www.regoconsulting.com Phone: 1-888-813-0444 Enhancing Customization and Automation Preparing Metrics that Matter
Transcript
Page 1: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

Enhancing Customization and Automation

Preparing Metrics that Matter

Page 2: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

2

● Functional Best Practices● Case Study – Emerging Health● Case Study – HSBC● Open Discussion● Technical Best Practices

Agenda

Page 3: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

3

Why do we utilize metrics?

● Align behaviors with organizational strategy

● What gets measured gets done

● Enables self-service performance management

● Benchmarking – Internal and External

● Manage based on data not gut feel

Page 4: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

4

• SMART• Specific• Meaningful• Aligned• Realistic goals • Time based

What makes a good Metric?

Page 5: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

5

• Balanced – Do not want to drive the wrong behavior• Drill Down – Need to be able to answer why• Automated – consistency, availability, accuracy• Incentives – rewards drive behavior• Positive Focus – Highlight good behavior not bad• Assign Ownership – Monitor, report improve• Leading vs Lagging – measure things that can be

changed

What makes a good Metric?

Page 6: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

6

How to Create KPIs?

1. Understand strategic goals of your organization2. Determine the Key Success Factors in reaching the goals3. Define Key Performance Indicators that measure the success

factors4. Determine the Success Factors for these metrics5. Define Performance Indicators that measure the success

factors6. Make KPIs, PIs and data available7. Communicate to all levels

Page 7: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

7

What Metrics Do You Use Today?● Scope

○ # changes / project duration in days (bad req. or bad PM)○ Customer satisfaction (survey 1-10)

● Schedule○ % of open tasks with finish date < one week ago (stale)○ % projects on-time○ % of tasks completed on time○ % of tasks completed within baseline duration○ % of tasks completed within baseline hours○ % Milestones on time○ Actual/Estimate - % to estimate ○ Average task duration or effort (good plans)○ % tasks assigned 3 months out (how well advanced

planning)○ # of baselines○ Milestone Burndown○ Cross Project Dependency Slack

● Budget○ % projects on-budget○ % complete vs. % money expended○ Actual / budgeted ROI○ Total support costs for x months after solution is

completed ○ Amount of project manager time vs. overall effort hours – % change in NPV/IRR from gate to gate – Benefits realized vs. benefits planned– % projects with current financial forecasts

• Overall Project– Subjective R/Y/G on projects by the PM (PMs thoughts)– Duration between steps, phases, stages, etc (diagnose

where issue. This will not solve issues)– # issues / project duration in days– How long issues remain open– % projects with current status reports– Number of defects discovered after initial acceptance /

development hours– Counts and amounts for projects in Red/Amber/Green

status– # issues by severity: opened, closed, on-hold– % projects failed gate review– % projects that delayed gate review

• Time (Not Project Related)– Time not submitted on time– Ave hours worked by staff– % internal vs. external resources– Time to assign WR (response time)– Time by % Admin, Projects, Maintenance (Doing the right

things)• Resource Management

– % of resources with “appropriate” allocations 6-9 months in the future

– % of resources with “appropriate” assignments 0-3 months in the future

– Forecasted Utilization % by project manager for next 0-3 months

– Actual Utilization % by project manager for last 3 months– Workloads by resources or manager - # projects they

support

Page 8: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

8

KPI Project Dashboard

Page 9: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

9

What will be Covered

• PM Dashboard portlet, Sub-Page & Drill Down

• Key Performance Indicators

• Governance

Page 10: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

10

Overview & Importance

• PM Dashboard– Provides PMs and Management with important

information related to project staffing, schedule and level of effort.

– Information drives Executive decisions related to project portfolios.

– Can be used by the PM as a project maintenance check list.

– Makes it easier for PMs to identify and correct project schedule and staffing issues.

– Accessible to all users

Page 11: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

11

Accessing PM Dashboard sub-page

Click the PM Dashboard sub-page link on the project properties page.

The sub-page will show all indicators related to the project.

Accessing from within a project

Page 12: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

12

Project Dashboard DetailProvides detailed information related to Red and Yellow Indicators. To launch the Detail information click on a Red or Yellow icon

Use:

The detail page for ETCs Past is the Project Team portlet. All others indicators link to the Project Dashboard Popup Page as shown to the right

Page 13: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

13

Portlet Defaults

• The portlet returns all active projects

• Indicator Update Frequency

Hourly Updates Daily Updates at 4:00 am Zero ETCETCs Past Milestone ScheduleNext Go Live Dt PastComment Dt Past

Resource BudgetUnfilled Roles within 30 daysAllocation Dt Past

Page 14: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

14

KPI Indicator Colors

A Green icon means the indicator is within the acceptable range and no action is required at this time.

A Gray icon means the indicator does not apply to the project in its current state.

A Yellow icon means there is a component of the project that needs attention.

A Red icon means there is a component of the project that needs immediate attention.

Page 15: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

15

Key Components of Governance

• Establish a governance structure with a Project Committee including appropriate subgroups

• Define your processes – e.g. start identifying what projects align with your strategic goals

• Ensure priorities are set by Senior Management and Executives

• Communicate priorities and progress on a regular basis

• Monitor Resource, Budget and Schedule regularly

• Implement effective Governance reporting based on the processes

Page 16: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

16

HSBC

Page 17: Preparing Metrics that  Matter

HSBC TECHNOLOGY AND SERVICES

}

Restricted for company use only

HSBC background

Clarity/Niku customer since 2005 Rego Consultant services provided since

2010 One partition

– 3 Main Department Functions – Global system

Integrated with HR and Finance systems Yearly Financial planning process

– Project setup– Billable Product tie back

Actuals = financial transactions (chargebacks to customers)

3 Main departments

37,200 active resources– 31,000+ OTE– 27,500+ Billable

39,500 + active projects– 27,000+ Billable

INTERNAL

Page 18: Preparing Metrics that  Matter

HSBC TECHNOLOGY AND SERVICES

}

Restricted for company use only

Overview Resource/Project Details

Gaining value from Clarity depends on effective use of the tool and increasing end-user adoption. Project and Resource management metrics are required to baseline and track adoption as part of monitoring and improving the value of the data on Clarity

Clarity Maturity Model (CMM) was implemented in 2008 in response to an audit requirement to track Clarity usage and data

Clarity SWAT are looking to materially improved the existing CMM model to eliminate “box ticking” and implement metrics that will drive sound resource and project management behavior

INTERNAL18

Page 19: Preparing Metrics that  Matter

HSBC TECHNOLOGY AND SERVICES

}

Restricted for company use only

Key Roles

LQSOs – Local Quality Service Organization; audit regional/departmental project and resource data

Clarity PPMT (Project and Portfolio Management Tooling) – Enhancement, defect and maintenance. Make CMM available and enhance/create new Metrics/KPIs

PMOs, Deployment Leads, Middle and upper Management; Direction and Take action on deployments

INTERNAL19

Page 20: Preparing Metrics that  Matter

20INTERNAL

CMM – Clarity Maturity model

Clarity/Niku customer since 2005

Rego Consultant services provided since 2010

37,200 active resources– 31,000+ OTE– 27,500+ Billable

39,500 + active projects– CTB 28,000+ RTB 11,500+– 27,000+ Billable

Integrated with HR and Finance systems

Yearly Financial planning process– Project setup– Billable Product tie back

Actuals = financial transactions (chargebacks to customers)

Page 21: Preparing Metrics that  Matter

21INTERNAL

CMM – Clarity Maturity model

Clarity/Niku customer since 2005

Rego Consultant services provided since 2010

37,200 active resources– 31,000+ OTE– 27,500+ Billable

39,500 + active projects– CTB 28,000+ RTB 11,500+– 27,000+ Billable

Integrated with HR and Finance systems

Yearly Financial planning process– Project setup– Billable Product tie back

Actuals = financial transactions (chargebacks to customers)

Page 22: Preparing Metrics that  Matter

22 INTERNAL

Page 23: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

23

Discussion Questions

For your organization:● What are your process pain points?● What behaviors are you trying to drive?● What are your reporting challenges?

Page 24: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

24

1. Process improvement

Identified

2. Requirements for a Metric

3. Technical Development

And Implementation

4. Reporting

5. Analyze the Trends

OR Other Impacts

Metrics Development Cycle

Strategic Goals

Happy Customer

Page 25: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

25

Check what is already available● OOB Metrics

○ Earned Value (CPI, SPI)

● RegoXchange○ Search for keyword “Dashboard” on the RegoXchange website

○ Rego Adoption Metrics (coming soon!)

Technical Best Practices

Page 26: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

26

Portlet Name Description

Dashboard: Baseline Comparison Compares multiple baselines on a project

Dashboard: Change Requests Provides an overview of all change requests on the project

Dashboard: Financial Summary by Charge CodeDisplays summary financial information by charge code on the project dashboard

Dashboard: Open Issues Provides an overview of all issues on the project.

Dashboard: Open Milestones Provides an overview of all milestones on the project.

Dashboard: Open Risks Provides an overview of all risks on the project.

Dashboard: Phase Gantt Provides an overview of highest-level tasks on the project.

Dashboard: Programs PortfoliosThis portlet displays all programs and portfolios a project is a subproject of

Dashboard: Project Information Provides an overview of the project.

Dashboard: Project Status Indicators Multi-lineProvides an overview of the project status on multiple lines.

Dashboard: Project Status Indicators Single-lineProvides an overview of the project status on a single line.

Executive DashboardA one-stop place for the PMO or management to view all critical information about projects.

Incident Dashboard Displays an overview of incident and related task information

Program Executive Dashboard Displays project information for projects within a program

Project Manager Dashboard Provides an overview of all projects.

RegoXchange Content

Page 27: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

27

Rego Adoption Metrics• We will have a set of metrics defined for projects, and a set of

defined for resources.

• Each metric will have a set criteria for levels 0-5 maturity, so that for each metric that item (i.e. project) will be given a maturity level from 0-5.

• Project Metrics will apply only to active projects

• Resource Metrics will only apply only to active users (exclude locked resources)

Page 28: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

28

Rego Adoption MetricsMetric Focus Metric Description

Project Project Allocation Adoption Metric

This adoption metric indicates if the project manager is keeping the project staff allocations in line with the effort that is being booked to the project through time entry. This metric looks at the prior three months and determines how close the allocations match the actuals. The closer the match, the higher the score.

Resource Resource Allocation Adoption Metric

This adoption metric indicates if the Resource Manager is keeping their staff’s allocations current. The metric scores increase as the allocations of the full resource capacity are within a reasonable range for longer future periods of time. Highest scoring goes to resources that have allocations close to 100% for the next 120 days.

Resource Resource Data Quality Metric

This adoption metric indicates if the Resource Manager is keeping specific fields in their resource’s data populated and demonstrates active management of the resource attributes by the Resource Manager role

Resource Resource Timesheet Entry Metric

This adoption metric indicates if the Time-entry Resource is entering their time on a timely basis. The metric looks back 4 weeks and determines how many timesheets were entered and how many are missing. The Highest scoring goes to timesheets submitted on time and with total hours greater than 10.

Resource Resource Commitment Metric

This adoption metric compares the resource Soft Booked and Hard Booked allocations within a 4 week view. Hard Booked allocation hours receive a higher range score while Soft Booked allocations are a lower score.

Project Project Baseline Adoption Metric

This adoption metric indicates the level of adoption in using baselines. The metric indicates if any baseline exists against the project. Scoring the metric on a project is either a zero (no baseline) or a 5 (has a baseline).

Project Project Status Reporting Adoption Metric

This adoption metric indicates if the project manager is creating and publishing a project status on a bi-weekly basis. The metric looks back over a 6 week period and increases the score based on increasing numbers of published status reports.

Project Project Risk Management Adoption Metric

This adoption metric indicates if the project manager is managing risks against the project within CA Clarity. The score indicates whether the risks are being used at all and increases the score value based on the completeness of the Risk data and for the higher scores the active management of risk resolutions.

Project Project Scheduling Adoption Metric

This adoption metric indicates if the project manager is managing more than summary time entry tasks within CA Clarity. Scores increased based on having 3 tasks or more and having the tasks closed when they were scheduled to be complete. Highest scores on the metric require active management of 10 or more tasks.

Page 29: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

29

Rego Adoption Metrics

Page 30: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

30

Rego Adoption Metrics

Page 31: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

31

● If the metrics you are looking for do not exist – ○ Make sure the requirements for the Metric are well defined○ Architect the Metrics with keeping potential

OBS/Department/Resources changes in perspective (e.g. Re-Org)○ Capture positive metrics

● Development approach○ Automate data collection overnight. Real time metrics may be overkill.○ Collect Data within Clarity○ Capture Actuals as well as Baseline (or Budget) value for comparison○ Capture the values at different levels of organization

(OBS/Departments/Roles)

Technical Best Practices

Page 32: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

32

● Reporting ○ Should be in visual format (Clarity Dashboards /Webi/Crystal or

Xcelsius Dashboards, not data extracts). ○ Dashboards should tell a story and highlight issues. Use 5 minute rule.○ Show Trends○ Drill down capability to show the details

Technical Best Practices

Page 33: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

33

CIO / Senior Executive View

Page 34: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

34

You know you have a metric malfunction if you hear:

● I didn’t know this was being measured.● We measure this because the boss says so.● I have no idea how I can affect this measure.● I have no idea what this number means.● I do not worry about that metric I measure my own.

Metrics Malfunctions

Page 35: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

35

Summary

● People-Process-Technology● Alignment Goals-KPIs-Pis-Data● Automate metric collection● Crawl-Walk-Run

Page 36: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

36

Metric ExamplesMetric Focus Metric Description

Project Project Allocation Adoption Metric

This adoption metric indicates if the project manager is keeping the project staff allocations in line with the effort that is being booked to the project through time entry. This metric looks at the prior three months and determines how close the allocations match the actuals. The closer the match, the higher the score.

Resource Resource Allocation Adoption Metric

This adoption metric indicates if the Resource Manager is keeping their staff’s allocations current. The metric scores increase as the allocations of the full resource capacity are within a reasonable range for longer future periods of time. Highest scoring goes to resources that have allocations close to 100% for the next 120 days.

Resource Resource Data Quality Metric

This adoption metric indicates if the Resource Manager is keeping specific fields in their resource’s data populated and demonstrates active management of the resource attributes by the Resource Manager role

Resource Resource Timesheet Entry Metric

This adoption metric indicates if the Time-entry Resource is entering their time on a timely basis. The metric looks back 4 weeks and determines how many timesheets were entered and how many are missing. The Highest scoring goes to timesheets submitted on time and with total hours greater than 10.

Resource Resource Commitment Metric This adoption metric compares the resource Soft Booked and Hard Booked allocations within a 4 week view. Hard Booked allocation hours receive a higher range score while Soft Booked allocations are a lower score.

Project Project Baseline Adoption Metric

This adoption metric indicates the level of adoption in using baselines. The metric indicates if any baseline exists against the project. Scoring the metric on a project is either a zero (no baseline) or a 5 (has a baseline).

Project Project Status Reporting Adoption Metric

This adoption metric indicates if the project manager is creating and publishing a project status on a bi-weekly basis. The metric looks back over a 6 week period and increases the score based on increasing numbers of published status reports.

Project Project Risk Management Adoption Metric

This adoption metric indicates if the project manager is managing risks against the project within CA Clarity. The score indicates whether the risks are being used at all and increases the score value based on the completeness of the Risk data and for the higher scores the active management of risk resolutions.

Project Project Scheduling Adoption Metric

This adoption metric indicates if the project manager is managing more than summary time entry tasks within CA Clarity. Scores increased based on having 3 tasks or more and having the tasks closed when they were scheduled to be complete. Highest scores on the metric require active management of 10 or more tasks.

Page 37: Preparing Metrics that  Matter

www.regoconsulting.com Phone: 1-888-813-0444

37

Questions

Contact US888.813.0444

Email [email protected]@[email protected]@regoconsulting.com

Web Sitewww.regoconsulting.com

"What gets measured gets done, what gets measured and fed back gets done well, what gets rewarded gets repeated.“

John E. Jones

Thank you.