+ All Categories
Home > Documents > Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and...

Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and...

Date post: 06-Mar-2018
Category:
Upload: vonguyet
View: 219 times
Download: 1 times
Share this document with a friend
25
Pre-Feasibility Study (Modified CA Cold Storage 1000 MT) Small and Medium Enterprises Development Authority Ministry of Industries & Production Government of Pakistan www.smeda.org.pk HEAD OFFICE 4th Floor, Building No. 3, Aiwan-e-Iqbal Complex, Egerton Road, Lahore Tel: (92 42) 111 111 456, Fax: (92 42) 36304926-7 [email protected] REGIONAL OFFICE PUNJAB REGIONAL OFFICE SINDH REGIONAL OFFICE KPK REGIONAL OFFICE BALOCHISTAN 3 rd Floor, Building No. 3, Aiwan-e-Iqbal Complex, Egerton Road Lahore, Tel: (042) 111-111-456 Fax: (042) 36304926-7 [email protected] 5 TH Floor, Bahria Complex II, M.T. Khan Road, Karachi. Tel: (021) 111-111-456 Fax: (021) 5610572 [email protected] Ground Floor State Life Building The Mall, Peshawar. Tel: (091) 9213046-47 Fax: (091) 286908 [email protected] Bungalow No. 15-A Chaman Housing Scheme Airport Road, Quetta. Tel: (081) 831623, 831702 Fax: (081) 831922 [email protected] June 2017
Transcript
Page 1: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study

(Modified CA Cold Storage 1000 MT)

Small and Medium Enterprises Development Authority

Ministry of Industries & Production

Government of Pakistan

www.smeda.org.pk

HEAD OFFICE

4th Floor, Building No. 3, Aiwan-e-Iqbal Complex, Egerton Road,

Lahore

Tel: (92 42) 111 111 456, Fax: (92 42) 36304926-7

[email protected]

REGIONAL OFFICE PUNJAB

REGIONAL OFFICE SINDH

REGIONAL OFFICE

KPK REGIONAL OFFICE

BALOCHISTAN

3rd Floor, Building No. 3,

Aiwan-e-Iqbal Complex, Egerton Road Lahore,

Tel: (042) 111-111-456 Fax: (042) 36304926-7

[email protected]

5TH Floor, Bahria Complex II, M.T. Khan Road,

Karachi. Tel: (021) 111-111-456

Fax: (021) 5610572 [email protected]

Ground Floor State Life Building

The Mall, Peshawar. Tel: (091) 9213046-47

Fax: (091) 286908 [email protected]

Bungalow No. 15-A Chaman Housing Scheme

Airport Road, Quetta. Tel: (081) 831623, 831702

Fax: (081) 831922 [email protected]

June 2017

Page 2: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

[Type here] i

Table of Contents

1 DISCLAIMER ................................................................................................................................. 1

2 EXECUTIVE SUMMARY ............................................................................................................... 2

3 INTRODUCTION TO SMEDA ........................................................................................................ 3

4 PURPOSE OF THE DOCUMENT .................................................................................................. 3

5 BRIEF DESCRIPTION OF PROJECT & PRODUCT .................................................................... 4

5.1 PRE-PROCESSING AND STORAGE PROCESS FLOW ......................................................................... 5 5.2 INSTALLED AND OPERATIONAL CAPACITIES .................................................................................... 6

6 CRITICAL FACTORS .................................................................................................................... 6

7 GEOGRAPHICAL POTENTIAL FOR INVESTMENT .................................................................... 7

8 POTENTIAL TARGET CUSTOMERS / MARKETS ...................................................................... 8

9 PROJECT COST SUMMARY ........................................................................................................ 8

9.1 PROJECT ECONOMICS .................................................................................................................. 8 9.2 PROJECT FINANCING .................................................................................................................... 8 9.3 PROJECT COST ............................................................................................................................ 9 9.4 SPACE REQUIREMENT ................................................................................................................ 10 9.5 MACHINERY & EQUIPMENT REQUIREMENT ................................................................................... 11 9.6 FURNITURE & FIXTURES REQUIREMENT ....................................................................................... 13 9.7 OFFICE EQUIPMENT REQUIREMENT ............................................................................................. 14 9.8 OFFICE VEHICLE REQUIREMENT .................................................................................................. 14 9.9 HUMAN RESOURCE REQUIREMENT .............................................................................................. 15 9.10 UTILITIES AND OTHER COSTS .................................................................................................. 15

10 CONTACT DETAILS.................................................................................................................... 16

10.1 MACHINERY SUPPLIERS ......................................................................................................... 16 10.2 RAW MATERIAL SUPPLIERS .................................................................................................... 17 10.3 TECHNICAL EXPERTS / CONSULTANTS ..................................................................................... 17

11 USEFUL WEB LINKS .................................................................................................................. 18

12 ANNEXURES ............................................................................................................................... 20

12.1 INCOME STATEMENT .............................................................................................................. 20 12.2 BALANCE SHEET .................................................................................................................... 21 12.3 CASH FLOW STATEMENT ........................................................................................................ 22

13 KEY ASSUMPTIONS ................................................................................................................... 23

13.1 OPERATING COST ASSUMPTIONS ............................................................................................ 23 13.2 PRODUCTION COST ASSUMPTIONS ......................................................................................... 23 13.3 REVENUE ASSUMPTIONS ........................................................................................................ 23 13.4 FINANCIAL ASSUMPTIONS ....................................................................................................... 23

Page 3: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 1

1 DISCLAIMER

This information memorandum is to introduce the subject matter and provide a general

idea and information on the said matter. Although, the material included in this

document is based on data/information gathered from various reliable sources;

however, it is based upon certain assumptions, which may differ from case to case.

The information has been provided on as is where is basis without any warranties or

assertions as to the correctness or soundness thereof. Although, due care and

diligence has been taken to compile this document, the contained information may

vary due to any change in any of the concerned factors, and the actual results may

differ substantially from the presented information. SMEDA, its employees or agents

do not assume any liability for any financial or other loss resulting from this

memorandum in consequence of undertaking this activity. The contained information

does not preclude any further professional advice. The prospective user of this

memorandum is encouraged to carry out additional diligence and gather any

information which is necessary for making an informed decision, including taking

professional advice from a qualified consultant/technical expert before taking any

decision to act upon the information.

For more information on services offered by SMEDA, please contact our website:

www.smeda.org.pk

Document Control

Document No. PREF-NO: 141

Revision No. 01

Prepared by SMEDA-Sindh

Revision Date June, 2017

For information Provincial Chief (Sindh)

[email protected]

Page 4: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 2

2 EXECUTIVE SUMMARY

Modified Controlled Atmosphere (CA) Cold storage is proposed to be located at in

any of the major cities across Pakistan. This project is designed for storing fruits and

vegetables using different compartments of the unit for storing multiple products,

where relative temperatures for respective products can be maintained

Product(s) include Apple, Mango Citrus and other fruits and vegetables.

Capacity; Installed capacity 1000 MT and initial utilization 500 MT, 50%

Total Cost Estimates is Rs.180.26 million with fixed investment Rs.176.15 million

and working capital Rs.4.11 million.

Given the cost assumptions IRR and payback are 16 % and 5.71 years respectively

The most critical considerations or factors for success of the project are:

Most significant consideration(s)

Careful selection of good location and purchase of land at competitive price.

Effective marketing and distribution of the product particularly to the exporters,

industrial units and super store buyers.

Complete adherence to best agronomic practices is critical to the success of

this project; therefore, technical knowledge & experience of the entrepreneur

in the field of horticulture and in fresh fruit processing business is absolutely

necessary.

Ensure Energy efficient construction hence low operating/fuel costs due to

efficient insulation

Equally important factor(s)

Selection of quality fruits on the basis of best analysis of cost and revenues

for a given season; cost efficiency through better management.

Awareness about HACCP standards and Strict Quality assurance of process

and products.

Page 5: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 3

3 INTRODUCTION TO SMEDA

The Small and Medium Enterprises Development Authority (SMEDA) was established

in October 1998 with an objective to provide fresh impetus to the economy through

development of Small and Medium Enterprises (SMEs).

With a mission "to assist in employment generation and value addition to the national

income, through development of the SME sector, by helping increase the number,

scale and competitiveness of SMEs", SMEDA has carried out ‘sectoral research’ to

identify policy, access to finance, business development services, strategic initiatives

and institutional collaboration and networking initiatives.

Preparation and dissemination of prefeasibility studies in key areas of investment has

been a successful hallmark of SME facilitation by SMEDA.

Concurrent to the prefeasibility studies, a broad spectrum of business development

services is also offered to the SMEs by SMEDA. These services include identification

of experts and consultants and delivery of need based capacity building programs of

different types in addition to business guidance through help desk services.

4 PURPOSE OF THE DOCUMENT

The objective of the pre-feasibility study is primarily to facilitate potential entrepreneurs

in project identification for investment. The project pre-feasibility may form the basis

of an important investment decision and in order to serve this objective, the

document/study covers various aspects of project concept development, start-up, and

production, marketing, finance and business management.

The purpose of this document is to facilitate potential investors in Modified CA Cold

Storage 1000 MT by providing them with a general understanding of the business with

the intention of supporting potential investors in crucial investment decisions.

The need to come up with pre-feasibility reports for undocumented or minimally

documented sectors attains greater imminence as the research that precedes such

reports reveal certain thumb rules; best practices developed by existing enterprises by

trial and error, and certain industrial norms that become a guiding source regarding

various aspects of business set-up and it’s successful management.

Apart from carefully studying the whole document one must consider critical aspects

provided later on, which form basis of any Investment Decision.

Page 6: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 4

5 BRIEF DESCRIPTION OF PROJECT & PRODUCT

Establishment of controlled atmosphere cold storage provides refrigerated storage

and preservation facilities for several fruits, vegetables & flowers. Because of

technology advancements and logistic strategies, the controlled atmosphere cold

storage of perishable items has become an important stage in the distribution between

manufacturers/processors and retail locations. The controlled atmosphere cold

storage will ensure the increased availability and improved quality of high value

perishable fruits and vegetables for both export and local sale, which would otherwise

perish or deteriorate. Following key parameters must be addressed as per pre-

feasibility study under preparation

Technology: CA cold storage is a used for storing produce such as vegetable and

fruits in an atmosphere that is considerably different from normal air with respect

to CO2 and O2 levels. The CO2 and O2 levels within gas tight stores are monitored

and adjusted to preserve the storage items. Due to metabolic activity of the

respiring fruits and vegetables in the store and leakage of gases through doors and

walls, the gas mixture will constantly change. The gases are therefore measured

periodically and adjusted to the predetermined level by the introduction of fresh air

or nitrogen or passing the store atmosphere through a chemical to remove CO2.

Location: CA Cold Storage can be set-up in any major city with significant

population such as Karachi, Hyderabad, Lahore, Rawalpindi, Islamabad, Multan,

Peshawar and Quetta preferably near Sabzi Mandi or fruit & vegetables trading

hub. This business can also be done in all small second tier towns in addition to

suburban towns of large cities.

Product: In the proposed controlled atmosphere cold storage there would be a

capacity to store high end imported or local products which can be stored for a

duration of about 06 months and more. The proposed products would be Apple

and Kinow due to their storage life in CA cold storage up to six months.

Target Market: Target market would be Growers, whole sellers, retailers, hyper

stores, Importers and Exporters of fruit and vegetables.

Employment Generation: The proposed project will provide direct

employment to 09 people. Financial analysis shows the unit shall be profitable from

the very first year of operation.

Page 7: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 5

5.1 Pre-processing and storage Process Flow

Page 8: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 6

5.2 Installed and Operational Capacities

The proposed cold storage facility has a maximum storage capacity of storing 1,000 metric tons. It will be functional throughout the year. Proposed capacity utilization is 50%1 with annual growth rate of 10%. This growth rate would be capped at 95% in 5th year.

6 CRITICAL FACTORS

The main critical success factors that affect the decision to invest in the proposed business setup are:

Better insulation technology and compartmentalization of cold storage as

compared to the rest of the cold storages in Pakistan.

Energy efficient construction hence low operating/fuel costs due to efficient

insulation.

Compartmentalization i.e. compartments has the provision of storing different

commodities at their respective temperatures.

Complete adherence to best agronomic practices is critical to the success of

this project; therefore, technical knowledge & experience of the entrepreneur

in the field of horticulture and in fresh fruit processing business is absolutely

necessary.

Awareness about HACCP standards and Strict Quality assurance of process

and products.

Selection of quality fruits on the basis of best analysis of cost and revenues

for a given season; cost efficiency through better management.

Appropriate post-harvest arrangement for transportation of product to the

processing unit in case of ‘own stock’ business model.

Appropriate storage arrangement and internal control for processed fruits; cold

chain refer container arrangements for transportation to local and international

markets.

Properly trained seed staff should be engaged and comprehensive staff

training programs to be adopted for capacity building.

Careful selection of good location and purchase of land at competitive price.

Effective marketing and distribution of the product particularly to the exporters,

industrial units and super store buyers.

1 As suggested by KESTRAL

Page 9: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 7

7 GEOGRAPHICAL POTENTIAL FOR INVESTMENT

Pakistan produces a variety of fruits and vegetables like potato, apple, mangoes, dates, banana, cherries, kiwi, apricots, pomegranates, peas, carrots, etc. Pakistan's total annual production of fruits amounts to nearly 7 million tons and that of vegetables to approximately 7 million tons with approximately 4 million tons of potato production2. However, it is estimated that in Pakistan 35%3 of fruits & vegetables produced each year are lost because of poor harvest conditions. This loss if calculated approximately amounts to 4.9 million metric tons and its estimated local market value reaches somewhere near US $ 800 million. The major reasons for this loss are careless harvesting, rough handling, inadequate transportation, and storage facilities.

Pakistan’s Agricultural lands in Punjab, Sindh receive all four seasons and therefore throughout the year cultivation and harvesting of different vegetables, and fruits are scattered evenly across the year. The harvest calendar of various fruits and vegetables is given below

2 Pakistan Economic Survey, Ministry of finance

3 Sindh Board of investment

Page 10: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 8

8 POTENTIAL TARGET CUSTOMERS / MARKETS

Most of the existing local Cold Storage’s are constructed on locally developed

methods, which maintain a uniform temperature for all commodities stored. The goods

are not stored at their recommended relative storage temperatures and life, and

because of this, the quality of stored commodity is badly affected. Vegetables and

fruits require specialized post-harvest treatment, appropriate temperature and relative

humidity control for their proper & optimum storage, which most of the existing local

cold stores lack. Following are the potential customers of cold storage:

Growers Wholesalers and Traders

Importers and Exporters

Retailers and/or Hyper stores

9 PROJECT COST SUMMARY

A detailed financial model has been developed to analyze the commercial viability of this project. Various costs and revenue related assumptions along with results of the analysis are outlined in this section.

9.1 Project Economics

All the figures in this financial model have been calculated for estimated sales of Rs. -

35.28 million in the year one. The capacity utilization during year one is worked out at

50 % with 10 % increase in subsequent years up to the maximum capacity utilization

of 95 %.

The following table shows internal rate of return, payback period and net present value

of the proposed venture:

Table 9.1: Project Economics

Description Details

Internal Rate of Return (IRR) 16%

Payback Period (yrs.) 5.71

Net Present Value (Rs.) 41,436,370

9.2 Project Financing

Following table provides details of the equity required and variables related to bank

loan:

Page 11: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 9

Table 9.2: Project Financing

Description Details

Total Equity (100%) Rs.180,260,534

9.3 Project Cost

Following fixed and working capital requirements have been identified for operations of the proposed business:

Table 9.3: Project Cost

Description Amount Rs.

Capital Cost

Land (01 acre) 10,000,000

Building/Infrastructure 55,644,629

Machinery & equipment 103,640,950

Furniture & fixtures 448,150

Office vehicles 1,450,000

Office equipment 424,200

Pre-operating costs 2,823,000

Misc. & Contingency 1,716,079

Total Capital Cost 176,147,009

Working Capital

Equipment spare part inventory 2,000,000

Up-front Insurance Payment 613,525

Cash 1,500,000

Total Working Capital 4,113,525

Total Project Cost 180,260,534

Page 12: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 10

9.4 Space Requirement

The space requirement for the proposed Modified CA cold storage is approx. 01 acre

and estimated by considering various facilities including management office,

production hall, storage, open space, etc. Details of space requirement and cost

related to land & building is given below:

Table 9.4: Space Requirement

Description Estimated Area

(Sq.ft.)

Unit Cost (Rs.)

Total Cost (Rs.)

Office Block 1,000 1,400 1,400,000

Committee Room 500 1,400 700,000

Micro Lab, Lab & Office 600 1,400 840,000

Sorting & Grading Hall 10,000 1,400 14,000,000

Cold Storage 12,000 1,400 16,800,000

Machine Room 600 1,400 840,000

Lobby 480 1,400 672,000

Store 3,000 1,400 4,200,000

Dining 500 1,400 700,000

Kitchen 400 3,000 1,200,000

Masjid 500 1,400 700,000

Restrooms 600 3,000 1,800,000

Change Room 250 1,800 450,000

Guard Room 120 1,800 216,000

Total Building Cost 30,550 44,518,000

External Development

Pavement/driveway 8,000 80 640,000

Main Gate 1 100,000 100,000

Page 13: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 11

Grounds Landscaping 5,000 50 250,000

Weighbridge Platform 1 1,400,000 1,400,000

Overhead Water Tank (Gallons) 5,000 400 2,000,000

Underground Water Tank (Gallons) 10,000 70 700,000

Boundary Wall 836 3,400 2,842,400

Misc. & Contingency 3% 1,573,512

Design & Supervision Charges 3% 1,620,717

Total External Development 11,126,629

Total Building & External Development Cost

55,644,629

9.5 Machinery & Equipment Requirement

Plant, machinery and equipment for the proposed project are stated below:

Table 9.5: Machinery & Equipment

Description Quantity Unit Cost

(Rs.)

Total Cost (Rs.)

1.0 INSULATION CHAMBERS

1.01 Insulation material Polyurethane, CFC Free

20,585,000

1.02 Inter floor of ripening chambers 865,000

1.03 Assembling of panels, Inclusive of fitment of profiles, filing and caulking of silicon.

3,090,000

1.04 Sliding Doors 12 155000 1,860,000

1.05 Door for 40 feet container 1 125000 125,000

1.06 Door for Hino 2 70000 140,000

1.07 Humidification System 12 150000 1,800,000

Page 14: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 12

1.08 CO2 exhaust system with fresh air, Air to air heat exchanger including CO2 controller

12 600000 7,200,000

1.09 Ethylene Generator 4 325000 1,300,000

1.10 Dock for Hino 2 65000 130,000

1.11 Dock for 40 feet container 1 100000 100,000

2. REFRIGERATION SYSTEM OF COLD STORE

2.01 Condensing Unit (15 HP) 8 925000 7,400,000

2.02 Evaporator Unit 8 550000 4,400,000

2.03 Refrigeration system 8 150000 1,200,000

3. REFRIGERATION SYSTEM OF RIPENING CHAMBERS

3.01 Condensing Unit (15 HP) 4 1250000 5,000,000

3.02 Evaporator Unit 8 480000 3,840,000

3.03 Refrigeration system 4 250000 1,000,000

SUB TOTAL 60,035,000

Sales Tax 17%

10,205,950

TOTAL COST OF CA COLD STORAGE

70,240,950

B. SORTING & GRADING LINE

Feeder, Brush Washer, Drying, Sorting and Grading

10,000,000

Fork Lift 2 2200000 4,400,000

Generator 250KVA Turbo Type, 250KVA, 400 Volts, 50 Cycles, 1500 RPM, Power Factor 0.8

1 5,300,000 5,300,000

Page 15: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 13

Weigh Bridge 30 x 10 feet size, 60 tons capacity

1 1,800,000 1,800,000

Drums / Bins 14,000 850 11,900,000

Total 103,640,950

9.6 Furniture & Fixtures Requirement

Details of the furniture and fixture required for the project are given below:

Table 9.6: Furniture & Fixture

Description Quantity Unit Cost (Rs.)

Total Cost (Rs.)

Managers Tables along with side tables

2 20,000 40,000

Manager / Officers Chairs 2 7,500 15,000

Visitor Chairs 8 6,000 48,000

Officers Tables along with side tables 5 20,000 100,000

File Racks 2 15,000 30,000

Sofa Set 2 35,000 70,000

Split Air-conditioner 1.5 Ton 2 65,000 130,000

Misc. & Contingency 5% 15,150

Total 448,150

Page 16: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 14

9.7 Office Equipment Requirement

Following office equipment will be required for CA Cold Storage facility.

Table 9.7: Office Equipment

Description Quantity Unit Cost (Rs.)

Total Cost (Rs.)

Computers with LCD 2 75,000 150,000

Printer 1 20,000 20,000

Scanner 1 5,000 5,000

Networking Equipment & Accessories 150,000

Telephone Sets 8 2,000 16,000

Fax Machine 1 15,000 15,000

Water Dispenser 1 18,000 18,000

Electric Water Cooler 1 30,000 30,000

Misc. & Contingency 20,200

Total 424,200

9.8 Office Vehicle Requirement

Following office vehicle will be required for the project.

Table 9.8: Office Vehicle

Description Quantity Unit Cost (Rs.)

Total Cost (Rs.)

Car (1000 cc) 1 1,450,000 1,450,000

Total 1,450,000

Page 17: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 15

9.9 Human Resource Requirement

In order to run operations of CA Cold storage smoothly, details of human resources

required along with number of employees and monthly salary are recommended as

under:

Table 9.9: Human Resource Requirement

Description No. of Employees

Monthly Salary per

person (Rs.)

Monthly Salary (Rs.)

Manager Plant 1 75,000 75,000

Manager Finance & Admin 1 45,000 45,000

Cold Store Operator 2 20,000 40,000

Lifter Operator 2 18,000 36,000

Office Boy 1 14,000 14,000

Guard 2 14,000 28,000

Total 09 238,000

9.10 Utilities and other costs

An essential cost to be borne by the project is the cost of electricity and fuel. The

electricity expenses are estimated to be around Rs. 8,398,571 per year, whereas, fuel

expenses are estimated to be Rs.480,468 per year (for fork lift and burner). Revenue

Generation

Based on the capacity utilization of 50 % sales revenue during the first year of operations is estimated as under:

Table 9.10: Revenue Generation – Year 1

Description Rental Price Rs. (Incl Sorting and Grading) / kg /month

Rental Revenue (Rs.)

Fruits 06 35,280,000

Total 35,280,000

Page 18: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 16

10 CONTACT DETAILS

In order to facilitate potential investors, contact details of private sector Service Providers relevant to the proposed project be given.

10.1 Machinery Suppliers

Machinery Supplier - 1

Name of Supplier

/Organization Kold Kraft Refrigeration Ltd

Address Plot No 83-A, Sector 27 Korangi Industrial Area, Karachi

Phone Tel: +92 300-0302887 Fax Fax: +92-21-

35074858

E-mail [email protected]

Website www.koldkraft-refrigeration.com

Machinery Supplier - 2

Name of Supplier

/Organization

Frostec

Address Suite # 605, Ibrahim Trade Tower, Shahra-e-Faisal,

Karachi - Pakistan

Phone +92-21-34327620 Fax 92-21-34327619

E-mail [email protected]

Website www.frostecint.com

Machinery Supplier - 3

Name of Supplier

/Organization Helperco (Pvt) Limited

Address Room # 3, 3rd Floor Al-Hafeez Tower, Shahra-e-Faisal

Karachi-75530

Page 19: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 17

Phone 92-21-35660920-22 Fax

E-mail [email protected]

Website www.helpercopvtltd.enic.pk

10.2 Raw Material Suppliers

Raw Material Supplier

Name of Supplier

/Organization Wax (Polish) Al-Aziz Enterprises

Address 10-km,Lahore Road, Sargodha

Phone +92-300-9606642 Fax

10.3 Technical Experts / Consultants

Technical Experts / Consultants - 1

Name of Expert

/Organization Durrani Associates

Address Opposite Baqai University, Super Highway, Karachi

Phone 92-21-34410231 Fax

Technical Experts / Consultants - 2

Name of Expert

/Organization Dr. M. Aslam Pervez

Address Director Institute of Horticultural Sciences, Facility of

Agriculture, University of Agriculture Faisalabad

Phone +92-41-9201281 Fax

Page 20: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 18

Technical Experts / Consultants - 3

Name of Expert

/Organization Imtiaz Enterprises

Address 2 & 3, Karachi Market, New fruit Vegetable Market, Super

Highway, Karachi

Phone 92-21-36870451-3 Fax

Technical Experts / Consultants - 4

Name of Expert

/Organization

Pakistan Cold Chain Development Company

Address Address: 106 / 3 Block C, Model Town, Lahore

Post Code: 54700

Email [email protected]

11 USEFUL WEB LINKS

Links of Federal & Provincial Government, Semi Government and other (sector & Cluster based) Development organizations are to be given under this heading so to enable potential investors to get benefit from the services offered. Web links of various organizations are given as example however, links of only relevant organizations should be given;

Small & Medium Enterprises Development Authority

(SMEDA)

www.smeda.org.pk

Government of Pakistan www.pakistan.gov.pk

Ministry of Industries & Production www.moip.gov.pk

Ministry of Education, Training & Standards in Higher

Education

http://moptt.gov.pk

Government of Punjab www.punjab.gov.pk

Government of Sindh www.sindh.gov.pk

Government of Khyber Pakhtunkhwa www.khyberpakhtunkhwa.gov.pk

Government of Balochistan www.balochistan.gov.pk

Government of Gilgit Baltistan www.gilgitbaltistan.gov.pk

Government of Azad Jamu Kashmir www.ajk.gov.pk

Page 21: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 19

Trade Development Authority of Pakistan (TDAP) www.tdap.gov.pk

Security Commission of Pakistan (SECP) www.secp.gov.pk

Federation of Pakistan Chambers of Commerce and Industry

(FPCCI)

www.fpcci.com.pk

State Bank of Pakistan (SBP) www.sbp.org.pk

Punjab Small Industries Corporation www.psic.gop.pk

Sindh Small Industries Corporation www.ssic.gos.pk

Pakistan Horticulture Development and Export Company

(PHDEC) www.phdec.org.pk

Punjab Vocational Training Council (PVTC) www.pvtc.gop.pk

Technical Education and Vocational Training Authority

(TEVTA) www.tevta.org

Pakistan Readymade Garment Technical Training Institute www.prgmea.org/prgtti/

Livestock & Dairy Development Department, Government of

Punjab. www.livestockpunjab.gov.pk

Punjab Industrial Estates (PIE) www.pie.com.pk

Faisalabad Industrial Estate Development and Management

Company (FIEDMC) www.fiedmc.com.pk

Page 22: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 20

12 ANNEXURES

12.1 Income Statement

Calculations SMEDA

Income Statement

50% 60% 70% 80% 90% 95% 95% 95% 95% 95%

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

Revenue 35,280,000 45,299,520 56,548,901 69,151,227 83,240,790 94,015,848 100,596,957 107,638,744 115,173,456 123,235,598

Cost of sales Per month/Kg

Ripening Cost of Orange 0.04 250,000 315,000 385,875 463,050 546,978 606,234 636,545 668,373 701,791 736,881

Ripening Cost of Apple 0.04 250,000 315,000 385,875 463,050 546,978 606,234 636,545 668,373 701,791 736,881

Labor Wages for Sorting & Grading 0.18 1,085,595 1,367,850 1,675,616 2,010,739 2,375,186 2,632,497 2,764,122 2,902,328 3,047,445 3,199,817

Production Labor 0.30 1,812,000 1,993,200 2,192,520 2,411,772 2,652,949 2,918,244 3,210,069 3,531,075 3,884,183 4,272,601

Machinery Maintenance 0.09 518,205 570,025 627,028 689,731 758,704 834,574 918,031 1,009,834 1,110,818 1,221,900

Electricity Cost 1.40 8,398,571 11,048,714 14,144,900 17,749,836 21,934,310 25,452,960 27,998,256 30,798,082 33,877,890 37,265,679

Fuel Cost 0.08 480,468 528,515 581,367 639,503 703,454 773,799 851,179 936,297 1,029,926 1,132,919

Total cost of sales 2.13 12,794,839 16,138,304 19,993,180 24,427,681 29,518,557 33,824,542 37,014,748 40,514,362 44,353,845 48,566,678

Gross Profit 22,485,161 29,161,216 36,555,721 44,723,547 53,722,233 60,191,306 63,582,209 67,124,382 70,819,611 74,668,920

64% 64% 65% 65% 65% 64% 63% 62% 61% 61%

General administration & selling expenses

Administration expense 0.17 ## 1,044,000 1,148,400 1,263,240 1,389,564 1,528,520 1,681,372 1,849,510 2,034,461 2,237,907 2,461,697

Administration benefits expense 0.01 52,200 57,420 63,162 69,478 76,426 84,069 92,475 101,723 111,895 123,085

Utilities (Electricity, Gas, Water etc) 0.07 419,929 552,436 707,245 887,492 1,096,715 1,272,648 1,399,913 1,539,904 1,693,895 1,863,284

Travelling expense 0.04 ### 214,200 235,620 259,182 285,100 313,610 344,971 379,468 417,415 459,157 505,072

Communications expense (phone, fax, mail, internet, etc.) 0.05 10% 285,600 314,160 345,576 380,134 418,147 459,962 505,958 556,554 612,209 673,430

Office vehicles running expense 0.04 0% 225,000 247,500 272,250 299,475 329,423 362,365 398,601 438,461 482,307 530,538

Office expenses (stationary, entertainment, janitorial services, etc.) 0.05 10% 285,600 314,160 345,576 380,134 418,147 459,962 505,958 556,554 612,209 673,430

Promotional expense 0.06 12% 342,720 325,584 309,305 293,840 279,148 265,190 251,931 239,334 227,367 215,999

Insurance expense 0.10 613,525 547,823 482,120 416,418 350,715 355,070 284,056 213,042 142,028 71,014

Professional fees (legal, audit, consultants, etc.) 0.02 5% 142,800 157,080 172,788 190,067 209,073 229,981 252,979 278,277 306,104 336,715

Depreciation expense 2.25 13,523,561 13,523,561 13,523,561 13,523,561 13,523,561 13,700,609 13,700,609 13,700,609 13,700,609 13,700,609

Amortization of pre-operating costs 0.09 564,600 564,600 564,600 564,600 564,600 - - - - -

Amortization of Contingency Cost 0.03 171,608 171,608 171,608 171,608 171,608 171,608 171,608 171,608 171,608 171,608

Miscellaneous expense 0.05 285,600 314,160 345,576 380,134 418,147 459,962 505,958 556,554 612,209 673,430

Subtotal 3.03 18,170,943 18,474,112 18,825,789 19,231,603 19,697,841 19,847,768 20,299,024 20,804,495 21,369,505 21,999,912

Operating Income 4,314,217 10,687,104 17,729,931 25,491,943 34,024,392 40,343,538 43,283,185 46,319,887 49,450,107 52,669,009

Earnings Before Interest & Taxes 4,314,217 10,687,104 17,729,931 25,491,943 34,604,392 40,343,538 43,283,185 46,319,887 49,450,107 52,669,009

Subtotal - - - - - - - - - -

Earnings Before Tax - 4,314,217 10,687,104 17,729,931 25,491,943 34,604,392 40,343,538 43,283,185 46,319,887 49,450,107 52,669,009

Tax 862,843 2,137,421 3,545,986 5,098,389 6,920,878 8,068,708 8,656,637 9,263,977 9,890,021 10,533,802

NET PROFIT/(LOSS) AFTER TAX 3,451,374 8,549,683 14,183,945 20,393,555 27,683,513 32,274,830 34,626,548 37,055,909 39,560,085 42,135,207

Page 23: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 21

12.2 Balance Sheet

Calculations SMEDA

Balance Sheet

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

Current assets

Cash & Bank 1,500,000 17,677,024 40,194,427 66,945,244 96,964,593 124,005,195 151,492,117 177,791,239 203,206,151 227,817,686 254,829,462

Accounts receivable 2,899,726 3,311,487 4,185,552 5,165,759 6,262,686 7,284,519 7,997,786 8,557,632 9,156,666 9,797,632

Equipment spare part inventory 2,000,000 2,100,000 2,205,000 2,315,250 2,431,013 2,552,563 2,680,191 2,814,201 2,954,911 3,102,656 -

Pre-paid insurance 613,525 547,823 482,120 416,418 350,715 355,070 284,056 213,042 142,028 71,014 -

Total Current Assets 4,113,525 23,224,572 46,193,035 73,862,463 104,912,079 133,175,513 161,740,884 188,816,269 214,860,721 240,148,022 264,627,095

Fixed assets

Land 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000

Building/Infrastructure 55,644,629 52,862,398 50,080,166 47,297,935 44,515,703 41,733,472 38,951,241 36,169,009 33,386,778 30,604,546 27,822,315

Machinery & equipment 103,640,950 93,276,855 82,912,760 72,548,665 62,184,570 51,820,475 41,456,380 31,092,285 20,728,190 10,364,095 -

Furniture & fixtures 448,150 403,335 358,520 313,705 268,890 224,075 179,260 134,445 89,630 44,815 -

Office vehicles 1,450,000 1,160,000 870,000 580,000 290,000 2,335,240 1,868,192 1,401,144 934,096 467,048 -

Office equipment 424,200 381,780 339,360 296,940 254,520 212,100 169,680 127,260 84,840 42,420 -

Total Fixed Assets 171,607,929 158,084,368 144,560,806 131,037,245 117,513,683 106,325,362 92,624,752 78,924,143 65,223,533 51,522,924 37,822,315

Intangible assets

Pre-operation costs 2,823,000 2,258,400 1,693,800 1,129,200 564,600 - - - - - -

Legal, licensing, & training costs 1,716,079 1,544,471 1,372,863 1,201,256 1,029,648 858,040 686,432 514,824 343,216 171,608 -

Total Intangible Assets 4,539,079 3,802,871 3,066,663 2,330,456 1,594,248 858,040 686,432 514,824 343,216 171,608 -

TOTAL ASSETS 180,260,534 185,111,811 193,820,505 207,230,164 224,020,010 240,358,914 255,052,068 268,255,235 280,427,470 291,842,554 302,449,409

Current liabilities

Accounts payable 1,227,335 1,511,081 1,837,323 2,211,692 2,640,524 3,005,384 3,279,107 3,578,861 3,907,183 3,999,095

Short term debt - - - - - - - - - - -

Other liabilities

Total Current Liabilities - 1,227,335 1,511,081 1,837,323 2,211,692 2,640,524 3,005,384 3,279,107 3,578,861 3,907,183 3,999,095

Other liabilities

Deferred tax 862,843 3,000,264 6,546,251 10,364,095 10,364,095 8,291,276 6,218,457 4,145,638 2,072,819 -

Total Long Term Liabilities - 862,843 3,000,264 6,546,251 10,364,095 10,364,095 8,291,276 6,218,457 4,145,638 2,072,819 -

Shareholders' equity

Paid-up capital 180,260,534 180,260,534 180,260,534 180,260,534 180,260,534 180,260,534 180,260,534 180,260,534 180,260,534 180,260,534 180,260,534

Retained earnings 2,761,099 9,048,626 18,586,057 31,183,689 47,093,762 63,494,874 78,497,137 92,442,437 105,602,018 118,189,780

Total Equity 180,260,534 183,021,633 189,309,160 198,846,591 211,444,223 227,354,296 243,755,407 258,757,671 272,702,971 285,862,552 298,450,314

TOTAL CAPITAL AND LIABILITIES 180,260,534 185,111,811 193,820,505 207,230,164 224,020,010 240,358,914 255,052,068 268,255,235 280,427,470 291,842,554 302,449,409

Liabilities & Shareholders' Equity

Assets

Page 24: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 22

12.3 Cash Flow Statement

Calculations SMEDA

Cash Flow Statement

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

Operating activities

Net profit 3,451,374 8,549,683 14,183,945 20,393,555 27,683,513 32,274,830 34,626,548 37,055,909 39,560,085 42,135,207

Add: depreciation expense 13,523,561 13,523,561 13,523,561 13,523,561 13,523,561 13,700,609 13,700,609 13,700,609 13,700,609 13,700,609

amortization of pre-operating costs 564,600 564,600 564,600 564,600 564,600 - - - - -

amortization of training costs 171,608 171,608 171,608 171,608 171,608 171,608 171,608 171,608 171,608 171,608

Deferred income tax 862,843 2,137,421 3,545,986 3,817,844 - (2,072,819) (2,072,819) (2,072,819) (2,072,819) (2,072,819)

Accounts receivable (2,899,726) (411,761) (874,064) (980,207) (1,096,927) (1,021,834) (713,267) (559,845) (599,034) (640,967)

Equipment inventory (2,000,000) (100,000) (105,000) (110,250) (115,763) (121,551) (127,628) (134,010) (140,710) (147,746) 3,102,656

Advance insurance premium (613,525) 65,703 65,703 65,703 65,703 (4,355) 71,014 71,014 71,014 71,014 71,014

Accounts payable 1,227,335 283,746 326,242 374,370 428,831 364,861 273,723 299,754 328,322 91,912

Cash provided by operations (2,613,525) 16,867,298 24,779,560 31,397,331 37,815,271 41,149,282 43,360,641 45,923,407 48,525,521 51,012,040 56,559,221

Financing activities

Issuance of shares 180,260,534 - - - - - - - - - -

Cash provided by / (used for) financing activities 180,260,534 - - - - - - - - - -

Investing activities

Capital expenditure (176,147,009) - - - - (2,335,240) - - - - -

Cash (used for) / provided by investing activities (176,147,009) - - - - (2,335,240) - - - - -

NET CASH 1,500,000 16,867,298 24,779,560 31,397,331 37,815,271 38,814,043 43,360,641 45,923,407 48,525,521 51,012,040 56,559,221

Cash balance brought forward 1,500,000 17,677,024 40,194,427 66,945,244 96,964,593 124,005,195 151,492,117 177,791,239 203,206,151 227,817,686

Cash available for appropriation 1,500,000 18,367,298 42,456,584 71,591,758 104,760,515 135,778,635 167,365,836 197,415,524 226,316,760 254,218,190 284,376,907

Dividend 690,275 2,262,156 4,646,514 7,795,922 11,773,440 15,873,718 19,624,284 23,110,609 26,400,505 29,547,445

Cash balance 1,500,000 17,677,024 40,194,427 66,945,244 96,964,593 124,005,195 151,492,117 177,791,239 203,206,151 227,817,686 254,829,462

Cash carried forward 1,500,000 17,677,024 40,194,427 66,945,244 96,964,593 124,005,195 151,492,117 177,791,239 203,206,151 227,817,686 254,829,462

Page 25: Pre-Feasibility Study - · PDF fileProduct(s) include Apple, Mango Citrus and other fruits and vegetables. Capacity; ... Pre-Feasibility Study Modified CA Cold Storage June 2017 7

Pre-Feasibility Study Modified CA Cold Storage

June 2017 23

13 KEY ASSUMPTIONS

13.1 Operating Cost Assumptions

Description Details

No. of Working Days in One Year 360

No. of Working Hours in One Day 24

13.2 Production Cost Assumptions

Description Details

Starting Storage Capacity Utilization 50%

Maximum Storage Capacity Utilization 95%

Capacity Utilization Growth Rate / Yr. 10%

13.3 Revenue Assumptions

Description Details

Rental Price /kg/month (Incl. sorting & grading) Rs. 06

Sale Price Growth Rate 07%

13.4 Financial Assumptions

Description Details

Debt 0%

Equity 100%

Required Rate of Return on Equity 10%