+ All Categories
Home > Documents > PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a...

PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a...

Date post: 09-Jun-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
96
AD-A275 292 PRELIMINARY ASSESSMENT ARMY RESERVE CENTER PEWAUKEE, WISCONSIN REPORT DOCUMENT NO. SFIM-AEC-IR-CR-93129 January 14, 1994 S,.PREPARED FOR: U.S. ARMY ENVIRONMENTAL CENTER INSTALLATION RESTORATION DIVISION BLDG. E4480 ABERDEEN PROVING GROUND, MARYLAND 21010 I - PREPARED BY: PEER CONSULTANTS, P.C. 12300 TWINBROOK PARKWAY SUITE 410 ROCKVILLE, MARYLAND 20852 DTI ELECTE I $FEB Q A AEC Form 45. Feb 93 replaces THAMA Form 45 whilch Is obselete
Transcript
Page 1: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

AD-A275 292

PRELIMINARY ASSESSMENT

ARMY RESERVE CENTERPEWAUKEE, WISCONSIN

REPORT DOCUMENT NO.SFIM-AEC-IR-CR-93129

January 14, 1994

S,.PREPARED FOR:

U.S. ARMY ENVIRONMENTAL CENTERINSTALLATION RESTORATION DIVISION

BLDG. E4480ABERDEEN PROVING GROUND, MARYLAND 21010I -

PREPARED BY:

PEER CONSULTANTS, P.C.12300 TWINBROOK PARKWAY

SUITE 410ROCKVILLE, MARYLAND 20852

DTIELECTE

I $FEB Q A

AEC Form 45. Feb 93 replaces THAMA Form 45 whilch Is obselete

Page 2: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

LREPORT DOCUJMENTATION PAGE ~ W

@mm.U "MV &Now I a. WO M Mt~n I Emu rm m ME ýmEý

January 1994 Final Report

Preliminary Assessment for the Army Reserve Centerin Pewaukee, Wisconsin

Pamela A. Lemme; John W. Tucker, Jr.

7. PIERFOnminG ORGANIZATiON KA*6S AND A002=15E) I ~IOI"OGNETO

PEER Consultants, P.C.12300 Twinbrook Parkway, Suite 410Rockville, Maryland 20852

9. SPONSOR1QJi MONITORING AGENCY XAME(5) AND ADONESUS) 4ES1JN~AMTRN

Cormmander AUDICT RDOKT NUN20E

U.S. Army Environmental CenterATTN: SFIM-AEC-IRP, Bldg, E4480 SFIM-AEC- IR-CR-93129Aberdeen Proving Ground, MD 21010-5401[

11. SUPPLEMENTARY NOTES

NONE

12a. 01STMzsUToON I AVu.A"&aTY STATEMENT 12h. DISTJRUTION C=1S

UNLIMITED

13. ASSTRAC7 waxo5mum ,ýcoO wv=

The Army Reserve Center Pewaukee has been in operation since 1960. The facility is currentlyoccupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission isconstruction and approximately 145 people are assigned to the unit. Routine maintenance of vehiclesassociated with the construction is performed on-site. Major repairs, repainting of vehicles, andrefueling and washing of vehicles are performed off-site. Records indicate that the potential sourcesof contamination include two beating oil USTs, which have subsequently been removed; one 400-gallonmobile storage tank and five 55-gallon drums containing waste oil, solvents, and water; and a paintstorage room. Based on the information determined from the investigation it is concluded that therehave been no releases to the groundwater, surface waters, soil or air from the site. Due to the lowvolume of wastes generated at the site and the control measures taken to prevent spills, potentialcontamination to groundwater, surface water, soil and air pathways from the site is low.

14. SUA1ECT TEMS 15. NuMMI OF PAGES5U.S. Army Reserve Center. Pewaukee, Wisconsin,I86th ARCOM, CERCLA, Preliminary Assessment, Hazardous Waste CD

17. SECURITY C-ASSW.C1ncin IL3 UY LSIMAIN11. SI5i5prY CLm~o AS* IF5pC17ION =,g UTATION OF AAST RAC7OF REPORT OF THM PAGE OF AKSTRACT NIIE

L UNCLASSIFIED UNCLASSIFIED UNCLASSIFIEDUNITENSN ~5-~8Q.SmnO ra Foam .9v 8 (Rey~ 2-639

A" M& Zii 5- #l E

Page 3: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

GIBR AL INSTRUCTIONS FOR COMPMI-n SF alThe Report Doca emam n Page (ROP) is used in announang and cnakaloi~g pmas. It is iUportmIKthat tis inforution be pgmn t with the reat of thAe rePOr Paiat 1 114 r aC e mid tle page.Instuctions for filling in eacd black of the form follow. It is imporant to SOY -1 dn Am to miet

Block 1. Agencv Use Only (Lm blank). Blohk 12a. Dh bjtiofAvmladailitv Stait.Denotes public avwlniilliy or limmoans. Cite anyBlock 2. Report Du!e. Full pulict=ik~on date avaiabilitytothpbldir.F~ntraddivian"

including day, month, and yew. if aveeadble (e.g. I limaiabil oriy o deia la n-go all captols 4.9.Jana8). Must dtl at 1restw yewr. NOFORN. REL. MARI.Block 3. Tvoe of Report and Dates Covered. 000 - See O 52O $30.24. "DisibutianStatewhether repoisintenm. final, etc. Ifapplicabl enter inclusive r"am dates (e.g. 10 Sacm TJun 87- 30 Jun 88). DOE - S authrins.

Block 4. Title and Subtte. A title is taken from NASA. See Handbook NHB 2200.2.the part of the report that provides he most NTIS - Leoa blankmeaningful and complete iniormalcon. When areport is prepared in more than one volume. Black 12b. Dis.nbution 50de.reoeatthe primary ttle, add volume number, andinclude subtitle for the specfic volume. Onclassified documents entertMe title classification DOE -lea OE blank.in D ren nese . O E -Enter DO E disnibution categoriesin parentheses. f Standard Distribution for

Block S. Fundino Numbers. To incduce contract Unclassified Scentfic and Technicaland grant numoers; may include program Reves.eiement numoens), project number(s), task NASA - Leave olanx-numoer(s). ana work unit numerus). use te NTIS - Leave blank.following taiets:

C - Contrac: PR - Project Block 13. A Includeabrief(MaximumG - Grant TA - Tasl 200 wor=) factual summary of the mostPE - Program WU - Work Unit significant information contained in the report.

Element Accession No.

Block 6. Authorfs•). Name(s) of aerson(s) Block 14. Subiect Terms. lKevworOs oronrasesresoonstie torwriting the report. performing Iden•siying malor suolects in tme resort.the researcn. or crediteo witn the content of the,eoort. .f eaitor or comoiier, this snouid followtme namets). Block 15. Numoer of P•ges. Enter tme total

numoer o0 pages.Block 7. 4erformrnq Orcanization Nameisi ana•Aaressi es Seif-excianatory. r Block 16. ;I-ce Coae. Enter acorooriate price

Block 8. -erforminq Oroanization Report coae (NM7S only).Numoer. =nter-tne unique aionanumenc reoortnumoers) assigned by the organization Blocks17..19. SecurtyCassifications. Self-performing the rep=ort.Bok 7.19 eJm ~s~ia~ efexplanatory. Enter U.S. Secunty Classification inBlock 9. SponsonngiMonLAtonpn AaenCy Name(s) accoroance with U.S. Securty Regulations (i.e.,and Addressiest. Self-explanatory. UNCLASSIFIED). If form contains classified

information. stamo classification on the too andBlock 10. Sconsonna/MononitonngAgency bottom of the page.Reoort Numoer. (If known)

Stock 11. Supotlenentarv Notes. Enter Block 20. Limitation of Abstrac. This block mustinformation not induaed eisewneresucri as: be comoleted to assign a limitation to thePreoarea in cooperation with.-; Trans. of...; To be aostract. Enter either UL (unlimited) or SAR (samepublished in.... When a recort is revied. incluoe as report). An entry in this block is necessary ifa statement wnether the new report superseces thae aosa ct is to be limited. If blank, the abstractor suoplements the older reorrt is assumed to be unlimited.

Stanrari Form 298 Baci tRev a -

Page 4: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

DISCLAIMKI NOTICK

THIS DOCUMENT IS BEST

QUALITY AVAILABLE. THE COPY

FURNISHED TO DTIC CONTAINEDA SIGNIFICANT NUMBER OF

PAGES WHICH DO NOT

REPRODUCE LEGIBLY.

Page 5: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

TABLE OF CONTENTS

1.0 1NTRODUCTION ........ 1

2.0 SITE DESCRIPTION .......................................... 1

2.1 SITE LOCATION ........................................ 12.2 SITE DESCRIPTION ..................................... I

3.0 SITE ACTIVITY, HISTORY, AND WASTE CHARACTERIZATION ..... 5

3.1 PAST ON-SITE ACTIVITIES AND HISTORY ................. 53.2 PRESENT ON-SITE ACTIVITY ............................ 83.3 WASTE CHARACTERIZATION ............................ 8

4.0 GROUNDWATER PATHWAY ................................. 10

4.1 HYDROGEOLOGIC SETTING ............................ 104.2 GROUNDWATER TARGETS ............................. 104.3 GROUNDWATER CONCLUSIONS ........................ 11

5.0 SURFACE WATER PATHWAY ................................ 12

5.1 HYDROLOGIC SETTING ................................ 125.2 SURFACE WATER TARGETS ............................ 125.3 SURFACE WATER CONCLUSIONS ........................ 14

6.0 SOIL EXPOSURE AND AIR PATHWAY ......................... 14

6.1 PHYSICAL CONDITIONS ................................ 146.2 SOIL AND AIR TARGETS ............................... 146.3 SOIL AND AIR CONCLUSIONS ........................... 14

7.0 OTHER ENVIRONMENTAL CONCERNS ........................ 15

7.1 RAD O N .............................................. 157.2 ASBESTOS ............................................ 15

8.0 SUMMARY AND CONCLUSIONS .............................. 15

REFERENCES ................................................... 16

o 94-04093PEWAUKEE PA REPORT

I ýE4 2 04 091,

Page 6: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

LIST OF FIGURES

FIGURE 1- SITE LOCATION ......................................... 2

FIGURE 2- GEOGRAPHIC LOCATION ................................ 3

FIGURE 3 - PROJECT SITE .......................................... 4

FIGURE 4- PAST ON-SITE WASTE LOCATIONS ......................... 7

FIGURE 5- PRESENT ON-SITE WASTE AND PHOTO LOCATIONS .......... 9

FIGURE 6- SURFACE WATER MIGRATION PATHWAY ................. 13

LIST OF TABLES

TABLE 1 - GROUNDWATER TARGET POPULATION ................... 11

APPENDIX A - GEOGRAPHIC COORDINATES WORKSHEET

APPENDIX B - HAZARDOUS WASTE GENERATOR STATUS

APPENDIX C - UST CLOSURE REPORT

APPENDIX D - INTERVIEW AND TELECON NOTES

APPENDIX E - DOCUMENT REVIEW REPORTS

APPENDIX F - INTERVIEW REPORTS

APPENDIX G - PHOTOGRAPHS

APPENDIX H - ENDANGERED RESOURCES INFORMATION

APPENDIX I - FIELD RECONNAISSANCE LOGBOOKA3eoosmon For

ITIS QRA&IDTIC TAB Q

DI¶IC QUALITY GTJED 8 Vuiannounced QJustifl-catio

By

Availability a40

U PEWAUKEE PA REPORT ii liet and/orl, V1

Page 7: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I!I LIST OF ABBREVIATIONS

I ARCOM - Army Reserve Command

I PA - Preliminary Assessment

RCRA - Resource and Conservation Recovery Act

USARC - United States Army Reserve Center

I USARCP - United States Army Reserve Center Pewaukee

i USTs - Underground Storage Tanks

I

IIILWU' A •R i

Page 8: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

1.0 INTRODUCTION

Under the authority of the Comprehensive Environmental Response, CompensationSand Liability Act (CERCIA), as amended by the Superfund Amendments andReauthorization Act (SARA), and Section 120 Federal Facilities, a PreliminaryAssessment (PA) was conducted at the U.S. Army Reserve Center located inPewaukee, Wisconsin. The purpose of the PA was to investigate and reviewconditions at the site to assess the threat posed to human health and the environmentand provide the infomation necessary to reevaluate the facility's status on theFederal Facility Docket. PEER Consultants, P.C. was retained to perform the PAunder Purchase Order (P.O.) No. DACA31-93-P-1658. The scope of the workincluded review of existing environmental documentation, perform a visual siteinspection, and gather demographic information from the relevant state, county andlocal government records to satisfy the requirements in the Guidance for PerformingPreliminary Assessments Under CERCLA, EPA/540/G-01/013, September 1991.

2.0 SITE DESCRIPTIONi2.1 SITE LOCATION

The U.S. Army Reserve Center Pewaukee (USARCP) is located at 619 WestWisconsin Avenue in the Village of Pewaukee, Waukesha County, Wisconsin. TheUSARCP is within a rural area of Waukesha County, approximately twenty mileswest of Milwaukee (Figure 1). It is located in the Northwest (NW) /4 of theNortheast (NE) ¼ of Section 8, Township 7 North, Range 19 East in PewaukeeTownship, Waukesha County. The geographic coordinates for the site are 43* 0518.5" North latitude and 880 16' 25.9" West longitude (Figure 2). A worksheetshowing the calculations of the geographic coordinates is included in Appendix A.

The summer months, June, July, and August, in the Milwaukee area are generallymild and humid with normal temperatures ranging from a high of 780 F and a lowof 59 F. The winter months, December, January, and February, are cold withnormal temperatures ranging from a high of 29 F and a low of 15 • F. The average

total annual rainfall is approximately thirty-three (33) inches (Ref. 1).

2.2 SITE DESCRIPTION

The site is located on approximately 5 acres of federally owned land. The propertyis bounded by County Highway "KF" to the west, Wisconsin Avenue to the south,West Avenue to the east, and an open field to the north (Figure 3). The terrain isrelatively flat, gently sloping downgradient to the southwest. Two buildings, whichwere constructed and occupied in 1960, are on the site. One is the 11,694 squarefoot (sf), one-story, brick, USARCP building and the other is a 2,251 sf, one-story,brick, vehicle maintenance shop. Approximately 100,000 sf of the property is pavedfor a driveway and parking. Approximately 84,000 sf of the property is landscaped

PEWAUKEE PA REPORT -1-

I

Page 9: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

00

0 __

IzI0IuI0

I0

0)

LL0 -2-

Page 10: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

090

I ,4

" nA

lo FA~- , t

>t~c.~ t;_'

S <

~A

00

Page 11: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

-Jý

IL10

IyIL

w 0t

IjI0

Page 12: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

with grass, trees, bushes, and flowers. The remaining portions of the propertyconsists of grassy areas which receive little or no maintenance. The property gentlyslopes downgradient toward an open drainage ditch which runs along the westproperty line. Visual observations indicate no staining, discoloration, or damage tovegetation at the site, except in the area north of the fence. The vegetation in thisyarea has been physically damaged because the area is used as a practice area forthe earth moving equipment.

According to discussions with the Facilities Manager at the project site, the propertyis connected to the local municipal water and sewer systems, which are operated andmaintained by the Village of Pewaukee Water Utilities, electrical power is obtainedfrom Wisconsin Electric Company, and trash is collected by Foyer Trash Collectors(Ref 2).

3.0 SITE ACTIVITY, HISTORY, AND WASTE CHARACTERIZATION

The Environmental Manager at the 86th U.S Army Reserve Command (ARCOM)in Forest Park, Illinois, the Environmental Manager from the 86th U.S. ARCOM atFort McCoy in Wisconsin, and the Facilities Manager for the USARCP wereinterviewed to determine site activities and history.

3.1 PAST ON-SITE ACTIVITIES AND HISTORY

A unit of the 84th Division occupied the Center during the period of 1982 until 1993.Its mission was primarily to provide space for armored vehicle training units andmilitary engineering units. A mission statement from a February 22, 1989 AnnualUtilization Survey (Ref. 3) states that the USARCP is to:

be utilized as primary mobilization site for tenant units;

provide headquarters area, office space, storage facilities to tenant units;

provide classroom space and learning center to tenant units;

provide dining kitchen facilities to tenant units;

provide space, storage area, and maintenance facility to tenant units insupport of their organizational vehicles, equipment, and other authorizeditems in the Modification Table of Organization and Equipment, CommonTable of Allowances, and Table of Distribution and Allowances(MTOE/CTA/TDA); and

provide an emergency shelter or other utilization as directed by higherheadquarters.

PEWAUKEE PA REPORT -5-

Page 13: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IThere were approximately 200 people in this unit. Large equipment such asbackhoes, scrapers, and dump trucks used by the Division were stored on-site.Touch-up painting and routine maintenance and repairs of vehicles were performedon-site. All major repairs, repainting of vehicles, and refueling and washing ofvehicles were performed at the Area Maintenance Support Activity 49 (AMSA 49)located at 5110 W. Silver Spring Drive, Milwaukee, Wisconsin. This facility islocated approximately 25 miles east of the subject site, on the north side ofMilwaukee, Wisconsin. The waste oils, antifreeze, and solvents generated on-site bythe touch-up painting and routine maintenance and repairs were collected in 55-gallon drums and hauled from the site by a private hauler (Ref. 2).

The USARCP was originally classified as a large quantity generator of hazardouswastes, as defined by the Resource and Conservation Recovery Act (RCRA), SubtitleC. Its EPA Identification Number (ID #) is W19210021953. In 1989, a request wasmade to change the hazardous waste generator status to "Very Small QuantityGenerator". A "Very Small Quantity Generator" generates less than 100 kilogramsor approximately 25 gallons of hazardous wastes in any One month period (Ref. 4).This change was granted by the Wisconsin Department of Natural Resources inJanuary 1991. No annual reporting is required with this status. A copy of thenotification granting the revision in hazardous waste generator status is in Appendix3 1B.According to a U.S. Army Toxic and Hazardous Materials Agency (USATHMA)Property report, dated March 1989, the facility had three potential sources ofhazardous substances or waste sites. They were a 1,000-gallon, heating oil,underground storage tank (UST); a 6,000-gallon, heating-oil UST; and, a paintstorage shed. The 1,000 gallon UST, which has subsequently been removed, waslocated near the northeast corner of the vehicle maintenance building. The 6,000-gallon UST, which has subsequently been removed, was located between the southwing and drill room of the USARCP building. The paint storage shed, which hassubsequently been removed, was a small corrugated metal shed reportedly locatednear the northwest corner of the vehicle maintenance shop. In addition, waste oiland solvents were stored in a 55-gallon drum inside of the Vehicle MaintenanceShed. Figure 4 indicates the location of the past on-site waste locations: the USTs,paint storage shed, and drum storage area.

In 1986, the facility's heating system was converted from oil to natural gas (Ref. 2).A "Mail-Out Questionnaire Response Sheet", found in the files maintained by thefacility, stated that the heating oil was removed from the USTs, except for a smallamount to prevent the tanks from floating (Ref. 5). On October 28, 1991 the USTswere removed. An Underground Storage Tank Removal Documentation Report wasprepared and submitted to the Wisconsin Department of Industry, Labor, andHuman Relations. The report states that there was no evidence of contaminationand that sample analysis results indicated that it was a clean closure site. A copy ofthe tank closure report is included in Appendix C. An interview with the a Village

PEWAUKEE PA REPORT -6-

Page 14: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

* -08 C cca

-0%

* 00 7 0

O' L..C 0

I02 0C. DIOiIa

'I -r- C,,(L- v) C)

CrLIiCL a

IV

Page 15: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

of Pewaukee Fire Inspector confirmed the findings of the report (Ref. 6).

3.2 PRESENT ON-SITE ACTIVITY

On April 1, 1993, the 84th Division moved out of the facility. The facility is presentlyoccupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM.The mission for this unit is construction. Approximately 145 people are assigned tothis unit. Five full-time employees and two part-time employees are on site. Theunit maintains readiness by performing non-profit construction projects in thecommunity. It has constructed items such as a soccer field in the Village ofPewaukee and a playground for the public schools. As before, only routinemaintenance and repairs of construction vehicles are performed on-site. Used oiland antifreeze are generated and collected at the site. Solvents are used for cleaningof parts and equipment. Approximately 40 to 50 gallons of non-RCRA used oil isgenerated per month. The used oil is collected in a 55-gallon drum satelliteaccumulation point inside the Vehicle Maintenance Shop. Once the drum is full, theoil is subsequently pumped into a 400-gallon mobile above ground storage tank. Theused oil, as well as used antifreeze and spent solvents, are collected and tested bySafety Kleen.

There are presently four potential sources of hazardous substances on-site: the paintstorage room, the 55-gallon drum storage area inside of the vehicle maintenancebuilding, the 100-gallon mobile storage tank, and the four 55-gallon drum storagearea. The paint storage shed is located in the northeast corner of the VehicleMaintenance Shop. The room is constructed of masonry block to the roof and isaccessed from outside of the building. There also are four 55-gallon drums and a400-gallon mobile storage tank on site. Samples of the contents of the drums andtank have been collected and are currently being analyzed by Safety Kleen.Preliminary results indicate that the drums contain a mixture of oil, solvents,antifreeze, and water; and that the mobile storage tank contains used oil and water.A temporary sand bag dike has been constructed around the drums and mobile tankfor spill control. Rain protection has also been provided for the drums. The locationof the paint storage room, 55-gallon drums and 400-gallon mobile storage tank aresubmitted to Fort McCoy to sample the materials in the 55-gallon drums and 400-

gallon mobile storage tank in order to determine the contents and appropriatelydispose of them (Ref. 2). Photographs of the site, the 400-gallon mobile storagetank, and the four 55-gallon drums are included in Appendix G. The location anddirection of the photos are indicated on Figure 5.

3.3 WASTE CHARACTERIZATION

The on-site waste source types can be described as drums, tanks, and storage room.The drums consist of the one 55-gallon drum, which contains used oil, located in theVehicle Maintenance Shop; and four 55-gallon drums, containing a combination of

I PEWAUKEE PA REPORT -8-

I

Page 16: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

*1c 02~ V)

c 0z

00

aaIv C:,Hf* 0

-- --- ---- --- -

wI%In3

ILI _ _ _ _ _ _ _

fV*c3 0)

Page 17: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Ioil, solients, antifreeze and water. The tanks consist of one 400-gallon mobilestorage tank, containing used oil and water; and two No. 2 heating oil USTs, one1,000-gallon and one 6,000-gallon. The two USTs were removed in 1992. The paintstorage room contains paints, varnish, and corrosion preventative. These materialsare stored in gallon and quart size containers; the quantity varies.

4.0 GROUNDWATER PATHWAY

4.1 HYDROGEOLOGIC SETTING

Waukesha County is located in the Central Lowland physiographic province. This

* area can be characterized as glaciated till covering bedrock which gently slopesdowngradient westward toward the Mississippi River. The site is not located in akarst terrain (Ref 7).

There are three principal sources of ground water in Waukesha County. They are,in order of depth below ground level, the sand-and-gravel aquifer in the glacial drift,the Niagara aquifer, and the sandstone aquifer (Ref. 8). The sandstone aquifer,which consists primarily of rocks in the Galena-Platteville formations, St. PeterSandstone, the Trempealeau formation, the Franconia, Galesville, Eau Claire, andMount Simon Sandstones, ranges from approximately 700 feet to 2,300 feet inthickness. This aquifer is continuous throughout the county. The Niagara aquiferincludes Silurian dolomite overlying Maquoketa shale. This aquifer, which is only inthe eastern two-thirds of the county, ranges from approximately 0 feet to 300 feet inthickness. Water from this aquifer is used extensively for domestic, commercial, andsmall municipal or subdivision water supplies. The sand-and-gravel aquifer consistsof sand and gravel deposits in the glacial drift. These deposits are found throughoutthe county and range in thickness of approximately 0 feet to 200 feet. Water fromthis aquifer is used mostly for domestic water supplies. Well Constructors Reportsfor wells constructed near the project site indicate that the geology in the areagenerally consists of, in order of depth, topsoil and/or clay, gravel, and limestoneand/or shale. The static water level ranged from five feet to 115 feet below groundlevel. It has been reported that the groundwater flow in the vicinity of the lake istoward the lake except at the spillway (Ref 9). Groundwater flow at the spillway isto the northeast. In the case of the project site, the groundwater flow would be to

* the south.

4.2 GROUNDWATER TARGETS

Groundwater targets are drinking water supply wells located within four miles of theproject site. Water supply wells within a 4-mile radius of the project site are usedfor drinking water, irrigation, and livestock. The drinking water supply wells consistof municipal water supply wells and individual private wells. According to the wellconstructors reports and interviews with local municipal water supply facilities, welldepths range from 22 feet to 2,200 feet, resulting in water being drawn from all three

PEWAUKEE PA REPORT -10-

I

Page 18: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

TABLE 1GROUNDWATER TARGET POPULATION

WITHIN A 4-MILE RADIUS

MUNICIPALITY MUNICIPAL WATER APPROXIMATESYSTEM NUMBER OF

(Blended Systems) INDIVIDUALN OT GPRIVATE WELLSINO. OF TARGETWELLS POPULATION

Town o Merton 6,600Village of Merton -.--- 1,300

Town of Pewaukee 7 5,000 5,400

Village of Pewaukee 3 5,550 _

Village of Hartland 4 7,280

Village of Sussex 4 6,100 _ _ ---*aquifers discussed in Section 4.1. Municipal water supplies with wells located in a4-mile radius of the project site are operated by the Village of Pewaukee WaterUtilities, the Town of Pewaukee Water Utility and Sanitary District, Village ofHartland Water Utilities, and the Village of Sussex Water and Sanitary District.These Utilities operate three to seven wells and each system is a blended system.None of these systems are in wellhead protection areas. The total population servedby these utilities is approximately 23,930. There are also many private wells in a 4-Smile radius of the project site. Based on population data, there are at least 13,300people serviced with private wells. The groundwater target population for eachmunicipality is presented in Table 1. Well Constructors Reports revealed at leastthirty-nine wells located within 'A-mile of the subject site (Ref. 10). The distance tothe nearest drinking water well is approximately 500 feet southwest of the site.There have been no reports of foul-tasting or foul-smelling water in any nearbydrinking water wells (Ref. 11 and Ref. 12).

* 4.3 GROUNDWATER CONCLUSIONS

Based on the site conditions, the analytical results in the UST closure report(Appendix D), and interviews with local officials, it has been determined that therehave been no suspected releases of hazardous substances to the groundwaterpathways. Due to the low volume of wastes generated at the site and the controlmeasures taken to prevent spills, potential groundwater contamination from the siteis low.

PEWAUKEE PA REPORT -11-

Page 19: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

5.0 SURFACE WATER PATHWAY

5.1 HDROLOGIC SETIINQ

At the project site, surface water flows either across the surface or through asubsurface drainage system to a drainage ditch along the west property line. The

Sdrainage ditch flows south approximately 1,000 feet to Pewaukee Lake. Accordingto the Waukesha County floodplain map, the site is not located in a flood plain(Ref. 13). Pewaukee Lake covers approximately 2,446 acres and is approximately 4.5miles in length. The drainage ditch along the site enters the lake approximately3,000 feet from the lake's spillway. The lake discharges into the Pewaukee Riverwhich flows in a southeasterly direction approximately four miles to the Fox River.Figure 6 is a sketch of the surface water migration pathway.

1 5.2 SURFACE WATER TARGETS

There are no drinking water intakes located within fifteen miles downstream of theproject site. Residents within fifteen miles downstream of the project site are servedby either municipal water supply systems from deep water wells, or by individualprivate wells.

I The Pewaukee Lake, Pewaukee River and the Fox River are used for recreationalfishing. The typical species of fish found in Pewaukee Lake are bluegill, pumpkinseed, crapppie, rock bass, bullhead, white bass, northern pike, and white sucker. Onethreatened species of fish, the pugnose shiner, has been found in the Pewaukee Lakeaccording to the Wisconsin Natural Heritage Working List (Ref. 14). Anotherspecies of fish, which has been listed as a State Special Concern Fish, the lakechubsucker, occurs in the Pewaukee Lake.

In addition, historical records (generally 25 years or older) indicate that a threatenedplant species had been known to occur in the area. It is not known whether or notthis species of plant still exists. A copy of the letter from the Wisconsin Departmentof Natural Resources providing the endangered resources information is included inAppendix H.

3 There are numerous wetland sites located within fifteen downstream miles of theproject site (Ref. 15). The nearest wetland site is approximately 4,000 feetdownstream. It is approximately five (5) acres in size and is classified as palustrinewet soil with needle-leaved deciduous shrubs by the Wisconsin Department ofNatural Resources, Bureau of Planning.

3 The distance to the nearest surface water is Pewaukee Lake, located approximately1,000 feet south of the site. The nearest fishery is Pewaukee Lake.

I3 PEWAUKEE PA REPORT -12-

I

Page 20: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

gqeeBLAW

* e41,

bP

CIL.

UU

Page 21: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

, jb ,

* a

SA r a

A r .a o* -.

* 14C7

'-I $ . . I.0

*1 o

*t~tL .

Page 22: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

-Ilk

Col

1'40.

F 1coil

(IA

f A

ows

C,,N

Page 23: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IThere has been no indication or report of contaminants to the surface waters fromthe site. The drainage ditch located to the west side of the property shows no signsof damaged vegetation, discoloration, or oil sheens. There are no drinking waterintakes located within fifteen downstream miles. There are three human food chaintargets located within fifteen downstream miles of the site. Human food chaintargets are any surface water body from which fish or other water animals are takenor could be taken for human consumption. They are the Pewaukee Lake, thePewaukee River, and the Fox River. The flow in the Pewaukee River is notmonitored.

5.3 SURFACE WATER CONCLUSIONS

Based on the site conditions and interviews with local officials it has been determinedthat there have been no suspected releases of hazardous substances to the surfacewater pathways. Due to the low volume of wastes generated at the site and thecontrol measures taken to prevent spills, potential surface water contamination fromthe site is low.

6.0 SOIL EXPOSURE AND AIR PATHWAY

6.1 PHYSICAL CONDITIONS

Approximately 55 percent of the property is impermeable (covered by buildings orpavement). The site is normally occupied during the day by five full-time employeesand two part-time employees. As many as 150 personnel car be on-site when allpersonnel are called to duty. The site is open to the public. Public functions, suchas elections, have been held at the site and the site has been designated as a publicshelter in case of an emergency. The Facility Manager stated that there have beenno reports or complaints of odors from the site and that no releases of hazardoussubstances to the air have been directly observed.

6.2 SOIL AND AIR TARGETS

- Six private homes are located within 200 feet of the site. It is estimated that a totalof twenty people live in these homes. There are no schools within 200 feet of thesite. The nearest school is located approximately 1,000 feet east of the site. Thereis a playground adjacent to the property, to the east. The total population locatedwithin a 4-mile radius of the site, based on census data provided by the County of3 Waukesha, is approximately 37,200. There are no terrestrial sensitive environments,areas which contain threatened or endangered species, or wetland sites located within200 feet of the site. The nearest wetland site is approximately five (5) acres and is3 located approximately 4,000 feet downstream along the Pewaukee River. Thenearest fishery is the Pewaukee Lake which contains one threatened species of fishand one State Special Concern fish. No threatened or endangered wildlife have beenidentified within 200 feet of the site.

3 PEWAUKEE PA REPORT -14-

I

Page 24: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

6.3 SOIL AND AIR CONCLUSIONS

Based on the site conditions and interviews with local officials it has been concludedthat there have been no suspected releases of hazardous substances to soil and airpathways. Due to the low volume of wastes generated at the site and the controlmeasures taken to prevent spills, potential contamination to soil and air pathwaysfrom the site is low.

7.0 OTHER ENVIRONMENTAL CONCERNS

7.1 RADO

The Environmental Manager stated that testing for radon had been performed onsite. The results indicated the levels to be below the EPA limits of 4.0 piC/liter.(Ref. 2)

I 7.2 AESTO

The Facilities Manager stated that limited asbestos sampling and analysis had beenperformed at the site. During the site inspection, suspect asbestos-containingmaterials were observed.

8.0 SUMMARY AND CONCLUSIONS

The Army Reserve Center Pewaukee has been in operation since 1960. Recordsindicate that the only potential sources of contamination include the two heating oil

-- USTs, which have subsequently been removed, the 400-gallon mobile storage tankand the four 55-gallon drums of unknown contents, the paint storage room, and thewaste oils and solvents generated from the routine maintenance activities. As stated

-- in Section 3.1, the two USTs were removed in 1991. There was no evidence ofleakage or contamination from the tanks when they were removed and they nolonger pose any threat. The 400-gallon mobile storage tank and the four 55-gallondrums of unknown contents are stored in the parking lot. A sandbag dike has beenconstructed around the mobile storage tank and 55-gallon drums for spill control.Rain protection has been provided for the drums. The 400-gallon mobile storagetank and drums are scheduled for removal and disposal once their contents havebeen determined. There is no evidence of leakage or contamination from the 400-3 gallon mobile storage tank and 55-gallon drums. Based on the informationdetermined from the investigation it is concluded that there have been no releasesto the groundwater, surface waters, soil or air from the site. Due to the low volume

I of wastes generated at the site and the control measures taken to prevent spills,potential contamination to groundwater, surface water, soil and air pathways from thesite is low.

PEWAUKEE PA REPORT -15-

I

Page 25: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I REFERENCES

1. Chris Sackerson, National Weather Bureau, Milwaukee, Wisconsin; telephoneconversation with Pamela Lemme of PEER Consultants; November 19, 1993. Re:Weather in the Milwaukee area (Telecon Note #21).

2. Mark Wisniewski, Facilities Manager; Colleen Reilly, Environmental Manager; DaveJennings, Environmental Manager; Interview with John Tucker and Pamela Lemnmeof PEER Consultants, November 1, 1993. Re: Site history and activities (Interview

I Report #1).

3. "Annual Utilization Survey - USAR Real Estate", Authority - AR 405-70, February22, 1989, Pg. 1.

4. Pat Brody, Wisconsin Department of Natural Resources, Bureau of Solid andHazardous Waste Management, Telephone conversation with Pamela Lemme ofPEER Consultants; November 23, 1993. Re: Hazardous Waste Generator

i Classifications (Telecon Note #22).

5. "Mail Out Questionnaire - Response Sheet", completed by Laura A. Sodemann, theprevious facility manager, as part of the Environmental Compliance AssessmentSystem. It is an internal report prepared by the 416th Engineering Command.

6. Charles Babe, Fire Inspector, Village of Pewaukee Fire Department; telephoneconversation with Pamela Lemme of PEER Consultants, November 2, 1993. Re: USTremoval and other environmental issues concerning site.

7. "Physiography of the United States", Charles B. Hunt, W.H. Freeman & Company,1967, pg. 205.

8. "Ground-Water Resources of Waukesha County, Wisconsin", Joseph B. Gonthier,U.S. Geological Survey, 1975.

9. "A Water Quality Management Plan for Pewaukee Lake", Community AssistancePlanning Report No. 58, Southeastern Wisconsin Regional Planning Commission,March 1984.

10. Well Constructors Reports, available for viewing at the Wisconsin Department ofNatural Resources, dated 1936 to present (Document Review Report #2)

11. Ms. Carol Plant, Secretary of the District, Town of Pewaukee Water Utility andSanitary District No. 3; telephone conversation with John Tucker of PEERConsultants, November 2, 1993 (Telecon Note #10).

12. Frank Edwinson, Public Health Sanitarian and George Morris, Manager, Wauikezha

PEWAUKEE PA REPORT -16-

I

Page 26: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

County Department of Environmental Resources; interview with John Tucker andPamela Lemme of PEER Consultants, November 2, 1993. (Interview Reports #2 and#3)

13. "Floodland Information Report for the Pewaukee River, Village of Pewaukee,Waukesha County, Wisconsin", Community Assistance Planning Report No. 9 (2ndEdition), prepared by the Southern Wisconsin Regional Planning Commission, March1985.

14. Wisconsin Natural Heritage Working List, Wisconsin Natural Heritage Program,Bureau of Endangered Resources, Department of Natural Resources, January 1993.

15. Wisconsin Wetlands Inventory Map for Township 7 North, Range 19 East, Waukesha

County, Wisconsin; revised 4/84.

16. Waukesha Quadrangle, Wisconsin; 15-Minute Series; U.S. Geological Survey; 1959.

17. Hales Corner Quadrangle, Wisconsin; 15-Minute Series; U.S. Geological Survey;1959.

18. Hartland Quadrangle, Wisconsin; 15-Minute Series; U.S. Geological Survey; 1959.

19. Eagle Quadrangle, Wisconsin; 15-Minute Series; U.S. Geological Survey; 1960.

20. Waukesha Quadrangle, Wisconsin; 7.5-Minute Series; U.S. Geological Survey;Photorevised 1971; Photoinspected 1976.

21. Hartland Quadrangle, Wisconsin; 7.5-Minute Series; U.S. Geological Survey;Photorevised 1971 and 1976.

22. Sussex Quadrangle, Wisconsin; 7.5-Minute Series; U.S. Geological Survey;Photorevised 1971; Photoinspected 1976.

23. Merton Quadrangle, Wisconsin; 7.5-Minute Series; U.S. Geological Survey;Photorevised 1971; Photorevised 1976.

PEWAUKEE PA REPORT -17-

Page 27: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IIII1IIII

APPENDIX A3 GEOGRAPHIC COORDINATES WORKSHEET

IIIII

I

S~PEWAUKEE PA REPORT

I _ _ _ _

Page 28: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

ILATITUDE AND LONGITUDS CALCULATION CZTJ 02LI USIN •ZZUG S 3SCau (1/60)

SITE Z NAM: U.S. Ce=,M-ýBtsi . C•,t .IS __

CI?!: -. -p o"k STATE.- ~ j zip ~cmz: 5mll.-2'iSITE REMPIRENCE POINT:_____ A~__________________________

USGs QUAD MAP Amm.: 4aw41-A i I TOWNSHIP: (2/.. ?s RamG: ict (j)W

i SCAULE (.j4OO tap DATE: ..... j SECTION: .1/4 _1/ ..41/4

MAP DATUM: 1927 1983 (CIRCL'E ONE) MERIDIAN:

COORDINATES FROM LOWER RIGHT (SOUTHEAST) CORNER OF 7.5* MAP ([atach photcopy):

LONGITUDE: 1.o -_- LATITUDE: AU . -.3COORDINATES FROM LOWER RIGHT (SOUTHEAST) CORMER OF 2.5' GRID CELL:

LONGITUDE: . i ' LATITUDE: o t_ -

l CALCULATIONS: LATITUDE (7.5' QUADRANGLE MAP)

A) NUMBER OF RULER GRADUATIONS FROM LATITUDE GRID Ln TO SITE RP POITm:

3 ) MULTIPLY (A) BY 0.3304 TO CONVERT TO SECONDS:

A x 0.3304 -i3C) EXPRESS IN MINUTES AND SECONDS (!'- 60): 0 J.5

0) ADD TO STARTING LATITUDE: 4"5 ý o- o ... t8

I _SIT LATITUDE: 4, ,5-- 5-

ICALCULATIONS: LONGITUDE (7.5' QUADRANGLE MAP)

A) NUMBER OF RULER GRADUATIONS FROM RIGHT LONGITUDE LINE TO SITE REF POINT:

I ) MULTIPLY (A) BY 0.3304 TO CONVERT TO SECONDS:

A x 0.3304 =. _. _-

IC) 3XPESS IN MINUTES AND SECONDS (11= 60"): s l0) ADD TO STARTING LONGITUDE: o +

SITE LONGITUDE: deL.j up. Z-T

1INVESTIGATOR: DA/-7

I

Page 29: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IIIIIIII

I APPENDIX B

3HAZARDOUS WASTE GENERATOR STATUS

IUi

III

3 PEWAUKEE PA REPORT

I

Page 30: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

* S ~Stat Of WISCOnSin \ DEPARTMENT OF NATURAL RESOURCESCarroll 0. lesadny

Secretary

BOX 7921

January 1991 MADISON, WI 53707

FILE REP 4430

I W19210021953 2 68 268246770ATTN: LAURA A SODEMANN-FAC MGRUS ARMY RESERVE CTR619 W WISCONSIN AVEPEWAUKEE, WI 53072

Dear Facility Owner/Operator or Hazardous Waste Generator:

I When you submitted your 1989 Hazardous Waste Report you indicated cn Form IC thata change in hazardous waste generator status was apprcpriate for your facility. Atthat time (Feb. 1990), our records showed your status WAS the following:

EPA ID#: Location: 619 W WISCONSIN AVE LARGE QNTY GENERATORWI9210021953 PEWAUKEE, WI 53072

I On your report you indicated that the generator category for your site SHOULD be:

VERY SMALL QUANTITY GENERATOR

I An audit of your facility records has been completed which included a file check forpending violations, a manifest activity review for the last two years, and a reviewof annual hazardous waste activity reports that have been filed with the DNR. YouI may have been contacted during this review for additional information. As a resultof this audit, we concluded that the appropriate hazardous waste generator statusfcr your facility IS:

VERY SMALL QNTY GENERATOR with NO ANNUAL REPORTING REQURED

If our records show that no annual reporting is required for your facility, youwill NOT be sent materials for 1990 reporting. However, should your haz.rdouq wasteactivities change, you may be required to submit a report in the future. You areresponsible for keeping track of your hazardous waste activities, determining ifreporting is required, and requesting reporting materials from the DNR if you needto submit a report for your site.

I am enclosing an information sheet for your reference in hazardous waste matters.One side shows the generation and accumulation amounts for each of the generatorcategories. The other side lists the hazardous waste activities for which annualreporting is required. If you have questions about the audit decision for yoursite, the waste regulations, the requirements for reporting, or questions specificto the activities at your site, please contact:

Wyvetta Davis (414)263-8668 DNR Southeast DistrictIf you have questions about the DNR procedures for hazardous waste status audits,please call me at (608)266-2414. Thanks.

Aggie Cook, Information TechnicianI Program Services SectionBureau of Solid & Hazardous Waste Mgmt

Page 31: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

UNITED STATESm • '• ENVIRONMENTAL PROTECTION AGENCY

cRCA AC•W IMs- oP.O. BMO MA7

* '~q~ ~ CHCAGO, KAMM=OI 60M

MAR 1 5 1989

*I

near MIotifier:

Enclosed you will find the U.S. Environrental Protection Agency (U.S. EPA)Identification (I) number that has been assigned to your installation.This ID number nust aopear on all manifest forms when transporting hazardouswaste. You will find your ID numbber on the second line of the cooy of theenclosed notification foam. This letter confirms tiat you have filed aNotification of Hazardous Waste Activity (Form 87T0-12) to comoly withSection 3010 of the Resource Conservation and Recovery Act (PCRA). Thisletter and the enclosed copy of the notification form should be retainedfor future use.

If your facility is in the state of ,1Vchigan and you were previously issuedand ID number with an MIG prefix, do not use the 7!.1G number. This is a statenurober. Re sure to use the MID number only.

If you have any further questions regarding hazardous waste activity, pleaseI contact our Hotline at (312) 886-4001.

Si~ele yours,

Art Kawatachi, ChiefInformation SectionRCRA Program Manacement Branch

UIII!______________________

Page 32: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IIIUIIIII APPENDIX C

I UST CLOSURE REPORT

IUIUUII

I ~PEWAUIKEE PA REPORT

I

Page 33: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

DEPARTMENT OF THE ARMYHAQ•UART•ERS. FORT MCCOY:IW 7~ OPMECK OF THE COMMANOERSPARTA. WISCONSIN 54656

2 9 JAN1•92

Environmental Management Division

II

I Mr. William MorrisseySafety and Buildings DivisionDepartment of Industry, Labor and Human Relations201 E. Washington AvenueMadison, Wisconsin 53707

I Dear Mr. Morrissey:

i-iclosed are Underground Petroleum Product Tank InventoryForms and Underground Storage Tank Removal Documentation Reportsfor tank removals at Army Reserve Centers in Pewaukee'andKewaunee, Wisconsin (Enclosures 1 and 2).

I One 1,000 gallon and a 6,000 gallon fuel oil tank wereremoved at Pewaukee. A 1,000 gallon fuel oil tank was removed atKewaunee. All soil samples results were less than 10 parts permillion total petroleum hydrocarbons, thus all three removalswere clean closures.

Please contact Mr. Kurt Brownell, Environmental ManagementDivision, Directorate of Engineering, at (608) 388-2160 if youhave any questions. Sincerely,

ORIGINAL SIGNEDWilliam S. StanleyColonel, U.S. ArmyCommanding

Enclosures

Copies Furnished:

I Mr. Terry Bauer, District 4, 2715 Post Road, Stevens Point, WI54481

I Chief, Off-Post Facilities Division

Page 34: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

WsosnOeloý,tmlflnt ofIdsr.Send Completed Form To:Labor and Human Relations UNDERGROUND Safety & Buildings oivisonPETROLEUM PRODUICT P.O. Box 7%99

For OffIce U so Only: Madison. Wt S3707* Tank 10 TANK INVENTORY Telephone (608) 267-S280This form is to be completed pursuant to Section 101. 142. Wis. Stats., to register all underground tanks in Wisconsin that

have stored or currently store petroleum or regulated substances. Please see tfle reverse side for additional informationon this program. An underground storage tank is defintd as any tank with at least 10 percent of its total volume*(included piping) located below ground level. A separate form is needed for each tank. Send each completed formto the agency designated in the top right corrner.rhos regisitration applies to a tank ilhacit. (check on*): Fire Otioartmont Proivoidin Fits Coverage

.C3In use 4. (% Abandtoned - Tank Removed 8. (0 Cianed Ovanersia Where Tank Is Located Is in:2.C Abandoned With Product 6. (3 Abandoned -Filled With (indicate new owner ]n City Q3 Virl~ae C3 Town of

3. 3 Abandaned No Product (empty) Inort Material in section A. &. bellow) Pe~iaticepat With Water T. ( Out of ServiceI A. IDENTIFICATION: (Please Print)

1. installation Name 2. Mailing Name of Omlffrent Than 0 1

U.S. AirW Reserve Center I __________________

installation Street Address (Mailing Address it stfefent Than *I619 West Wisconsin Ave. ___________________

M city 0ea e C3village Ql Town at: C3 city C village C3 Town af:

~365~2-247 ~ StatsZip CocaCont

3. Nameot atContact Porson 4. Owner Name it Oiftsrent Than 03TWirr?, Rrrw Pn_1 __________________U Street Address StreettAddress

* HO - ort: McCem. A=-~I A=Z-flE-SCity C3 Town I Stats Zip Code 03 City (3 Town SaeZpCcvillage of: Sparta IWI 151U56-5000 (3 Villaget ofI

County Tlcode) County ielplnone No. (include area code)

kAgo (date installed. it known: or years old) 6. T gIk6 cit~y (gIons) 7. Tat Manufacturer's Name (it known)

S. TYPE OF USER (check one),1. 'C Gas Station 2. Suilt Storage 3. 0 uiJlity 4. C3 Mercantitl*S. [3 Industrial 6. aGovernment 7. C0 School S.0 Rsssoential9. 03 Agricultural 10. C3 Otheir(saoecify):___________________

* C. TANK CONSTRucT1na

I. safe Steel 2. Q] Cathodically Protected and Coated Steel (a. [3 Sacrificial Anodes of b. a impressed Current)3. *0 Coated steel A. 9 Fiberglass 5. C3 Other(speotiiy): ______________

6. C3 Refined 7. C9 Steel - Fiberglass Reinforced Plastic Composite 9. C3 unknown

Atioroival: 1. Nat'l Std. 2. C3 UL 3. a Other: Iis rank Oouble Walled? 9l Y'r5 1 NoI Overfill Protection Provided? OYss .Na tfyes~id~ntity ty0e: I soill Containmevint? C2 Yes ISNoTanr leak detection method: 1. C] AutomatiC tank gauging 2. 0vapor monitoring 3. 9 Groundwater monitoring

4. C] inventory control and tightness testing 5. C0 lnterrtmti monitoring 6. Ntraieda rsn

0. PIPING CONSTRUCTIONPNo eurdapesn

I.. lC Sate Steel 2. C]Catriodically Protected and Coated orWrop~ed Steel(a. C3Sacrificial Anodes or b. [3 mpressed Current) 1. Q Coated Stec-A. Q Fibergqlass S. C] Other (soievify): 9 3vkov

Piping System Type: 1.C PreSsurized piping with: a.C0 auto snutoth; b. 0 alarmo;or c. 0 flow restctor 2. CI Suction pipiong with check valve at tackv3. JV Suction oiaming with cheock valve at oumo and inspoictab4o

Piping leak detection method: used if pressurized or cnieck valve at tank: 1.Q Vacar monitoring 2. Q Interstitial monitoring3. rl Groundwater mnorrcoring 4 0 Tightness testing S. [3 Uris Leak Oetector 6. (SNat ReouirsdU opoval: I O 3NatIlStd 2. C3UL 3. Q3Oter: OoualeWalled: 9e Ies NO

E. TANK CONTENTS1 . C3 Oiesel 2. 93 Leaded 3. C3 Unleaded a. Fuel OilS. E3 Gasohol 6. C3 Other 7. 0] Empt S. Ci'Sarodl~lavellilurry9. 9: Linknowe 10. 93 Premix 11. 93 Waste~il 12. C3 Propane

13. C3 Chemical ___________ ____ 14. 9: Kerosene, IS. (3 Aviation

*if A 13 is checkead, indicate the chemical namep(s) or numwberfs) of the chemical or waste.

Fit Tank Abandoned. Give Oats (mo ldayryt):l mas a sit@ assesment been completed? (set reverse oide lor details)

Ren~wed 30 October 1991 M e (3NG

il installation of a new tank is being reported. indicate whiO performed the installation inspection:1.9C Fire Oitoartment 2. C9 OILHR 3. (9 Orther (identify)

Sognas le of Perwn Cpmplettinq Retoor: DOateSigned:

560.-7 A37 (P., 01149)

Page 35: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I MC CUTCHIN CRANE SERVICE727 West Chapel StreetDodgeville, Wisconsin 53533(608) 935-9411 Telephone(608) 935-9645 FacimilleI

I UNDERGROUND STORAGE TANK REMOVAL DOCUMENTATION REPORT

II

Site: US Army Reserve Center619 West Wisconsin AvePewaukee, Wisconsin 53072-2497Waukesha County

Prepared For: US Dept of ArmyDirectorate of ContractingBuilding 2103Fort McCoy, Wisconsin 54656-5000

******************************** ************************************ ****

I

McCut in Crane Seri Date

IC

Page 36: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

TABLE OF CONTENTS

Page:

1. INTRODUCTION & BACKGROUND ................................ 1.

2. TANK REMOVAL ACTIVITIES ................................... 1.

3. VISUAL OBSERVATIONS ...................................... 2.

4. SOIL SAMPLE COLLECTION & RESULTS ......................... 2.

5. CLOSING DISCUSSION ....................................... 2.

Enclosures With Report:

Site Location Map ............................................. A.Chain of Custody For Soil Samples ............................. B.Soil Analysis Results From Laboratory ......................... C.Site Worksheets .............................................. D1-D3Checklist For Underground Tank Closure Form#SBD-8951

S Underground Tank Inventory Form# SBD-7437 For Each TankManifest For Disposal Of Tanks ................................ E.

Page 37: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I.I

Ii1. INTRODUCTION & BACKGROUND

I This report is for documentation of underground tank removals performed on10-29-91 at the USARC, 619 West Wisconsin Ave, Pewaukee, Wisconsin,Waukesha County.

The owner of this site is the US Dept Of Army, Fort McCoy, Wisconsin.Directorate of Contracting who was responsible for overseeing this projectI is Bernie L Honish who may be reached by calling 608 388-2924,or by writing to the US Dept of Army, Directorate of Contracting, Bldg2103, Room 2, Fort McCoy, Wisconsin 54656-5000.

The tanks which were removed were one 6,000 gallon heating fuel tank andone 1,000 gallon heating fuel tank.

The Dept of Army requested bid proposals on this work to be performedaccording to all State & Federal Regulations concerning removals &closures of underground tanks.

McCutchin Crane Service of Dodceville was awarded the bid & authorized toperform the removals. McCutcnin provided their own backhoe for theexcavation.The Dept of Army had a Contracting Officer Representative whose name wasOfficer Irv Capaul on site while all work was being performed.

2. TANK REMOVAL ACTIVITIES

I McCutchin Crane Service, Officer Irv Capaul, and Inspector Charles Babefrom the Pewaukee Fire Dept arrived on site to remove the tanks onOct 28th, 1991. Diggers Hotline had been notified & requested to mark alllines, but because of inclimate weather had not done so yet as of Monday,Oct 28th. Diggers Hotline arrived on Tuesday Oct 29th.Before work began all safety precautions were in place. Only air runequipment is used on tank removal jobs, and all work is performed inaccordance with OSHA Safety Standards.

Before removal all product was drained from the piping into the tanks.The piping was then disconnected, from the tank, capped & removed,except for one pipe going into the furnace room from the 6,000 gallon

tank, which we were unable to remove, was drained, and capped.Once all product was drained into the tanks the liquid contents wereI pumped out ( 1,200 gallons of fuel oil from the 6,000 gal tank & 30 galfuel oil from the 1,000 gal tank ), & hauled away by McCutchin.The tank was then purged with liquid C02, opened & cleaned.A total of 3gallon of fuel oil sludge was cleaned from the tanks.

**USTUSARCPEW**

Page 38: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

'he tanks were removed from the hole, labeled, and loaded ontoIcCutchins trailer to be hauled away & disposed of.

)nce the site assessment evaluation was complete & collection of soil3amples were gathered the sites were filled in with clean native fillI material and the site restored to grade.

I 3. VISUAL OBSERVATIONS

Before removal of the tanks began visual observations were made forevidence of the undgeround tanks having a system failure. We were lookingfor such things as dead vegetation, staining, saturated soils etc. Therewas no evidence of any dead vegetation, nor was any staining on the groundevident.

The tanks were located in two different areas so there were 2 excavationholes. The excavation at the 6,000 gallon tank measured 14'x 37'x l0'deep.The tank in this excavation measured 6' x 30'

The excavation at the 1,000 gallon tank measured 8' x 10' x 8' deep.The tank in this excavation measured 5'4" x 6'.

The soil types encountered were of sand & clay mixture. There were novisual observations showing contamination, no staining of the soils, nofree product in the excavation holes , no significant smell, etc.

The inspection of the tanks did not show any failure. There were noholes,cracks, or deep corrosion which could have caused leakage. Allfittings & connections on the tank were secure.

4. SOIL SAMPLE COLLECTION AND RESULTS

Once the tank was out of the hole & the visual site evaluation completesoil samples were gathered under each end of the 6,000 gallon tank, under2 areas of the piping run from that tank to where the piping entered thebuilding, and one sample was taken under the center of the 1,000 gallontank.

The samples were gathered with a clean hand trowel and placed into 4ozjars provided to us by our laboratory. These jars have ID information onthem pertaining to the site and are kept with a chain of custody untildelivery to the laboratory. The laboratory analyized the samples forTPH,and all results returned at no action limits at under 1OPPM.

5. CLOSING DISCUSSION

Based on all visual inspections of the tanks, excavation hole, aad resultsof the soil analysis, it is our opinion that this should be a cleanclosure site.

**USTUSARCPEW** (2)

Page 39: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I' ~ :SARC

- .4. tPEWAUKEE, Wl

-. 17~(2 7anks)

___ ___ IA

It. 00 M

-4. 412

IA .

Vol,,j~2 .*i

4.

WTar

It 0 + ~ 4t '

r .:;ti A VA

I.t

j I% ~ .I

(A'3

Page 40: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IJSARC. 619 W, Wiscons;n Ave Date 10-30-91

Pewaukee, Wdisconsin, Waoukesha County

S,,.rneCI By: McCutchin Crane Service Map Not Drawn to ScaLe

4- 4' 4- 4' 4- %P 41 - 4 ' 4 4

4- 4'pte#2 4 'Soa4mpte 3

%41 IV

41~ IVA

,, '4, ,, - 4 46,000 alon Fue' (i( Tank ' '

S• ~Tnak Dlnmenslons= 2•9' x 6' •.4 -4 *,I---------------------------------------------------------I It

",V 41 q V VI All V, I 1 V - •I V "

Line 4Sampe -5 Line Sample - 4

IJSARC, Building - OPF~ices & Assembly Haill, Building #•1, Pewaukee, Idisconsin

•~I \ 4 4 , 4 •" ,y ,, ,, Y • V , , IV

:~~~I V 'I, YV \Y" \je ,4x l p ,t •V , I

Tdnsconsin otreet

Page 41: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

i.,.!

te USARC - MVS BuildIng Dote 10-29-91

619 W Wisconsin Ave, PewQukee, W', Waukesha County

m Ppored By: McCutchin Crone Service Scale, 1- = 5'

7 -m ie 54 6 ,0 aln u lOlT n - / -7 - -~ - -~~ - - - - - i - - l i/--

..- ,,j ./,I I t i 7,diii, t,,,

it ep /Po

an1

7 / h t a n~k ¼ , K K . t t -~ - -/ - - -i. - -tl ~ . ;~ -2' /, i - -- -t

1 % t *

it..t I .

,-,

//0S . / i i #2

,..ii.i,,.

-cavation Hole Size =8' x 10' x 8'Deep

-n Size = 5'4' x 6' - 1,000O goalon F'ueL O~il Tank---------------

i •p~at, except €'or an TPH Analysis

,.ning enablingj access I]

* ,,: t he to , n k ,/

-'itt//i 7

.. , ,,-..

.7' , 1'. '. .. , / t, i it 7 ti+,1 t t

1 2l

---- " - 1 . :p .',V<Q , /

• • .,,t ,

iiiI • ?iit lit It

/--tl I I ,

il i. 'il

I- ii IlI ii/t

• • • t i., II.,,,9

I.""'JACPwukeMVSBulg1* 9I2/;7/:~,t;t1 " -..

Page 42: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

NET Midwest Inc.

NATIC' 'JAL W.,&V,.*0ho~~EN V VONMENTAL o., 2ENWRNMETALWatetnown, Wl 53094

STESTING, INC. Te: (414) 261-166TET G,=F (414) 261-6120

CH I-IXTN OF CUSTOD'Y

Client Project

Send Report to: MCCUTCHIN CRANE SERVICE Name dsti"d- Reim-,eee,* 727 W. Chapel Strest

Address Dodgeville, Wl 535a3 Collected by:6M-935-9411 I'l C."ANE SERVICTelephone # 608-935.94fl MCCUTCHIN CRANE SEl•1afpel SeVC

R?7 *. Qnapli StmW-1ville, Wl 5353Dodgeville, W1 2vi11I 535331

F- Cotlectizn tnform!aian

*SampL e Salpking Oats Tim K 0 Soate a( -OfID Locat 'on A Ni Type Can-

S P tainrarý

__ 'S- - _ afy&& -Z- If

I _ __ I - --

I Remarks:

Relinquished by: Date Time Received by: Date Time

Stppi.ng Noces/Lab Comments Receiv•: t •r•NET Midwest by:

Samples Field Filtered: Yes __ No

Seals Intact Upon Receipt: - Yes __ No __ N/A

.U'

Page 43: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

NET Midwst. Inc.SNATIONAL •Id.V,. o.,,wNATIOAL S Commwere onve

ENVIRONMENTAL ,,.o.88Watertown. WI 53004

*m TESTING, INC. Tot (414) 2614.20Fax: (414) 261-4120•I

ANALYTICAL REPORT1Clinton McCutchin 11/19/1991McCUTCHIN CRANE SERVICE Job No: 91.3581424 W. Washington Street Account No: 49210Dodgeville, WI 53533 Purchase Order:

Job Description: USARC-Pewaukee

Page 1

U.Date Taken: SEE BELOW Date Received: 11/04/1991

35611 USARC-Pewaukee #l-USARC Pewaukee

3 Solids, Total 77.TPH NONAQUEOUSGasoline <5.0 mg/kg3 Diesel Fuel <5.0 mg/kg

35612 USARC-Pewaukee #2-USARC Pewaukee

I Solids, Total 83.TPH NONAQUEOUSGasoline <5.0 mg/kgDiesel Fuel 6. mg/kg

35613 USARC-Pewaukee #3-USARC Pewaukee

Solids, Total 88.TPH NONAQUEOUSGasolina <5.0 mg/kgDiesel Fuel 7. mg/kg

!I

P2aid W. Havick, ManagerWatertown DivisionICetfcto o 2033

I

Page 44: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I_ _ _ _ _NET Midt.l, Inc.KiIATl'IONAL Watedw.o, OWsonNA'lS IONb 602 Commerce OnveII ''~ENVIRONMENTAL .. , 2ENVIONMETALWatrmtown. W1 53094

TESTING, INC. Tel: (414) 261-1660Fax: (4141 2614120IANALYTICAL REPORTU

Clinton McCutchin 11/19/1991McCUTCHIN CRANE SERVICE Job No: 91.3581424 W. Washington Street Account No: 49210Dodgeville, WI 53533 Purchase Order:3: Page 2

Job Description: USARC-PewaukeeI"Date Taken: SEE BELOW Date Received: 11/04/1991

35614 USARC-Pewaukee #4-USARC PewaukeeSolids, Total 90.

TPH NONAQUEOUSGasoline <5.0 mg/kgDiesel Fuel <5.0 mg/kg

35615 USARC-Pewaukee #5-USARC Pewaukee

Solids, Total 90. %TPll 11O11AQUEOUSGsol ine <5.0 :g/kq

Dicsel Fuel

I

I#

If

David W. Havick, ManagerWatertown DivisionCertification No. 128053530

Page 45: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

* . . .********.*fSIfTE ASSESSMENT INFORMATION

Site: - 2Dat~9

I "Site Owner '2 R C. UST system owne/ip

Description of past and present property use =I7A 54

I Legal Description of Site

i IHas There been any previous reported or non reported releases at thie site, includeany system leaks or repairs made .

Results of previous Geotechnical Investigations 2,d

I Lave any tanks or un~lerground systems been removed from this site previously to thisjob? If so, when & by whom? -i.--z. '

Tanks which are being removed at this time /l9,'• . •(

Are inventory records available ,2•Has this system-had tank tightness test performed & are those results available? a:,_L

Has any associated piping been left in the ground,, if so , give reason why , and hasI li hetil)[58, bee~n dratiied & calited '.:/,e•.•,••<••t•ý,,, /l,;. A / ý ,C4

Will a y-underground tanks remain in place at this site____________ _

I what is their status?______

OBSERVATIONS: Size & Depth of excavation a,' -I•, "i ,,' epth to Bedrock

Soil Types encoutered _ ,_.4/ / , '

*Seasonal High Water table / M49tling & colorations of soil? At what depths?

I Was there presence of free standing water in the excavation o"p,

Depth to groundwatcr? •, ,..to which systemns would ,!rehiii.go be ikely to flow?II___________________________Were water samples takent2

Was any of the following encountered: Free product, stained soils, oders, dead vegetL

or other evidence of contamination ,• ,

3 Tank & piping conditions 0i ...- _-Possible leak locations I I

3 If contamination was found who was notified & what procedures were taken?3]__ __

Page 46: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

CutchiiLi Crane -'er'Vt ULCLL

I TE DATE~

k D# Capacity Dimensions Ag Manufacturer Construction t.onter• B~r0%utnv ock

I- -

- a- 1k

I _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ __ _ _ __....

Fi

a tanks purged on site? dii-t r~i~r ~~""hat method)

UL liquids pumped from tanks (quantity of each type) /' 7"7) .

"e tanks) cleaned on site 7-_

I A sludge ( quantity of eacb/type) cleaned from tanks '? 6,

-I e will fill out: DISPOSITION OF WASTE PRODUCT, TANK SLUDGES, AND TANKS

Ii

,re there pumps on this site & how were they disposed of ,---,.-t• . -

:ere was piping disposed of "2., d1.. , ..

aer Comments: /*0dE

/I- /7i' 7J 212j,

Page 47: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

SOIL SAMPLE LOG

* SITE NAME : 1Z 4 -

ADDRESS: 1City

I "

39xnsbi of:

COUNTY: /Lfit-ir'

DATE /z90 0i- SAMPLES TAKEN BY N9CtUeJ 6 0,'ej-ej'1I ank Size Tank ID# Sample# Time Taken Depth Approx soil temp Rel Mois.

Content-

W 4.442 zI ____7" "--2

Oc sape werel colceo eete trd- -

tae n hanle in acodnewt tt fWsosnDLRCoueadsil s

n 4|

techniques as described in September 1990 requirements & checklist.

Signature of 3rd oarty witness to sample collectionsi DXH oeis

Page 48: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

i"

MC CUTCHIN CRANE SERVICE424 WEST WASHINGTON STREETDODGEVILLE, WISCONSIN 53533608 935-9411 OR 608 935-2552

**************** CERTIFICATE OF REASSURANCE***************

McCutchin Crane Service on this day has disposed ofaccording to regulations 2 underground storage tankswhich were hauled away from USARC, 619 West WisconsinAve, Pewaukee, Wisconsin Waukesha County.These tanks have been opened, cleaned, and cut up to be

sold as scrap iron. Any contents such as sludge which mayhave been cleaned from the tank is ultimately disposed ofby Safety-Kleen Corp, who picks up from McCutchin on aquarterly basis. Safety-Kleen Corp then enters the productinto a treatment process which is deemed suitable for thespent materials, which is in compliance with allapplicable regulatory and permit requirements.

I By acceptance of these tanks McCutchin Crane Service shallhold harmless USARC Pewaukee, US Dept. of Army, Fort McCoyWisconsin, and any previous owners of the said tanks anytype of liability claims arising from the storage,handling, cutting, and disposing of the tanks.The tanks which were hauled away & disposed of were a6,000 gal. heating fuel & a 1,000 gal heating fuel. Atotal of 1,230 allons of heating fuel was pumped from thetanks and 3 gal ons of fuel oil sludge was cleaned fromthe tanks.

McCutchin Crane Service Generator Waste EPA ID# WID9885759McCutchin Crane Service Generator Waste IL ID# 9550498134McCutchin Crane Service Hazardous Waste Hauler Licensenumber for Wisconsin ------------------------------ # 12372

DATE .. . ........

McctcynCrane Servie

Page 49: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Wisconsin oqpartment of Indus"ry CHECKLIST FOR UNDERGROUND RETU RNCOMPETIEDCH ECK UST T* Labor and Human Relations ~.Safety & Buildings Division

Co peeoefr o TANK CLOSURE Fire Prevention & UndergroundCompeteone ormforStorage Tank Section

each site closure. IP. 0. Box 7969. Madison, WI 53707A. IDENTIFICATION: .P1ease Print)

1.IaalaoNO" Z. OWnerNa(Me

I nsmalsoon Strom A4drew m Sie As

UavI4Vdage U Town ot LCay{Vag U ..w ] Town at Stat zip code

z ip , comfyr Teiepfioie N, ake amcodeY

3. losir Co~mwNam Cowie orrPO SkssI Address City. StaW. Zi-pZCod

' 1! rj~VICz COV. RO VIMe~ IN~ CRANE SERVICIE Remfover Ceralicatijor No.

4. Naf 727 W. Cha 9e1 Street saet MWra ,Srit

608.35&91 1 PoCompniy Telephone No, Iiciwljo sMoea COiblie Assessor NarricU"w-95iittJ AesrCenditiaton No.

Tank ID # Closure Temp. Closure Closure In Place Tank Capacity Contents' Closure Assessment_. _______0 0 0 JZ 04 V QN

4. _ __ _ _ [7l 0_ _ _ ElY fIlN

[7 [7 . .. .. n_____ ___ _ EY 0 N6. 0 0 0 1 Q_ QY 0N'Indicate which prdct by numeric code: 0 1-Diesel; 02-Leaded; 03-Unleaded; 04-Fuel Oil; 05-Gashl; 06)-Other: 09-Unknown: 1 0-Prem ix

1-Waste oil; f3 -Cemical (indicate the chemical name(s) or numbers(s) _____14-Kerosene: 15-Aviation.

Notification was provided to the local authorit ies 15 days in advance of closure date . ........ [. rY C]N C]NAAll lclpermits weeobtained before beginning closure. tL4eu,, -,* .4.:r [3/;N95NACheck applicable box at right In response to all stateijfients In Sections B - E. Remover Inspector NA

B.TMOAIYOUT OF SERVICE Ve-rified Verified

.PodtReoea. Prod~uct fines drained into tan~k (or other containor) and resulting liq~uid rem oved, AND ..... 0Y 0ON 0 0b. All prod t removed to bottom of suctida.,lille. OR.....................................I Y ON 0 0c. All produc 01noved t~wtin I*- of bottom ............................................ 0 N 0 0

2. Fill pipe, gauge ,tank truck vapor recovery kngs, and vapor return lines capped . ....... 0 Y 'EN 0 03. All product lines 7at 4~e islands or pumps located els~qre are removed and capped. OR 0.... Y 0N 0 04. Dispensers/pumps let.blt place but locked and power dike nleced ......................... 0 V 0 N 0O 05. Vent lines left open. ....... .. ........... Q . Y ON E916. Written inspector approval ltemporary closure obtained, which

is effective until (Datel................... .0 Oy ON 0 ED7. Inventory form filed by owner indicating temporary closure ................................ Q V 0 N 03 0

C. CLOSURE B3Y REMOVAL1. Product from piping drained into tank (or other container).2. Piping disconnected from tank and capped or removed . .................. a 0 N 0 0I3. All liquid and residue removed fromi tank using explosion proof pumps or hand pumps . ...... Rf 0 N [a 04. All pump motors and suction hoses bonded to tank or otherwise grounded .................... 24~ 0 N la 05. Fill pipes, gauge pipes, vapor recovery connections, submersible pumps and other fixtures removed. Q'¶ 0 N 0 0

NOTE: DROP TUBE SHOULD NOT BE REMOVED IF THE TANK IS TO BE PURGED THROUGHTHE USE OF AN EDUCTOR.

7. Vent lines left connected until tanks purged ........................................... C12 0 N 08. Tank openings temporarily plugged so vapors exit through vent ............................ 0'e 0 N ED 09. Tank atmosphere reduced to 10% of the lower flammable range (LEL) - see Section F.L4 0 N El 0

10. Tank removed from excavation alter PUAGING/INERTING; placed on level ground and blockedto prevent movement.................................... .... V ON Q 0

SBD-895i (N 02/91) - CONTINUE ON NEXT PAGE -

Page 50: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Remover InoUrNAc: CLOSURE BY REMOVAL (continued) e v.N_.A

12. Tank labeled in 2- high letters after removal but before being moved from site .............. N C3NOTE, COMPLETE TANK LABELING SHOULD INCLUDE WARNING AGAINST REUSE;FORMER CONTENTS; VAPOR STATE; VAPOR FREEING TREATMENT, DATE.

13. Tank vent hole (tI8 th "in uppermost paW of tank) installed prior to moving the tank from site .... QN 0 " f]14. Inventory form filed by owner with Safety and Buildings Division indicating closure by removal...... Y mf a15. Site security is provided while the excavation is open . ................................... NJ ( ]

0. CLOSURE IN PLACENOTE: CLOSURES IN PLACE ARE ONLY ALLOWED WITH THE PRIOR APPROVALOF THE DEPARTMENT OF INDUSTRY, LABOR AND HUMAN RELATIONS.

I. Product from piping drained into tank (or other container).2. Piping disconnected from tank and capped og removed ................................... E]QY (:I N Q3. All liquid and residue removed from tank using explosion proof pumps or hand ,pumps ........... C] Y 0 N Q4. All pump motors and suction hoses bonded to tank or otherwise grounded ................... Q Y 0 N 0 05. Fill pipes, gauge pipes, vapor recovery connections, submersible pumps and other fixtures removed. Y Q] NNt 0 .

NOTE: DROP TUBE SHOULD NOT BE REMOVED IF THE TANK IS TO BE PURGED THROUGHMUTE(SE OF AN EDUCTOR.

6. Vent lines left connected until tanks purged. ...... EI................... \ .......... [] Y Q N 0 Q7. Tank openings temporarily plugged so vapors exit through vent ............... Q] Y Q N 0 E8. Tank atmosphere reduced to 10% of the lower flammable range (ILEL) - see Section F ......... [ Y [] N 09. Openings cut in tank top if necessary to introduce inert'material ............................ Y [ N Q

10. Solid inert material (sand, cyclone boiler slag, pea gravel recommended) introduced and tank filled. (3 Y r N []11. Vent line disconnected or removed . ................................................ 0 Y C] N Q12. Inventory form filed by owner with Safety and Buildings Division indicating closure in place .E...... l Y Q] N Q

E. CLOSURE ASSESSMENTSNOTE: DETERMINE IF A CLOSURE ASSESSMENT IS REQUIRED BY REFERRING TO ILHR 10.

1. Individual conducting the assessment has a closure assessment plan (written) whichis used as the basis for their work on the site ........................................ Q [ N Q C12. Do points of obvious contamination exist? ............................................. El Y O.N, 0 13. Are there strong odors in the soils? ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C] Y QN Q 0l4. Was a field screening instrument used to pre-screen soil sample locations? ................... Q [ N [f El5. Was a closure assessment omitted because of obvious contamination? ...................... E Y .N S El6. Was the DNR notified of suspected or obvious contamination? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . El Y 21 ( El

Agency and office contacted:7. Contamination suspected because of: 0 Odor [ Soil Staining 0 Free ProductO] Sheen On Groundwater 0 Field Instrument Test

F. METHOD OF ACHIEVING 10% LEVEL DESCRIPTIONEducator Or Diffuse4 Air Blower

Eductor driven by compressed air, bonded and drop tube left in place; vapors discharged minimum of 12 feet above ground.Diffused air blower bonded and drop tube removed. Air pressure not exceeding 5 psig.

Dry IceDry ice introduced at 1.5 pounds per 100 gallons of tank capacity. Dry ice crushed and distributed over the greatest possible tankarea. •'yNe evaporated before proceeding.

Inert Gab0O/2 0) N/2) NOTE: INERT GASSES PRODUCE AN OXYGEN DEFICIENT ATMOSPHERE. THE TANK MAY NOT BEENTEmU'N THIS STATE WITHOUT SPECIAL EQUIPMENTGas introduced through a single opening at a point near the bottom ol the lank at the end of the tank opposite the vent.Gas introduced under low pressure not to exceed 5 psig to reduce static electricity. Gas introducing device grounded.

Tank atmosphere monitored for flammable or combustible vapor levels.Calibrate combustible gas indicator. Drop tube removed prior to checking atmosphere. Tank space monitored at bottom, middleand upper portion of tank. Readings of 10% or less of the lower flammable range (LEL) obtained before removing tank fromground.

G. NOTE SPECIFIC PROBLEMS OR NONCOMPLIANCE ISSUES BELOW

I. INSPECTOR INFORMATION(. / .~/ __ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _

inspector'Name (pnrly inspector Signature-'- inspector Uertification No.

1- #DI- For Location where Inspection Performed Inspector telephone Number Tiate Signead

OWNER

Page 51: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IIIIII

I APPENDIX D

I INTERVIEW AND TELECON NOTES

I

IIII

I PEWAUKEE PA REPORT

Page 52: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Office. Aerial photos can be obtained from Parks and Planning. Geologicalinformation can be obtained from the Southeastern Regional PlanningCommission located in the Old Courthouse located on Main Street.

TELECON NOTE 4

Date: November 2, 1993

Interviewer: Pamela Lemme

Name: Eileen CampbellTitle: Assessor's Office ClerkAffiliation: Town of Pewaukee AssessorPhone No.: (414) 691-0820

Remarks: The project site is located in the Village of Pewaukee; therefore, you mustcontact the Village of Pewaukee to review tax assessor's information for thissite.

TELECON NOTE 5

Date: November 2, 1993

Interviewer: John Tucker, Jr.

Name: Kathy SchulneTitle: Water Utilities ClerkAffiliation: Village of Pewaukee Water UtilitiesPhone No.: (414) 691-5660

Remarks: The Village of Pewaukee Water Utilities serves the Village of Pewaukee.The Village of Pewaukee has a population of approximately 5,550 people asof January 1993. There are four deep wells around the Village. She did notknow the locations, depths or capacities of the wells. She stated that I shouldtalk with Louis Thibault, who is on vacation this week, or Richard Leutsches.Mr. Leutsches is a supervisor and can be reached at (414) 691-5690. Heworks from 7:30 a.m. to 4:00 p.m. He takes lunch form 12:00 to 12:30.

There have been no reports of contamination. There were some high bacteriacounts in October 1993. DNR required chlorination until the bacteriadisappeared. Only complaint from customers was during chlorination. Phonecalls complained about odor and the change in taste. The Village normallydoes not chlorinate.

PEWAUKEE PA REPORT D-2

Page 53: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

She was not aware of any need for special sampling for hazardous wasteconcentrations. When asked if any wells had been shut down, she said theyhave but only for mechanical reasons.I

TELECON NOTE 6

Date: November 2, 1993

Interviewer: Pamela Lemme

Name: Charles BabeTitle: Fire InspectorAffiliation: Village of Pewaukee Fire DepartmentPhone No.: (414) 691-9223

Remarks: He was present when the two fuel oil tanks were removed from the projectsite. He said there was no evidence of contamination when the tanks wereremoved. He confirmed that the 1,000 gallon tank was located near thenortheast corner of the maintenance building. The tanks had been tarred andwere buried in sand. The company performing the work collected samplesand took pictures.

As far as reports of any overflows, spills, or leaks, the Fire Department is notaware of any.

TELECON NOTE 7

Date: November 2, 1993

Interviewer: Pamela Lemme

Name: Sharon SchaverTitle:Affiliation: Wisconsin Department of Natural Resources - Groundwater DivisionPhone No.: (414) 961-5435

Remarks: She recommended obtaining a copy of the Waukesha Geological SurveyReport, Circular #29, dated 1975, to obtain information about the geology inWaukesha County. To obtain information about private wells, wellconstructors reports can be reviewed at 4041 Richard Street. Contact VictoriaAnderson to schedule an appointment to review the reports. VictoriaAnderson can also provide information concerning LUST reports. Her phonenumber is (414) 961-2738. Additional information concerning groundwater

PEWAUKEE PA REPORT D-3

Page 54: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

and private wells can be obtained from Irene UIpheld at the WisconsinDepartment of Natural Resources in Madison, Wisconsin. Her number is(608) 262-7430. The phone number for the Wisconsin Geological Survey is(608) 262-1705.

TELECON NOTE 8

Date: November 2, 1993

Interviewer: Pamela Lemnme

Name: Irene LipheldTitle:Affiliation: Department of Natural ResourcesPhone No.: (608) 262-7430

Remarks: Information pertaining to a specific site can be obtained from wellconstructors reports. Wisconsin does not have a database which includesinformation about groundwater contamination in wells. Copies of reportsgenerated from this office can be obtained from maps sales located at 3817Mineral Point Road, Madison, Wisconsin between the hours of 8:00 a.m. and4:30 p.m.

TELECON NOTE 9

Date: November 2, 1993

Interviewer: John Tucker

Name: Patricia WilliamsTitle: Office ManagerAffiliation: Lake Pewaukee Sanitary DistrictPhone No.: (414) 691-4485

Remarks: Lake Pewaukee Sanitary District only collects wastewater. Wastewater istransferred to the Brookville Wastewater Treatment Plant, which is owned bythe City of Brookville, for treatment.

PEWAUKEE PA REPORT D-4

Page 55: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

"-3 TELECON NOTE 10

Date: November 2, 1993

I Interviewer: John Tucker

3 Name: Ms. Carol PlantTite: Secretary of the DistrictAffiliation: Town of Pewaukee Water Utility and Sanitary District #3Phone No.: (414) 691-0804

Remarks: Service area is all of the Township of Pewaukee except residents immediatelyaround Lake Pewaukee. Serves approximately 2,000 customers. Most peoplehave private wells. Residents around the Lake are served by Lake PewaukeeSanitary District for sewers only.

Source of water is from seven deep wells ranging in depth from 380 feet to1,200 feet. The closest well to the Army Reserve Center is about 1½ to 2miles away at W-240, N-3065 Pewaukee Road (east of town near intersectionof Line and "J" Road)

I There has been no reports of groundwater contamination. They are undernew guidelines by EPA for testing. At this time, they have not detectedU anything unusual.

No wells have been closed in the past. There have been no reports of foulsmelling or foul tasting water from residents. There has been no analyticalor circumstantial evidence that suggest any contamination.

There is no well field. Wells are scattered throughout the area.

The well closest to the Center has a capacity of 380 gpm.

Site is not in a well head protection area.

Village of Pewaukee serves the Army Reserve Center. Other in the area haveindividual private wells.

Have not heard any complaints from private well owners, but the Villageprobably would not receive the complaints. The County Health Departmentwould receive the complaints.

P3 PEWAUKEE PA REPORTD5

ID-

Page 56: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

ITELECON NOTE 11

Date: November 3, 1993

Interviewer: Pamela Lemme

3 Name: Ron PieTitle:Affiliation: Wisconsin Bureau of Endangered Species - Fisheries DivisionPhone No.: (414) 263-8614

Remarks: I informed him that I was trying to obtain information concerning endangeredspecies in Waukesha County. He said that he could provide informationpertaining to fisheries. Information about other animals or species wouldhave to be obtained from Chuck Pils of the Wisconsin Bureau of Endangered

II Species in Madison, Wisconsin. I scheduled a visit for 1:00 p.m. at which timehe provided me with information pertaining to endangered fish in thePewaukee area.

3 TELECON NOTE 12

Date: November 3, 1993

I Interviewer: Pamela Lemme

Name: Richard LeutschesTitle: SupervisorAffiliation: Village of Pewaukee Water UtilitiesPhone No.: (414) 691-5690

Remarks: He stated that the Village of Pewaukee obtains its water from four deep3 wells. The wells are located at Main Street by WCTC, 104 Hickory Streetand near the intersection of Capital and High Streets. Samples from two ofthe wells revealed unsafe levels of chloroform. This has been corrected andthere have been no problems since then. Additional information can beobtained from Louis Thibault.

I

3PEWAuKEE PA REPORT D-6

Page 57: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

TELECON NOTE 13

Date: November 3, 1993

Interviewer: Pamela Lemme

Name: Bob DavisTitle:Affiliation: Waukesha Water and Sanitary DistrictPhone No.: (414) 521-5272

Remarks: The source of water for the City of Waukesha is ground water. The City hasten deep wells and the water supply system is interconnected. There havebeen no reports of contamination in any of the wells. There were high levelsof iron in Well #7; however, it has been cleaned and is reopened. None ofthe wells have been permanently closed. Some have been temporarily closedfor rehabilitation.I

TELECON NOTE 14

I Date: November 4, 1993

3 Interviewer: Pamela Lemme

Name: Becky IsenringTitle:Affiliation: Bureau of Endangered ResourcesPhone No.:

I Remarks: In order to obtain information concerning endangered species, a request mustbe submitted in writing. A legal description and a map showing the areashould be submitted with the request. The process takes about two to threeweeks once the request has been received by her office. If you come in to fillout an application we will try to process it as quickly as possible. It can notSbe processed while you wait, so leave an address so the information can besent.

I

PEWAUKEE PA REPORT D-7

Page 58: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

TELECON NOTE 13

Date: November 16, 1993

Interviewer: Rakesh Aurora

Name: Bob DavisTitle:Affiliation: Waukesha Water and Sanitary District - Water UtilitiesPhone No.: (414) 521-5272

Remarks: The City of Waukesha maintains ten municipal water supply wells. Depthsof the wells range from 1,800 feet to 2,200 feet. The wells are interconnectedand serve approximately 56,000 to 57,000 people. The wells are located at:

1. East North Street2. Baxter Street3. Newhall Road4. South Moreland Blvd.5. East Avenue & Sunset Drive6. Sunset Drive7. Sunset Drive8. Seylesville9. Crestwood Drive10. Wolf Road

TELECON NOTE 16

Date: November 16, 1993

Interviewer: Rakesh Aurora

Name: Jim WilsonTitle: Director of DPWAffiliation: Village of Hartland - Department of Public Works3 Phone No.: (414) 3674880

Remarks: The Village of Hartland is supplied with municipal water from four wellsapproximately 150 feet deep. Approximately 7,000 people are served. Thewells are interconnected. The wells are located at:

the intersection of Lindenwood Drive and Manchester Court• Progress Drive• Sunny Slope Drive• @ end of Penbrook Way

PEWAUKEE PA REPORT D-8

Page 59: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

TELECON NOTE 17

Date: November 16, 1993

I Interviewer: Rakesh Aurora

Name: Ms. Sue FribeitTide:Affiliation: Village of Sussex - Water Utility3 Phone No.: (414) 246-5200

Remarks: The Village of Sussex has four deep water wells. They are interconnected.3 The locations and depths are as follows:

La Depth Diameter

First Street 1,292 feet 12 inchesMaple Ave. (South 1,230 feet 17.25 inches

of Main Street)Lilac Drive 1,288 feet 12 inchesDonna Street 1,296 feet 12 inches

They also have one 1-million gallon storage standpipe and one ¼4-million3 gallon storage standpipe.

3 TELECON NOTE 18

Date: November 16, 1993

I Interviewer: Rakesh Aurora

Name: CarolTide: Town ClerkAffiliation: Merton Town3 Phone No.: (414) 966-2125

Remarks: There are private wells on each person's property. The wells are not3 interconnected.

II3 PEWAUKEE PA REPORT D-9

I_________ __ _____

Page 60: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

TELECON NOTE 19

Date: November 17, 1993

Interviewer: Rakesh Aurora

Name: Louis ThibaultTitle: SuperintendentAffiliation: Village of Pewaukee Water and SewerPhone No.: (414) 691-5690

Remarks: The Village of Pewaukee maintains three municipal water supply wells. Theaverage depth of the wells is approximately 1,300 feet. The wells serveapproximately 5,200 people. The wells are located on Hickory Street, CapitalDrive, and Main Street. The wells are interconnected.

TELECON NOTE 20

Date: November 18, 1993

Interviewer: Rakesh Aurora

Name: Michele NelsonTitle: Deputy Village ClerkAffiliation: Merton VillagePhone No.: (414) 538-0820

Remarks: There are private wells for each home. There are approximately 600 homesin the Village. The total population for the Village is approximately 1,333.The average depth of the wells is 150 feet. The range of depths is 22 feet to200 feet.U

TELECON NOTE 21

Date: November 19, 1993

Interviewer: Pamela Lemme

Name: ChrisTitle:Affiliation: National Weather Bureau, MilwaukeePhone No.: (414) 744-8000

PEWAUKEE PA REPORT D-10

Page 61: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Remarks: Average annual rainfall and rainfall equivalent in Milwaukee is 32.93 inches.(The rainfall equivalent is the amount of snow converted to rainfall inches.)The normal summer temperatures are: high - 78" F, low - 59" F.The normal winter temperatures are: high - 29" F, low - 15" F.

Summer includes the months of June, July, and August. The winter monthsinclude December, January, and February. The rainfall equivalent is theamount of snowfall calculated to an equivalent amount of rainfall.

TELECON NOTE 22

Date: November 23, 1993

Interviewer Pamela Lemme

Name: Mr. Pat BrodyTitle: Hazardous Waste SpecialistAffiliation: Wisconsin Department of Natural Resources, Bureau of Solid and Hazardous

Waste ManagementPhone No.: (414) 961-2717

I Remarks: Wisconsin's hazardous waste generator classifications are similar to the federalclassifications. A "Very Small Quantity Generator" is a facility that generatesless than 100 kg, 220 lbs., or 25 gallons of hazardous wastes in any one monthperiod. A "Small Quantity Generator" is a facility that generates less than1,000 kg, 2,200 lbs. or 300 gallons of hazardous wastes in any one month.

IIIUI

IPEWAUKEE PA REPORT D11

ID-

Page 62: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IIII

I

Page 63: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

DOCUMENT REVIEW REPORT #1

Document Reviewed by: Pamela LemmeDate Reviewed: November 4, 1993

Remarks: The state leaking underground storage tank (LUST) list, the LUST CaseTracking System List, was reviewed on November 4, 1993. The list isprepared by the Wisconsin Department of Natural Resources and was dated10/26/93. No reports of spills or LUSTs were found on the list for thesubject site.

DOCUMENT REVIEW REPORT #2

Document Reviewed by: Pamela LemmeDate Reviewed: November 4, 1993

Remarks: Well Constructors Reports, located at the Wisconsin Department of NaturalResources, 4041 Richard Street, Milwaukee, Wisconsin, were reviewed onNovember 4, 1993. The well constructors reports provided informationpertaining to water supply wells developed throughout the state. Theinformation included, but is not limited to, location of the well, depth of well,depth to water table, contractor performing the drilling, and the owner of thewell. Reports dated as far back as 1936 were reviewed. There were noreports of wells within a 4-mile radius of the site closing due tocontamination.

PIII1I

I

Page 64: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IIII

U APPENDIX F

3 INTERVIEW REPORTS

PIAKEPARPR

Page 65: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

INTERVIEW REPORT #1

Date: November 1, 1993

Interviewer: John Tucker and Pamela Lemme, PEER Consultants

Name: Mark Wisniewski, Colleen Reilly, Dave JenningsTitle: Facilities Manager, Environmental Manager, Environmental Manager,

respectively.Affiliation: 86th ARCOM

Remarks: The reserve center has been occupied since 1961. Mark Wisniewski has beenemployed at the facility since 1979, and has been the facility manager sinceApril, 1993. Mr. John Jekel was the-facility manager since the ReserveCenter's inception until 1981. The 84th Division and the 961st EngineeringBattalion, a unit of the 86th ARCOM, have both occupied the facility untilApril 1, 1993, when the 84th Division moved out. It is currently occupied onlyby the 961st Engineering Battalion.

The 961st Engineering Battalion's mission is construction. The unit hasperformed non-profit community work, such as construction of a soccer fieldand a playground for the public schools. There are approximately 145personnel in the unit. There are five full-time employees and two part-timeemployees. There are no refueling operations on site. Vehicles are notwashed at the site. The vehicles are taken to the facility in Milwaukee. Onlytouch-up painting, minor repairs, and routine maintenance are performed onsite. Painting of the building is performed by private contractors. The facilityuses municipal water and sewer systems. Electrical power is from WisconsinElectric. The nearest school is approximately 1½2 blocks east of the site at St.Mary's Church. The nearest day care center is approximately 11/2 miles eastat the Waukesha County Technical College. The facility manager has notobserved any evidence of contaminated soils or damaged vegetation. Thefacilities heating was changed from oil to natural gas in 1986. The USTswhich stored the heating oil were removed in October 1991. Trash iscollected every Monday by Foyer Trash Collection. Used oil, antifreeze, andsolvents are tested, collected, and recycled or disposed of by Safety Kleen.All other hazardous wastes or unknown materials are handled by DRMO.

PEWAUKEE PA REPORT F-I

Page 66: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IINTERVIEW REPORT #2

Date: November 2, 1993

IInterviewer: John Tucker and Pamela Lemme, PEER Consultants

Name: Mr. Frank EdwinsonTitle: Public Health SanitarianAffiliation: Waukesha County Department of Environmental Resources

Remarks: The County Department of Environmental Resources samples local wells, atthe request of the owner, for bacteria, chlorine, fluoride, iron, hardness,chloride, and nitrates. There have been no reports of contamination isgroundwater wells in the vicinity of the project site. Reports or complaintsabout oil or other contaminants would be referred directly to the WisconsinDepartment of Natural Resources.

INTERVIEW REPORT #3

Date: November 2, 1993

Interviewer: John Tucker and Pamela Lemme, PEER Consultants

Name: Mr. George MorrisTitle: ManagerAffiliation: Waukesha County Department of Environmental Resources

Remarks: Waukesha County has begun to perform environmental assessments forCounty facilities. To date, there have been no reports of groundwatercontamination in the area.

PEWAUKEE PA REPORT F-2

Page 67: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

INTERVIEW REPORT #4

Date: November 1, 1993

I Interviewer: John Tucker and Pamela Lemme, PEER Consultants

Name: Sergeant Thomas CharlierTitle: Motor SergeantAffiliation: 86th ARCOM

Remarks: Laura Sodemann was the former facility manager. He did not have a currentStandard Operating Procedures for hazardous waste management. A copyof the SOP for the 84th Division was available. It is dated February 27,1990and states that hazardous wastes will be handled by the 84th DivisionHeadquarters located in Milwaukee. Approximately 40-50 gallons of wasteoil is generated per month. Only routine maintenance is performed on site.Some solvents are on site for cleaning of wheel bearings, etc. The vehiclemaintenance building had a grease pit; however, in 1979 it was cleaned andfilled in with concrete.

IP

!

I

Page 68: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

IIIIIIIII APPENDIX G

I PHOTOGRAPHS

IIII PWUE ARPR

I

Page 69: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

II

I

II

IPHOTO 1 - LOOKING NORTHWEST AT THE SOUTHEAST CORNER OF THE MAIN BUILDING

I ••-I" •

IIIII

PHOTO 2 - LOOKING NORTHWEST AT THE SOUTH SIDE OF THE MAIN BUILDINGII

I

Page 70: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

PHOTO 3 - LOOKING WEST AT THE EAST SIDE OF THE MAIN BUILDING

PHOTO 4 - LOOKING SOUTH AT THE NORTH SIDE OFCLASSROOM WING OF THE MAIN BUILDING

_ PWAUKE- PA P.Mogr G-2

Im

Page 71: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I

III

PHOTO 5 - LOOKING SOU'h-WEST AT THE NORTH SIDEOF THE DRILL ROOM OF THE MAIN BUILDING

I i

PHOTO 6 - LOOKING WEST AT THE PARKING LOT BEHIND THE MAIN BUILDINGU

3 PEwAUKE PA •mow G-3

I

Page 72: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

II

PHOTO 7 - LOOKING NORTHWEST AT THE MAINTENANCE FACILIT

I

PHOTO 8- LOOKING SOUTHWEST AT THE 400-GALLON MOBILIE

I STORAGE TANK AND THE FOUR 55-GALLON STORAGE DRUMS

U

UPWUE ARPR "

Um

Page 73: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

PHOTO 9 - LOOKING SOUTHEAST AT THE 400-GALLON MOBILESTORAGE TANK AND THE FOUR 55-GALLON STORAGE DRUMS

J~m ' .......r,

II

PHOTO 10- LOOKING NORTH AT THE 400-GALLON MOBILE STORAGE TANK

PSWA T ORE PA TNA TEOr G-5

Page 74: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

II

I'IIII1 PENI

ENANEEDREORCS.NOR ..O

Page 75: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I State of Wisconsin k DEPARTMENT OF NATURAL RESOURCES101 Sou* Web~w Seft

Box 7921UPT'. WF MAT" Uam IM P - "i 3707

CmTRE.1HOWE SM60-219-221GeeroW L. Ihwe TELIFAX O08247-3579Seemr"y TDO 608-267-MS7

November 24, 1993 IN REPLY REFER TO. 1650

Ms. Pamala Le~mme

PEER Consultants P. C.12300 Twinbrook PkwyRockville, MD 20852

SUBJECT: Endangered Resources Information Review (Log Number 93-434)

Dear Ms. Lemme:

The Bureau of Endangered Resources has reviewed the project area described in your request for informationof 4 November 1993 for the environmental assessment for army reserve center near Pewaukee Lake.

Our Natural Heritage Inventory (NHl) data files contain the following rare species information for theproject site located in Sections 5-9 in T7N R19E, Waukesha County. In addition to the actual project site, Iam providing endangered resource information for an area within one mile of the project's location (withinfive miles for aquatic species.) I provide this information both so impacts to nearby endangered resources canbe assessed and to assist in determining which rare species may occur in the project's impact area ifappropriate habitat exists. If the described habitat types occur in the project's impact area, then species that

occur nearby may be present there. The species information provided includes the location, date of the mostrecent observation, and other information useful in planning protection measures. Rare species occurringwithin or near :he project site include:

Erimazon sae (lake chubsucker), a State Special Concern fish, occurs in Pewaukee LakeThe observation date for this occurrence record is 1977. This species prefers lakes, oxbowIs

lakes, sloughs of large rivers and quiet streams with dense vegetation over bottoms of sand, gravel, orrubble. Spawning occurs from late March through early July.

-- Special Concern (Watch) species are species about which some problem of abundance or distribution issuspected but not yet proved. The main purpose of this category is to focus attention on certainspecies hefore they become endangered or threatened.

In addition to the above information, our data files also contain historical records (generally, records that are25 years old or older) of rare species known to occur within the vicinity of the project site. Unfortunately,the Bureau does not have more current survey information documenting the continued existence of thisspecies in this area. I am including this older record as an indication of which species may still occur in theproject area if appropriate habitat exists:

3 G ib an (yellowish gentian), a plant listed as Threatened in Wisconsin, has been known to occur

in In Wisconsin this species has been observed in wet, sandy railroad pr-air'--:thin soil on open and wooded ridges and bluff-top; wooded ravine in clay soils and damp roadside ;n

edge of woods. Blooming occurs from mid-August through early October.

*

Page 76: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

II 2

Cmp e endangered resourc surveys hm not been completed for the propect ares. As a result, ourdata files may be incomplete. The lack of addional known occurrences does not preclude the possibilitythat other endangered resources may be presen.

The specific location of endangered resources a sensitive infomation that has been pro"ded to you for theanalysis and renew of this project. Ez=r lo,,zons should not be released or gr,•edUcd in any oR;b7vdi s mnated doc-,,, s...

This letter is for informatiotmW urpom and oaly addresses endangred resour isues. This letter doesnot constitute Department of Nural Resources authoriation of the p ropoed project and does notexempt the project fromn secuing necessary permitus and approvals from the Department.

Please contact Becky Isenring at (608) 264-86 if you have any questions about this information.

Sincerely,

Charles M. PilsDirector, Bureau of Endangered Resources

3 cC: Bruce Braun - EA/6Jim Morrissey - SEDFrank Trcka - SEDBetty Les - ER/A

IIIIIIIUI

Page 77: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

APEDII

FILIEONISAC OBO

II

IImIEAKE ARPR

Page 78: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

m p l W 4

44.BOO 47 In-*.W

4* 10

* ~~JAU\Em ri'c

I~~~~~~~~~~~~~~ 80SET r~ ' ~OLG AGN*4-6 !'"

-. W

,~sa .4 '* *

DENKSMSTATINERY ROCUC S COIR GA A07134

Page 79: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

ArI

3 Arcv~~§ ~~act W-c 1 ~'e ~~J~

1 1 1~~cc4eC~rz ~ro K 4s eec~yk ',,,V-, ccJoUSr4

Q. Al0 -fe~-c rLLAAiOr dC'i- 5.ý

't s & ")r\ cr-AAc \ o rckZO~~ ncy

r 3 an -Nv\,Cý

I-.-

Page 80: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Tk 4 Ci 4- ý

TV,-Mc Co-6 Z.,A is C,ý Y-1 aWci

* ~~~o, -We-'

1-7 c1)~o ~~c .~

'. UT C c: -~ CA~occ 4-7.~

a cChx sc C.~

Page 81: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

A-P c-p-P

Ifý -AýjCC(m&-~ ~

*5 7V~ &L)C --,tvc e'nr5~\& L.3cCJL -ýx C-49 CL- r4Z r

3~~~~7 A4%-~,r4~ 4 A W

4\&cJCCY c-eýo~-cm

Page 82: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

II

CK. r->e 1. C,~s -ý2c4-ryc

ScfcA\ko U:-T ustA --4o bx..

a- -rr-ke Cd + -sVorvjcr

Page 83: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

So- or cr -ýý ECAS R(-

2.~~F ScAA CL $c9c ~¾

5. ft. z.4z vcr Ccjaý-

II

II

Page 84: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

1 41 CLv

-i

6 K C -C+

---- ,Soo

Page 85: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

'--- sc-4--p-

Page 86: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

L \~ A5, LŽArk..,

ck.w-ý -00.VkjcAtec rzs+wAia-ý

C.4

-13 1-ý<-

Page 87: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

It

lit

I 3

.. ,1 .. - -, --.. -}-, ,, -.. ..

I :A ,.f,\ \A". -

I..

t 0!

U�'�,L 'I

.! ¢__ -- •. 'i.-i .-.• ,

3! 2

I-

Page 88: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I

IL,,I , L c .... . .... .... .. .. ...... .

I ~ 'CiAC Y•.s •

I

II

Page 89: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

CICI2z-

77 c. ~

I~ Qc

Page 90: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

L 2/7y

~g --; ~ \J( (z-7

-- O rA Acc VcIJ

I b\&-, ~ 4 .

I ..V§ ~~-,~Lt(- -K2

- AC

Page 91: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

K~ -j

PIP

aA-kU- -------- _______ __A

C( .14 Ik

Page 92: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

ISAC

I1 o.G o c, nk.+ 3 ,

I ICAc +-I-,,:( wcI

61I I'\~ y C- C47

0ccv ~~I<~)v --- ~

c.~y -4 ~

Page 93: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

4 -GSL'•deI C - .c e .

4T 2 -

• ' " • • .,.c• -% , - 54 ? -

- c

.. ,,..Ii

Page 94: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Ia � �zu�±x�hzzr�

I - � TQ�4�\i� _�QI���.���____

I T��L1

/

Cjc� Zt�.

IfI if

.2rScN§- A�A-� T�J &'�C �� y�.�Z..&?fS -�

I�v"'-' L - "� v

1

I- -. \-.-

-IU S.- \Al �

--4. /'. (� .- �-t

� ,�.A �.--

* .L�ZM *

I ., �JL.

I-� ,-- L.. *'�&--.U 1�; j Lr

I 1-.-.

Page 95: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

Ai1-

II

. .o-1r-, -7.

I/

,- " ' - I"s

I - -41

Le - ~ .-

Page 96: PRELIMINARY ASSESSMENT ARMY RESERVE CENTER … · occupied by the 961st Engineering Battalion, a unit from the 86th Army ARCOM. Its mission is construction and approximately 145 people

I.. L) 4 10oKVl x4-y tL'

LI


Recommended