Combination without Dragline

Sr No Seam Extractable Reserves (Mtes) considered for

proposed mining plan for 30 years

Quarry-1 Quarry-2 Quarry-3 Quarry-4 Total

a) III Bottom 2.48 16.44 1.05 19.97

b) III Top 30.72 41.14 54.00 2.77 128.63 (Merged)

c) IV 4.99 1.41 2.01 0.11 8.52

d) V 1.23 0.03 - - 1.26

e) Total 36.95 45.06 72.45 3.95 158.40

f) Total 148.51 168.16 319.95 37.35 673.97 OBR(Mm

3)

g) S.Ratio 4.02 3.73 4.42 9.45 4.25 (m3/te)

3.5.7 Product –Mix Quality

The average product mix quality of coal seams from all the quarries (Quarry-1, 2, 3 & 4) is Grade-E (Avg. ash 31.54 %, Avg. UHV 3738 (KCal/Kg). The Average range

of quality and seam mix in Quarry-1, Quarry-2, Quarry-3 and Quarry-4 planned in

Paturia and Gidmuri block is given in Table-6.

TABLE-6

SEAM WISE AVERAGE QUALITY IN PROPOSED QUARRY & PRODUCT MIX

QUALITY

RESERVES SEAM M % ASH% UHV Grade Sp Gr (Mtes) (K Cal/Kg)

1.96 V 5.94 40.073 2549.2 F 1.68

Quarry-1 7.09 IV 4.32 47.32 1767 G 1.75

37.96 IIITOP 5.47 32.94 3662 E 1.61

Total-Q1 47.01

Average (Quarry-1) 5.07 35.41 3330 F 1.63

0.84 V 6.3 42.83 2044 G 1.7

Quarry-2 3.56 IV 5.79 43.39 2114 G 1.71

10

Page 13: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

51.03 III TOP 5.67 33.34 3528 E 1.61 2.48 III BOT 7.13 21.37 5051 C 1.49

Total-Q2 57.91

Average (Quarry-2) 5.75 33.58 3485 E 1.61

3.12 IV 5.12 39.07 2788 F 1.67

Quarry-3 72.97 III TOP 6.14 30.94 3753 E 1.58

21.64 III BOT 6.67 21.54 5014 C 1.49

Total-Q3 97.73

Average (Quarry-3) 6.23 29.05 4010 E 1.57

Total(Q1+Q2+Q3) 202.65

Average(Q1+Q2+Q3) 5.82 31.85 3698 E 1.59

3.04 IV 5.28 44.63 2020 G 1.72

Quarry-4 25.83 III TOP 5.78 32.41 3630 E 1.6

11.81 III BOT 6.59 20.69 5113 C 1.48

Total-Q4 40.68

Average(Quarry-4) 5.97 29.92 3940 E 1.58

Total (Q1+Q2+Q3) 243.33

Q1+Q2+Q3+Q4 Average 5.85 31.53 3738 E 1.59

3.5.8 Opencast Mine

As per GRs of Gidhmuri and Paturia Blocks, the reserves of all the seams beyond 1:5, coal to OB cut off ratio have been earmarked for U/G working and the reserves

were calculated on I30 basis. On detailed techno economic study it was found that all

the reserves upto seam-III (geological reserves 280.83 Mtes) can be economically

mineable by opencast method of mining upto 48 years. The reserves were

recalculated on I100 basis. Accordingly, the detail of open cast reserves in both

Gidhmuri & Paturia Blocks are given in Table-7. TABLE-7

OPEN CAST RESERVES

Sr. Geological Opencast Reserves Quarries Planned

No Blocks Net Geological Seams considered

Reserves (Mte)

a Paturia 200.561 IIB, IV and V Quarry-3 & Quarry-4 and part of Quarry-2

b Gidhmuri 80.268 III Top, IV, V Quarry-1 and part of Quarry-2

Total 280.829 IIB, IIT, IV and V Quarry-1, Quarry-2, Quarry-3 & Quarry-4

Net Geological Reserves as per Geological Report of Gidhmuri and Paturia Coal Block

A total of 349.515 mt of proved net geological reserves has been estimated on I30

(U/G) from seam-V to seam-I in Gidhmuri & Paturia blocks taken together. Out of

above reserves 269.247 is contributed by Paturia block from scam-IV to seam-I and

80.268 mt has been contributed from seam-V to Seam-III Top composite seam.

A total of 68.686 mt of proved Net geological Reserve has been estimated 0 from

seam-II & seam-I in Paturia block. This reserve is contributed by thin seams which

lies with considerable parting of around 60 m can be mined only by the U/G mines.

Excluding these reserves 280.829 mt of reserves is available from Paturia and

Gidmuri block from seam-III Bottom to seam V. A total of 200.561 mt is reserve is

available from Paturia block from seam IV to III bottom seam and balance 80.268 mt is reserve is available from Paturia block from Seam IV to III Bottom seams

which includes 16.054 mt quarriable reserve estimated up to 1.5 cut ratio.

11

Page 14: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Reserves (Geological, Mineable and Extractable)

Opencast Mine

The mineable reserves of opencast mine for Gidhmuri & Paturia Blocks are given in

Table-9. The balance sheet of net Geological Reserves of opencast mine for

Gidhmuri & Paturia Blocks are given in Table-10.

TABLE-9

MINEABLE RESERVES (Upto 48 years)

Coal Av. Net Extractable reserves

seams Thickness Geological ( Mte)

(M) Reserves Quarr Quarr Quarr Quarr Total

%Extrac

( Mte)

y-1

y-2 y-3

y-4 tion

V 1.8 3.78 1.96 0.84 - - 2.80 73.81

IV 3 19.88 7.08 3.56 3.12 3.04 16.80 84.56

III Top 8 236.42

37.96

51.03 72.93

25.83

187.75 79.43

(Merged)

IIIB 3 49.60 - 2.48 21.68 11.81 35.97 72.44

Total 309.68 47.00 57.91 97.73 40.68 243.33 78.57

TABLE-10 BALANCE SHEET OF NET GEOLOGICAL RESERVES

Extractable reserves 243.33 Mtes

Mining losses 16.81 Mtes

Coal blocked in the batter of the quarries 30.54 Mtes

Coal blocked in the safety zone 19.00 Mtes

NET Geological reserves (I30 basis) 309.68 mtes

Transportation of Coal

It is proposed that coal from the mine will be dispatched by rail/road. The proposed railway siding for this mine has to be provided by CSEB. Empty rake would be

brought near the loading point below Silo. Rake will remain attached to the pilot

engine during loading operation. After loading the wagons, the pilot will move

through M.G.R bulb to reach the terminal station or its destination without

decoupling of locomotive. Here provision has been made by rapid load out system to

load minimum six rakes per day by silos and bunker in combination with reclaim & loading conveyors. The formation level of loading point has been assumed as ground

level.

3.6 Raw materials required along with estimated quantity, likely source, marketing area of final product/s, Mode of transport of raw material and finished product.

No raw material is required as this is a mining activity. Only diesel would be

required for transportation of vehicles, operation of HEMM and generators in case of emergency. Coal from Mine after weighing the trucks will be unloaded at insitu

crusher to reduce the size less than 200 mm. From the crusher units the coal will be

transported to the coal surface storage bunker by conveyor system. From the

surface bunker, coal will be transported to Power station through road/railway. The

overburden will be removed using shovels/backhoes and will be transported with a

fleet of Rear discharging dumpers.

12

Page 15: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

3.7 Resource optimization/ recycling and reuse envisaged in the project, if any,

should be given.

Resources like Explosives, Diesel Oil, Machinery, Land, Power and Water are fully optimized to minimize unnecessary losses during the process of excavation and

supply of coal to the customers. The production capacity from Mine will be 5.6

Million Tonnes per annum at peak requirement. The coal does not require

beneficiation. The resources which are used in the mining will be recycled by various

methods. Sludge generated from domestic wastewater treatment will be composted

and used as manure. Spent oil from transformers, will be sold to the authorized

vendors. The ground water pumped for safe mining will be used for drinking water. Mine sump water collected at settling pits shall be discharged from quarry through

pumps and used for dust suppression, mining activity, irrigation to surrounding

villages.

3.8 Availability of water its source, Energy/ power requirement and source

should be given.

3.8.1 Power

The proposed mine will get power from CSPDCL substation and power will be distributed by 33 KV line.

Electric power will be supplied for pumping and illumination for the opencast mine as the major equipment of Gidhmuri & Paturia. The power requirement for the mine will

be 80 MVA.

Standby DG Sets of adequate capacity. Fuel requirement will be about 172 KL/day of HSD.

3.8.2 Water Supply & Sewerage

It is proposed that requirement of potable water requirement is met from ground

water resources. For meeting the initial industrial water requirement also ground water resources may be utilized. After the mine starts production i.e. attains full

production capacity the mine inflow water will be recycled to meet industrial water

demand. Demand of potable water is proposed to be met by ground water source by

making bore wells and distributed through ground reservoir. Industrial water

demand is proposed to be met from bore wells. The water will be stored in ground

reservoir and distributed through overhead storage tanks located at suitable points.

Domestic and industrial effluent will be disposed of after suitable treatment in the effluent treatment plants (STP/ ETP) located in colony and industrial area.

3.9 Quantity of wastes to be generated and scheme for their Management/ disposal.

Solid waste:

Out of the total volume of OB estimated of 644.95 Mm3, only 25.65 Mcum is

proposed to be dumped externally while the remaining 619.30 Mcum of OB is proposed to be dumped internally. The maximum RL of all the dumps is +520m. Due to the fact that the seams are very gentle in gradient and overall geology amenable to internal dumping, external dumping requirement is very less (2.2% of total dumping needs). All the external dumps will be accommodated in non-forest zone.

13

Page 16: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

TABLE-11

CAPACITY OF DUMPS (MCUM) – UPTO 30TH

YEAR OF QUARRY OPERATION

EXTERNAL DUMP 1 7.67

EXTERNAL DUMP 2 8.35

EXTERNAL DUMP3 9.63

TOTAL EXTERNAL 25.65

INTERNAL DUMP 1 54.06

INTERNAL DUMP 2 80.00

INTERNAL DUMP 3 36.35

INTERNAL DUMP 4 127.63

INTERNAL DUMP 5 139.04

INTERNAL DUMP 6 178.33

INTERNAL DUMP 7 3.88

TOTAL INTERNAL 619.30

TOTAL DUMP CAPACITY 644.95

Land requirement for Spoil Dumping

It may be observed that the amount of OBR to be dumped externally is very less

(2.2% of total OBR), thanks to the very gentle gradient of the seams and overall geology. The external dumps have been planned keeping in view the minimization of

lead and land requirement. External OB dumps have been planned in such a way

that there is no requirement of forest land for external dumps. Non Forest Land

required for external dumping for Quarry-1, 2, 3 & 4 is 101.26 ha.

3.10 Schematic representations of the feasibility drawing which give information of EIA purpose.

Schematic diagram showing the operation of OB & coal Excavation which give

information of EIA purpose is shown below. These are the activities which are the

source for Pollution. The pollution will be mitigated effectively.

14

Page 17: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE-4

SCHEMATIC DIAGRAM SHOWING THE OPERATION OF OB & COAL EXCAVATION

Overburden Excavation

Drilling Blasting in

Hard portion of

Overburden

Excavation of

Overburden using

Shovel/Backhoe

Transportation of

Overburden through

Dumpers

Backfilling in Mined

out area

Top soil spreading in

backfilled area, Biological

Reclamation, Afforestation

and Restoration of Land

to original soil Condition

Coal Excavation

Excavation of Coal

using Shovel / Backhoe

Transportation of

Coal to Crusher

through Dumpers

Crushing of Coal to

160 mm Size

Storing of Coal in

Stockyard

Transportation of Coal from

Stockyard to Power station

Through Road /Railway

15

Page 18: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

4 SITE ANALYSIS

4.1 Connectivity.

The Paturia-Gidhmuri blocks is located near the NH-111 joining Bilaspur to

Ambikapur forms western boundary of the mine. The nearest railway station is about 100 km (by road)away from the block. Korba is 100 km (by road) SE of the

mine on Champ-Korba broad gauge loop line of South East Central Railways. Pendra

road is 82 km of the mine on Bijuri-Ambikapur section. Bisrampur 49 km NE of the

mine on Bijuri-Bisrampur broad guage loop line of the South East Central Railway.

a) Road Link

The NH-111 joining Bilaspur to Ambikapur forms western boundary of the mine.

b) Rail Link

The nearest railway station is about 100 km (by road) away from the coal block. Korba is about 100 km (by road) in SE direction of the mine on Champ-Korba broad

gauge loop line of South Eastern railways. Pendra road is 82 km of the mine on

Bijuri-Ambikapur section. Bisrampur is about 96 km (by road) in NE direction of the

mine on Bijuri-Bisampur broad guage loop line of the South Eastern Railway.

c) Air Link

Raipur is the nearest airport to the proposed coal mine, which is situated around 260 km from the project site and connected by all-weather road.

4.2 Land details

The total requirement of land for Paturia-Gidhmuri opencast coal mine has been

estimated as 1751.92 Ha including 1478.859 Ha of forest land under Bare Jhar ka

jungle. The land lease hold area, village-wise land schedule of coal mine, land use for mining and land use for mine life and of Gidhmuri & Paturia is given in Table-12

Table-13 Table-14 and Table-15 respectively

TABLE-12

LEASE HOLD AREA

Type of Land Area(ha) for proposed mining plan (30 years life)

Forest 1466.839

Non-Forest 285.081

Total 1751.920

TABLE-13 VILLAGE WISE LAND SCHEDULE OF COAL MINE

Land Type Madanpur Paturiya Gidmuri Uchlenga Total

Government Land 2.211 2.354 1.619 - 6.184

Private land 55.442 126.763 94.260 2.432 278.897

Van Adikar Patta 3.844 2.428 3.522 - 9.794

Revenue Forest 43.684 271.480 124.670 - 439.834

Orange Area - 69.517 - 33.618 103.135

Protected Forest 914.076

Total Area 105.181 472.542 224.071 36.050 1751.920

Land Requirement upto 30 Years: 1751.920 Hectares

16

Page 19: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

TABLE-14

LAND UTILISATION DURING MINING

Particulars Land Required (% ha) % Utilisation

Quarry 1476.66 84.29 %

Industrial Area (CHP, W/S etc) 52.39 2.99 %

External OB dump 101.26 5.78 %

U/G incline 0.0 0.0 %

Safety Zone/ embankment 121.61 6.94 %

Total 1751.92 100 %

TABLE-15 LAND USE FOR LIFE OF MINE

Sr.No Item Total Land (Ha.)

1 Quarry-I 360.24

2 Quarry-II 443.89

3 Quarry-III 596.05

4 Quarry-IV 76.48

5 Ext OB Dump 101.26

6 Industrial Area 52.39

7 Safety- Zone Embankment / Garland drain 121.61

8 U/G incline 0.0

Total 1751.92

Life of Mine

For the rated output of 5.6 MTPA of ROM coal and with the extractable reserves of 243.33 Mtes, the life of the open cast mine is estimated as 48 years.158.40 Mtes of coal is proposed to be mined in phase (up to 30 years) Balance reserves of 84.93

Mtes are proposed to be mined beyond 30th

year .The life has been estimated from

the year of start of excavation.

4.3 Topography and drainage

The Gidhmuri & Paturia blocks cover an area of about 1751.92 Hectares in four

villages, namely Gidhmuri, Paturia, Madanpur and Uchlenga. The area exhibits a

land use pattern that mainly consists of forest and agricultural land. The proposed

site is covered with fairly dense forest. The topography and relief of the area is southeast and south-westward. The study area best represents as moist region. The

vegetation is fairly dense and occurs on Barakar rocks and reddish yellow loam soils.

Soil and topography vary together. It can be helpful to differentiate three subtypes

of topography, hilltops and plateaus, lower hill slopes, and valley bottom. There is

light shrub and weed growth under the forest canopy.

The maximum elevation above MSL in the block is 525 m in the mid of Paturia block,

and lowest is 459 m near Bamhni river in the north western part of Paturia block.

The general slope of the ground is from south to north in the Paturia block whereas it is north to south in the Gidhmuri block.

Hasdeo river is the most important river in the Gidhmuri & Paturia coal blocks area. All

the smaller natural channels like Dokka nalla, Bamhni nalla and Bisrar nalla, join the

Hasdeo river. Together these form the group representing the surface water resources in

the region. Dokka Nalla and Bisrar Nalla are passing through mid of property of quarry-

1. It is recommended to divert Dokka Nalla and Bisrar Nalla for safe mining operation

after detailed topographical study and drainage pattern of the

17

Page 20: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

area. Catchment area on the north of quarry-3 is naturally draining into Bamhni

Nalla meeting into Hasdeo river. A garland drain is proposed to arrest the rainwater

entering into the mine. Eastern Boundary of quarry-1 has been kept at safe distance

of 40 m from western bank of Dokka Nalla.

4.4 Existing land use pattern, shortest distances from the periphery of the

project to periphery of the forests, water bodies.

The Gidhmuri & Paturia blocks cover an area of about 1751.92 Hectares in four

villages, namely Gidhmuri, Paturia, Madanpur and Uchlenga. The area exhibits a land

use pattern that mainly consists of forest and agricultural land. The proposed site is

covered with fairly dense forest. The topography and relief of the area is southeast

and south westward. The study area best represents as moist region. The vegetation

is fairly dense and occurs on Barakar rocks and reddish yellow loam soils. Soil and

topography vary together. It can be helpful to differentiate three subtypes of

topography hilltops and plateaus, lower hill slopes, and valley bottom.

The existing land use plan for Gidhmuri & Paturia blocks is presented in Table-14 and Table-15

Nearest Water bodies in the 10 km radius of the proposed coal mine are given in Table-16

TABLE-16

NEAREST WATER BODIES

Sr.No Rivers & Nalas

1. Bisrar Nala Within ML area

2. Dokka Nala 0.1 km, ESE

3. Bamhni Nala 0.3 km, N

4. Rumrabahar Nala 1.4 km, E

5. Semarduwari Nala 2.5 km, S

6. Manasi Nala 3.8 km, NNW

7. Maniari Nala 4.0 km, SW

8. Chhoti Chornal Nadi 5.2 km, SSE

9. Bongo Reservoir 6.0 km, S

10. Bagabahar Nala 6.8 km, E

11. Chornal Nadi 7.7 km, SE

12. Atem Nadi 9.3 km, NE

Nearest Forest Blocks within 10 Km radius of the proposed mine is given in Table - 17

18

Page 21: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

TABLE-17

LIST OF FOREST BLOCKS WITHIN 10 KM RADIUS

Sr.No Reserve Forests and Protected Forest:

1. Paturiya P.F Within ML area

2. Dhajak P.F Within ML area

3. Phatepur P.F Adjacent, NE

4. Pidiya R.F 1.0 km, N

5. Matringa P.F 1.4 km, E

6. Lampahar P.F 2.6 km, S

7. Ghatbara P.F 5.8 km, NE

8. Sakho P.F 6.0 km, S

9. Gumga P.F 8.7 km, NE

Map showing Surface and Geological plan and Conceptual plans and Reclamation plans are shown in Figure-5, Figure-6, Figure-7 and Figure-8 respectively.

19

Page 22: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE-5 SURFACE PLAN /GEOLOGICAL PLAN

20

Page 23: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE- 6 CONCEPTUAL PLAN (30 YEARS)

21

Page 24: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE- 7 DUMP RECLAMATION PLAN (48 YEARS)

22

Page 25: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

FIGURE- 8 INFRASTRUCTURE IN LAND USE PLAN

23

Page 26: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

4.5 Infrastructure Facility

The workshop will have two separate sections to look after the maintenance needs of HEMM and other P&M. HEMM section will look after the maintenance needs of all the

heavy earth moving equipment provided in the project. P&M section will look after the

maintenance needs of all the other equipment like pumps, CHP equipment, power

supply, light vehicles etc. provided in the project. The workshop and project store will

be located in the same compound for faster availability of spares required by the

workshop. Separate provision for a store yard of adequate area is planned for

loading/unloading, truck movement etc. Store racking system, weigh scale, fork lift truck shall also be provided in the stores which will be located adjacent to the

workshop complex for quick issuing of materials to the workshops.

The infrastructure area is shown in Figure-8 of Land Use plan.

The following facilities will be provided for proper mine drainage:

The garland drains will be developed in advance for each mine stage such that water is collected in these garland drains and discharged properly outside the pit.

Working faces will be laid such that the water from the working areas will flow into

the sump by gravity from where it will be pumped out to surface drains.

Face pumps of adequate capacity will be provided at working faces to keep these dry.

Slurry pumps will be provided to deal with slurry formed during rainy season.

As the mine life is 30 years, all buildings will be of permanent type. Service buildings like Office buildings, sub-station, statutory buildings such as first aid center, rest

shelter, canteen etc. of appropriate area will be provided near the mine. A service

magazine of about 10 t capacity will be provided in dipside of the property which is

proposed to be shifted during the later stage. The residential buildings and allied

facilities of the project will be located at khirti village, korba district, which is about 7

km SW (64 J/10) from the proposed mine.

Haul roads suitable for plying 35 T rear dumpers with side drains and dozer path will

be provided. Approach road to project site will be provided. Approach road to colony and magazine also will be provided.

4.6 Soil classification

Soil is ranging is thickness 0.5 m to 11 m and is of residual in nature. It is generally yellowish to reddish brown in colour and sandy in nature.

4.7 Climatic data from secondary sources

Secondary information on meteorological conditions has been collected from nearest

IMD station at Ambikapur which is at a distance of 60 Km, from the ML area. IMD data for ambient temperature, relative humidity, wind speed and rainfall is given in

the Table-18.

24

Page 27: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

TABLE-18

CLIMATOLOGICAL DATA-STATION: IMD, AMBIKAPUR

Month Atmospheric Temperature (0C) Relative Rainfall

Pressure (mb) Humidity (%) (mm)

0830 1730 Mean Max Mean Min 0830 1730

January 947.8 944.8 27.8 3.4 75 44 16.7

February 946.1 942.8 31.7 5.6 65 35 24.3

March 944.5 940.7 36.7 10.3 47 25 16.3

April 941.7 937.6 40.4 15.8 36 21 11.8

May 937.7 933.8 42.4 20.9 37 22 13.5

June 934.2 931.1 40.8 21.3 64 54 176.9

July 933.7 931.1 33.7 21.2 86 80 456.5

August 934.7 932.2 32.4 21.2 88 83 417.2

September 938.4 935.4 32.2 19.6 84 77 230.4

October 943.7 940.6 31.9 13.0 76 62 67.4

November 947.2 944.2 29.3 7.7 69 50 3.4

December 948.3 944.6 27.0 4.5 76 47 5.1

Total 1439.5

Source: India Meteorological Department, Pune

4.8 Social Infrastructure Available

Socio-economic aspects of people will be covered in the proposed Social Impact

study (SIA). Social infrastructure like road and rail, communication, health,

sanitation, community centres, education, financial institutions, income source, etc.

are well established due to the presence of CSPGCL

Social Infrastructure available in this area are

o Well-connected Road to District and State head quarters

o Power supply network and communication network o Hospital o Schools o Necessary market facilities and shops

5. PLANNING BRIEF

5.1 Mining Method

The Mining method is shovel /Backhoe will be deployed in the advancing benches.

The excavated overburden will be spread back by using dumpers in the mined out area. After Top soil spread, the backfilled area will be biologically reclaimed and

afforested to restore to pre-mining condition.

5.2 Design Criteria

Sequential mining suited for achieving the objective of placing maximum possible

OB in the internal dumps. Thus external dump quantities from this pit will be

minimized.

The following design criteria have been considered for waste dumps.

1) Separate spoil dumps are proposed for Topsoil and hard OB

2) Maximum height of topsoil dump is to be 10 meters. 3) Overburden will be dumped in external dump in 30 m decks and up to a

maximum height of 30 meters.

4) Dump bench slope will be maintained at 370, OB Bench slope- 70

0 and Overall

pit slope will be 370.

25

Page 28: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

5) Track dozers will be deployed for shaping the dumps. Benching the dump and

plantation over the dump will help in better stabilization of dumps and reduction

of soil erosion. 6) Internal dumping of overburden will be carried out in 20-30 m height benches.

5.3 Mining Parameter

Considering the geo-mining characteristics of the deposit, the mine is proposed to

be worked by Conventional Mining Equipment (CME) Technology (Shovel /Backhoe -

Dumper system). All the overburden/parting is proposed to be excavated by shovel/

dumper combination with and without dragline. The coal horizons is proposed to be

extracted by hydraulic shovels/backhoes and transported to Coal Stockyard by rear

dumpers. The proposed mining system parameters for coal mining and OB removal are as follows.

1) Mining Benches

a) Maximum Bench Height

Dragline bench – 35 m 20 Cu m rope shovel bench – 15 to 18 m 8.3 Cu m hyd shovel bench – 12 to 15 m 4.5 Cu m Hyd shovel bench – 10 -12 m

b) Minimum Bench width

Working Bench width for 4.5 cum Hyd Shovel – 40 m Non-Working Bench width for 4.5 cum Hyd Shovel – 25 m Working Bench width for 8.3 cum Hyd Shovel – 50 m Non-Working Bench width for 8.3 cum Hyd Shovel – 30 m Working Bench width for 20 m Rope Shovel – 60 m Non-Working Bench width for 20 m Rope Shovel – 35 m Bench width of dragline – 60 to 70 m

2) Width of the permanent haul road – 30 m 3) Width of the temporary transport - 20 m

4) Usual height of the spoil dump bench – 30 m

5) The width of the active dump bench – 60 m 6) Bench slope working

OB Bench : 700

Coal Bench : 700

Dump Bench : 370

7) Overall pit slope : 370

No of annual working days : 330 No of daily shifts : 3

Duration of shift, hours : 8

Annual productivity of excavators is based on the following considerations apart

from the above design criteria:

a. Hardness of OB & Coal b. Specific gravity of OB & Coal

c. Swell factors of OB & Coal

d. Availability of HEMM e. Utilization of HEMM

26

Page 29: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

5.4 Main mining equipment

The tentative peak requirement of main mining equipment to be deployed in the project for achieving the target capacity of coal production is as follows, given in the Table-19. The finalized Mining equipment configuration will be arrived during

preparation of Mining Plan /Feasibility Report.

TABLE -19 MAIN MINING EQUIPMENT

Sr No Equipment Size Nos (for Mine Life from 1-30 years)

Coal

1) Electric Hyd Shovel 4.5 cum 3-5

2) Rear dumpers 35 T 16-53

3) RBH drill 160 mm 3-5

4) Wheel dozer 300 HP 2-4

5) Dozer 410 HP 3-5

OB

6) Dragline 26/96 2-3

7) Electric Hyd Shovel 4.5 cum 2-3

8) Rear Dumpers 35 T 14-28

9) Electric Hyd Shovel 8.5 cum 3-7

10) Rear Dumpers 85 T 17-56

11) Elec rope Shovel 20 cum 1

12) Rear dumper 170 T 3-8

13) RBH drill 250 mm 2-15

14) RBH drill 160 mm 2-3

15) Wheel dozer 460 HP 3

16) Dozer 770 HP 2-13

Common

17) Electric Hyd Shovel 1.2 cum 3-4 (with back hoe)

18) Grader 280 HP 4-5

19) RT Crane 70 T 1-2

20) RT Crane 20 T 2-4

21) Mobile crane 8 T 2-5

22) FE Loader 5-6 cum 1-3

23) Water sprinkler 28 KL 3-7

24) Wheel dozer 460 HP 1-4

25) Dump trucks 10 T 4-12

26) Vibratory 30 T 1-2 Compactor

27) Fuel Trucks 16 KL 1-2

28) Hyd Rock Breaker 1

29) Cable Handler 1

Reclamation

30) FE Loader 5-6 cum 3-4

31) Dozer 320 HP 3-4

32) Water Sprinkler 28 KL 4-6

33) Dumper 35 T 5-7

27

Page 30: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

5.5 Drilling and Blasting pattern

Main overburden comprises of clay, sandstone/clayey sandstone and shale which are friable in nature. Hard strata will be loosened by using selective blasting. Drilling of top OB and dragline benches envisages to be done by 250 mm drill whereas drilling of partings and coal envisages to be done by 160 mm drills. Drilling of coal & OB

benches is recommended to be done vertically at 900. Slurry explosive in cartridge

/site mixed slurry will be utilised for better result and enhance safety with proper stemming material. Secondary blasting is not in any circumstances. Mine shall create proper explosive storage capacity to cater daily explosive requirement to meet the annual coal target.

The mining plan envisages following type of drills for dragline bench /top OB bench

and partings and coal given in Table-20

Sr No Top OB /dragline Partings/coal

1 250 mm dia drill 160 mm drill

2 Blast hole depth- Max depth – 10 m 35 m dragline

18 m (20 cum Rope shovel)

15 m (8.3 cum Hyd Shovel)

12 m (4.5 cum Hyd shovel)

5.6 Blasting Pattern

A powder factor 0.125 to 0.167 kg/m3 of waste (average: 0.143 kg/m³) is

applicable, depending on rock conditions. Slurry / Emulsion Explosives are used. Rows of holes will be initiated through delay detonation of 25 to 50 milliseconds. Drill hole spacing would be 3m by 5m to 4m by 5m based on strata condition

5.7 Population Projection

The following villages are likely to be affected due to mining & its related activities:

About 485 number of project affected families involving about 2036 project affected persons will be affected as per census 2011.

It is obvious to assume that the activities of the mining operations will improve the

socio-economic levels in the study area. The anticipated impact of this project on

various aspects is described in the following sections:

a) Impact on Human Settlement

Human settlement is expected to increase after this project gets operational

b) Impact on Population Growth

This project will have an impact on the population growth, as it will provide good

value of employment to the families in the nearby villages. Preference will be given

to local unemployed youth for employment during development of mine and in

operation of mines which will substantially increase the income status of population

of the area and due to migration of people from outside area will be having impact

on the area

28

Page 31: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

c) Impact on Literacy and Educational Facilities

The literacy level of the project area is likely to increase as there will be influx of

many educated people taking up jobs in the mine, which is likely to result in establishment of better educational facilities.

d) Impact on Civic Amenities

The impact of mining on the civic amenities will be substantial after the commencement of mining activities. The construction of new roads in the project

area will enhance the transportation facilities.

e) Impact on Health Care Facilities

It is imperative to have proper health care facilities near the mining area. Health care centre will be developed at proposed residential colonies, which will also

extending the medical facilities in the surrounding villages through its rural welfare

schemes.

f) Impact on Economic Aspects

The proposed mining activities will provide employment to persons of different skills

and trades. The local population will have preference to get an employment. The

employment potential will ameliorate economic conditions of these families directly and provide employment to many other families indirectly who are involved in

business and service oriented activities. This in-turn will improve the socio-

economic conditions of the area.

5.8 Land use planning

The present and conceptual Land use within the core zone of the ML area is given

in the Table-21. TABLE-21

LANDUSE PATTERN VILLAGE-WISE

LAND TYPE MADANPUR PATURIADAND GIDHMURI UCHLENGA TOTAL

Government Land 2.211 2.354 1.619 - 6.184

Private land 55.442 126.763 94.260 2.432 278.897

Van Adikar Patta 3.844 2.428 3.522 - 9.794

Revenue Forest 43.684 271.480 124.670 - 439.834

Orange Area - 69.517 - 33.618 103.135

Protected Forest KENDAI FOREST RANGE- 914.076

Total Area 105.181 472.542 224.071 36.050 1751.920

5.9 Assessment of Infrastructure and Amenities/Facilities.

a) Workshop

The workshop will have two separate sections to look after the maintenance

needs of HEMM and other P&M.

b) HEMM Section

This section will look after the maintenance needs of all the heavy earth moving

equipment provided in the project and shall have the following facilities:

Daily maintenance including washing of equipment.

29

Page 32: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Scheduled technical maintenance including lubrication and inspection

Day-to-day minor repairs/replacement of components and sub-assemblies.

Routine inspection and scheduling for attending to major repairs and overhauls

from outside agencies.

c) E & M Section

This section will look after the maintenance needs of all the other equipment like

pumps, CHP equipment, power supply and light vehicles etc. provided in the project and shall have the following facilities:

Washing of LMV, lubrication, inspection and minor repairs of the E&M equipment as required.

Routine/scheduled maintenance of all E&M equipment (lubrication and minor adjustments and filling of POL etc.).

Incidental minor repair/replacement of sub-assemblies and components of CHP

equipment and accessories, water pumps and pumping installations and other E&M equipment.

Day-to-day repair and maintenance of LMVs including repair of dynamos, self-starters, radiators and battery charging etc.

Repair of small electrical motors, switch gears and instruments etc. including rewinding jobs.

Inspection and scheduling of major repairs from outside agencies.

d) Project Store

The workshop and project store shall be located in the same compound for faster

availability of spares required by the workshop. Provision for a closed shed is

made for the project stores. Separate provision for a store yard of adequate area is also made for loading/unloading, truck movement etc.

Store racking system, weigh scale, fork lift truck are also provided in the stores which shall be located adjacent to the workshop complex for quick issuing of

materials to the workshops.

The infrastructure area is shown in Figure -7.

e) Mine Drainage

The following facilities would be provided for proper drainage:

The garland drains shall be developed in advance for each mine stage such that

water is collected in these garland drains and discharged properly outside the pit.

Working faces would be laid such that the water from the working areas will flow into the sump by gravity from where it would be pumped out to surface drains.

Face pumps of adequate capacity would be provided at working faces to keep

these dry.

Slurry pumps would be provided to deal with slurry formed during rainy season.

f) Buildings

All buildings should be of permanent type since the mine life is 30 years including

construction period, which will extend after inclusion of reserves.

30

Page 33: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Service Buildings

Office buildings, sub-station, statutory buildings such as first aid centre, rest

shelter, canteen etc. of appropriate area would be provided near the mine.

Requirement of bulk explosive is proposed to be met by the supplier directly.

However, a service magazine of about 10 t capacity would be provided in the dip

side of the property which is proposed to be shifted during the later stage.

Residential Buildings

The residential buildings and allied facilities of the project shall be located at a

suitable place.

g) Roads

Following types of roads would be provided:

Haul Roads

Haul roads suitable for plying 35 T rear dumpers with side drains and dozer path

would be provided.

Colony Roads

The 3.75 m wide roads with drains etc. would be provided.

Approach Road

Approach road to project site would be provided. Approach road to colony and magazine also would be provided.

6.0 PROPOSED INFRASTRUCTURE

6.1 Industrial Area

a) Workshop

The workshop will have two separate sections to look after the maintenance needs

of HEMM and other P&M.

b) HEMM Section

This section will look after the maintenance needs of all the heavy earth moving

equipment provided in the project and shall have the following facilities:

Daily maintenance including washing of equipment.

Scheduled technical maintenance including lubrication and inspection

Day-to-day minor repairs/replacement of components and sub assemblies.

Routine inspection and scheduling for attending to major repairs and overhauls from outside agencies.

c) E & M Section

This section will look after the maintenance needs of all the other equipment like

pumps, CHP equipment, power supply and light vehicles etc. provided in the project and shall have the following facilities:

31

Page 34: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Washing of LMV, lubrication, inspection and minor repairs of the E&M equipment

as required.

Routine/scheduled maintenance of all E&M equipment (lubrication and minor

adjustments and filling of POL etc.).

Incidental minor repair/replacement of sub-assemblies and components of CHP

equipment and accessories, water pumps and pumping installations and other

E&M equipment.

Day-to-day repair and maintenance of LMVs including repair of dynamos, self-starters, radiators and battery charging etc.

Repair of small electrical motors, switch gears and instruments etc. including rewinding jobs.

Inspection and scheduling of major repairs from outside agencies.

d) Project Store

The workshop and project store shall be located in the same compound for faster

availability of spares required by the workshop. Provision for a closed shed is made

for the project stores. Separate provision for a store yard of adequate area is also

made for loading/unloading, truck movement etc.

Store racking system, weigh scale, fork lift truck are also provided in the stores

which shall be located adjacent to the workshop complex for quick issuing of materials to the workshops.

e) Service Buildings

Office buildings, sub-station, statutory buildings such as first aid centre, rest shelter, canteen etc. of appropriate area would be provided near the mine.

Requirement of bulk explosive is proposed to be met by the supplier directly.

However, a service magazine of about 10 t capacity would be provided in the dip

side of the property which is proposed to be shifted during the later stage.

6.2 Residential Area

The residential buildings and allied facilities of the project will be located at Khirti

village, Korba District, which is about 7 km SW (64 J/10) from the proposed mine.

6.3 Drinking Water Management (Source & Supply of water)

It is proposed that requirement of potable water requirement is met from ground water resources. An amount of 1281 m3/day will be required for the proposed mine.

Application for the approval from CGWA is under process.

It is proposed to be diverted Dokka nalla and Bisrar nalla for safe mining operations as per the approved plan by Water Resources Department, Raipur, Chhattisgarh.

6.4 Sewerage System

Domestic and industrial effluent will be disposed off after suitable treatment in the

effluent treatment plants (STP/ ETP) located in colony and industrial area.

6.5 Industrial Waste Management

Mine discharge

Mine effluent contains silt and coal particles, which will be treated in two stages at

primary sedimentation sump in mine floor and secondary sedimentation sump at

32

Page 35: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

mine surface.

The mine discharge will be used to meet the requirement of the washery,

afforestation / plantation, dust suppression, fire fighting, other industrial, domestic applications. Surplus water meeting the prescribed standards, if any, will be

discharged into nearby surface body.

Washery effluent

Waste water will be collected in slime ponds and circulated back into the process. Zero effluent discharge will be practiced.

Workshop effluent

The workshop effluent will be treated in a proper effluent treatment plant. Oil and grease will be skimmed using oil trap and stored in leak proof containers and will be sold to authorized vendors.

Domestic effluent

STP will be provided. Sludge after digestion will be used as manure / compost.

6.6 Solid Waste Management

The total overburden of 644.95 Mm3. Only 25.65 Mm

3 is proposed to be dumped

externally, while the remaining 619.30 Mm3 of OB is proposed to be dumped

internally.

Settling pond silt will be disposed in mined out areas along with OB. Retention wall of adequate dimensions will be constructed at the base of

external dumps as per the guide lines of MOEF. Garland drain and check dam

will be constructed. Proper overall slope of around 30o angle will be maintained

for over burden dumps. Dumps will be gradually reclaimed in phased manner and rehabilitated using

suitable plant species and grasses.

6.7 Power Requirement & Supply / source.

The proposed mine will get power from CSPDCL substation and power will be distributed by 33 KV line.

Electric power will be supplied for pumping and illumination for the opencast mine as the major equipment of Gidhmuri & Paturia. The power requirement for the mine will

be 10 MVA.

7. REHABILITATION AND RESETTLEMENT (R & R) PLAN

(i) Policy to be adopted in respect of the project affected persons including home oustees, land oustees and landless labourers:

CGSPCL Shall pay the suitable compensation to the land loser and project affected

family’s due to the proposed project by implementing the Rehabilitation

&Resettlement (R&R) packages as per the national R&R policy and Land acquisition

Act, 2013.

As per preliminary estimate, opencast mining affected people are given in Table-

22.

33

Page 36: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

TABLE-22 REHABILITATION AND RESETTLEMENT DETAILS

Sr.NO Village No.of Houses No. of Land Population Owner

1 Paturia 251 192 1055

2 Madanpur 96 76 363 (East of Highway)

3 Gidhmuri 138 77 594

4 Uchlenga - 6 24

Total 485 281 2036

a) Proposed Rehabilitation Policy:

Resettlement:

Development alternate free house plot in resettlement colony with necessary infrastructure facilities or provision for resettlement.

Free transport arrangement for belongings and reusable material or suitable transport grant.

Infrastructure to be provided includes primary school, dispensary, panchayat ghar, drinking water well/ hand pumps, WBM roads, drainage, Sulabh

Sauchalaya etc. Suitable Resettlement grant etc.

Rehabilitation

“Land for land” on a “willing buyer willing seller” basis. Other rehabilitation options based on need and requirement. Capacity Addition Programmes. Suitable Rehabilitation Grants, Subsistence Allowance etc. Other innovative measures like incentivising purchase of land by the landless

etc.

Additional Economic Opportunities as per need and requirement.

8. PROJECT SCHEDULE & COST ESTIMATES

(i) Likely date of start of construction and likely date of Completion

Initial two year has been kept for Approval and clearance stage. After Approval and

clearance stage, two year will be required for Development or construction stage.

Operation will start from 2019-2020. Yearly production planned until achievement of

full capacity has been given in Table-23 below:

TABLE-23

YEARLY PRODUCTION

Year Overburden (Mcum) Coal (MT)

1) 5.29 1.00

2) 6.39 2.20

3) 9.8 4.00

4) 13.95 5.60

5) 14.43 5.60

6) 15.37 5.60

7) 18.82 5.60

34

Page 37: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

Year Overburden (Mcum) Coal (MT)

8) 20.09 5.60

9) 23.83 5.60

10) 23.87 5.60

11) 24.33 5.60

12) 25.07 5.60

13) 25.34 5.60

14) 25.21 5.60

15) 24.87 5.60

16) 26.33 5.60

17) 26.32 5.60

18) 25.74 5.60

19) 25.59 5.60

20) 26.18 5.60

21) 26.23 5.60

22) 24.15 5.60

23) 23.68 5.60

24) 25.15 5.60

25) 26.66 5.60

26) 27.31 5.60

27) 27.58 5.60

28) 27.44 5.60

29) 28.34 5.60

30) 30.58 5.60

Total 673.94 158.40

(ii) Estimated project cost along with analysis in terms of economic

viability of the project.

The mining operations will be started only after getting all the clearances. The

capital cost of the project is Rs 2,010 Crores including environment protection measures.

Total Capital Investment

Initial capital investment has been provided in the proposal till the year of achieving

rated coal production in the 4th

year of operations. The Initial capital investment up to the target year has been proposed to be financed by debt and budget allocation from Government of Chhattisgarh.

9. ANALYSIS OF PROPOSAL (FINAL

RECOMMENDATIONS) Financial and Social Benefits

The project will improve the socio-economic status of the society in the region by generating direct and indirect employment opportunities. The project will contribute

additional revenue to the State & Central exchequers in the form of taxes, cess, etc.

The anticipated positive impacts of the project are explained below:

Human settlement is expected to increase after this project gets operational. In the

long term, the project will have impact on the population growth due to migration of people from outside area. Indirect employment opportunities will also add to this.

35

Page 38: Pre-Feasibility Report For Proposed Gidhmuri … › writereaddata › Online › TOR › ...Pre-Feasibility Report For Proposed Gidhmuri &Paturia Coal Mine of 5.6 MTPA Capacity in

The literacy level of the project area is likely to increase as there will be influx of

many educated people taking up jobs in the project, which is likely to result in

establishment of better educational facilities.

The impact of the project on the civic amenities will be minimal. Health care

facilities will be developed for the employees of the proposed project. These medical

facilities will be extended to surrounding villages.

The project related construction activities will benefit the local populace in a number of ways such as supply of construction labourers – skilled, semi-skilled and un-

skilled, tertiary sector employment and provision of goods and services for daily

needs including transport. The proposed project will provide employment to the

skilled as well as un-skilled persons. The local population will be given preference

depending upon their suitability to the job requirement. Besides direct employment,

indirect employment opportunities will also open up. The project will have positive

impact in the region. Quality of life of the people will improve, which in-turn will improve the socio-economic conditions of the area.

***********

36


Recommended