ANNUAL PROGRESS REPORT, 2017
Page 1
AKWAPIM SOUTH DISTRICT ASSEMBLY
ANNUAL PROGRESS REPORT, 2017
PREPARED BY: DISTRICT PLANNING
COORDINATING UNIT
ANNUAL PROGRESS REPORT, 2017
Page 2
Table of Contents
Executive Summary 4
PART ONE: GENERAL PROFILE OF THE AKWAPIM SOUTH DISTRICT 5
1.0 Backgroud 5
1.1 Location and Size 5
1.2 Vision Statement 5
1.3 Mission Statement 6
1.4 Population Size and Density 6
1.5 Rural-Urban Split 6
1.6 Economic Potentials of the District 7
1.7 Structure of the Akwapim South District Assembly 8
1.8 Executive Committee of the Akwapim South District Assembly 8
1.8.4 Organogram of the Akwapim South District Assembly 11
1.8.6 Human Resource Management 13
1.9 Processes and Difficulties in undertaking the Monitoring and Evaluation 15
PART TWO: PROGRAMMES AND PROJECTS IMPLEMENTATION 17
2.0 Implementation Status of the District MTDP (2014-2017) 17
2.1 Issues from the 2017 Annual Action Plan 21
2.2 Programs and Projects 24
PART THREE: FINANCE, INDICATORS & TARGETS AND DEVELOPMENT
INTERVENTIONS 29
3.1 Funding Sources for the District’s Programmes and Projects 29
3.3 Efforts to Increase Revenue Generation 34
3.4 Update on Disbursements 35
3.7 Update on Indicators and Targets 40
3.8 Critical Development Interventions 45
3.8.5 Agricultural Extension Service 47
PART FOUR: CHALLENGES AND MITIGATION STRATEGIES 50
4.1 Challenges and Mitigation Strategies 51
ANNUAL PROGRESS REPORT, 2017
Page 3
LIST OF TABLES
Table 1.1: List of under-developed tourist sites in Akwapim South District, 2017 9
Table 1.2: Human Resource strength by Category and sex, 2017 15
Table 1.2: Capacity Building Trainings Undertaken in the Year 2017 17
Table 2.1: Implementation Status of 2017 Annual Action Plan by Thematic Area 26
Table 2.2: Projects undertaken by Akwapim South District Assembly, 2017 28-31
Table 3.1: Financial Performance of the Assembly, 2017 34
Table 3.2: Revenue Performance of the Assembly, 2017 36
Table 3.3: Comparison of 2016/2017 Disbursements 39
Table 3.4: Summary of Progress Made on Indicators and Targets for 2017 by thematic area 46
Table 3.5: Training for LEAP Beneficiaries in making Soap and Parazone, 2017 49
Table 3.6: Agriculture development activities for year 2017 50
Table 3.7: Top 10 Causes of OPD Attendance in the District, 2017 51
Table 3.8: District Level Enrolment in Education for 2016/2017, Public 52
Table 3.9: District Level Enrolment in Education for 2016/2017, Private 52
LIST OF FIGURES
Figure 1:1 District Assembly’s Organogram 2
Figure 2.1: Comparison of Programmes/Projects Completion status for 2017 and 2016 19
Figure 2.2: Sectorial Distribution of Projects for 2017 and 2016 20, 21
Figure 3.1: Comparison between Revenue receipts and Expenditure for 2017 and 2016 33
Figure 3.2: District Revenue Generation Model 34
Figure 3.3; Comparison of 2017/2016 Disbursements Compared 36
Figure 3.4: Topmost Illnesses for OPD attendance for 2017 47
ANNUAL PROGRESS REPORT, 2017
Page 4
EXECUTIVE SUMMARY
This report covers the period 1st January 2017 to 31st December, 2017. The report highlights the
achievements and implementation status of the 2017 Annual Action Plan.
The Akwapim South District Assembly set its M&E objectives to assess the overall performance
of the 2017 annual Action plan. These included the measurement of implementation
performance during project execution, measurement of the outcomes from projects/programmes
that have been implemented. Others included the creation of a knowledgebase on
project/programme implementation performance and outcome analyses and lastly improvement
upon subsequent project/programme implementation.
Some of the District’s processes for the monitoring and evaluation of the MTDP in 2017
involved site meetings, public/community fora, Assembly meetings, scorecarding etc.
The District Assembly achieved about 40.2 percent of implementation of the 2017 Annual
Action Plan. A total of 82 projects and programmes comprising of 42 projects and 40
programmes were earmarked to be implemented during the year under review.
By the end of 2017 assessment year, 22 projects and 11 programmes were implemented and most
of these especially capital projects were at various stages of completion.
Out of the 22 projects implemented, 14 of them (64%) were on-going at various levels of
completion while the remaining 8 (36%) was completed and handed over to the user departments
and or communities.
The DACF is the bigger source of funding for the Assembly’s developmental activities. It
contributed 59.2 percent of the entire receipts obtained by the Assembly in 2017.
A total amount of Ghȼ 9,900,729.81 was disbursed by the Assembly as at end of 2017. These
funds were used to finance ongoing and new programmes, projects and services. Funds were
disbursed, as much as possible, in line with the annual budget in the areas of Administration,
Compensation, Goods & services and Investment.
ANNUAL PROGRESS REPORT, 2017
Page 5
PART ONE: GENERAL PROFILE OF THE AKWAPIM SOUTH DISTRICT
INTRODUCTION
1.0 Background
This report critically examines the projects and programmes of the Assembly that were
implemented in 2017. A careful analysis has been done on how the Assembly fared in the
implementation of the 2017 Annual Action Plan and 2017 Annual Composite Budget. The
report gives a true state of the District during the year under review in the areas of socio-
economic, political, administrative, security among others.
1.1 Location and Size
The Akwapim South District is one of the twenty-six (26) District Assemblies in the Eastern
Region of Ghana. It was carved out of the Nsawam/Adoagyiri Municipality. The L.I 2040 of 6th
February, 2012 and Act 1742 established the Akwapim South District. It has Aburi as the
District capital.
The District shares boundaries with the Nsawam/Adoagyiri Municipality to the west, South-East
by the Kpone – Katamanso District, to the South by the Ga East Municipality and to the North-
East by the Akwapim North Municipality.
Geographically, the district lies between latitudes 5.5° N and 5.58°N and longitude 0.0° W. The
District has a population of 37,501 and a land size of 224.13km².
The strength of Akwapim South District lies in two major identified development areas of
comparative advantage. These areas are agricultural and tourism sectors. Therefore, development
plans of the Assembly have been geared towards improving the two identified areas with the aim
making development trickle down to other sectors.
1.2 Vision Statement
The Akwapim South District Assembly aims at becoming a first class development and client
oriented District Assembly.
ANNUAL PROGRESS REPORT, 2017
Page 6
1.3 Mission Statement
The Akwapim South District Assembly exists to improve the quality of life of its people through
the provision of social services and the creation of an enabling environment for accelerated and
sustainable development, within the framework of democratic decentralization.
1.4 Population Size and Density
The population of the Akwapim South District, according to the 2010 Population and Housing
Census (PHC) is 37,501 representing 1.4 percent of the region’s population. Males constitute
48.5 percent and females form 51.5 percent. There are 9,287 households with a household
population of 36,932.
The fertility rate of the district’s population is 3.8 percent with a growth rate of 3.2.
According to the 2010 Population and Housing Census, the district has a density of 167 persons
per sq km which is higher than the regional and national densities of 106 and 103 respectively.
Population growth and densities may have been affected by the spillover effect from Accra that
results in the district figures being higher than the regional and national ones.
1.5 Rural-Urban Split
According to the 2010 Population and Housing Census, the District has about three-quarters
(73.4%) of its population residing in the rural areas as against 26.6% in the urban set up. This
implies, the district is rural in nature and therefore faces myriad of challenges of inadequate
social infrastructure and amenities as any rural area in Ghana.
The District has a sex ratio of 94 males to 100 females and a dependency ratio of 76.7 with male
sex having the highest dependency proportion of 81.6 compared to female ratio of 72.4. This is
mainly due to the high youthful population which constitutes 40.1% of the district’s population
and an elderly population of almost 6% which age categories are not supposed to engage in any
active economic activity.
Significant proportion of the urban population resides in Aburi, the district capital with the rural
population distributed within the dispersed settlements in the valley regions of the district.
ANNUAL PROGRESS REPORT, 2017
Page 7
1.6 Economic Potentials of the District
Akwapim South District prides itself in two major sectors for the development of its economic
potential. The agricultural and tourism sectors are important to the district’s local economy.
The District is an important food basket, involved in the cultivation of pineapples, mangoes and
citrus for both domestic and foreign markets. Majority of its farming population is engaged in
crop farming. Some food crops cultivated include maize, cassava, plantain, vegetables. Livestock
farming is not predominant as compared to food crop farming. Poultry, sheep, goats, pigs, cattle
and so forth are some of the main animals reared in the district.
The district is noted for its endowment with a number of important national monuments and
tourist sites which contribute over 60 percent to the district’s local economy. Notable among
them include:
Presidential lodge; a presidential lodge at Peduase built by Ghana’s first president Dr.
Kwame Nkrumah.
The Aburi Botanical Gardens; situated in Aburi, and was built by the Basel
Missionaries in 1890 contains preserved rare species of biodiversity. The gardens is
always described as a revered national asset.
The Aburi Craft Village; a hub for traditional artifacts and souvenirs.
Other tourist sites which could be developed but currently have not seen investments are listed in
the table 1.1.
ANNUAL PROGRESS REPORT, 2017
Page 8
Table 1.1: List of under-developed tourist sites in Akwapim South District, 2016.
TOURIST SITE LOCATION REMARK
1. Waterfalls Boade Requires further development
2. Natural rock bridge with a
stream running underneath
Pepawani Requires further development
3. Osei Tutu shrine Berekuso Requires further development
4. Coffin-shaped rock Oboadaka Requires further development
5. Obo-guanten (rock with
sheep-like look
Kobiso Requires further development
Source: DPCU Survey, 2017
1.7 Structure of the Akwapim South District Assembly
The Akwapim South District Assembly, the highest political and administrative body in the
District is made up of 24 elected Assembly Members and 11 appointed by President of the
Republic. There exists a Member of Parliament and the District Chief Executive who are also
members of the Assembly.
1.8 Executive Committee of the Akwapim South District Assembly
The Executive Committee is composed of the chairpersons of the various sub-committees
including the five mandatory ones as listed below:
Finance and Administration,
Justice and Security,
Works,
Social Services, and
Development Planning
The District Chief Executive is the chairman of the Executive Committee.
1.8.1 Sub-committees of the Assembly
Five statutory sub-committees have been created and each consists of a minimum of 7 Assembly
Members and headed by a chairman selected from among the members. These sub-committees
are as shown below:
ANNUAL PROGRESS REPORT, 2017
Page 9
a. Finance and Administration c. Works
b. Justice and Security d. Social Services
e. Development Planning
1.8.2 Additional committees
The Assembly has created these additional committees for the effective and efficient
implementation of policies, programs and projects. The list includes the;
Education sub-committee
Public Relations and Complaints committee
Disability Fund Management committee
District Security Committee
District Entity Tender Committee
District Tender Review Board
Statutory Planning Committee
Market Committee
District AIDS Committee
District Standing Implementation Committee
Audit Report Implementation Committee
Some of these committees are ad-hoc; constituted to deal with a situation on hand while some are
standing.
1.8.3 Functions of the District Assembly
The functions of the Akwapim South District Assembly are as those derived from the statutes
existing in the Local Governance Act, Act 936 of 2016, and the Legislative Instrument 2040 of
2012, Act 1742 which established the Assembly. These functions are being performed in a
manner that will satisfy the vision and mission of the Assembly.
The political and administrative functions as found in Section 10 sub-section (1) of the Local
Governance Act, Act 936 of 2016 are continually pursued by the Assembly.
An adjustment of the Assembly’s structure is intended so that the new organogram takes into
account the changes brought about by the Local Governance Act 936 of 2016 requiring creation,
ANNUAL PROGRESS REPORT, 2017
Page 10
mergers and removal of departments. Notwithstanding, the departments that exist already liaise
with one or more for the performance of the District’s functions to facilitate development. For
the time being, the organogram below has being adopted.
ANNUAL PROGRESS REPORT, 2017
Page 11
1.8.4 Organogram of the Akwapim South District Assembly
Figure 1:1 District Assembly’s Organogram
ANNUAL PROGRESS REPORT, 2017
Page 12
1.8.5 Local Government Service Departments and Agencies
There exist the following departments, government sub-vented agencies and services in the
Akwapim South District.
Departments of the Assembly:
Central Administration
Department of Social Welfare and Community Development
Department of Agriculture
Department of Physical Planning
Works Department
Department of Births and Deaths
Department of Finance
Department of Environmental Health
Decentralized Departments
Ghana Health Service
Ghana Education Service
Government Sub-vented Agencies
National Disaster Management Organization (NADMO)
National Commission for Civic Education
Electoral Commission of Ghana
Services
Ghana Police Service
Ghana National Fire Service
Ghana Immigration Service
ANNUAL PROGRESS REPORT, 2017
Page 13
1.8.6 Human Resource Management
Overall, there are 111 staff who work at the Assembly which comprises 67 males and 44
females. The table below indicates the breakdown of the existing staff capacity in gender, senior
and junior staff categories for the centralized and decentralized units/divisions/departments of
the Akwapim South District Assembly.
ANNUAL PROGRESS REPORT, 2017
Page 14
Table 1.2: Human Resource strength by Category and Sex, 2017
Source: Human Resource Unit, Akwapim South District Assembly, 2018
Department/Unit SENIOR STAFF TOTAL JUNIOR STAFF TOTAL TOTAL STAFF TOTAL
MALE FEMALE MALE FEMALE MALE FEMALE
Administration
4 3 7 3 4 7 7 7 14
Department of Agriculture
11 4 15 2 0 2 13 4 17
Development Planning Unit
2 0 2 0 0 0 2 0 2
Department of Finance
3 1 4 0 0 0 3 1 4
Budget Unit
2 1 3 0 0 0 2 1 3
Revenue
1 1 2 2 1 3 3 2 5
Procurement unit
0 2 2 0 0 0 0 2 2
Internal Audit unit
1 2 3 0 0 0 1 2 3
Human Resource Unit
0 2 2 0 0 0 0 2 2
Department of Social Development
6 10 16 1 1 2 7 11 18
Department of Physical Planning
0 0 0 5 0 5 5 0 5
Works Department
8 0 8 0 0 0 8 0 8
Department of Environmental Health
4 3 7 5 5 10 9 8 17
Department of Births and Deaths 0 1 1 0 0 0 0 1 1
Security 0 0 0 3 0 3 3 0 3
Cleaners 0 0 0 0 3 3 0 3 3
Drivers 0 0 0 4 0 4 4 0 4
TOTAL 42 30 72 25 14 39 67 44 111
ANNUAL PROGRESS REPORT, 2017
Page 15
1.9 Processes and Difficulties encountered in undertaking the Monitoring and Evaluation
The District Planning Co-ordinating Unit (DPCU) adopted multidisciplinary approaches in its
monitoring and evaluation activities in the year under review. It also faced a number of
difficulties which negatively affected effective monitoring and evaluation in the period. Below
are some of the processes involved and the challenges encountered in the monitoring and
evaluation activities:
1.9.1 Key Monitoring and Evaluation Objectives
The key monitoring and evaluation objective of the Akwapim South District Assembly for 2017
was to assess the extent to which project and program implementation in the annual action plan
enhances increased enrolment at basic schools and reduces post harvest losses of agric produce
in the district.
Other objectives for the year include:
to measure implementation performance during project execution
to measure outcomes from projects/programmes that have been implemented
create a knowledgebase on project/programme implementation performance and
outcome analyses
improve upon subsequent project/programme implementation
1.9.2 Processes Used in Monitoring and Evaluation, 2017
Reports from decentralized departments and agencies
Site meetings
Visits to projects sites
Stakeholder engagements especially beneficiary communities and user agencies and
departments
Assembly meetings
ANNUAL PROGRESS REPORT, 2017
Page 16
1.9.3 Difficulties Encountered in Monitoring and evaluation for the year
Lack of full complement of decentralized departments and agencies to constitute DPCU
Late release of District Assemblies Common Fund and other Donor Grants
Non-release of funds for monitoring and evaluation
Inadequate relevant logistics such as vehicles, computers and printers to support DPCU
activities
ANNUAL PROGRESS REPORT, 2017
Page 17
PART TWO: PROGRAMMES AND PROJECTS IMPLEMENTATION
INTRODUCTION
Part Two covers implementation issues regarding the District’s Medium Term Development
Plan. It presents in tables, programmes and projects that were undertaken or penciled to be
undertaken in 2017 as per the quarters in the year. Other major subjects under discussion in this
part of the report include sources of funds, efforts at revenue generation, disbursement of funds
et cetera.
The section also captures the District’s indicators and targets covering the four quarters and
lastly on critical development interventions that were carried out in the year 2017.
2.0 Implementation Status of the District MTDP (2014-2017)
The year 2017 represents the final year of the implementation of the 2014-2017 District Medium
Term Development Plan under the Ghana Shared growth and development agenda II. A special
feature of the development plan for the year under review is the roll-over of;
- projects and programmes that could not be started in the year 2016 implementation
period of the action plan and were still relevant to the communities and or
- projects and programmes that were started in 2016 but could not be completed. The chart
below shows the implementation status of the action plan for 2017.
The 2017 annual action plan achieved a 40.2 percent implementation level as against 90 percent
in 2016. This is attributable to the fact that in 2016 the Assembly received more financial
releases than 2017. In terms of the overall proportion of the 2014-2017 DMTDP implementation,
2017 experienced a 48.6 percent implementation level, the second lowest achievement after
2014.
The table below illustrates the 2017 annual action plan implementation.
ANNUAL PROGRESS REPORT, 2017
Page 18
Proportion of the district medium term development plan implemented, 2014-2017
Indicators 2017 2016 2015 2014
Proportion of the annual action plans
implemented by the end of the year
40.2% 90 % 50% 35%
Proportion of the overall medium term
development plan implemented by the end of
the year
48.6% 95% 60.2% 40.5%
Source: DPCU Annual Reports, ASDA
ANNUAL PROGRESS REPORT, 2017
Page 19
Figure 2.1: Comparison of Programmes/Projects Completion status for 2017 and 2016
0
2
4
6
8
10
12
14
16
18
20
100% Range of 90% Range of 80% Range of 70% Range of 60% Range of 50% Range of 40% Range of 30% Range of 20% Range of 10% Below 10%
PROGRAMMES/PROJECTS COMPLETION AT PERCENTAGE LEVELS - 2017 & 2016
2017 2016
ANNUAL PROGRESS REPORT, 2017
Page 20
Most projects that were started during or commenced before the year under review witnessed
high levels of completion with at least 20 projects witnessing between 70 percent and 100
percent completion levels. This was not different from the 2016’s record. This means that the
pace at which the Assembly expedited action on its projects execution has been commendable
and needs to be continued.
This was partly attributable to the urgent need to complete most of the mandatory projects,
frequent monitoring embarked upon by the DPCU. If enough revenue was received or generated
in 2017, it would have been possible that many more projects could be completed.
Sector by Sector Level of Implementation of 2017 Annual Action Plan
In this section, an overview is given of the sectorial implementation of projects and or
programmes from the MTDP for the year 2017. Education ranks high with 9 projects undertaken
during the 2017 fiscal year and were either completed or on-going.
Figure 2.2: Sectorial Distribution of Projects for 2017 and 2016.
2
9
5 5
2
0
1
2
3
4
5
6
7
8
9
10
Economic Education Health Environment/SanitationGovernance
Distribution of Projects in Various Sectors, 2017
ANNUAL PROGRESS REPORT, 2017
Page 21
In 2016, the education sector recorded the highest number of projects implemented (12) and was
followed by the health and environment/sanitation sectors. The 2017 trend has followed the
pattern of 2016 with the difference being that in 2017 fewer numbers were recorded across the
various sectors. The Assembly is still resolute on its commitment to ensuring that poverty and
disease are eradicated through access to basic education for all in the District.
In terms of absolute numbers, there was no improvement in the sector of governance in 2017 as
compared to that in 2016. However, the citizenry in the district participated in the development
process of the District such as the preparation of the 2018-2021 DMTDP.
2.1 Issues from the 2017 Annual Action Plan
2.1.1 Implementation Status of the 2017 Annual Action Plan
The overall assessment of implementation of the 2017 Annual Action Plan per the various
quarters under given thematic areas is presented in table 2.1. Figure 2.3 further gives details and
visual illustration of table 2.1.
It is observed from table 2.1 that in 2017, Human Development, Productivity & Employment
thematic area recorded the highest number of programmes and projects implemented (18) during
the year under review. This is so because the Assembly as a newly created one is committed to
ensuring that basic facilities for education, health and sanitation which bother on human
6
12
6
10
21
2
0
2
4
6
8
10
12
14
Economic Educat ion Health Environment Governance Administrat ion Sanitat ion
Distribution of Projects in Various Sectors, 2016
ANNUAL PROGRESS REPORT, 2017
Page 22
development are adequately provided for the people and are accessible to all irrespective of
gender, age, economic or social standing of a person.
Infrastructure and Human Settlements Development sector performed abysmally in the overall
performance of the 2017 Annual Action Plan implementation, recording only 11 percent as
against 60.2 percent record in 2016.
The overall effect is that resources were prudently allocated to the most needed sectors of the
plan that needed urgent attention and were strategic in having a net effect in boosting the other
sectors of the district’s economy.
ANNUAL PROGRESS REPORT, 2017
Page 23
Table 2.1: Implementation Status of 2017 Annual Action Plan by Thematic Area
Source: DPCU Monitoring and Evaluation, 2017
Thematic Area
2017 2016
No. of
project/progra
mmes
scheduled for
implementatio
n
No.
implemented
%
performance
by Thematic
Area
Overall
Thematic
performance
in the year
(%)
No. of
project/progr
ammes
scheduled
for
implementati
on
No.
implemented
%
performance
by Thematic
Area
Overall Thematic performance in
the year (%)
Ensuring and Sustaining Macro
Economic Stability
0 0 0 0 0 0 0 0
Enhancing Competitiveness of Ghana’s
Private Sector
8 2 25.0 2.4 11 10 96.6 13.3
Accelerated Agricultural
Modernization and Sustainable
Natural Resource Management
6 3 50.0 3.7 17 15 88.0 15.7
Infrastructure and Human Settlement 18 2 11.0 2.4 26 16 60.2 24.8
Human Development, Productivity and
Employment
34 18 53.0 22 26 15 57.1 23.9
Transparent and Accountable
Governance
16 2 13.0 2.4 23 13 57.1 19.5
ANNUAL PROGRESS REPORT, 2017
Page 24
2.2 Programs and Projects Implementation, 2017
The 2017 Annual Action Plan principally comprised of roll over activities from the 2016 Annual
Action Plan. These activities were physical projects that were either implemented and not
completed or not implemented at all in 2016 due to factors such as inadequate funds. The
projects had to be rolled over because they were considered very relevant in the provision of
services critical to the needs of the people in the District for the year 2017.
From table 2.2, the education sector had the most number of projects implemented in 2017. In
all, 9 projects were implemented from the 2017 Annual Action Plan and targeted at educational
infrastructure. Projects and programmes were implemented across other sectors including health,
economic and environment.
The reason education ranked high on project implementation is that it focuses on one of the key
development priorities identified and contained in the District’s MTDP 2014-2017 (pg. 59)
which targets expansion of educational infrastructure to fill a ballooning gap in the sector,
perhaps, due to the fact that the District is relatively new and therefore would naturally lack basic
infrastructure such as educational, health and toilet facilities.
Table 2.2 outlines programmes and projects in the 2017 Annual Action Plan and the extent of
their implementation.
ANNUAL PROGRESS REPORT, 2017
Page 25
Table 2.2: Projects/Programmes undertaken by Akwapim South District Assembly, 2017
Item. Project
Description
Location Sector Contractor
/
Consultant
Contract
Sum
Source of
Funding
Date of
Award
Expected
Date of
Completion
Expenditur
e To-Date
Outstanding
Balance
Status of
Implementati
on
Remarks
1. Construction of
1No. 6Unit
classroom block
with ancillary
facility
Aburi Kemp Education
M/S
Mojoson
Company
Ltd.
179,788.90 DACF 30/5/14 30/5/15 106,184.13 73,604.77 70%. Roofing
level
Contract
terminated and
reawarded
2. Construction of
1No. 6Unit
classroom block
with ancillary
facility
Yaw
Nyarkokro
m
Education M/S Opanin
Nyarko
Constructio
n works
174,889.00 DACF 30/5/14 30/5/15 156,160.00 18,729.00 80%. Roofing
completed
Delay in
release of
funds affects
progress of
work
3. Construction of
community
hospital
Kitase Health M/S Living
Grace Co.
Ltd.
134,101.80 MP’s
Common
Fund
30/5/14 30/5/15 115,851.16 18,250.64 90%
Plastering
works
completed
On-going
4. Construction of
28 lockable
stores
Aburi Economic M/S
Delovely
Co. Ltd.
322,620.55 DDF 31/5/13 30/4/14 306,070.55 16,550.00 95%.
Painting on-
going
On-going
5. Construction of
158m Drain
Aburi
Aboanum
Environm
ent
Mills Sarfo
Co. Ltd.
92,681.40 DACF 31/8/13 31/8/14 71,567.52 21,113.88 80% On-going
6. Construction of 1
No 6-Unit class
room block with
ancillary facility
Berekuso Education M/S
Delovely
Co. Ltd
199,982.95 GETFUN
D
5/11/2013 5/5/2014 ---- --- 80% On-going
7. Construction of 1
No. CHPS
compound with
ancillary facilities
Obodan Health Fort-Kofi
Limited
199,136.70 DACF 31/7/2015 31/07/2016 73,082.47 126,054.23 60% On-going
8. Construction of
1No. CHPS
compound with
ancillary facilities
Dumpong Health EddyMarth
Constructio
n Ltd.
199,032.00 DACF 31/7/2015 31/07/2016 98,872.20 100,159.9 60%. level
On-going
9. Construction of
CHPS Centre
with an outhouse
Yaw Duodu Health Issahaku L.
Const. Ltd
199,836.50 DACF 01/3/2016 28/02/2017 163,788.85 36,047.65 90%. Contract
terminated
10. Construction of a
4-in-one
teachers’ quarters
with auxiliary
Dumpong Education M/S
Chriskad
Projects
474,380.00 GETFund 10/2/2016 09/09/2016 84,388.85 389,991.15 60% On-going
ANNUAL PROGRESS REPORT, 2017
Page 26
facilities
No. Title of Project Location Sector Contractor
s
Contract
Sum
Funding
Source
Award
Date
Expected
Completion
Date
Expenditur
e To-Date
Outstanding
Balance
Status Remarks
11. Construction of a
4-in-one
teachers’ quarters
with auxiliary
facilities
Ayim Education M/S
Wealthwell
Company
Ltd.
456,799.09 GETFund 10/2/2016 09/09/2016 315,481.34 141,317.75 100% Handed over
to school
12. Construction of
CHPS Centre
with an outhouse
Adjenase
Piem
Health Northern
Co. Ltd
199,979.00 DDF 01/3/2016 28/02/2017 179,582.00 20,397.00 90%.
Finishing
works to be
done
Contract
terminated
13. Construction of
1No. 12 seater
WC toilet facility
with mechanized
borehole
Aburi –
Aboanum
Environm
ent
M/S
SALPEZ
Trading and
Constructio
n Ltd.
160,050.00 DACF 00/4/2016 00/10/2016 130,005.00 30,045.00 100% of work
done
Completed
and in use
14. Construction of
10 seater
institutional
latrine
Yaw
Nyarkokro
m
Environm
ent
M/S
SALPEZ
Trading and
Constructio
n Ltd.
48,000.00 DDF 00/4/2016 00/06/2016 48,000.00 0.00 100% Completed
and in use
15. Construction of
1No. 6 unit
classroom block
with auxiliary
facilities
Ayim Education M/S Bilford
Constructio
n Ltd
325,600.00 DACF 20/11/201
7
20/05/2018 19,997.80 305,602.20 Footing level
at 10%
Contract
repackaged
and awarded.
M/S Bilford
awarded
contract
16. Construction of 1
No. 3 unit
classroom block
Pokrom Education M/S
Chriskad
Projects
Ltd.
250,300.00 DACF 20/11/201
7
20/05/2018 20,000.00 230,300.00 5% Contract
repackaged
and awarded.
M/S Chriskad
awarded
contract
17. Reshaping of
selected roads
District-
wide
Economic Oldman
Richard
Trading
Ent.
85,800.00 DACF ----- ----- 85,800.00 0.00 100% Completed
18. Maintenance of
street lights
District-
wide
Security District
Works
Department
11,768.00 DACF ----- ----- 11,768.00 0.00 100% of work
done
Completed
ANNUAL PROGRESS REPORT, 2017
Page 27
No. Title of Project Location Sector Contractor
s
Contract
Sum
Funding
Source
Award
Date
Expected
Completion
Date
Expenditur
e To-Date
Outstanding
Balance
Status Remarks
19. Reroofing of
Methodist JHS
Gyankama Education District
Works
Department
5,750.00 DACF ---- ----- 5,750.00 0.00 100% Completed
and in use
20. Renovation of
KVIP
Domeabra Environm
ent
District
Works
Department
7,816.00 DACF ---- ----- 7,816.00 0.00 100% Completed
21. Construction of 1
No. crèche block
Pokrom Education B & M
Company
Ltd.
176,823.00 DACF 31/07/201
5
31/07/2016 176,823.00 0.00 100% d Completed
and in use
22. Supply of official
vehicle tyres
Central
Admin.
Governanc
e
Great
Azatolarr
Enterprise
3,900.00 DACF 07/2017 07/2017 3,900.00 0.00 100% Completed
and in use
23. Rent for
education office
Central
Admin.
Governanc
e
Nana Oteng
Akuffo-
Akoto
23,400.00 DACF ---- ---- 23,400.00 0.00 100% Completed
24. Construction of
septic bank
Aburi Police
Station
Environm
ent
District
Works
Engineer
15,294.00 DACF ---- ---- 15,294.00 0.00 100% Completed
and in use
ANNUAL PROGRESS REPORT, 2017
Page 28
2.2.1 Highlights of Assembly’s Achievements in 2017
The Akwapim South District Assembly scheduled to implement a total of 82 projects and
programmes during the 2017 fiscal year which comprised of 42 projects and 40 programmes.
By the end of the year 2017, a total of 22 projects and 11 programmes were implemented during
the year and most of them especially capital projects were at various stages of completion. It
means therefore that 40.2 percent of the 2017 Annual Action Plan was implemented.
Out of the 22 projects implemented, 14 (64%) of them were on-going at various levels while the
remaining 8 (36%) was completed and handed over to the user departments and or communities.
All the 11 programmes implemented were completed because they were short term and eventful
in nature. The conduct of farm and home visits under the Department of Agriculture is a classic
example of a programme which may not be rolled over to another year.
ANNUAL PROGRESS REPORT, 2017
Page 29
PART THREE: FINANCE, INDICATORS & TARGETS AND DEVELOPMENT
INTERVENTIONS
3.1 Funding Sources for the District’s Programmes and Projects
The District Assembly obtains its revenue and funding for development from various sources.
These include, among others, the Internally Generated Fund (IGF), the District Assemblies’
Common Fund, GETFUND, Government of Ghana Grants which come to support specific
programs/projects, District Development facility which is provided to support specific projects,
MPs Common Fund, the Disability Fund et cetera.
In table 3.1, the DACF remains the major source of funding for the Assembly’s developmental
activities. It contributed as high as 59.2 percent of the entire receipts obtained by the Assembly
in 2017. The proportionate contribution is however meagre when compared to the 2016’s figure
of 66 percent.
Internally Generated Revenue, however, experienced a growth in 2017 in the region of 16
percent against the 2016 figure though it fell short (4.6%) in its contribution to total receipts of
the Assembly as compared to 2016 (13.3%). This is a clear indication of the Assembly’s
improved efforts at revenue mobilization notwithstanding the absence of market, lorry parks and
the unwillingness of property owners to honour their property rate obligations. It is instructive to
note that IGF contributed more in nominal terms to the entire finances of the Assembly in 2017.
Again from table 3.1, the Assembly relied heavily (79.5%) on transfers from the central
government to execute the 2017 Annual Action plan. This calls for the adoption of urgent and
pragmatic steps to ensure that more revenue is generated by the Assembly to improve its
financial leverage and widen the fiscal space to enable it undertake the numerous infrastructure
needs of the District. There is the need to stop total reliance on external funding which of late is
dwindling and even delays in coming due to the assumption of Ghana as a lower middle income
country.
ANNUAL PROGRESS REPORT, 2017
Page 30
Table 3.1: Sources of Funds and Amounts realized, 2017
Source of
Fund
Baseline
2013
2017
(Amt in Gh ȼ)
Percentage
contribution
to Total
Receipts
2016
(Amt in Ghȼ)
Percentage
contribution
to Total
Receipts
2015
(Amt in Ghȼ)
Percentage
contribution
to Total
Receipts
2014
(Amt in Ghȼ)
Percentage
contribution
to Total
Receipts
Target Actual Target Actual Target Actual Target Actual
IGF - 436,443.00 481,837.01 4.66 444,043.00 417,094.98 13.3 382,813.07 426,459.04 20.99 413,920.00 371,329.83 28.95
DACF - 3,003,085.
00
1,252,310.39 59.2 2,318,953.
17
2,070,626.
70
66.0 2,498,420.
00
1,355,246.03 66.70 2,293,420.55 345,892.64 26.97
MPs Common
Fund
- 470,000.00 363,261.39 3.52 470,000.00 130,731.89 4.2 241,507.00 170,945.04 8.41 40,000.00 196,207.29 15.30
DDF - 345,800.00 0.00 0.00 596,347.00 368,129.04 11.7 214,057.00 0.00 0.00 402,102.95 294,602.12 22.97
Disability
Fund
- 70,000.00 12,492.54 0.12 100,000.00 93,260.48 3.0 70,000.00 79,223.15 3.90 70,000.00 74,560.43 5.81
HIV/AIDS
(MSHAP)
- 13,214.74 4,280.98 0.04 13,501.74 7,312.99 0.1 --- --- --- --- --- ---
LEAP - --- --- --- --- --- --- --- --- --- --- ---
Sub-total - 4,338,542.
74
2,114,182.31 3,942,844.
91
3,087,156.
08
GOG
GRANTS
(Salaries and
Staff
compensation)
- 9,000,000.
00
8,218,411.86 - 90,000.00 52,000.00 --- --- --- --- --- ---
Total Revenue - 13,338,542
.74
10,332,594.1
7
100.00 4,032,844.
91
3,139,156.
08
100.00 3,406,797.
07
2,031,873.26 100.00 3,219,443.5 1,282,592.31 100.00
Source: Finance Department & Budget Unit, Akwapim South District Assembly, 2018
ANNUAL PROGRESS REPORT, 2017
Page 31
3.2 Revenue and Expenditure Performance & Analysis in 2017
In table 3.2, rates witnessed a significant increase in performance from 92.5 percent in 2016 to
126.5 in 2017 in terms of the actual figures realized. This was partly due to public sensitization
and awareness creation that the Assembly embarked upon vigorously in 2017.
Lands and Concessions also increased in actual terms, that is 11.8%, over the 2016 figure. Fees
& Fines and Licenses together experienced some 9 percent reduction in performance in 2017
compared to that of 2016.
The changes were very substantial enough to cause an increase in total IGF of GH₵ 409,412.98
in 2016 to GH₵ 459,735.74 in 2017.
On expenditure, except Grants, all expenditure heads had more than 90 percent utilization in
2017. Social benefits reduced significantly by 32.1 percent to its current figure of 41.4 percent in
2017. The Assembly managed to control its expenditure on non-financial assets thereby reducing
it by 19.7 percent in 2017.
ANNUAL PROGRESS REPORT, 2017
Page 32
Comparative Statement of Revenue for 2017-2014
Table 3.2: Revenue Performance of the Assembly, 2016
Head Revenue
Head and
Sub-Head
Baseline (2013) Target 2017 (GH₵) Actual as at
31/12/2017
(GH₵)
Performance
%
Target 2016
(GH₵)
Actual as at
31/12/2016
(GH₵)
Performance
%
IGF
1 Rates 65,000.00 82,255.00 126.5 65,000.00 60,154.00 92.5
2 Lands &
Royalty
(Concession).
205,700.00 232,907.00 113.2 160,000.00 208,408.98 130.3
3 Fees & Fines 33,743.00 32,242.74 95.5 55343.00 26,581.00 48.0
4 Licenses 118,000.00 95,977.00 81.3 158,100.00 114,269.00 72.0
5 Rent 10,000.00 -- 0.00 1,000.00 - 0.00
6 Investment
Income
1,000.00 -- 0.00 600.00 - 0.00
433,443.00 459,735.74 440,043.00 409,412.98 93.0
7 Grants 12,886,472.00 9,917,068.01 77.0 3,373,558.86 11,890,706.66 352.5
8 Miscellaneous 3,000.00 2,207.26 73.6 4,000.00 7,672.00 191.8
Total Receipts 13,322,915.00 10,362,657.01 77.8 3,817,601.86 12,307,791.64 322.4
Head Revenue
Head and
Sub-Head
Baseline (2013) Target 2015 (GH₵) Actual as at
31/12/2015
(GH₵)
Performance
%
Target 2014
(GH₵)
Actual as at
31/12/2014
(GH₵)
Performance
%
IGF
1 Rates 55,000.00 32,720.00 59.5 4,000.00 20,977.00 52.44
2 Lands &
Royalty
(Concession).
124,422.00 168,538.00 123.8 220,000.00 245,561.00 111.61
3 Fees & Fines 33,228.00 22,268.00 69.1 5,400.00 9,764.00 375.53
4 Licenses 149,113.07 119,814.00 147.7 61,144.00 58,472.00 91.44
5 Rent 12,000.00 0.00 -- 0.00 0.00 --
6 Investment
Income
600.00 0.00 -- 0.00 0.00 --
7 Grants 4,859,557.56 10,342,001.63 212.8 2,847,342.50 1,541,236.47 54.1
8 Miscellaneous 18,000.00 13,445.00 74.7 34,080.00 36,555.83 107.3
Total Receipts 5,182,912.63 10,696,778.63 3,208,066.50 1,912,566.30
ANNUAL PROGRESS REPORT, 2017
Page 33
Comparative Statement of Expenditure for 2017-2014
Head Expenditure
Head and Sub-
Head
Baseline
(2013)
Target 2017 (GH₵) Actual as at
31/12/2017
(GH₵)
Performance
%
Target 2016
(GH₵)
Actual as at
31/12/2016
(GH₵)
Performance
%
1 Compensation of
Employees
124,000.00 133,260.36 107.5 138,600.00 140,451.20 101.3
2 Goods and
Services
213,700.00 216,556.45 101.3 176,443.00 164,460.78 93.2
3 Interest 2,000.00 2,043.83 102.2 1,000.00 1,224.34 122.4
4 Grants 12,886,472.00 9,456,965.84 73.4 3,373,558.86 12,527,482.9 371.3
5 Social Benefits 44,000.00 42,922.33 97.6 64,000.00 63,219.50 98.8
6 Other Expenses 32,743.00 29,470.00 90 39,000.00 37,251.95 95.5
7 Non-Financial
Assets
20,000 19,511.00 97.6 25,000.00 24,300.00 97.2
Total Payments 13,322,915 9,900,729.81 74.3 3,817,601.86 12,958,390.67 339.4
Head Expenditure
Head and Sub-
Head
Baseline
(2013)
Target 2015 (GH₵) Actual as at
31/12/2015
(GH₵)
Performance
%
Target 2014
(GH₵)
Actual as at
31/12/2014
(GH₵)
Performance
%
1 Compensation of
Employees
152,869.00 141,916.42 92.8 113,421.00 116,324.31 102.6
2 Goods and
Services
171,844.00 143,494.49 83.5 132,500.00 116,501.97 121.13
3 Interest 4,000.00 5,020.00 105.5 4,000.00 1,933.04 48.3
4 Grants 4, 765,093.63 10,014,983.03 210.3 1,757,000.5 1,096,524.98 62.4
5 Social Benefits 22,000.00 9,105.20 41.4 48,424.00 69,127.1 142.75
6 Other Expenses 44,600.00 42,902.09 96.2 18,500.00 31,207.62 168.68
7 Non-Financial
Assets
22,500.00 31,860.00 141.6 -- --
Total Payments 5,182,906.63 10,389,281.23 200.5 2,073,845.50 1,475,619.02 59.86
ANNUAL PROGRESS REPORT, 2017
Page 34
Figure 3.1: Comparison between Revenue receipts and Expenditure for 2017 and 2016
3.3 Efforts to Increase Revenue Generation
As part of efforts to help boost revenue generation, the Assembly put in place a Revenue
Mobilization Task Force to help in that regard. In addition, the work of the revenue collectors
was reviewed with the aim of improving upon their performance.
Management of the Assembly held a number of meetings with revenue collectors and rate payers
to review revenue collection activities and instituted effective supervision and monitoring
mechanisms to enhance and reduce leakages in order to improve revenue mobilization.
Management adopted the model below to block the leakages in revenue mobilization.
0.00 2,000,000.00 4,000,000.00 6,000,000.00 8,000,000.00 10,000,000.0012,000,000.0014,000,000.00
ACTUAL RECEIPTS 2016
ACTUAL EXPENDITURE 2016
ACTUAL RECEIPTS 2017
ACTUAL EXPENDITURE 2017
REVENUE AND EXPENDITURE TRENDS FOR 2017/2016
ANNUAL PROGRESS REPORT, 2017
Page 35
Figure 3.2: District Revenue Generation Model
Source: DPCU M&E, 2017
3.4 Other Challenges with Regard to Revenue Mobilization
Other challenges affecting revenue generation in the District are enumerated below:
poor road network;
the vehicle for revenue mobilization has broken down;
low public awareness on honouring their civic duties regarding payment of tax which led
to poor attitude towards payment of taxes and rates;
inadequate logistics to support revenue collectors e.g. motorbikes/bicycles, raincoats,
revenue leakages etc.
3.4 Update on Disbursements
A total amount of Ghȼ9,956,685.57 was disbursed by the Assembly as at close of 2017. These
funds were used to finance ongoing and new programmes, projects and services. Funds were
•Sensitize rate payers
•Update revenue database
•Renumber properties especially households
EDUCATION AND DATABASE
•Serve demand notices for payment of property rates and other levies before end of 1st quarter each year
•Erect revenue barriers to collect tolls on exports from the District (basically farm produce)
REVENUE COLLECTION
•Cede some revenue to Area Councils
INCENTIVES
ANNUAL PROGRESS REPORT, 2017
Page 36
disbursed, as much as possible, in line with the annual budget in the areas of Administration,
Compensation, Goods & Services and Investment. The summary of disbursements is given in
table 3.3 below and graphically illustrated in figure 3.3.
ANNUAL PROGRESS REPORT, 2017
Page 37
Table 3.3: Update on 2017 Expenditure and other years
Disbursement Target
2017
( GH¢)
Actual
2017
(GH¢)
% Target 2016
(GH¢)
Actual 2016
(GH¢)
% Target
2015
(GH¢)
Actual 2015
(GH¢)
% Target 2014
(GH¢)
Actual 2014
(GH¢)
%
Compensation
for employees
124,000.00 1,008,530.0
2
10.13 138,600.00 140,451.20 1.08 152,869.00 141,916.42 1.38 113,421.00 116,324.31 8.31
Use of goods
and services
213,700.00 225,808.57 2.27 176,443.00 164,460.78 1.27 171,844.00 143,494.49 1.39 132,500.00 116,501.97 8.32
Interest 2,000.00 1,576.54 0.02 1,000.00 1,224.34 0.009 4,000.00 5,020.00 0.049 4,000.00 1,933.04 0.14
Grants 12,886,472.
00
8,651,869.4
1
86.90 3,373,558.86 12,527,482.9 96.7 4,
765,093.63
10,014,983.03 97.1 1,757,000.
5
1,096,524.
98
78.3
Social Benefits 44,000.00 40,660.03 0.41 64,000.00 63,219.50 0.49 22,000.00 9,105.20 0.088 48,424.00 69,127.1 4.94
Miscellaneous 70.00 0.0007 61,551.95 0.47
Total
Expenditure
9,956,685.5
7
12,958,390.6
7
5,115,806.
63
10,314,519.14 2,055,345.5 1,400,411.4
Source: Finance Department, Akwapim South District Assembly, 2018.
ANNUAL PROGRESS REPORT, 2017
Page 38
Figure 3.3; Comparison of 2017/2016 Disbursements Compared
Source: Finance Department, Akwapim South District Assembly (2018).
0 1000000 2000000 3000000 4000000 5000000 6000000 7000000 8000000 9000000 10000000
Compensation for employees
Use of goods and services
Interest
Grants
Social Benefits
Miscellaneous
2017 Disbursements
0.00 2,000,000.00 4,000,000.00 6,000,000.00 8,000,000.00 10,000,000.00 12,000,000.00 14,000,000.00
Compensation for employees
Use of goods and services
Interest
Grants
Social Benefits
Miscellaneous
2016 Disbursements
ANNUAL PROGRESS REPORT, 2017
Page 39
Aside Grants, Compensation for employees representing 10.13% was the most paid for in the
year 2017 as the graph above shows. Payment for goods and services was also third (3rd) high in
the list of disbursement items for the same period. Compensation and Goods & Services
payments amounted to 12.4% of total disbursements in 2017.
In 2016 however, Compensation payment was a little over a percent (1.1) reducing significantly
against Grants (96.7 percent). Goods and Services together with Compensation accounted for
only 2.4% of disbursements during 2016.
3.5. Adequacy of Funds
There are as many as 17 projects under funding from the DACF and 3 from the DDF. The
Assembly depends on these two important resources for investment mostly in its capital projects.
As much as Gh¢ 941,656.63 and Gh¢ 84,947 are outstanding balances from physical projects
being implemented under the sources of DACF and DDF respectively.
The total DACF funds received for year 2017 was Gh¢ 1,252,310.39 whilst DDF was Gh¢0.00.
For projects funded with DACF, it meant that all of them could be funded from this total but
since all of the DACF revenue is not put into capital expenditure, this source of funding was
therefore not sufficient for the project needs.
No DDF funds were received in 2017 and given the balance outstanding, resources were
therefore unavailable for the implementation of projects and capacity building activities
scheduled under DDF.
Considering that the District is an ‘infant’ one, the inadequacy of funds led to non-achievement
in full of its medium term goals and objectives for the year. As a result, some programmes and
projects have had to be rolled over to 2018.
3.6 Utilization of funds in accordance with the budget for 2017
The basis for expenditure has been the Annual Composite Budget for the fiscal year of 2017. An
over-run of 2.5 percent of expenditure has been made mainly due to emergencies occurring
during the year under review. The general indication however is that most expenditure in the
year 2017 was in line with the budget for the 2017 fiscal year.
ANNUAL PROGRESS REPORT, 2017
Page 40
3.7 Update on Indicators and Targets
Table 3.4 provides a summary of assessment of performance on the Ghana Shared Growth and
Development Agenda (GSGDA II) and District core indicators that were identified and
monitored in 2017. A summary of the progress made on indicators and targets as at the end of
December, 2017 is provided below.
ANNUAL PROGRESS REPORT, 2017
Page 41
Table 3.4: Summary of Progress made on Indicators and Targets for 2017 by thematic area.
S/N INDICATORS
(categorized by GSGDA
Thematic Area)
DISTRICT
BASELINE
2013
DISTRICT
TARGET
2017
ACTUAL
2017
DISTRICT
TARGET
2016
ACTUAL
2016
DISTRICT
TARGET
2015
ACTUAL
2015
DISTRICT
TARGET
2014
DISTRICT
ACTUAL
2014
PRIVATE SECTOR COMPETIVENESS
1. Change in yield of selected
crops and livestock.
Maize 2.29kg 2.8 2.5 3.2 2.5 3.2 2.6 2.75
Rice (milled) --- --- --- --- --- --- ---
Cassava 27.3kg 10.3 4.2 10.3 4.2 10.3 26.9 27.6
Plantain 9.25 6.0 7.2 6.0 7.1 6.0 30.8 10.3
Pineapple 19.5 16.5 12.1 16.5 11.6 51.0 19.7 19.5
Pawpaw --- --- --- --- --- --- --- Mango --- --- --- --- --- --- --- Banana --- --- --- --- --- --- --- Cocoyam 5.35 kg 3.4 4.1 2.8 4.2 2.8 5.5 6.0
Yam 16.20 36kg 3.2kg 35kg 2.8kg 35Kg 9.6kg 16.5
Tomatoes 6.20 11kg 5.8kg 20kg 5.7kg 20.0Kg 12.8kg 6.7
Pepper 2.1 5kg 3.6kg 5kg 3.0kg 5kg 4.0kg 2.5
Sheep 20.1kg 21.1 17.1 21.1 17.0 22.1 23.6 33.8kg
2. Proportion/length of roads maintained/rehabilitated
- Trunk Roads (in km) - Urban Roads (in km) - Feeder Roads (in km)
- - - - - - - - -
- 30km 5km 40km 32km 40km 10km 20km 0km
- 70km 66.5km 50.2km 45.6km 50km 20.4km 35km 0km
3. Percentage change in
number of households
with access electricity
70% 74% 73% 74% 73% 74% 71% 75% 70%
ANNUAL PROGRESS REPORT, 2017
Page 42
S/N INDICATORS
(categorized by GSGDA
Thematic Area)
DISTRICT
BASELINE
2013
DISTRICT
TARGET
2017
ACTUAL
2017
DISTRICT
TARGET
2016
ACTUAL
2016
DISTRICT
TARGET
2015
ACTUAL
2015
DISTRICT
TARGET
2014
DISTRICT
ACTUAL
2014
4. Hectares of degraded forest, mining, dry and wet
lands
rehabilitated/restored.
a. Forest b. Mining c. Dry and wetland
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5. Number of tourist arrivals
in the District per annum
40,000 46,000 42,000 45,000 40,360 45,000 51,200 45,000 40,000
6. Teledensity/Penetration rate
--- --- --- --- --- --- --- ---
HUMAN RESOURCE DEVELOPMENT
7. HIV/AIDS prevalence rate (% of adult population 15-
49yrs, HIV positive)
--- --- --- --- --- --- --- --- ---
8. Maternal mortality ratio (number of deaths due to
pregnancy and childbirth
per 100,000 live births)
0 0 0 0 0 0 0 0 0
9. Under-five mortality rate (number of deaths
occurring between birth
and exact age five per
1,000 live births)
0 0 0 0 0 0 0 0 0
10. Malaria case fatality in children under five years
per 10,000 population
0 0 0 0 0 0 0 0 0
ANNUAL PROGRESS REPORT, 2017
Page 43
S/N INDICATORS
(categorized by GSGDA
Thematic Area)
DISTRICT
BASELINE
2013
DISTRICT
TARGET
2017
ACTUAL
2017
DISTRICT
TARGET
2016
ACTUAL
2016
DISTRICT
TARGET
2015
ACTUAL
2015
DISTRICT
TARGET
2014
DISTRICT
ACTUAL
2014
11. Percent of population with access to safe water
sources
61% 72% 71% 68% 70% 68% 64% 58% 61%
12. Percent of population with access to improved
sanitation (flush toilets,
KVIP, Household latrine)
45% 58% 50.5% 55% 48.8% 55% 49.3% 46% 45%
13. a. Gross Enrolment rate
Primary
JHS
SHS
120.0%
118.0
122.5%
118.0
122.5%
118.0%
122.5%
120.0%
120.0%
128.6% 126.4 121.65% 126.4 121.65% 126.4% 129.3% 130% 128.6%
105.7% 103.6% 122% 103.6% 122% 103.6% 93.5% 95% 105.7%
b. Net Admission rate in
primary schools.
70.0% 72.0% 70.5% 72.0% 70.5% 72.0% 72.6% 65% 70.0%
14. Gender parity index (GPI):
KG
Primary
JHS
SHS
0.8
0.85
0.6
1.2
1.0
1.0
1.0
2.3
0.93
1.0
0.9
1.3
1.0
1.0
1.0
2.3
0.93
1.0
0.9
1.3
1.0
1.0
1.0
1.30
26.3
0.9
0.99
0.8
KG
Primary
JHS
SHS
15. Percentage of unemployed
youth benefiting from
Skills/Apprenticeship and
entrepreneurial training
12% 18% 15%
18% 14%
18% 12.8% 12%
16. Total amount of internally
generated revenue (IGF)
-- 436,443.00 481,837.01 444,043.00 417,094.98 382,813.07 426,459.04 343,844.00 371,329.83
ANNUAL PROGRESS REPORT, 2017
Page 44
GOOD GOVERNANCE AND CIVIC RESPONSIBILITY
17. Amount of Development
Partner and NGO funds
contribution to DMTDP
implementation
18. % of DA expenditure
within the DMTDP budget
9% 13% 19.8% 13% 19.8% 13% 17% 12% 9%
19. Number of reported cases of abuse (children, women
and men)
20. Police citizen ratio 1:620 1:600 1:700 1:650 1:720 1:730 1:600 1:750
Source: DPCU M& E, 2017
ANNUAL PROGRESS REPORT, 2017
Page 45
3.8 Critical Development Interventions in the District
The following key intervention programmes and policies are being implemented in the Akwapim South District Assembly.
3.8.1 Update on Critical Development and Poverty Issues in 2017
Table 3.5: Development and Priority Issues
Critical Development and Poverty
Issues
Description 2017
Allocation
GH ¢
2017
Actual
Receipt
No. of Beneficiaries TOTAL
Target Actuals
1. Ghana School Feeding Programme Only one basic school is currently
under the school feeding programme
in the entire district
- - M: F: M: 173 F: 202 375
2. Capitation Grant 87 public basic schools exist in the
district
- 51,301.58 12,000 M: 5922 F:5296 11,218
3. National Health Insurance Scheme - - - - -
4. Livelihood Empowerment Against
Poverty (LEAP) programme
Six (6) LEAP payments since the
inception of programme
179,820.00 140,500.00 900 M: 321 F: 548 869
5. National Youth Employment
programme (GYEEDA)
Four models operate in the district - - - M: 47 F: 23 70
6. One-District-One-Factory programme Not implemented yet --- --- --- --- --- 7. One-village-One Dam programme Not implemented yet --- --- --- --- ---
8. One-Constituency-One Million
Dollars programme
Not implemented yet
9. Planting for Food & Jobs programme i. Provision of 80 bags of maize seeds
ii. 1000 bags of Fertilizer subsidized
iii. 500kg of Pepper seeds supplied
- 80 bags
1000 bags
500kg
M: 129 F: 8
M: 1567 F: 487
M: F:
2,191
10. Free SHS programme Four public senior high schools exist
in the district
3,106,149.36 561,716.23 1,300 - 1,424
11. National Entrepreneurship and
Innovation Plan (NEIP)
--- --- --- --- --- ---
12. Infrastructure for Poverty Eradication
programme (IPEP)
--- --- --- --- --- ---
ANNUAL PROGRESS REPORT, 2017
Page 46
13. Disability Groups catered for from
Disability Fund
Disability Fund Management
Committee provided educational,
medical and commercial services to
persons with disability in the District
2% of DACF
GH
¢12,292.54
M: 172 F: 178
154
16. HIV/AIDS i. Free testing and counselling
ii. Distribution of condoms
0.05% of
DACF
-NIL- M: 140
F: 78
218
Source: DPCU, 2017
ANNUAL PROGRESS REPORT, 2017
Page 47
3.8.2 Disaster
Work started in June 2016 on the falling rocks on the Aburi – Ayi Mensah Highway at the side
of the Accra bound end of the road. That end of the road has since been opened to traffic in
January 2018 even though work has been estimated to be incomplete. Other events are indicated
3.8.3 Agricultural Extension Services
During the year 2017, the District Agriculture’s Department embarked on a lot of activities;
some of which are indicated below.
Table 3.6: Agriculture development activities for year 2017
Activity
Beneficiary
Farmers
Period
Male Female Total
1. Home and farm visits 4,633 1,679 6,312
Year 2017
2. Educated farmers on correct use of agro-
chemicals, pest/disease recognition,
prevention
and control,
1,586 673 2,259
3. Educated farmers on record keeping,
improved
crop variety
1,022 266 1,288
Year Activity/Event Start/Period End/Period Remark
2017
Spillage of dam at
Dumpong
affecting over 200
farmers
N/A N/A Compensation has since been
paid to affected persons
Flooding at
Adamorobe
July 2017 July 2017 No casualty was recorded.
Army worm
infestation
April, 2017 - 51 maize farmers affected.
Rain/windstorm N/A N/A Caused 26 people to be
displaced.
5 schools ripped off and 8
houses
Relief
administration
--- --- No relief items were received
from the regional secretariat
for onward distribution
ANNUAL PROGRESS REPORT, 2017
Page 48
These farmers were engaged in various educational activities organized by the District’s
Department of Agriculture. It is encouraging that female farmers and stakeholders were involved
in the agriculture sector as the District is keen on an all-inclusive accelerated agriculture
modernization.
3.8.4 Environmental Health Activities
The District Environmental Health Department performed the following activities for the year
2017:
Screening of 1,200 food/drink vendors (200 Males and 1000 females)
1, 733 Premises were inspected at Ahwerase, Aburi, Kitase, Konkonnuru, Gyankama and
other major towns in the district
Community health education at Aburi market and Amanfro communities
74 chop bars and 102 drinking spots in the District were inspected during the year under
review
3.9 Health Services Delivery in the District
In 2017, the list of diseases that made the top 10 causes of sickness ailments did not change from
the record of 2016.
3.9.1 OPD Attendance
Table 3.7: Top Causes of OPD Attendance in the District, 2017
NO. CONDITION NO.OF
CASES
Females Males
1 Malaria 14,275 8377 5898
2 Upper Respiration Tract Infection 8440 5006 3434
3 Acute Eye Infection 3603 2530 1,073
4 Rheumatism & Other Joint Pains 2435 1720 715
5 Skin Diseases 2264 1225 1039
6 Anaemia 780 537 243
7 Diarrhoea Diseases 683 366 317
8 Hypertension 535 429 106
9 Diabetes Mellitus 45 39 6
TOTAL 33,060 20,229 12,831
Source: DHMT, 2017
ANNUAL PROGRESS REPORT, 2017
Page 49
Malaria still ranked topmost of the causes of OPD attendance in the year 2017 in the district’s
health facilities. It accounted for 43.2% of all OPD attendance whilst 25.5% was for
Upper/Acute respiratory Tract Infection (U/ARTI). Malaria and U/ARTI accounted for 68.7% of
all OPD cases which means all other diseases recorded 31.3 percent.
The figure below presents the disease prevalence situation in 2017.
Figure 3.4: Topmost Illnesses for OPD attendance for 2017
3.10 Education
The District Assembly is focused on the development of education in all its aspects with
particular attention to educational infrastructure to increase access. As a result, as many as 8
projects in the 2016 annual action plan under education were rolled over to 2017. Due to this
focus on education, enrolment figures have increased as a result.
Table 3.8: District Level Enrolment in Education for 2016/2017, Public schools
Crèche/Nursery Kindergarten Primary JHS
Boys 32 1,229 3,688 1,521
Girls 37 1,246 3,454 1,332
Total 69 2,475 7,142 2,853
Source; EMIS, District Education Office, 2017.
Malaria
43.2%
Acute Resoiratory
Infection
25.5%
All other Diseases
31.3%
TOPMOST ILLNESSES OF OPD ATTENDANCE,2017
ANNUAL PROGRESS REPORT, 2017
Page 50
Table 3.9: District Level Enrolment in Education for 2016/2017, Private schools
Crèche/Nursery Kindergarten Primary JHS
Boys 415 527 1,127 339
Girls 344 523 1,122 335
Total 759 1,050 2,249 674
Source; EMIS, District Education Office, 2017.
It is remarkable that the enrolment figure in the public schools for JHS remains higher than that
of the private JHS for all sexes. In spite of the quality concerns in public JHS, enrolment is still
high against that of private JHS thereby giving credence to the Assembly’s efforts at improving
quality teaching and learning in the public sector.
3.11 Development and Community Planning
The Physical Planning Department of the District Assembly as one of the important units
performs the following functions relating to physical development in the District. Its activities in
2017 are presented in the table below.
Activity Result Remarks
1. Preparation of planning
schemes
Draft scheme prepared for
Kitase
65% of work done
2. Street naming and property
addressing system
Roads, properties tracked
and named
45% of work done
3. Access demarcation --- ---
Source: Physical Planning Department, ASDA, 2017
ANNUAL PROGRESS REPORT, 2017
Page 51
PART FOUR: CHALLENGES AND MITIGATION STRATEGIES
4.1 Challenges and Mitigation Strategies
The Assembly is faced with the following challenges classified in order of priority in the table
below as well as suggested measures to mitigate them.
No. Challenge Priority
Level
Mitigating Strategy
1. Permanent office and residential
accommodation for officers
High The construction of Assembly complex is
at 80% completion level.
2 Low revenue mobilization due to
leakages, inadequate data and
unassessed properties
High Consultant to be engaged to mechanize
collection centres for effective tracking.
Revaluation of all properties to be carried
out in 2018. Plan ready for DPCU to
gather data but no funds to implement
3 Managing a strategic planning
scheme for physical and controlled
development
High Action plan drawn for implementation
4 Lack of vehicles and other
logistics to undertake monitoring
and evaluation, gather data and
effectively coordinate the
activities in the district
High Tendering processes completed to acquire
vehicles but no funds available
5 Inadequate office logistics for staff
to work with
High Procurement unit to take up the matter
ANNUAL PROGRESS REPORT, 2017
Page 52
4.2 Key issues addressed
1. Delay in the release of funds to the Assembly.
As a result of delay in the release of funds, the Assembly could not fulfill its obligation to
some contractors. The DPCU encouraged the contractors to continue to finance the
projects till funds were released from the central government, a situation most of the
contractors could not bear due to financial constraints.
4.3 Key issues yet to be addressed
The following issues were however yet to be addressed;
1. Limited funds for M&E activities as a result of the precarious financial position of the
Assembly.
2. Inadequate logistics for M&E activities.
3. Inadequate funds to execute most of the projects in the Annual Action Plan.
4. Unavailability of data from the departments to report on.
4.4 Update on Evaluations Conducted
The District Planning Coordinating Unit could not conduct an in-depth evaluation of its projects
due to lack of logistics and resources. Monitoring was however done on all projects and
programmes that enable the unit to prepare the 2017 Annual progress report. An evaluation
would be done when funds were made available so as to incorporate same in the subsequent
quarterly progress reports.
4.5 The way forward /Recommendations
1. To consider as a matter of urgency the construction of office and residential
accommodation facilities for officers.
2. To improve revenue mobilization; this will broaden the financial capacity of the
Assembly to be able to complete all ongoing projects.
3. Focusing on prioritized projects for completion in the year to avoid roll over projects.
4. Office equipment and logistics such as furniture, printing accessories and others to be
provided to enhance productivity.
ANNUAL PROGRESS REPORT, 2017
Page 53
4.6 Conclusion
The Akwapim South District Assembly as the development and planning authority has to a
greater extent performed creditably in the provision of social services and infrastructural
development especially in the areas of education, sanitation, peace and security. In addition, it
did well regarding accountability, transparency and social justice to all and sundry in every nook
and crony of the District during the period under consideration.
It is in the light of this that in 2017, the Ghana Strengthening Accountability Mechanism
(GSAM) programme funded from USAID and in partnership with IBIS, ISODEC, and
Care Ghana scored the District 98% in the performance of key indices in capital projects
implementation.
From the above, there is clear indication that the District Assembly remains very much
committed to providing quality development to its people and expanding citizens’ participation.
Notwithstanding its achievements, the Assembly faces a myriad of problems as outlined above
including revenue mobilization, office accommodation, logistics and other capacity gaps to
enhance the effectiveness regarding the discharge of its responsibilities to the people OF
Akwapim South.