Date post: | 26-Dec-2015 |
Category: |
Documents |
Upload: | eleanor-armstrong |
View: | 219 times |
Download: | 3 times |
King Fahad Cardio. Surgery & Disease
center Project
Group.1 Prepared By
Supervisor: Prof.Naif bin Humaid mahmoud Abdullrhman Bin
Mohammed ALMannaa Abdullah ALQhtani
Yazed ALarafj Emad Shieraz
Faisal ALolyani Meshari ALOabied
Project Introduction The work comprises of detailed shop drawing design
of civil, structural, building works, electrical, plumbing and mechanical installation work, site work and all other works for the construction, completion of the King Fahad Cardio- Surgery and Disease Center Building. This is a seven (7) storey building a total floor area of 70.000 m2, one (1) of which is basement.
The project duration is 720 calendar days from the site handover date confirmed with a signed acceptance by ABV Rock Group Ltd., Project Manager.
Project HighlightsClient : King Saud University, Ministry for Higher
EducationDesign Consultant : Zuhair Fayez PartnershipShop Drawing : ABV Rock Group
LimitedContractor : ABV Rock Group LimitedContract Type : Lump sum contractProject Area : 70.000 M2 [Building/Floor
Area]Project Start Date : 27th December 2009Project Finish Date: 29 April 2012 (After Receiving an
Extension Time)
Progress Achievements :Partial Site hand over from 27th December
acceptedExcavation in hand-over area of the building
mostly completedStructural work with foundation started, into
the fifth floor.Masonry works started in basement, ground
and 1st floor
Project Progress Overview
DIV DETALLS REMARKS
1 General Requirements
Soil Investigation
- Soil Testing/Boreholes
- Cavity Probing
- Cavity Injection
Done
Done
Not required
2 Site Work & General Excavation Started and on-going in handed over area
3 Cast-In-Place Concrete Work on-going up to roof floor
4 Masonry Startedin basement, Ground floor and 1st floor
5 Metal Works
6 Wood & Plastic
7 Thermal & Moisture Protection Work on-going
8 Doors & Windows
9 Finishes
10 Specialties
14 Conveying System
15 Mechanical Works – sub- Structure Drainage system work in progress
Plumbing and fire protection started up to 2nd floor
16 Electrical Works Grounding work under progress
Electrical first fix started up to 5th floor
Abdullah ALQhtani description quantity unit cost total cost اليتجاوز لعمق بالموقع متر 7حفر
حفر الطبيعية االرض منسوب من 105300m3 35 3685500 excavate over site to form basement notللبدرومexceeding 7m deep الموقع خارج quantity daily prod of crew crew make up man hours total 1170000 13 90000نقل
man hours total crew hours avg wage rate 105300 100 1forman - labor3 per unit 11232 3744 12.5 0.106 labor subtotal rate per hour equip subtotal total cost 140400 6×700÷8=525 1965600
- 1بوكلين__3 20 2106000 7200h 7200(88+75)=1173600$=12.5÷90000قالبي truck 2شويل 1173600÷90000=13 13 100m3/day÷8h/day=12.5m3/h اليتجاوز بعمق واالساسات الربط كمرات لزوم خنادق 1حفر
االرض مكنسوب من excavate trenches for tie beams and bases not 3800 50 3م76مترexceeding1 m deep اليتجاوز لعمق االعمدة قواعد الطبيعية 1حفر االرض منسوب من 15400 50 3م308متر
excavate pits for column pads not exceeding 1m deep commencing at existing ground level الموقع خارج من او الحفر نواتج مواد من اختيارها تم معتمدة حبيبية بمواد فحص m3 108072$/12 3م9006ردم تقرير توصيات حسب
القسم المواصفات حسب اعمال من ذلك وماشابه الدك اعمال متضمنة المناسيب لتعويض وذلك الموقع 02200تربةapproved granular fill selected from excavated material according or imported fill material to site soil report recommendation and subject to engineers approval in making up levels including compaction and the like as per specifications section 02200 quantity daily prod of crew crew make up man hours total man hours total crew hours avg wage rate 9006 600m3/day 2 per unit 234.156 117 12.5 0.026 labor subtotal
rate per hour equip subtotal material total cost material total cost $/m3 2927 350 40950 5 $/m3 45030 88907 تريال 10$ =6 ×3م20سعة يوم / =8يوم/ ÷ 3م120رحلة يوم/ ÷3م600ساعة/ 3م15س لشويل/ للقالبي/ =3م120يوم تريال 5يوم
س/ +150تريال×5س)120ساعة 120يوم=15تريال=5÷120÷3م9006 $125=) /$ س $105000 م/ 12=$9006÷105000 و $3 االساسات فوق جيدة بصورة ومدكوكة الموقع خارج من موردة انشائية ردم مواد
من m3 633395$/35 3م18097 طبقة المطلوبة الكثافة الى الوصول حتى الدك ذاك شامال المناسيب إلى للوصول القواعدبسمك المدموك الخشن االوض 100الحصى سطح على البالطات تحت m3 640 100mmthick drainage layer$/8 3م80مم
to underside of slab on grade as per specifications section 02200 وعلى البالطات االبيضتحت النمل ضد التربة معالجةالمبنى محيط m3 128480 to formation subgrade of slabs and beds including periphery of$/8 2م16060طول
building الموقع ظروف حسب بالصخر الفراغات ومأل m3 500000 allow for cavity filling as$/1000 3م500حصرrequired total cost 6245287$
sample calculationFOR CONCRETE
quantity HEIGHT WIDTH LENGTH quantity DESCRIPTOIN
2946 0.5 49.1 60 26" SLAB
By Emad & Faisa;
مقدمة : , و V متأخرا السعودية العربية المملكة في التأمين وصل
تزال , ال اآلن وحتى الهندسي الجانب في V خصوصاالضخمة , المشاريع في محدودة التأمين استخدامات
التأمين أنواع على ج نعر[ الجزئية هذه في ولعلناالمثال , – سبيل على ونأخذ بالمملكة الموجودة
للتأمين التعاونية بالسوق – الشركة قدمها بحكمالتأمين شركات سوق على تربعها على Vعالوة السعودي
.
الهندسي : الـتأمين أنواع
" " : األخطار جميع ضد المقاولين تأمين أوًال' : المقاولين وآليات تجهيزات تأمين ثانيا' : اآلًالت عطب تأمين ثالثا' : عنعطب الناتجة األرباح خسائر تأمين رابعا'
اآلًالت : الضغط وأوعية المراجل تأمين خامسا' : األلكترونية األجهزة تأمين سادسا'
التالية : البيانات يحضر أن التأمين طالب يطلبمن , , , المقاولين العنوان الموقع رقمه و المشروع اسم
االستشاريين , المهندسين الباطن و الرئيسين , , : طرق األساسات نوع المساحة المشروع أعمال وصف
التشييد , مواد التشييد
بعض بعد على يجيب أن منه يطلب ذلكمنفذ و بالمشروع المتعلقة األسئلة
المشروع : ؟ خبرة سابق المقاول هل التأمين مدة , , , : العواصف الفيضان الحرائق في الخطوة مدى
الزالزل , , البراكين التفجير ؟ السالمة مستوى مدى ما التحتية التربة تفاصيل الجوفية المياه األمطار مواسم بالمشروع المحيطة الممتلكات تأثر مدى
على : النوع هذا في التأمين يشمل : المادية األضرار : , توريدها تم التي المواد منها المؤقتة و الدائمة األعمال
العمل صاحب قبل من التشييد معدات و تجهيزات االنشاءات في المستخدمة االليات المخلفات إزالة العمل بموقع الكائنة الممتلكات