PRE – FEASIBILITY REPORT
i
CONTENT LIST
S. NO. CONTENTS PAGE NO.
1.0 EXECUTIVE SUMMARY 01
2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 04
(i) IDENTIFICATION OF PROJECT & PROJECT PROPONENT 04
(ii) BRIEF DESCRIPTION OF NATURE OF THE PROJECT 05
(iii) NEED FOR THE PROJECT & ITS IMPORTANCE TO THE COUNTRY /REGION 06
(iv) DEMAND-SUPPLY GAP 07
(v) IMPORTS VS. INDIGENOUS PRODUCTION 07
(vi) EXPORT POSSIBILITY 07
(vii) DOMESTIC/EXPORT MARKETS 07
(viii) EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE
PROJECT
07
3.0
PROJECT DESCRIPTION 07
(i) TYPE OF PROJECT INCLUDING INTERLINKED AND INDEPENDENT
PROJECTS, IF ANY
07
(ii) LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION,
AND PROJECT BOUNDARY & PROJECT SITE LAYOUT) WITH
COORDINATES
08
(iii) DETAILS OF ALTERNATIVE SITE CONSIDERED 10
(iv) SIZE OR MAGNITUDE OF OPERATION 10
(v) PROJECT DESCRIPTION WITH PROCESS DETAILS 10
(vi) RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY,
LIKELY SOURCE, MARKETING AREA OF FINAL PRODUCTS, MODE OF
TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT
13
(vii) RESOURCES OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE
PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED
13
(viii) AVAILABILITY OF WATER ITS SOURCE, ENERGY /POWER REQUIREMENT
AND SOURCE
13
(ix) QUANTITY OF WASTE TO BE GENERATED (LIQUID AND SOLID) AND
SCHEME FOR THEIR MANAGEMENT/DISPOSAL
14
4.0 SITE ANALYSIS 15
(i) CONNECTIVITY 15
(ii) LAND FORM, LAND USE AND LAND OWNERSHIP 15
(iii) TOPOGRAPHY 15
(iv) EXISTING LAND USE PATTERN {AGRICULTURE, NON-AGRICULTURE,
FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)}, SHORTEST
DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF
THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE
AREAS, WATER BODIES (DISTANCE FROM THE HFL OF THE RIVER), CRZ.
IN CASE OF NOTIFIED INDUSTRIAL AREA, A COPY OF THE GAZETTE
NOTIFICATION
15
ii
S. NO. CONTENTS PAGE NO.
(v) EXISTING INFRASTRUCTURE 18
(vi) SOIL CLASSIFICATION 18
(vii) CLIMATIC DATA FROM SECONDARY SOURCES 18
(viii) SOCIAL INFRASTRUCTURE AVAILABLE 18
5.0 PLANNING BRIEF 18
(i) PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, AND
TRANSPORTATION ETC.) TOWN AND COUNTRY
PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION
18
(ii) POPULATION PROJECTION 18
(iii) LAND USE PLANNING 19
(iv) ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) 19
(v) AMENITIES/FACILITIES 19
6.0 PROPOSED INFRASTRUCTURE 19
(i) INDUSTRIAL AREA (PROCESSING AREA) 19
(ii) RESIDENTIAL AREA (NON PROCESSING AREA) 19
(iii) GREEN BELT DEVELOPMENT 19
(iv) SOCIAL INFRASTRUCTURE 20
(v) CONNECTIVITY 20
(vi) DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER) 20
(vii) SEWERAGE SYSTEM 20
(viii) INDUSTRIAL WASTE MANAGEMENT 20
(ix) SOLID WASTE MANAGEMENT 20
(x) POWER REQUIREMENT & SUPPLY/SOURCE 21
7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN 21
(i) POLICY TO BE ADOPTED (CENTRAL/STATE)IN RESPECT OF THE PROJECT
AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND
LANDLESS LABORERS (BRIEF OUTLINE TO BE GIVEN)
21
8.0 PROJECT SCHEDULE & COST ESTIMATES 21
(i) LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF
COMPLETION (TIME SCHEDULE FOR THE PROJECT TO BE GIVEN)
21
(ii) ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF
ECONOMIC VIABILITY OF THE PROJECT
21
9.0 ANALYSIS OF PROPOSAL 21
iii
LIST OF TABLES
TABLE NO. NAME PAGE NO.
1. SALIENT FEATURES OF THE PROJECT 01
2. DETAILS OF MANPOWER 07
3. WATER REQUIREMENT 14
4. POWER REQUIREMENT 14
5. ENVIRONMENTAL SETTING DETAILS 16
LIST OF FIGURES
FIGURE NO. NAME PAGE NO.
1. MAP SHOWING GENERAL & SPECIFIC LOCATION OF THE PROPOSED
MINE SITE
09
2. MAP SHOWING ENVIRONMENTAL SETTING OF THE STUDY AREA 17
ANNEXURES LIST
S. NO ANNEXURE ANNEXURE NO.
1. KHASRA MAP I
2. LEASE DOCUMENTS II
3. ENVIRONMENT CLEARANCE DATED 30th NOVEMBER, 2012 III
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 1
PRE-FEASIBILITY REPORT
1.0 EXECUTIVE SUMMARY
M/s. UltraTech Cement limited (Unit: Aditya Cement Works) has proposed expansion in Limestone
Production capacity from 10.0 Million TPAto 13.17 Million TPA (ROM 14.22 Million TPA- including
limestone & screen rejects) (M L No. 24/92, ML area-760.692 ha) of its Aditya Limestone Mine at
Villages –Medi-Ka-Amarana, Bad-Ka-Amarana, Neem-Ka-Amarana, Rail-Ka-Amarana, Amarpura,
Sawa, Nayakheda, Sindaudi, Jorawar-Singh-Ka-Kheda, Karunda and Charlia, Tehsil– Chittorgarh &
Nimbahera, District–Chittorgarh (Rajasthan).
Table – 1
SALIENT FEATURES OF THE PROJECT
S. No. Particulars Details
A. Nature of the Project Aditya Limestone Mine, Expansion in Limestone Production
Capacity from 10.0 Million TPA to 13.17 Million TPA (ROM
14.22 Million TPA- including limestone & screen rejects) (M L
No. 24/92, ML area-760.692 ha).
B. Size of the Project
1. Mining Lease Area 760.692ha
2. Proposed Enhancement in Limestone
Production capacity
From 10.0 Million TPA to 13.17 Million TPA (ROM 14.22 Million
TPA- including limestone & screen rejects)
C. Location Details
1. Villages Medi-Ka-Amarana, Bad-Ka-Amarana, Neem-Ka-Amarana, Rail-
Ka-Amarana, Amarpura, Sawa, Nayakheda, Sindaudi,
Jorawar-Singh-Ka-Kheda, Karunda and Charlia
2. Tehsil Chittorgarh & Nimbahera
3. District Chittorgarh
4. State Rajasthan
5. Latitude & Longitude Latitude - 24042’28.45”N to 24
045’19.2”N
Longitude - 74 035’46.74"E & 74
036 ’57.86”E
7. Toposheet No. 45 L/9 and 45 L/10
D. Cost Details
1. Total Project Cost No capital investment required as existing infrastructure is
sufficient for the expansion project.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 2
S. No. Particulars Details
2. Cost for Environment Protection
Measures.
Capital Cost :Rs. 1.0 Crore/-
Recurring Cost : Rs. 5.0 Crores/ annum
E. Requirements of The Project
10. Water Requirement 598 KLD
Source- Ground Water through borewells for drinking
purpose and Rain water harvested in mine pits.
11. Power Requirement 13.0 MW
Source – Captive Power Plant and State Electricity Board/
Grid
12. Man Power Requirement Total: 175 Persons
ENVIRONMENTAL MANAGEMENT PLAN
A. Air Quality Management
Drilling
� Drilling machines are equipped with water injection system to prevent dust from being
air borne.
Blasting
� Controlled Blasting is adopted with the optimum use of explosive energy which helps in
reducing air pollution.
� Rock breaker for breaking over sized boulders which eliminates the generation of dust.
� No secondary blasting is carried out. Hydraulic breakers are deployed in place of
secondary blasting.
� Water spray on blasted muck pile.
Transportation
� Regular water spraying on the haul roads is being done.
� Regular maintenance of HEMMs & transportation vehicles.
� Overloading of material during transportation is avoided.
� Water sprinkling on crushed limestone before transportation is done.
� Crushed limestone is transported to Cement Plant through Covered Conveyor Belt.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 3
Greenbelt Development & Plantation
� Green belt development & Plantation is being carried out in & around mining lease area as
per guidelines.
� Periodic air quality monitoring is carried out.
All the above mentioned practices/activities will be adopted in the proposed production
expansion project.
B. Water Quality Management
� No waste water is/will be discharged outside ML Area.
� Waste water from workshop is treated using Oil – Water separator and treated water is
being used in equipment washing, dust suppression, etc.
� Domestic wastewater generated from mines office is being disposed off in soak pit via
septic tank.
� Retaining walls, Garland drains along the periphery of pits and dumps & settling ponds
have been constructed to arrest surface run-offs and to channelize it.
� Periodical monitoring of Ground water level & quality is being carried out regularly.
All the above mentioned practices/activities will be adopted in the proposed production
expansion project.
C. Noise Level Management
� Controlled Blasting is being adopted. Blasting is done during day hours only.
� All HEMMs are equipped with AC cabins for operators.
� All mines employees are provided with earplugs/earmuffs.
� Proper maintenance, oiling and greasing of machines is being done to reduce generation
of noise at regular intervals.
� Periodical monitoring of noise is done.
� Development of green belt & plantation around lease boundary, roads and other places is
being/ will be carried out.
All the above mentioned practices/activities will be adopted in the proposed production
expansion project.
D. Greenbelt/ Plantation
� As on 01.04.2016, plantation has been developed over an area of 103.85 ha. in the Mining
Lease area. Native plant species like Neem, Sheesham, Karanj, Amaltash, Cassia Simea,
etc. have been planted.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 4
� The same will be maintained and enha nced in future.
� Greenbelts are developed around the lease boundary, haul roads and plantation are done
on undisturbed area, reclaimed area, dumpsite, around crusher plant, workshop & mine
office, etc.
� Native species are planted as per the advice of DFO, Chittorgarh.
2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
(i) IDENTIFICATION OF PROJECT AND PROJECT PROPONENT
� IDENTIFICATION OF PROJECT
� Aditya Limestone Mine is a captive mine of M/s. UltraTech Cement Ltd. (Unit: Aditya
Cement Works). M/s UltraTech Cement limited has proposed expansion in Limestone
Production capacity from 10.0 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-
including limestone & screen rejects) (M L No. 24/92, ML area-760.692 ha) of its Aditya
Limestone Mine at Villages – Medi-Ka-Amarana, Bad-Ka-Amarana, Neem-Ka-Amarana,
Rail-Ka-Amarana, Amarpura, Sawa, Nayakheda, Sindaudi, Jorawar-Singh-Ka-Kheda,
Karunda and Charlia, Tehsil–Chittorgarh & Nimbahera, District–Chittorgarh (Rajasthan).
• IDENTIFICATION OF PROJECT PROPONENT
� M/s. UltraTech Cement Ltd. (UTCL) is a flagship company of Aditya Birla Group.
� A US $41 billion corporation, the Aditya Birla Group is in the League of Fortune 500.
Anchored by an extraordinary force of over 120,000 employees belonging to 42
nationalities, the Aditya Birla Group has been ranked fourth in the world and first in Asia
Pacific in the ‘Top Companies for Leaders’ study 2011, conducted by Aon Hewitt, Fortune
Magazine and RBL (a strategic HR and leadership Advisory firm). The Group has topped
the Nielsen's Corporate Image Monitor 2014-15 and emerged as the Number one
corporate, the 'Best in Class', for the third consecutive year.
� Over 50 per cent of its revenues flow from its overseas operations spanning 36 countries
– Australia, Austria, Bangladesh, Brazil, Canada, China, Egypt, France, Germany, Hungary,
India, Indonesia, Italy, Ivory Coast, Japan, Korea, Laos, Luxembourg, Malaysia, Myanmar,
Philippines, Poland, Russia, Singapore, South Africa, Spain, Sri Lanka, Sweden,
Switzerland, Tanzania, Thailand, Turkey, UAE, UK, USA and Vietnam.
� Aditya Birla Group is a dominant player in the sectors of cement, metals, viscose staple
fibre, acrylic fibre, viscose filament yarn, branded apparel, carbon black, chlor-alkali,
fertilizers, insulators, retail business, mobile telephony and fina ncial services.
� UTCL is the largest Cement producer in India with the production capacity of 69.3 Million
TPA. Its operations span across India, UAE, Bahrain, Bangladesh and Sri Lanka.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 5
� It has 12 Integrated cement plants, 1 clinkerisation plant, 19 grinding units, one white
cement plant and 7 bulk terminals in India.
� The Premium Brands comprise of - UltraTech Cement, Birla Super, UltraTech Concrete,
Birla super ready mix concrete, Birla white & Birla wall care putty.
(ii) BRIEF DESCRIPTION OF THE NATURE OF PROJECT
� The proposal is for expansion in production capacity of Aditya Limestone Mine.
� M/s. UltraTech Cement limited (Unit: Aditya Cement Works) has its existing Integrated
Cement Plant and has proposed enhancement in Clinker Production Capacity (8.4 Million
TPA to 8.9 Million TPA) by process optimization at village- Sawa Shambupura, Tehsil &
District- Chittorgarh (Rajasthan).
� In order to meet the raw material requirement (limestone) for their existing and
proposed expansion in Cement plant, M/s UTCL has proposed expansion in Aditya
Limestone Mine (ML Area 760.692 ha.) with Limestone Production Capacity from 10.00
Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA- including limestone & screen
rejects) at Villages – Medi-Ka-Amarana, Bad-Ka-Amarana, Neem-Ka-Amarana, Rail-Ka-
Amarana, Amarpura, Sawa, Nayakheda, Sindaudi, Jorawar-Singh-Ka-Kheda, Karunda and
Charlia, Tehsil–Chittorgarh & Nimbahera, District–Chittorgarh (Rajasthan).
Mining Lease Status
� The mining lease over an area of 760.692 was granted in favour of Grasim Industries Ltd.
vide letter no. p-5 (96)/ Mines/ Group – 1/92 dated 01.03.1994 for a period of 20 years
from 29.04.1994 to 28.4.2014.
� By virtue of the order dated 11.06.2010 of the Hon’ble Bombay High Court and the order
dated 01.07.2010 passed by the Hon’ble High Court of Gujarat at Ahmedabad in Company
Petition under Sections 391 & 394 of the Indian Companies Act, 1956, the name of the
mining lease holder Company stands changed from Grasim Industries Ltd. (Unit: Aditya
Cement) to UltraTech Cement Ltd. (Unit: Aditya Cement Works). Relevant documents
have been submitted to Mining Engineer (Chittorgarh), Department of Mines & Geology
(Udaipur) and Mines Secretariat–Jaipur. Name change in the lea se documents is under
process with the department.
� Mining Lease has been extended upto 28.04.2044, under Section 8A (5) of M.M.D.R.
Amendment Act, 2015, by the State Government vide letter dated 16.03.2015. Mining
Lease documents are enclosed as Annexure-2.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 6
Existing Clearances & Consents
Environmental Clearance for the existing limestone production capacity of 10.0 Million
TPA has been obtained in the name of Grasim Industries Ltd. from MoEFCC, New Delhi
vide Letter no. J-11015/229/2010-IA.II (M) dated 30.11.2012. Copy of the same is enclosed as
Annexure 2.
Consent to Establish (CTE) under section 21(4) Air (Prevention & Control of Pollution)
Act, 1981 and under section 25/26 of Water (Prevention & Control of Pollution) Act, 1974
was obtained from Rajasthan State Pollution Control Board (RSPCB) vide their Order No.
2014-2015/Mines/2105 dated 07.05.2014, which is valid upto 20.03.2016.
Consent to Operate (CTO) under section 21(4) Air (Prevention & Control of Pollution) Act,
1981 and under section 25/26 of Water (Prevention & Control of Pollution) Act, 1974 was
obtained from Rajasthan State Pollution Control Board (RSPCB) vide their letter no. F
(Mines)/ Chittorgarh (Chittorgarh) /11 (1)/ 2009-2010/5021-5025 dated 11.09.2014 valid upto
31.08.2017.
Regular Compliance reports of EC / Consents conditions are being submitted to the
concern authorities on regular basis.
Screening category of Project
As per EIA Notification dated 14th
September, 2006 as amended from time to time, the
project falls under Category “A”, Project or Activity 1(a) – 3.
(iii) NEED FOR THE PROJECT & ITS IMPORTANCE TO THE COUNTRY AND OR REGION
M/s. UltraTech Cement limited (Unit: Aditya Cement Works) has its existing Integrated
Cement Plant and has proposed enhancement in Clinker Production Capacity (8.4 Million
TPA to 8.9 Million TPA). Therefore, in order to meet the raw material requirement
(limestone) for their existing and proposed expansion in Cement plant M/s UTCL has
proposed expansion in Aditya Limestone Mine (ML Area 760.692 ha.) with Limestone
Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-
including limestone & screen rejects) at Villages – Medi-Ka-Amarana, Bad-Ka-Amarana,
etc. at Tehsil–Chittorgarh & Nimbahera, District–Chittorgarh (Rajasthan).
The proposed expansion project will prove beneficial in terms of socio-economic
development as it will create employment opportunities to locals. Further, the average
income level, which is the indicator of socio – economic status of households is expected
to increase, which will ultimately result in better standard of living of the local people.
With respect to the importance of the project to the nation, it can be well said that in a
developing nation like India, cement makes a backbone for infrastructural development.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 7
Thus, keeping in mind this requirement, mining of limestone is necessary for the nation’s
growth.
(iv) DEMAND – SUPPLY GAP
Limestone produced from the limestone mine is being / will meet the
requirement/demand of limestone for the Cement Plant of M/s UltraTech Cement Ltd.
(Unit- Aditya Cement Works)
(v) IMPORTS VS. INDIGENOUS PRODUCTION
Limestone produced from the Aditya Limestone Mine is being / will be used for captive
purpose in the existing Cement Plant of Aditya Cement Works.
(vi) EXPORT POSSIBILITY
Limestone produced from the Aditya Limestone Mine is being / will be used for captive
purpose in the Cement Plant of Aditya Cement Works.
(vii) DOMESTIC/EXPORT MARKETS
Limestone produced from Aditya Limestone Mine is being / will be uti lized for captive use
in the cement plant. Thus there will be no other users for the limestone produced from
this mine.
(viii) EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT
The total manpower for this mining project is 175 persons. There will be no additional
manpower requirement. Preference for employment has been given to locals as per their
eligibility & qualification. However, the project will generate indirect employment
opportunities for the locals.
Table -2 Details of Manpower
S .No Particulars Existing Proposed
1 HEO Operators 85
No additional manpower will be required and existing manpower will be utilized for proposed
expansion also.
2 Drillers 5
3 Blasters 4
4 Diesel Mechanics 16
5 Auto Electrician 5
6 Welder/fitter (Mines & Crusher) 4
7 Helpers 20
8 Officers & Staff 36
Total 175
3.0 PROJECT DESCRIPTION
(i) Type of Project Including Interlinked And Independent Projects, If Any:
M/s. UltraTech Cement Limited has proposed expansion in Limestone Production capacity
from 10.0 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA- including limestone &
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 8
screen rejects) (M L No. 24/92, ML area-760.692 ha) of its Aditya Limestone Mine at
Villages – Medi-Ka-Amarana, Bad-Ka-Amarana, Neem-Ka-Amarana, Rail-Ka-Amarana,
Amarpura, Sawa, Nayakheda, Sindaudi, Jorawar-Singh-Ka-Kheda, Karunda and Charlia,
Tehsil–Chittorgarh & Nimbahera, District–Chittorgarh (Rajasthan).
Interlinked Project: Proposed enhancement in Clinker Production Capacity (8.4 Million
TPA to 8.9 Million TPA ) by process optimization at village- Sawa Shambupura, Tehsil &
District- Chittorgarh (Rajasthan).
ii) Location (map showing general location, specific location, and project boundary &
project site layout) with coordinates
Location details
� Villages: Medi-Ka-Amarana, Bad-Ka-Amarana, Neem-Ka-Amarana, Rail-Ka-
Amarana, Amarpura, Sawa, Nayakheda, Sindaudi, Jorawar-Singh-Ka-
Kheda, Karunda and Charlia
� Tehsil: Chittorgarh & Nimbahera
� District: Chittorgarh
� State: Rajasthan
� Latitude: 24042’28.45”N to 24045’19.2”N
� Longitude: 74 035’46.74"E & 74 036 ’57.86”E
� Toposheet no. : 45 L/9 and 45 L/10
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 9
4.0 LOCATION MAP
Figure 1: Location Map showing general location, specific location, project boundary & project site layout
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 10
(iii) Details of alternate sites considered
No alternative site has been taken into consideration as the mineral (Limestone) has been
proved with adequate reliability at this site to support Captive cement plant of Aditya Cement
Works. Also, this is an existing project & all required infrastructure is already available at the
site.
(iv) Size or Magnitude of Operation
Expansion in LimestoneProduction Capacity is proposed from 10.0 Million TPA to 13.17 Million
TPA (ROM 14.22 Million TPA- including limestone & screen rejects) within existing Mining
Lease Area of 760.692ha.
(v) Project Description with Process Detail
A. Local Geology
Aditya Limestone Mine deposit belongs to Nimbahera limestone formation of Khorip
group of Lower Vindhyans. Nimbahera limestone is overlain and underlined by Suket
shale & Bari shale respectively. Details of the geology of the mining lease area are as
follows:
Rock types of the study area
Limestone, shale and weathered stone / clay are the major rock types found in the area.
Limestone found in the area is very fine grained, compact and thinly layered. Layers are
very distinct due to their varying colours ranging from shades of grey to pink. The
sequence of rock types found in the mining lease area is as follows:
� Overburden soil
� Weathered stone/Clay
� Shale
� Dark grey limestone
� Upper grey limestone
� Pink limestone
� Lower grey limestone
� Light grey limestone
Chemical constituents of different rock types found in the deposit are as follows.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 11
Principal Constituents
1 2 3 4 5 6 7
Dark grey Limestone
Upper grey Limestone
Pink limestone
Lower grey Limestone
Light grey Limestone
**
Shale
**Weathered Stone / Clay
CaO% 40.34 46.20 47.13 46.48 42.33 19.04 28.41
SiO2% 20.08 12.96 10.78 12.51 18.07 44.21 35.41
Al2O3% 3.05 1.73 1.78 1.95 2.50 9.57 5.53
Fe2O3% 1.79 1.01 0.94 0.89 1.21 5.11 4.25
** Shale is treated as waste rock and is not mixed with limestone.
Note: No toxic element has been reported during chemical analysis of rock samples of the
deposit during exploration activity.
B. Details of Mining
Mining operation is being/ will be carried out by fully mechanized opencast method,
utilizing Heavy Earth Moving Machines (HEMM) in conjunction with Deep Hole drilling &
blasting. Loading is being/ will be done by Hydraulic Excavators and transport of blasted
limestone is being/ will be done by dumpers to the crusher. Screened & crushed
limestone is being/ will be transported to Cement Plant by covered Conveyor Belt.
Sequence of Mining
� Top soil (wherever present) removal for direct usage or stacking at designated place.
� Drilling & Blasting for OB removal.
� Waste rock removal & dumping at designated dump.
� Drilling & blasting for limestone.
� Loading of ROM Limestone in Dump trucks.
� Transportation of ROM Limestone to Crusher.
� Separation of clay fraction (screen reject), which is rich in silica by combination of
primary & secondary screen system & dumping at designated place.
� Crushing of Limestone.
� Transportation of Limestone to Cement Plant by covered belt conveyor system.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 12
PRESENT METHOD OF MINING:-
a) Drilling Specifications:-
Height of bench 9 – 11 m
Width of bench About 25m
Slope of the bench 75o – 90
o
Diameter of blast hole 115 mm
Length of hole 9- 11 m
Spacing 6 – 7 Meter
Burden 4 – 5 Meter
No of row of holes 2
b) Blasting:-
Explosive used-
a. Slurry- 83 mm dia cartridge – 2.78 kg each & 33 cm in length.
b. ANFO- 94% fertilizer grade ammonia & 6% diesel by weight .Both are suitably mixed in the
said proportion to make an explosive mixture.
c. ANFO Charging:-
Permission to prepare explosive charge at ANFO shed has been obtained from chief
controller of explosive and DGMS.
d. Mode of charging: - Primer cartridge is placed at the bottom & remaining cartridges are
loaded over one another covering approx 3.5 to 4 m of the length of hole. Bottom charge
is called booster charge & remaining is called column charge. In case of ANFO charging,
booster charge is slurry while column charge is ANFO.
e. Stemming Material-
During drilling of blast holes, drill cutting which are flushed out of hole and get
accumulated at the collar of each hole. These cut materials have been found to be most
effective stemming materials.
i) Length of stemming:-
After charging of explosives, remaining length is stemmed with drill cuttings.
Compactness of stemming is very important. It improves blasting efficiency & reduces
noise & vibration level and fly rock also.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 13
ii) Secondary blasting: -
No secondary blasting is carried out. Hydraulic breakers are deployed in place of
secondary blasting.
iii) Powder Factor: -
Yield per hole = 9m (L) X 7m(S) X 5m (B) X 2.5(b d) = ~790 T
Charge per hole = 50 to 55 Kg
Powder Factor = 13-14 T/kg
iv) Storage of explosive:-
There are two no. explosive magazines.
Magazine-1: 1.5 Tons and 40000 mtrs DF
Magazine-2: 1.97 Tons and 26400 Nos Detonators
(vi) Raw Material required Along With Estimated Quantity, Likely Source, Marketing Area of
Final Products, Mode of Transport of Raw Material and Finished Product
� This is a Limestone mining project hence no raw material will be required.
� Limestone will be used in captive cement plant, so no marketing area will be required.
� Limestone will be transported from mine to the crusher by dumpers and to Cement Plant
via covered conveyor belt.
(vii) Resources Optimization/ Recycling and Reuse Envisaged in the Project, if any, should be
briefly Outlined.
� No waste water is being/ will be discharged outside the Mining Lea se Area.
� Oil – Water separator has been provided at the workshop and treated water is being re-
cycled for equipment washing and dust suppression, etc.
� Top soil & Waste Rock comprising of Clay/ weathered stones, screen rejects (clay) and
Shale are being/ will be utilized in land reclamation and for plantation purpose.
(viii) Availability of Water, Its Source, Energy /Power Requirement and Source
A. Water Requirement
The total water requirement will be 598 KLD. Out of which the drinking & sanitation
water requirement of 18 KLD will be met from ground water (bore wells) and remaining
requirement of 580 KLD from rain water stored in mine pit.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 14
Table -3
Water Requirement
S.
No. Water Requirement
Existing
Requirement
(in KLD)
Proposed (Additional
Requirement) (in
KLD)
Total
Requirement Source
1. Dust suppression 450 - 450
Rain water
harvesting pit 2.
Workshop – HEMM
washing (KLD) 45 - 45
3. Greenbelt 85 - 85
4. Drinking & Sanitation 18 - 18 Ground water
from Bore wells
Total 598 Nil 598 -
B. Power Requirement
Total Power requirement after expansion for lime stone mine will be 13.0 MW which will
be sourced from Captive Power plant and State Electricity Board/ Grid.
Table -4
Power Requirement
Existing Requirement in MW
Proposed (Additional Requirement) in MW
Total Requirement after expansion in MW
Source
10.00 (Connecting Load)
3.00 (Connecting Load)
13.00 (Connecting Load) Captive Power Plant &
SEB/Grid
(ix) Quantity of Waste to Be Generated (Liquid and Solid) And Scheme for Their
Management/Disposal
A. Liquid
� Domestic Waste water generated from mine office is being/will be disposed off in
soak pits via septic tank.
� Oil – Water separator has been provided at the workshop and treated water is being
re-cycled for equipment washing a nd dust suppression etc.
B. Solid
� Wastes comprise of Topsoil, O.B. / waste rocks and Screen rejects / clay.
� Topsoil (negligible amount) is being/will be stacked separately and is being/ will be
utilized for plantation.
� The O.B. / waste rocks is being/ will be dumped at earmarked sites as per approved
mining plan. Part of them is being / will be used for constructing protective bunds
and in backfilling in the mined out area.
� Screen rejects/ clay is being/will be utilized for plantation on un-worked area in ML
area, along the lease boundary, over the dumps, etc.
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 15
4.0 SITE ANALYSIS
(i) Connectivity
The site is well connected with nearest town Shambhupura at about 3.5 km ENE direction
& Chittorgarh city is in NNE direction at 15 km. National Highway -79 (Ajmer-Indore) is
about at 2.3 km in East direction from the mine site and National Highway -76 is about at
8.5 km in NW direction from the mine site. Nearest railway station is Shambhupura at
about 4.0km in NE direction. The nearest airport is Maharana Pratap Airport, Dabok
Udaipur at about 74 km in WSW direction. The site is well connected with the
communication facilities such as telephone, telefax and internet.
(ii) Land Form, Land Use and Land Ownership
The total Mining lea se area is 760.692 ha. Major portion of the mining lease area
constitutes of waste land/rocky land.
(iii) Topography& Drainage
The terrain is more or less flat with gentle undulations. As compared to the Central part of
the area, the ground level rises by 10m & 15m towards the northern and southern ends
respectively. The maximum a nd minimum reduced levels found in the mining lease area are
444m & 429m respectively. The general slope of the area is towards east.
The area is drained by seasonal nalla hs flowing across it from West to East, one of these is
located south of the Jorawar-Singh-Ka-Khera village. The other nallah is towards the
southern end of the ML area i.e. south of villages namely Amarpura and Sindaudi. These
two nallahs finally meet the Satkhandanallah located at about 2.6 Kms towards East of the
mining lease boundary, which ultimately meet Gambhiri river.
(iv) Existing Land Use Pattern {Agriculture, Non-Agriculture, Forest, Water bodies (Including
Area Under CRZ)}, Shortest Distances From The Periphery Of The Project To Periphery Of
The Forests, National Park, Wild Life Sanctuary, Eco Sensitive Areas, Water Bodies
(Distance From The HFL Of The River), CRZ. In Case Of Notified Industrial Area, A Copy Of
The Gazette Notification.
There is no National Park, Wild Life Sanctuaries, Biosphere Reserves, Tiger Reserves, and
Wildlife Corridors etc. within 10 km radius of the mining lease area.
Details of Environmental settings around the project site are given in the table below:
Expansion in Limestone Production Capacity from 10.00 Million TPA to 13.17 Million TPA (ROM 14.22 Million TPA-including limestone & Screen Rejects)
at Aditya Limestone Mine.
At Tehsil & District - Chittorgarh (Rajasthan)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 16
Table -6
ENVIRONMENTAL SETTINGS DETAILS
S.No. Particulars Details
1. National Park, Wild Life Sanctuaries,
Biosphere Reserves, Tiger Reserves,
Wildlife Corridors
There is no National Park, Wild Life Sanctuaries, Biosphere
Reserves, Tiger Reserves, and Wildlife Corridors etc. within 10
km radius of the mining lease area.
2. Reserved/ Protected Forests About 8 Reserve Forests & 4 Protected Forests fall within 10
km radius study area.
3. Water bodies There is no perennial water body flowing through ML Area.
Two seasonal Nallahs pass through ML Area. Following water
bodies exist in study Area:
• Murliya Dam (~1.3Km in SE direction)
• Sathkhanda nalla (~2.6 km in East direction)
• Gambhiri River (~7.5km in NE direction)
4. Nearest Town
Nearest City
Nearest Town: Shambhupura (~3.5 km in ENE direction)
Nearest City :Chittorgarh city (~15 km in NNE direction)
5. Nearest Highway NH – 79: Ajmer-Indore (~2.3 km in East direction)
NH – 76 (~ 8.5 km in NW direction)
6. Nearest Railway Station Shambhupura (Western Railway) (~4.0 km in NE direction)
7. Nearest Airport Maharana Pratap Airport, Dabok Udaipur (~74 km in WSW
direction)
9. Seismic Zone Zone – II as per IS: 1893 (Part-I) : 2002
Adi tya L ime st o ne Mi ne (M L Area 76 0 .6 92 ha .) E xp an s io n in L ime s to ne P ro du cti o n C a pa ci ty f ro m 10 .00 M i ll i on T P A to 13 .17 Mi l li on T P A(R OM 1 4.22 M i ll i on T P A )
At Vi ll age s – Me d i-Ka-Am ara na, Ba d-Ka-A mara na, N eem- Ka-Ama ran a, etc.,Te h si l- C hi tt or gar h&N im ba hera, Dist ric t- C hi tt org ar h ( Ra ja st ha n)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd. (Unit- Aditya Cement Works) 17
Figure -2: Map showing Environmental Settings of the study area
Adi tya L ime st o ne Mi ne (M L Area 76 0 .6 92 ha .) E xp an s io n in L ime s to ne P ro du cti o n C a pa ci ty f ro m 10 .00 M i ll i on T P A to 13 .17 Mi l li on T P A(R OM 1 4.22 M i ll i on T P A )
At Vi ll age s – Me d i-Ka-Am ara na, Ba d-Ka-A mara na, N eem- Ka-Ama ran a, etc.,Te h si l- C hi tt or gar h&N im ba hera, Dist ric t- C hi tt org ar h ( Ra ja st ha n)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 18
(v) Existing Infrastructure
The site is well connected with nearest town Shambhupura at about 3.5 km ENE direction &
Chittorgarh city is in NNE direction at 15 km. National Highway -79 (Ajmer-Indore) is about at
2.3 km in East direction from the mine site a nd National Highway -76 is about at 8.5 km in NW
direction from the mine site. Nearest railway station is Shambhupura at about 4.0 km in NE
direction. The nearest airport is Maharana Pratap Airport, Dabok Udaipur at about 74 km in
WSW direction. The site is well connected with the communication facilities such as
telephone, telefax and internet.
(vi) Soil Classification
The area mainly consists of two types of soil i.e. black soil and lateritic soil. The dominant
texture of the soil found in the area is Clayey Loamy type.
(vii) Climatic Data from Secondary Sources
Climate is generally dry except during the south – west monsoon i.e. rainy season, which lasts
for two months from Mid July to Mid September. Pre-monsoon season i.e. summer extends
from March to June. Post monsoon season extends upto November followed by winter
season upto February. Maximum temperature in summer reaches upto 450 C and the
minimum touches as low as 30 C in December / January. The annual rain fall of the area is
around 700mm. Wind speed is highest in June a nd lowest in November / December. Dominant
wind direction is NE.
(viii) Social Infrastructure Available
Nearest town is at Shambhupura, which is ~3.5 km from the mine site. The area has good
network of public roads. Telephone, Electric connections, Medical facilities and Telegraph
facilities are available in the area.
5.0 PLANNING BRIEF
(i) Planning Concept (Type of Industries, Facilities, and Transportation etc.)
TOWN AND COUNTRY PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION
This is a proposed production expansion limestone mining project. This is a captive mine of
Cement plant of UTCL. Blasted limestone will be transported to crusher by dumpers and
from crusher to cement plant by covered conveyor belt.
(ii) Population Projection
Temporary influx of people will be there as the managerial and supervisory staff will
generally be from outside the area.
Adi tya L ime st o ne Mi ne (M L Area 76 0 .6 92 ha .) E xp an s io n in L ime s to ne P ro du cti o n C a pa ci ty f ro m 10 .00 M i ll i on T P A to 13 .17 Mi l li on T P A(R OM 1 4.22 M i ll i on T P A )
At Vi ll age s – Me d i-Ka-Am ara na, Ba d-Ka-A mara na, N eem- Ka-Ama ran a, etc.,Te h si l- C hi tt or gar h&N im ba hera, Dist ric t- C hi tt org ar h ( Ra ja st ha n)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 19
(iii) Land Use Planning
The total Mining lease area is 760.692 ha. Major portion of the mining lease area constitutes
of waste land/rocky land. Proposed expansion of limestone production capacity will be in
the existing mining lease area. Modification of present Mining plan for the proposed
expansion project is under preparation. Land use planning for proposed expansion project
will be as per the approved mining plan.
iv) Assessment of Infrastructure Demand (Physical & Social)
UTCL has assessed the demand of infrastructure (Physical & Social) in nearby area of the
mine site and same is being developed under corporate social responsibilities programmes.
This is a n existing Mine. There will be negligible additional impact as the existing
infrastructure will be sufficient for the expansion project.
v) Amenities/Facilities
UTCL has developed / will develop the Amenities/Facilities in the nearby area of the
proposed mine site as per requirement of local people of the nearby area under corporate
social responsibilities programmes. Amenities/facilities for employees like residential
colony, school, market complex, hospital are already available in Aditya Cement Works of
M/s. UltraTech Cement Ltd.
6.0 Proposed Infrastructure
(i) Industrial Area (Processing Area)
Proposed limestone mining lease area is 760.692 ha. Expansion in limestone production
capacity has been planned from 10.0 Million TPA to 13.17 Million TPA (ROM 14.22 Million
TPA- including limestone & screen rejects) and all the required infrastructures like Mine
office, workshop building, roads, crusher house and conveyors, etc. are already available in
the existing mining lease area.
(ii) Residential Area (Non- Processing Area)
The company has already developed a residential colony for the mines and cement plant
employees. The colony is well designed having electricity and water supply and laid with
plantation, parks, recreation facilities, telephone, school, post office, banking, hospital and
market facilities.
(iii) Green Belt Development
� As on 01.04.2016, plantation has been developed over an area of 103.85 ha. in the
Mining Lease area. Native plant species like Neem, Sheesham, Karanj, Amaltash, Cassia
Simea, etc. have been planted.
Adi tya L ime st o ne Mi ne (M L Area 76 0 .6 92 ha .) E xp an s io n in L ime s to ne P ro du cti o n C a pa ci ty f ro m 10 .00 M i ll i on T P A to 13 .17 Mi l li on T P A(R OM 1 4.22 M i ll i on T P A )
At Vi ll age s – Me d i-Ka-Am ara na, Ba d-Ka-A mara na, N eem- Ka-Ama ran a, etc.,Te h si l- C hi tt or gar h&N im ba hera, Dist ric t- C hi tt org ar h ( Ra ja st ha n)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 20
� Green Belt is being developed around the lease boundary, haul roads and plantation are
done on undisturbed area, reclaimed area, dumpsite, near crusher plant, workshop &
mine office, etc.
� Native species are planted in consultation with Forest Department.
(iv) Social Infrastructure
Proposed expansion project will result in growth of the surrounding areas by increased
indirect employment opportunities in the region including ancillary development and
supporting infrastructure. The project has also/ will also all its established social
infrastructure for its employees as well as for the local community.
(v) Connectivity
The site is well connected with nearest town Shambhupura at about 3.5 km ENE direction &
Chittorgarh city is in NNE direction at 15 km. National Highway -79 (Ajmer-Indore) is about at
2.3 km in East direction from the mine site and National Highway -76 is about at 8.5 km in
NW direction from the mine site. Nearest railway station is Shambhupura at about 4.0 km in
NE direction. The nearest airport is Maharana Pratap Airport, Dabok Udaipur at about 74 km
in WSW direction. The site is well connected with the communication facilities such as
telephone, telefax and internet.
(vi) Drinking water management (source & supply of water)
The total water requirement will be 598 KLD. Out of which the drinking & sanitation water
requirement of 18 KLD will be met from ground water (borewells) and remaining
requirement of 580 KLD from rain water stored in mine pit.
(vii) Sewerage system
The domestic wastewater generated from mine office is being/ will be disposed off in soak
pits via septic tanks.
(viii) Industrial Waste Management
Oil – Water separator has been/ will be provided at the workshop and treated water is being
re-cycled for equipment washing and dust suppression etc. There is no discharge of waste
water outside the mine site.
(ix) Solid Waste Management
Wastes comprise of Topsoil, O.B. / waste rocks and Screen rejects / clay. Topsoil (negligible
amount) is being/will be stacked separately and is being/ will be utilized for plantation. The
O.B. / waste rocks is being/ will be dumped at earmarked sites as per approved mining plan.
Part of them is being / will be used for constructing protective bunds and in backfilling in
the mined out area. Screen rejects/ clay is being/will be utilized for plantation on un-worked
area in ML area, along the lease boundary, over the dumps, etc.
Adi tya L ime st o ne Mi ne (M L Area 76 0 .6 92 ha .) E xp an s io n in L ime s to ne P ro du cti o n C a pa ci ty f ro m 10 .00 M i ll i on T P A to 13 .17 Mi l li on T P A(R OM 1 4.22 M i ll i on T P A )
At Vi ll age s – Me d i-Ka-Am ara na, Ba d-Ka-A mara na, N eem- Ka-Ama ran a, etc.,Te h si l- C hi tt or gar h&N im ba hera, Dist ric t- C hi tt org ar h ( Ra ja st ha n)
Pre -F ea si b il it y Re po rt
M/s. Ultra Tech Cement Ltd.
(Unit- Aditya Cement Works) 21
(x) Power Requirement & Supply/Source
Total Power requirement for limestone mine will be 13.0 MW which will be sourced from
Captive thermal power plant and State Electricity Board/ grid
7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN
(i) Policy To Be Adopted (Central/State)In Respect Of The Project Affected Persons Including
Home Oustees, Land Oustees And Landless Laborers (Brief Outline To Be Given)
The total Mining lease area is 760.692 ha. No forest land is involved. This is an existing
mining project & proposed expansion will take place within the existing ML Area.
8.0 PROJECT SCHEDULE & COST ESTIMATES
(i) Likely Date of Start Of Construction And Likely Date Of Completion
This is an existing mining project.
(ii) Estimated Project Cost Along With Analysis In Terms Of Economic Viability of the
Project(Kindly provide the same)
���� Capital Cost of the Project: No capital investment will be required as existing
infrastructure is sufficient for the expansion project
���� Cost for Environment Protection for the Expansion Project:
���� Capital cost –Rs. 1.0 Crores/-
���� Recurring cost- Rs. 5.0 Crores/ annum
� ANALYSIS OF PROPOSAL
Expansion in Limestone production capacity will result in growth of the surrounding areas by
increased indirect employment in the region including ancillary development and supporting
infrastructure.
Development of social amenities is being/ will be done in the form of medical facilities, education
to underprivileged children and creation of self help groups. No major adverse effect on
environment is envisaged as the required mitigation measures are inbuilt in the project.
=
ANNEXURE -I
KHASRA MAP
ANNEXURE -II
LEASE DOCUMENTS
ENGLISH TRANSLATION Registered AD
Government of Rajasthan Mining Engineer Office, Mines & Geology Department, Chittorgarh
Khanij Bhawan/ Chittorgarh -312 001 Telephone 01472-251870 Fax 01472-251870
(Email:- [email protected])
S.No./ME/Chittorgarh/CC-1/M.L.24/1992/2341 Date: 16/03/2015
To :-
M/s. Grasim Industries
Sawa - Sambhupura, Chittorgarh
Sub- With reference to Mining Lease Validity extension as per the Amendment in M.M.D.R Act
1957, Section 8A
Reference- With reference to mining lease granted in favour of Limestone Mineral (cement Grade)
located near Village- Medi Ka Amrana, Tehsil – Chttorgarh, District- Chittorgarh.
Sir,
In accordance with the above subject, this is to inform you that recently Section 8A of M.D.D.R
(Amendment) Ordinance, 2015 has been included which is related to time period of Mining leases.
The mining lease validity of the respective mine was applicable till 28.04.2014. On the date of issuing of
above ordinance, the 1st/2nd/3rd renewal application letter of the mining lease was pending. As per the
Section 8A (5) / 8A (6) of Amendment in M.D.D.R Ordinance 2015, (which is already applicable), the
validity of the mining lease has been extended to date 28.04.2044 own its own.
Hence, the contract of the respective mine is considered to be amended automatically.
(Aasif Ansari)
Mining Engineer, Chittorgarh
Date……/…../2015
S.No/ME/Chittor/CC-1/ML 24/1992
Copy to: Sent to following for information and necessary action:
1. Joint Administrative Secretary, Jaipur vide their Letter No. P.4 (7)/Mines/Group- 2/86-Part
dated 10.02.2015.
2. Director, Mines & Geology Department, Udaipur, Rajasthan vide their Letter No. 569-618,
dated 10.02.2015.
3. Additional Director (Mines), Udaipur Zone, Udaipur.
4. Superintendent Mine Engineer, Bhilwara, Bhilwara Circle.
Mine Engineer, Chittorgarh
ANNEXURE - III
ENVIRONMENT CLEARANCE DATED 30.11.2012