+ All Categories
Home > Documents > Prefabricated Bridge Elements and Systems · PDF filePrefabricated Bridge Elements and Systems...

Prefabricated Bridge Elements and Systems · PDF filePrefabricated Bridge Elements and Systems...

Date post: 16-Mar-2018
Category:
Upload: dinhquynh
View: 235 times
Download: 2 times
Share this document with a friend
20
33-1 33 Prefabricated Bridge Elements and Systems Michael M. Sprinkel, P.E. * 33.1 Practical Applications........................................................33-1 33.2 Types of Elements .............................................................33-3 Precast and Prestressed Slab Spans Multi-Stemmed Beam Prestressed Double-Tee and Channel Prestressed Inverted Channel Prestressed Single-Tee Prestressed I-Beams Prestressed Box Beams Prestressed Bulb-Tee Segmental Construction Prestressed Subdeck Panels Precast and Prestressed Deck Slabs Precast Parapet Substructure Elements Precast Culverts 33.3 Construction Considerations .........................................33-15 33.4 Looking Ahead ................................................................33-16 References ...................................................................................33-16 33.1 Practical Applications A prefabricated concrete bridge element is defined as part of a bridge that is precast away from its final position (Sprinkel, 1985). A system is a combination of elements. Prefabricated concrete bridge elements and systems are used to construct new bridges and to rehabilitate or replace old ones. Prefabricated elements can reduce design effort, enhance quality, simplify and expedite construction, lessen inconve- nience to the traveling public, improve safety for workers and the traveling public, and minimize cost. Design effort can be reduced when the same design is used on multiple bridge projects. Historically, bridge-design engineers have customized bridge designs for each site, making the prefabrication of elements impractical except for use on major multiple-span bridge projects. Recent efforts have involved making more adjustments to the site to accommodate a standard design and have developed designs that are more versatile. Fabricating elements in the controlled environment of a precast or prestressed concrete plant enhances quality. Plants are typically certified and well established, although temporary on-site plants are constructed to produce elements for a major bridge project. Plants can use high-quality reusable forms; temperature, relative humidity, and wind can be controlled; the concrete can be batched at the plant; and labor is more efficient because tasks are repeated. Prefabricated elements, set in place at the bridge site, simplify and expedite construction by minimizing forming, form removal, and placing and curing concrete in a difficult-to-control environment. In addition, prefabricating the bridge element away from its final location minimizes traffic safety issues for both the * Associate Director, Virginia Transportation Research Council, Charlottesville, Virginia, and Section Head, Trans- portation Research Board; expert in materials and construction, particularly public works. © 2008 by Taylor & Francis Group, LLC
Transcript

33-1

33Prefabricated Bridge

Elements and Systems

Michael M. Sprinkel, P.E.*

33.1 Practical Applications........................................................33-133.2 Types of Elements .............................................................33-3

Precast and Prestressed Slab Spans • Multi-Stemmed Beam • Prestressed Double-Tee and Channel • Prestressed Inverted Channel • Prestressed Single-Tee • Prestressed I-Beams • Prestressed Box Beams • Prestressed Bulb-Tee • Segmental Construction • Prestressed Subdeck Panels • Precast and Prestressed Deck Slabs • Precast Parapet • Substructure Elements • Precast Culverts

33.3 Construction Considerations .........................................33-1533.4 Looking Ahead ................................................................33-16References ...................................................................................33-16

33.1 Practical Applications

A prefabricated concrete bridge element is defined as part of a bridge that is precast away from its finalposition (Sprinkel, 1985). A system is a combination of elements. Prefabricated concrete bridge elementsand systems are used to construct new bridges and to rehabilitate or replace old ones. Prefabricatedelements can reduce design effort, enhance quality, simplify and expedite construction, lessen inconve-nience to the traveling public, improve safety for workers and the traveling public, and minimize cost.Design effort can be reduced when the same design is used on multiple bridge projects. Historically,bridge-design engineers have customized bridge designs for each site, making the prefabrication ofelements impractical except for use on major multiple-span bridge projects. Recent efforts have involvedmaking more adjustments to the site to accommodate a standard design and have developed designs thatare more versatile. Fabricating elements in the controlled environment of a precast or prestressed concreteplant enhances quality. Plants are typically certified and well established, although temporary on-siteplants are constructed to produce elements for a major bridge project. Plants can use high-quality reusableforms; temperature, relative humidity, and wind can be controlled; the concrete can be batched at theplant; and labor is more efficient because tasks are repeated.

Prefabricated elements, set in place at the bridge site, simplify and expedite construction by minimizingforming, form removal, and placing and curing concrete in a difficult-to-control environment. In addition,prefabricating the bridge element away from its final location minimizes traffic safety issues for both the

* Associate Director, Virginia Transportation Research Council, Charlottesville, Virginia, and Section Head, Trans-portation Research Board; expert in materials and construction, particularly public works.

© 2008 by Taylor & Francis Group, LLC

33-2 Concrete Construction Engineering Handbook

traveling public and the worker and minimizes delays and inconvenience for the motorist. Lanes can beopen during peak travel periods and closed during off-peak periods for the rapid replacement of bridgesections. Once in place, the fully cured element is ready to receive traffic. Polymer concrete and high-early-strength patching materials now make the rapid connection of prefabricated elements easier. The mostsignificant reasons to use prefabricated elements include the economy realized from the repeated use offorms, the reduction in on-site construction time, and improved safety because of the rapid construction.Initial construction costs can be lower, depending on the costs for cast-in-place concrete construction.Life-cycle costs will likely be lower because of the higher quality and longer life of the structure. Whenthe costs of delays and inconvenience to the motorist are considered, prefabricated elements that can beassembled and put into use during off-peak traffic periods will almost always be economical. Prefabricatedelements are increasingly popular as highway funds are used to rehabilitate and replace deterioratingbridges. Bridges with high volumes of traffic can usually only be replaced during off-peak traffic periods(at night or on weekends), and prefabricated elements provide an attractive solution. Mass-produced,easily assembled elements are just as practical for replacing bridges on low-volume roads.

Prefabricated elements, however, are not the best solution for every bridge construction and replace-ment project. The demand for a particular shape may be too low to justify an investment in forms.Shipping costs may be too high because the nearest plant is hundreds of miles away. Connection detailsmay cause maintenance problems that result in a higher life-cycle cost. An advantage of concrete is thatit can be formed into almost any shape; thus, the architectural and site requirements for a bridge maybe so complicated that custom on-site forming is required and the prefabrication of elements is notpractical. A decision-making tool can be used to decide whether or not a prefabricated bridge is effectivefor a specific location (Rawls, 2006).

A 1984 survey indicated that the use of prefabricated bridge elements was increasing and that thestructures were economical in many situations (Hill and Shirole, 1984). Earlier applications includedprecast and prestressed slabs and I-beams for simple spans. Later, use expanded to include subdeck panels,deck slabs, parapets, and substructure elements. Currently, all elements in a bridge can be economicallyconstructed or replaced with prefabricated ones. Entire spans and bridges can be moved into place witha brief road closure.

In the past, cranes were typically used to move large bridge elements into place. Recent developmentswith bridge-moving systems have facilitated the rapid replacement of entire bridges or bridge spans(FHWA, 2004). The new systems include self-propelled modular trailers that are multi-axle, computer-controlled vehicles that can move in any horizontal direction without damaging or deforming the element.Other systems include special load frames, modular jacking systems, horizontally skidding or slidingsystems, incremental launching systems, floating barges, and vertically lifting systems.

High-performance concrete mixtures containing pozzolans and admixtures have led to the fabricationof elements with concrete compressive strengths in excess of 10,000 psi (68.9 MPa). The higher qualityconcretes allow smaller cross-sections, longer spans, greater girder spacings, and longer service. A varietyof deck wearing and protection systems can be placed on the prefabricated elements to provide a smooth-riding, skid-resistant surface that retards the penetration of chlorides and water. Wearing and protectionsystems that have been used include a thin bonded hydraulic cement concrete overlay, waterproofmembrane overlaid with asphalt, thin bonded epoxy concrete overlay, additional monolithically castconcrete on the precast element, and low-permeability concrete in the precast element (Sprinkel, 2004).

Already in the new millennium, many publications have supported the use of prefabricated bridgeelements and systems. In response to public demand for minimized traffic disruption, the Texas Depart-ment of Transportation has been a leader in the use of prefabricated bridge elements in bridge designand construction (Pruski et al., 2002). Prefabricated bridges are meeting growing market demands forfast and efficient structures (Johnson, 2002). New girder designs, strand technologies, and concrete mixesare making precast prestressed concrete bridges more popular (Dick, 2002). New guidelines and loadand resistance factor design (LRFD) specifications for full-depth, precast-concrete bridge deck panelsystems with no overlays or post-tensioning are now available (Badie et al., 2006). According to theFederal Highway Administration (FHWA), the use of prefabricated elements can improve construction

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-3

zone safety, minimize the traffic impacts, and improve constructability (FHWA, 2002). A brochureprovides descriptions of 15 bridge projects that solved site-specific challenges using prefabricated bridgeelements and systems (AASHTO, 2002). Implementation efforts by the Federal Highway Administrationand the American Association of State Highway and Transportation Officials (AASHTO) have signifi-cantly increased the acceptance and use of prefabricated bridge elements and systems (AASHTO, 2004;FHWA, 2003; FHWA/AASHTO, 2004).

33.2 Types of Elements

The most frequently used prefabricated concrete elements and systems are the prestressed I-beam,prestressed box beam, prestressed channel, and slab span (Sprinkel, 1985). The prestressed subdeck panelwas frequently used in the late 1970s and 1980s, but such use has declined in recent years because ofreflective cracking in the site-cast overlay concrete. Precast parapets have been used on occasion, butproblems with leakage under the parapet have curtailed acceptance. Recent years have seen increasedinterest in post-tensioned segmental construction for economy in medium and long spans, substructureelements to reduce the environmental impact of construction, and full-depth deck replacement slabs tofacilitate the rapid replacement of decks during off-peak traffic periods. Longitudinal, partial-depth, orfull-depth deck slabs that are precast on one or more concrete or steel beams have also been successfullyused (FHWA, 2004).

33.2.1 Precast and Prestressed Slab Spans

Slab span elements (Figure 33.1) may be cast in various widths, depths, and lengths to accommodatespans up to 50 ft (15 m) (Table 33.1). Shorter slabs may be conventionally reinforced and fabricated atsimple precast plants. Longer slabs are typically voided and prestressed or post-tensioned (PCI, 1975;VTRC, 1980). Slabs are easy to fabricate, transport, and erect. Department of Transportation (DOT)bridge crews have precast slabs (Sprinkel, 1976).

FIGURE 33.1 Slab span. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRP Synthesis 119,Transportation Research Board, Washington, D.C., 1985.)

Field weld

Portland cement grout

Tie rod4 53c3b3a21

1. Solid slab—Dimension range: 8'–1'-0"; width, 3'-0"–6'-0"

4. Typical connection—Weldplate (also see Figure 33.2)5. Typical connection—Tie rod

2. Voided slab—Dimension range: 12"–2'-0"; width, 3'-0"–6'-0"

3a, b, c. Typical keyway details

Bituminous wearing surfaceGrouted keyway

Voided slabs Solid slabs

© 2008 by Taylor & Francis Group, LLC

33-4 Concrete Construction Engineering Handbook

33.2.2 Multi-Stemmed Beam

Multi-stemmed beams (Figure 33.2) may be cast in various lengths and increments of width to accom-modate short spans. Weld plates and grouted keyways provide shear transfer between beams.

33.2.3 Prestressed Double-Tee and Channel

Most prestressed concrete producers have forms for fabricating double-tees and channels for use inbuilding construction. Additional prestressing, wider webs, and thicker flanges are typically required forbridge loadings (Figure 33.3) (Tokerud, 1975). Forms have been modified and new forms fabricated toproduce members for highway applications when there has been sufficient support provided by a DOTto justify the investment in forms (Sprinkel and Alcoke, 1977). Channel beams and double-tees aretypically used for medium-length spans, and shear transfer between beams is typically provided bygrouted keyways or weld plates. Site-cast concrete is usually placed as an overlay, but channel and double-tee members have been overlaid with asphalt (PCI, 1975).

TABLE 33.1 Typical Span Lengths for Elements

Element Length (ft) Length (m)

Precast slab span 10–30 3–9 Prestressed slab span 20–50 6–15Multi-stemmed beam 25–50 8–15Prestressed double-tee and channel 20–60 6–18Prestressed inverted channel 30–80 9–24Prestressed single-tee 30–80 9–24Prestressed I-beam 40–100 12–30Prestressed box beam 50–100 15–30Prestressed bulb-tee 60–80 18–24Post-tensioned segmental 50–400 15–122

FIGURE 33.2 Multi-stemmed beam. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRPSynthesis 119, Transportation Research Board, Washington, D.C., 1985.)

Weld plate

Keyway to be groutedSlab reinforcingShear reinforcing

Weld studsAnglePlateWeld

1'-0"–2'-0"

4'-0"–6'-0"

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-5

33.2.4 Prestressed Inverted Channel

The inverted channel (Figure 33.4) may be cast in the inverted position or cast in conventional channelforms and inverted before erection at the bridge site. Longer spans can be achieved in the inverted positionbecause more prestressing can be placed in the bottom of the beam. The Missouri Department ofTransportation used the inverted channel on many bridges (Salmons, 1971). Site-cast concrete must be

FIGURE 33.3 Double-tee and channel. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRPSynthesis 119, Transportation Research Board, Washington, D.C., 1985.)

FIGURE 33.4 Prestressed inverted channel. (From Sprinkel, M.M. 1985. Prefabricated Bridge Elements and Systems,NCHRP Synthesis 119, Transportation Research Board, Washington, D.C.)

Keyway to be grouted

3'-0"–5'-0"

4'-0"–7'-0"

1'-6"–3'-0"

20'–60'

Double-teeDetail of weld plate

connection

Reinforcing bar

Metal angle

Channel beam

Cast-in-place concrete deckReinforcing bar

Stay-in-place steel form

Inverted prestressed

concrete channel

3'-0"–5'-0"

1'-6"–3'-0"

© 2008 by Taylor & Francis Group, LLC

33-6 Concrete Construction Engineering Handbook

placed to connect the channels and provide a deck surface. An alternative to the channel is invertedT-beams placed adjacent to each other and then made composite with cast-in-place concrete placedbetween the webs of the tees and over the tops of the stems to form a solid member (see FHWA, 2004).

33.2.5 Prestressed Single-TeePrestressed single-tee beams are used in building construction. Prestressed concrete plants can some-times fabricate the beams for shorter spans using the same forms as used in building construction withadditional prestressing strands to accommodate the heavier loading. With adequate support from aDOT, a precast producer can invest in new forms to produce longer span beams (Figure 33.5) suitablefor highway loadings (Sprinkel and Alcoke, 1977). The single-tee is unstable by design and must besupported at the bridge site to prevent overturning until the diaphragms can be cast and the keywaysgrouted. Site-cast concrete is usually placed to connect the tees and to provide a deck (Sprinkel, 1978).An asphalt wearing surface can be used when the flange of the tee is thick enough to accommodateshear loads.

33.2.6 Prestressed I-BeamsThe prestressed I-beam (Figure 33.6) is the prefabricated element most used by DOTs (Sprinkel, 1985).Many prestressed concrete producers invested in forms during the construction of the interstate system.The standard AASHTO cross-sections simplify design and provide for mass production (Panak, 1982).The beams, cast in a variety of widths and depths, are economical for spans of 40 to 100 ft (12 to 30 m).Spans up to 140 ft (43 m) have been constructed (Anderson, 1972; PCI, 1975). Longer spans can beachieved by field-connecting the beams end to end and post-tensioning them (Fadl et al., 1977; Oesterleet al., 1989). The prestressed beams can be positioned more rapidly than a site-cast concrete beam canbe constructed. For convenience, other elements are typically constructed with site-cast concrete, limitingthe economy of mass production and rapid assembly to the beams. Prestressed concrete subdeck panelshave been used, and a National Cooperative Highway Research Program (NCHRP) publication, RapidReplacement of Bridge Decks, addresses the development of designs for prestressed full-depth deck panels

FIGURE 33.5 Prestressed single-tee. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRPSynthesis 119, Transportation Research Board, Washington, D.C., 1985.)

Tee with deck precast on flange

Weld plate pocket

Keyway to be grouted with nonshrink cement paste

Tee with lower part of deck precast on flange

Bituminous wearing surface

Site-cast concrete wearing surface

2'-0"–4'-4"

4'-0"–6'-0"

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-7

to be used with the beams (Tadros and Baishya, 1998). A recently completed NCHRP project, Full-Depth,Precast-Concrete Bridge Deck Panel Systems, includes designs for full-depth, precast deck panels withoutpost-tensioning and overlays (Badie et al., 2006).

33.2.7 Prestressed Box BeamsThe box beam (Figure 33.7) may be precast in a range of widths, depths, and lengths to accommodatespans of approximately 50 to 100 ft (15 to 30 m) (PCI, 1975). Boxes placed next to each other are typicallytensioned in the transverse direction and covered with a wearing surface of asphalt. Boxes spaced apart

FIGURE 33.6 Prestressed I-beam. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRP Syn-thesis 119, Transportation Research Board, Washington, D.C., 1985.)

FIGURE 33.7 Prestressed box beam. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRPSynthesis 119, Transportation Research Board, Washington, D.C., 1985.)

Standard AASHTOI Beams20"

16"12"

12"

3'-6"

5'-3"

2'-4"26"18" 22"16"

6'-0"

2'-4"

3'-6"

4'-6"

3'-0"3'-9"

2'-4"VIVIVIIIIII

Intermediate diaphragmCast-in-place concrete deckStirrupsPrestressed concrete subdeckCast-in-place concrete deckMortar bed

(1)Typical box beam-dimension range:

depth, 2'–3'-6"; width, 3'–6'

(2)Typical longitudinal section

(3)Typical keyway detail

Cast-in-place concrete wearing surface

Prestressed concrete subdeck panel(see Figure 33.10 for detail)

Bituminous wearing surfaceGrouted keyway(see Figure 33.1 for connection details)

Spread boxes Adjacent boxes

© 2008 by Taylor & Francis Group, LLC

33-8 Concrete Construction Engineering Handbook

are connected with diaphragms. Site-cast concrete is typically used for the diaphragms and deck. Pre-stressed concrete subdeck panels can also be used with the box beams. A methodology for the transversedesign of concrete box beams without a composite topping has been developed (El-Remaily et al., 1996).This procedure requires that the post-tensioning be applied after the shear keys are grouted, and thedesign provides a more durable structure. A bridge with a precast double-cell adjacent box beam super-structure was recently constructed in Pennsylvania (Scanlon et al., 2002).

33.2.8 Prestressed Bulb-Tee

Some DOTs have developed modified versions of the AASHTO girder (Figure 33.8) that are moreeconomical for spans greater than 80 ft (PCI, 1972; Rabbat et al., 1982). The beams have a high sectionmodulus-to-weight ratio, and spans up to 160 ft have been constructed.

FIGURE 33.8 Prestressed bulb-tee. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRP Syn-thesis 119, Transportation Research Board, Washington, D.C., 1985.)

Minimum width and depth

5

63

23

15

9*

24

120*

2

24

63

3½*

33½* 19½

60*

Maximum width and depth

2 5

23

15

57

*

All dimensions in inches

* Variable dimension

19½

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-9

33.2.9 Segmental Construction

Elements (Figure 33.9) are typically full width, match cast, prestressed in the transverse direction, andpost-tensioned in the longitudinal direction (VTRC, 1981). The elements are suitable for use on a widerange of span lengths. For shorter spans, the elements are usually erected on false work or assembled ona truss supported from pier to pier. For longer spans, the elements are erected by balanced cantilever,incremental launching, or progressive placing (Sprinkel, 1985). A patented segmental concrete overpasssystem economical for spans of 50 to 115 ft (15 to 35 m) provides at least 2 to 3 ft (0.6 to 0.9 m) ofincreased under-clearance and halves the on-site construction time for a two-span structure (Freyermuth,1996). A procedure for the economical replacement of the top slab of a precast post-tensioned segmentalbridge has recently been developed, so deck deterioration will not require the replacement of the super-structure (Stelmack and Trapani, 1991).

33.2.10 Prestressed Subdeck Panels

Prestressed subdeck panels are cast in a variety of lengths and widths, typically 4 to 8 ft (1.2 to 2.4 m).The length is a function of the spacing of the supporting beams. The panels are typically 3.5 in. (89 mm)thick and are set in a bed of grout about 0.5 in. (13 mm) thick. Site-cast concrete is placed over thepanels to provide a reinforced deck (Figure 33.10). The panels are easily installed with a small crane andseveral laborers and do not require temporary forms or platforms to work from. Cracks usually occurin the site-cast concrete directly above the joints between the panels; consequently, many DOTs havediscontinued or restricted the use of the panels. Cracking is less pronounced when the panels are placedon prestressed girders with short spans. Precast concrete subdeck panels can provide an economical andrapidly constructed deck (PCI, 1987).

33.2.11 Precast and Prestressed Deck Slabs

The deck is usually the first element in a bridge to deteriorate and to require funds for rehabilitation.In situations where traffic volumes are high, it is often necessary to rehabilitate or replace the deck insections during off-peak periods. Because of the time required for site-cast concrete to cure, a number

FIGURE 33.9 Post-tensioned segmental construction. (From Sprinkel, M.M., Prefabricated Bridge Elements andSystems, NCHRP Synthesis 119, Transportation Research Board, Washington, D.C., 1985.)

12'–20'

32'–42'

8'–10'

18'–25'

8½"–20"

Truss hanger rods

Truss assembly

Typical segment

© 2008 by Taylor & Francis Group, LLC

33-10 Concrete Construction Engineering Handbook

of replacement strategies have been developed using prefabricated deck slabs (Issa et al., 1995a,b). Mostof the systems involve a transverse segment (Figure 33.11) connected to the supporting beams with arapid-curing polymer or hydraulic cement concrete. Shear transfer between adjacent slabs is achievedthrough the use of grouted keyways, site-cast concrete, and post-tensioning. Composite action isachieved through the use of studs on steel beams that extend into voided areas in the slabs that are thenfilled with polymer or hydraulic cement concrete.

Precast deck slabs can behave in a full-composite manner when connected to steel stringers with studsand epoxy mortar and when keyways are grouted with epoxy mortar (Osegueda et al., 1989). An earlierstudy identified some suitable connection details and concluded that the deck slabs are more economicalthan site-cast concrete because of the structural efficiency provided by post-tensioning and prestressingand because of the reduced construction time (Berger, 1983). Improved connection details for the useof panels on steel beams and prestressed concrete beams have been developed (Tadros and Baishya, 1998).More recently, a special loop bar reinforcement detail has been developed to provide live load distributionacross transverse and longitudinal joints (see FHWA, 2004). A new full-depth precast prestressed concretebridge deck slab system has been developed that includes stemmed slabs, transverse grouted joints,longitudinal post-tensioning, and welded threaded and headless studs (Tadros and Baishya, 1998). Thedeck slabs are thinner and lighter than a conventional deck and can be constructed faster.

Prestressed deck slabs typically have been used on major bridge deck replacement projects (Figure33.12) such as the Woodrow Wilson Bridge (Lutz and Scalia, 1984). Also, most replacements have involvedthe use of transverse slabs. The decks on the George Washington Memorial Parkway were replaced usingprecast longitudinally post-tensioned transverse deck slabs (Jakovich and Alvarez, 2002). A latex-modified

FIGURE 33.10 Prestressed subdeck panels. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems,NCHRP Synthesis 119, Transportation Research Board, Washington, D.C., 1985.)

Prestressed concrete I beam

Precast prestressed concrete subdeck panel

Mortar bedPrestressing strand

Reinforcing barSite-cast concrete deck

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-11

FIGURE 33.11 Prestressed deck slabs. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRPSynthesis 119, Transportation Research Board, Washington, D.C., 1985.)

FIGURE 33.12 Prestressed post-tensioned deck slabs were installed at night to replace the deck of the WoodrowWilson Bridge.

6"

15"

4 –0"

14"

Steel beamStuds as required

Epoxy mortar bed

Grouted keyway

Bituminous overlay

Void filled with epoxy mortar

Post-tensioning

duct

Prestressed

deck slab

Movable

barrierTwo-way

traffic pattern

© 2008 by Taylor & Francis Group, LLC

33-12 Concrete Construction Engineering Handbook

concrete overlay was placed over the slabs. The truss spans of the deck on I-95 in Richmond, Virginia,were recently replaced with night lane closures using the full-depth transverse deck slabs (Figure 33.13).The slabs were also used to replace the deck on Route 50 in Fairfax County, Virginia (Babaei et al., 2001).The Virginia Department of Transportation first used transverse precast deck slabs to replace a deck onRoute 235 over Dogue Creek in Fairfax County in 1981 (Sprinkel, 1982). Longitudinal slabs weresuccessfully used to rehabilitate the Freemont Street Bridge (Smyers, 1984), and a new bridge was builtin Thailand (Zeyher, 2003).

Longitudinal, partial-depth, or full-depth deck slabs that that are precast on one or more concrete orsteel beams have also been used successfully (FHWA, 2004). The superstructure elements are set next toeach other and are typically connected by transverse post-tensioning in the deck and diaphragms betweenthe beams. Keyways in the deck are grouted. The deck on I-95 in Richmond, Virginia, was recentlyreplaced with night lane closures using the full-depth deck slabs on steel beam superstructure elements.When partial depth deck superstructure elements are set next to each other, reinforced site-cast concretefacilitates the connection of the elements.

33.2.12 Precast Parapet

The precast parapet (Figure 33.14) lends itself to prefabrication because it has a standard shape and canbe easily mass produced. Several connection details have been developed to anchor the parapet. Theparapet has been used in a number of states, but acceptance has been slow because of problems withwater and chloride solutions leaking between the base of the parapet and the top of the deck.

33.2.13 Substructure Elements

More time is usually required to construct the substructure than the superstructure, and major reductionsin construction time can be achieved by prefabricating the elements of the substructure. Most substruc-ture elements have been prefabricated. Examples include pilings, piers, pier caps, abutments, and wingwalls. Figure 33.15 shows abutment and wing-wall panels placed on temporary pads and anchored withweld plates and a site-cast concrete footing (PCI, 1975). To simplify erection, abutment and wing-wallelements have been precast with the footing and set on a site-cast footing (Sprinkel, 1985). Prestressedpiling has been used for years, but pile caps are usually site cast. Bridges with prefabricated piers, piercaps, abutments, and wing walls are limited in number but use is increasing, particularly by the TexasDepartment of Transportation (Billington et al., 1999; Matsumoto et al., 2001, 2002). A bridge with a

FIGURE 33.13 Special loop bar connection detail for deck slabs. (From FHA, Prefabricated Bridge Elements andSystems in Japan and Europe, Summary Report, International Technology Exchange Programs, Federal HighwayAdministration, Washington, D.C., 2004; http://www.fhwa.dot.gov/bridge/prefab/pbesscan.htm.)

50 concrete

overfill

22 dia. studs

203 spa. (typ.)

305

Blockout

Typical each girder

Concrete milled

to an even surface

Steel reinforcing

(typical)CL Exsiting

rolled beamConcrete-filled grid

reinforced deck

18

2

13

2

Polymer

concrete

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-13

FIGURE 33.14 Precast parapet. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRP Synthesis119, Transportation Research Board, Washington, D.C., 1985.)

FIGURE 33.15 Precast abutment and wing wall. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems,NCHRP Synthesis 119. Transportation Research Board, Washington, D.C., 1985.)

Grouted void#8 bar

Mortar bed

Reinforcing bar

2'-8"

Dowel sleeve for anchorage of deck members

Weld plate

Precast abutment panel

Temporary bracing

Reinforcing bar

Deadman footing

Concrete erection pad

Reinforcing bar in footing

Site-cast concrete footing

© 2008 by Taylor & Francis Group, LLC

33-14 Concrete Construction Engineering Handbook

precast abutment was recently constructed in Pennsylvania (Scanlon et al., 2002). It is difficult tostandardize the elements because of differences between bridge sites and between piers at the same sitethat involve soil characteristics, location of bedrock, and the depth at which acceptable bearing can beobtained (Ganga Rao, 1978). A well-known example of the use of prefabricated piers is the Linn CoveViaduct (Anon., 1984). The entire bridge was prefabricated to minimize environmental impact. Precastsegmental superstructure segments were progressively placed and post-tensioned until a pier locationwas reached. Working from the cantilevered superstructure, holes were drilled into the ground. Pre-stressed piles were placed in the holes, and precast pier segments were placed and post-tensioned together.Site-cast concrete was placed around the bottom segment (Figure 33.16). The SPER system is a methodof rapid construction of piers using precast concrete panels as both structural elements and formworkfor cast-in-place concrete (see FHWA, 2004). The Texas Department of Transportation has developedand used a precast pier bent (Figure 33.17). The bent is placed on piers, and the voids in the bent aroundthe reinforcement that extends from the piers are filled with grout.

FIGURE 33.16 Prefabricated pier segments.

FIGURE 33.17 Precast concrete pier bent. (Figure courtesy of the Texas Department of Transportation, Dallas.)

Precast post-tensionedsuperstructure segment

Precastpost-tensionedpier segment

Site-cast footing

Pile

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-15

33.2.14 Precast Culverts

Culverts can be used instead of bridges in situations where the cross-section will not restrict flow. Culvertsare easy to install, do not have a deck to deteriorate, and seldom require extensive plans. Culverts cannotbe used on navigable streams. Precast culvert designs (Figure 33.18) include the pipe, box, inverted U,and arch. Site-cast footings and end walls are typically used with the inverted U and the arch. Concretepipe is used for spans of 1 to 10 ft (0.3 to 3 m), and concrete boxes are used for spans of 4 to 12 ft (1.2to 3.7 m) (Concrete Pipe and Products Company, 1993). Precast U-shaped culverts have been used forspans up to 16 ft (4.9 m), and the arch shape has been used for 40-ft (12-m) spans (Conspan BridgeSystems, Inc., 1995; Lambert, 1982).

33.3 Construction Considerations

On-site construction time is typically reduced when prefabricated elements are used because the concreteforming, casting, and curing occur at a precast plant. Quality elements are typically produced undercontrolled conditions. Elements are typically inspected at the plant and approved for shipment. Elementsshould fit together at the site when they are fabricated to the tolerances prescribed by the PrestressedConcrete Institute (PCI, 1977, 1978). Precasting operations should be organized to minimize the numberof times an element must be moved. Excessive handling is costly and time consuming and increases thechances for damage (Waddell, 1974). The contractor should have an approved erection plan. Propercommunication between the fabricator and contractor is essential. Elements should be delivered in theorder in which they are to be assembled. Each element should be checked for damage that might haveoccurred during delivery and the plant stamp of approval should be verified. The hardware, rigging, andequipment required for handling the elements and the lifting locations should be preapproved beforelifting an element. Handling and erection stresses can be greater than in-service stresses. Care should betaken to keep the stresses to a minimum. When feasible, elements should be supported during erection

FIGURE 33.18 Precast culverts.

1'–10' 4'–12' 4'–16'

10'–40'

Precast pipe Precast or

site-cast boxInverted U-shaped precast

concrete culvert with

site-cast bottom or footings

Arch with site-cast footings

© 2008 by Taylor & Francis Group, LLC

33-16 Concrete Construction Engineering Handbook

as they are during delivery and storage. When lifting equipment is to be placed on the structure, the designshould be checked and approved to ensure that the structure is not overstressed. Lifting equipment shouldbe large enough to handle the elements. It is better to have equipment that is too large than too small.

Before placing elements, bearing areas should be properly prepared. Elements that fit properly can beassembled in a few minutes. Additional time is required to make corrections for improperly fittingelements. The advantage of match casting elements is a good fit. Several mortars and grouts for hydrauliccement and polymer concrete have been developed to facilitate the erection and connection of prefab-ricated elements (Gulyas et al., 1995). Temporary shims may be used. High-early-strength mortars andgrouts can anchor the elements in a short time. When the elements have been assembled, a wearing andprotection surface is usually installed. Asphalt is popular because of its low cost, but it should be usedin connection with a properly installed membrane to prevent the infiltration of water and chloride ionsinto the prefabricated elements. Hydraulic cement concrete overlays can be installed to provide the finalwearing surface. Bonded hydraulic cement concrete overlays can have a life of 30 years or more; however,these overlays are not easy to install, and construction should be done according to recommendedpractice. The recent failures of a number of bonded concrete overlays on major bridges before openingthem to traffic or shortly thereafter illustrate the difficulties associated with constructing a successfuloverlay. Thin epoxy overlays have been used successfully as a wearing and protection system. Finally,deck elements can be precast with the final wearing surface, and irregularities can be removed by shotblasting or grinding the surface to provide good ride quality (Sprinkel, 2004).

33.4 Looking Ahead

The use of prefabricated bridge elements and systems will continue to increase for many reasons. Withprefabrication, the work force can be more productive and can produce a better product in the controlledenvironment of a precast plant, compared to forming and placing reinforcement and concrete outdoors.The enhanced productivity and quality promote economy. The need to replace bridges and bridgeelements is growing as our transportation system ages. The number of structures subjected to highvolumes of traffic also continues to increase. Element replacement during off-peak traffic periods isbecoming a necessity, and replacement with prefabricated elements is one of the few feasible options.Reducing delays for the traveling public is an additional economic incentive to use prefabricated elements.In recent years, the connection details that have caused maintenance problems and reduced the servicelife of elements have been improved. Better designs, enhanced materials, and more post-tensioning areallowing the construction of bridges with prefabricated elements that are more economical on a life-cyclebasis than bridges constructed with site-cast concrete. There will always be a place for site-cast concrete,because concrete can take the shape of any form in which it is placed. This flexibility and versatility arenecessary to satisfy many construction needs. It would be foolish to try to prefabricate concrete for everysituation. Even so, the outlook for prefabricated bridge elements and systems has never been better. Theuse of prefabricated bridge elements and systems has increased significantly since the first edition of thisHandbook was published. Universities, state DOTs, the FHWA, and the bridge industry have takenleadership roles in the new developments. The FHWA Summary of Prefabricated Bridge Elements andSystems website provides abstracts and contact information for recent publications on the subject (FHWA,2004). Use will continue to increase as our roadways become more congested.

References

AASHTO. 2002. Prefabricated Bridges. Technical Implementation Group, American Association of StateHighway and Transportation Officials, Washington, D.C. (www.fhwa.dot.gov/download/bro-chure.pdf).

AASHTO. 2004. Prefabricated Bridge Elements and Systems Fact Sheet. Technical Implementation Group,American Association of State Highway and Transportation Officials, Washington, D.C.(www.fhwa.dot.gov/download/facts.pdf).

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-17

Anderson, A.R. 1972. Systems Concepts for Precast and Prestressed Concrete Bridge Construction, HRBSpecial Report 132: Systems Building for Bridges. Transportation Research Board, Washington,D.C.

Anon. 1984. Concrete today: markets, materials, and methods. Eng. News Rec., pp. 6, 8, 19, 20.Babaei, K., Fouladgar, A., and Nicholson, R. 2001. Nighttime Bridge deck replacement with full-depth

precast concrete panels at Route 7 over Route 50, Fairfax County, Virginia. In Proceedings of theTransportation Research Board Meeting, January 7–11, Washington, D.C.

Badie, S., Tadros, M., and Girgis, A. 2006. Full-Depth, Precast-Concrete Bridge Deck Panel Systems,NCHRP Report 12-65. National Cooperative Highway Research Program, TransportationResearch Board, Washington, D.C.

Berger, R.H. 1983. Full-Depth Modular Precast, Prestressed Bridge Decks. Transportation ResearchBoard, Washington, D.C., pp. 52–59.

Billington, J.E., Barnes, S., and Breen, R. 1999. A Precast Substructure Design for Standard Bridge Systems.Center for Transportation Research, University of Texas, Austin.

Concrete Pipe and Products Company, Inc. 1993. Pipe Design Concepts. Vienna, VA.Conspan Bridge Systems, Inc. 1995. Dayton, OH.Dick, J.S. 2002. Precast technology and bridge design. Struct. Eng. News, Views, Indust. Trends, 3(4), 24–29.El-Ramaily, A., Tadros, M.K., Yamane, T., and Krause, G. 1996. Transverse design of adjacent precast

prestressed concrete box girder bridges. PCI J., 41(4), 96–113.Fadl, A.I., Gamble, W.L., and Mohraz, B. 1977. Tests of a Precast Post-Tensioned Composite Bridge Girder

Having Two Spans of 124 Feet, Structural Research Series No. 439. University of Illinois, Chicago.FHA. 2002. Prefabricated Bridge Elements and Systems: A Winning Idea. Federal Highway Administra-

tion, Washington, D.C. (http://www.tfhrc.gov/focus/may02/prefab.htm).FHWA. 2003. Prefabricated Bridge Technology: Get In, Get Out, and Stay Out. Federal Highway Admin-

istration, Washington, D.C. (http://www.tfhrc.gov/focus/april03/04.htm).FHWA. 2004. Prefabricated Bridge Elements and Systems in Japan and Europe, Summary Report,

International Technology Exchange Programs. Federal Highway Administration, Washington,D.C. (http://www.fhwa.dot.gov/bridge/prefab/pbesscan.htm).

FHWA/AASHTO. 2004. Prefabricated Bridges 2004. FHWA and AASHTO Technical ImplementationGroup, Washington, D.C. (http://www.fhwa.dot.gov/bridge/prefab/2004best.htm).

Freyermuth, C.L. 1996. Evaluation Findings: The Segmental Concrete Channel Bridge System, CERFReport HITEC 96-01. Civil Engineering Research Foundation, Washington, D.C.

Ganga Rao, H.V.S. 1978. Conceptual substructure systems for short-span bridges. Transport. Eng. J.,104(1).

Gulyas, R.J., Wirthlin, G.J., and Champa, J.T. 1995. Evaluation of keyway grout test methods for precastconcrete bridges. PCI J., 40(1), 44–57.

Hill, J.J. and Shirole, A.M. 1984. Economic and Performance Considerations for Short-Span BridgeReplacement Structures, TRR 950. Transportation Research Board, Washington, D.C., pp. 33–38.

Issa, M.A., Idriss, A., Kaspar, I.I., and Khayyat, S.Y. 1995a. Full depth precast and precast, prestressedconcrete bridge deck panels. PCI J., 40(1), 59–80.

Issa, M.A., Yousif, A.A., and Issa, M.A. 1995b. Construction procedures for rapid replacement of bridgedecks. Concrete Int., 17(2), 49–52.

Jakovich, G. and Alvarez, J. 2002. The bridges that good planning and execution rebuilt. Public Roads,66(2), 6–9.

Johnson, J. 2002. Prefabricated bridges. Bridge Builder, 5(2), 10–14.Lambert, A.V. 1982. Instant arches: European style. Concrete Int., 4(1), 44–47.Lutz, J.G. and Scalia, D.J. 1984. Deck widening and replacement of Woodrow Wilson Memorial Bridge.

PCI J., 29(3), 74–93.Matsumoto E.E., Waggoner M.C., Sumen G. Kreger M.E., Wood S.L., and Breen J.E. 2001. Development

of a Precast Bent Cap System. Center for Transportation Research, University of Texas, Austin; U.S.Department of Transportation, Washington, D.C.; Texas Department of Transportation, Austin.

© 2008 by Taylor & Francis Group, LLC

33-18 Concrete Construction Engineering Handbook

Matsumoto, E.E., Kreger, M.E., Waggoner, M.C., and Sumen, G. 2002. Grouted Connection Tests inDevelopment of Precast Bent Cap System. Transportation Research Board, Washington, D.C., pp.55–64.

Oesterle, R.G., Glikin, J.D., and Larson, S.C. 1989. Design of Precast Prestressed Girders Made Continuous,NCHRP Report 322. National Cooperative Highway Research Program, Transportation ResearchBoard, Washington, D.C.

Osegueda, R.A., Noel, J.S., and Panak, J.J. 1989. Verification of Composite Behavior of a Precast DeckedSimple Span, TRR 1211. Transportation Research Board, Washington, D.C., pp. 72–83.

Panak, J.J. 1982. Economical Precast Concrete Bridges, Research Report 226-1F. Texas State Departmentof Highways and Public Transportation, Austin, pp. 1, 12–18, 27–32.

PCI. 1972. Modern concepts in prestressed concrete bridge design. PCI Bridge Bull., Second Quarter.PCI. 1975. Short Span Bridges. Prestressed Concrete Institute, Chicago, IL.PCI. 1977. Manual for Quality Control for Plants and Production of Precast Prestressed Concrete Products.

Prestressed Concrete Institute, Chicago, IL.PCI. 1978. Precast prestressed concrete industry code of standard practice for precast concrete. PCI J.,

23(1), 14–31.PCI. 1987. Precast prestressed concrete bridge deck panels. PCI J., 32(2), 26–45.Pruski, K.R., Medlock, R.D., and Ralls, M.L. 2002. Prefabrication Minimizes Traffic Disruptions, HPC

Bridge Views No. 21. Federal Highway Administration, Washington, D.C.; National Concrete BridgeCouncil, Skokie, IL (http://www.portcement.org/br/newsletters.asp).

Rabbat, B.G., Takayanagi, T., and Russell, H.G. 1982. Optimized Sections for Major Prestressed ConcreteBridge Girders, Report No. FHWA/RD-82/005. Federal Highway Administration, Washington, D.C.

Rawls, M. L. 2006. Framework for Prefabricated Bridge Elements and Systems Decision Making. FederalHighway Administration, Washington, D.C. (http://www.fhwa.dot.gov/bridge/prefab/framework.cfm).

Salmons, J.R. 1971. Structural performance of the composite U-beam bridge superstructure. PCI J., 16(4),21–23.

Scanlon, A., Aswad, A., and Stellar, J. 2002. Precast Posttensioned Abutment System and Precast Superstruc-ture for Rapid On-Site Construction. Transportation Research Board, Washington, D.C., pp. 65–71.

Smyers, W.L. 1984. Rehabilitation of the Fremont Street bridge. PCI J., 29(5), 34–51.Sprinkel, M.M. 1976. In-House Fabrication of Precast Concrete Bridge Slabs, VHTRC 77-R33. Virginia

Highway and Transportation Research Council, Charlottesville.Sprinkel, M.M. 1978. Systems construction techniques for short span concrete bridges. Transport. Res.

Rec. 665 Bridge Eng., 2, 222–227.Sprinkel, M.M. 1982. Precast Concrete Replacement Slabs for Bridge Decks, VHTRC 83-R2. Virginia

Highway and Transportation Research Council, Charlottesville.Sprinkel, M.M. 1985. Prefabricated Bridge Elements and Systems, NCHRP Synthesis of Highway Practice

119. National Cooperative Highway Research Program, Transportation Research Board, Washing-ton, D.C.

Sprinkel, M.M. 2004. Deck protection systems for precast prestressed bridge deck panels. In Proceedingsof the PCI/FHWA International Symposium on High-Performance Concrete, October 17–20, Atlanta,GA.

Sprinkel, M.M. and Alcoke, W.H. 1977. Systems Bridge Construction in Virginia. American Road andTransportation Builders Association, Washington, D.C., pp. 11–13.

Stelmack, T.W. and Trapani, R.J. 1991. Design Provisions for a Replaceable Segmental Bridge Deck, Vol. 1,TRR 1290. Transportation Research Board, Washington, D.C., pp. 77–92.

Tadros, M.K. and Baishya, M.C. 1998. Rapid Replacement of Bridge Decks, NCHRP Report 407. NationalCooperative Highway Research Program, Transportation Research Board, Washington, D.C.

Tokerud, R. 1975. Economical structures for low-volume roads. In Low-Volume Roads, Special Report160. Transportation Research Board, Washington, D.C., pp. 273–277.

© 2008 by Taylor & Francis Group, LLC

Prefabricated Bridge Elements and Systems 33-19

Virginia Transportation Research Council (VTRC). 1980. Bridges on Secondary Highways and Local Roads,Rehabilitation and Replacement, NCHRP Report 222. National Cooperative Highway ResearchProgram, Transportation Research Board, Washington, D.C.

Virginia Transportation Research Council (VTRC). 1981. Rehabilitation and Replacement of Bridges onSecondary Highways and Local Roads, NCHRP Report 243. National Cooperative Highway ResearchProgram, Transportation Research Board, Washington, D.C.

Waddell, J.J. 1974. Precast Concrete: Handling and Erection. American Concrete Institute, FarmingtonHills, MI.

Zeyher, A. 2003. Soaring on the feet of an elephant. Roads Bridges, 41(8).

© 2008 by Taylor & Francis Group, LLC

(a) Test specimen, University of California, San Diego; (b) precast seismic bracing elements, Paramount Building inSan Francisco, California.

(a)

(b)

© 2008 by Taylor & Francis Group, LLC


Recommended