PRESENTATION ON ROAD DEVELOPMENT PROGRAMME IN NORTH EASTERN REGION
State wise National Highways and length
State Total length of
NHs (km)
Length under
SARDP-NE (km)
Balance length (km)
Remarks
Arunachal Pradesh
1987 1388 599 Out of 599km, 232km is under China Study group and 367km under NH(O).
Assam 3068 1305 1763 Out of 1763km, 670km is under NHDP-II as part of East West Corridor and 1093 km under NH(O).
Manipur 1317 39 1278
Meghalaya 1171 376 795 Out of 795km, 104km is under NHDP-III and 691km under NH(O).
Mizoram 1027 221 806
Nagaland 494 81 413
Sikkim 149 149 0
Tripura 400 130 270
TOTAL 9613 3689 5924
Comparison with National Average
TOTAL NH LENGTH - 82621 KM IN NE STATES - 9613 KM (11.63%)
ALL INDIA NE REGIONLength (km) / 1000 sq km 25.14
27.99 Length (km) /
lakh population 6.84 8.20
Major Road Development Programme in NE Region
NHDP-II (East-West Corridor)NHDP-IIISpecial Accelerated Road Development
Programme in North East (SARDP-NE)Phase ‘A’Arunachal Pradesh Package of Roads and Highways
Phase ‘B’ (approved for DPR preparation only)
EAST WEST CORRIDOR PROJECTS IN ASSAM
Total length in Assam = 670 kmStarts from Silchar (km 306.25 of NH-54) and ends at Assam/West Bengal Border (km 0 of NH-31C) Srirampur
Passes through Silchar, Maibong, Lumding, Daboka, Nagaon, Sonapur, Guwahati, Nalbari and Bijni
Four laning completed = 18 km (Guwahati Bypass)To be awarded after completion of 2 laning by State PWD (progress 70%) = 31 km
Under Implementation = 621 km (26 Packages)
Length completed = 474 km
Target Date of Completion = December 2014.
ContinuedThe stretch of 31 km from Balachera to Herangajo
is being widened from single lane to two lanes by the State PWD. Clearance for Borail Wild Life and Borail Reserve forest is awaited. Four laning would be done after completion of two lane by PWD, Assam.
Most of the contracts were awarded in November/December 2005.
All the contractors had mobilized to site and works are in progress except in 5 contract packages in NC Hills district where the work has been stopped by the previous contractors since April’2008 due to non-handing over of encumbrance free site and law & order situation. All the five civil packages of NC Hills district had been foreclosed and re-awarded.
Status of NHDP (III) Projects in Meghalaya
State NH Stretch Length (km)
Cost for 2-laning (Rs. crore)
Remarks
Meghalaya 44 Jowai-Meghalaya/
Assam Border
(Ratachhera)
102 390.7 Work awarded on 20th March, 2012 to M/s Simplex Infrastructure Pvt. Ltd., Kolkatta and concession agreement signed on 05.06.2012.
TotalTotal 102102 390.7390.7
Objectives of SARDP-NEUpgrade National Highways to 2/ 4 lane;To provide connectivity of all 88 District
Headquarter by 2-lane road;connectivity to backward and remote areas of
NE region;Improve roads of strategic importance;Improve connectivity to neighboring countries
SPECIAL ACCELERATED ROAD DEVELOPMENT PROGRAMME IN
NORTH EAST (SARDP-NE)
Phase ‘A’ (Approved for execution)
- 3213 km (Rs 12821 cr)
Phase ‘A’ (Approved ‘In-Principle’)
- 886 km ( Rs 8948 cr)
Total Phase ‘A’ - 4099 km (Rs 21769 cr)
Arunachal Pradesh Package
- 2319 km (Rs 11919 cr)
Total Phase ‘A’ & Arunachal Package
- 6418 km (Rs 33688cr)
Phase ‘B’ (Approved for DPR only) - 3723 km (Rs. 64 crore)
Total of SARDP-NE - 10141 km (Rs. 33752 cr)(NH 4798km (47%), SR (343km(53%))
10
Length in km
STATE
SARDP-NE Phase 'A'
Arunachal Pradesh Package of Roads and
Highways SARDP-NE Phase 'B' Grand Total
NHs SR/GS Total NHSR/GS/ Strtg
Total NHSR/GS/ Strtg
Total NHSR/GS/
StrtgTotal
Arunachal Pradesh
52 212 264 1346 835 2181 0 931 931 1398 1978 3376
Assam 1179 177 1356 126 12 138 0 285 285 1305 474 1779
Manipur 39 166 205 0 0 0 0 202 202 39 368 407
Meghalaya 259 526 785 0 0 0 161 201 362 420 727 1147
Mizoram 221 100 321 0 0 0 416 272 688 637 372 1009
Nagaland 81 350 431 0 0 0 622 169 791 703 519 1222
Sikkim 80 505 585 0 0 0 0 68 68 80 573 653
Tripura 130 22 152 0 0 0 86 310 396 216 332 548
Total 2041 2058 4099 1472 847 2319 1285 2438 3723 4798 5343 10141
State-wise road length distribution under SARDP-NE
SR: State Road; GS: General Staff roads & Strtg: Strategic roads
Item
Phase ‘A’ Arunachal Package
Item rateIn
principle incl. BOT
Total Item rateHybrid BOT
(Annuity)
Total
Total Length (Estimate cost)
3213 km (Rs 12821 cr)
886 km * (Rs 8948
cr)
4099 km (Rs 21769
cr)
1543km (Rs 6808
cr)
776 km ** (Rs 5111
cr)
2319 km (Rs 11919
cr)
Works sanctioned/ awarded
2366 Km (Rs 9812 cr)
132 Km (Rs 1026cr)
2498 Km (Rs 10838
cr)
566 km (Rs 2732 cr)
775 km (Rs
5111 cr)
1341 km (Rs
7877 cr)
3839 km (Rs 18715 cr)
Roads completed
995 km 69 km 1064 km 88 km Nil 88 km
Target for completion
March, 2015 for ongoing works June, 2016
*Out of 886 km NHAI is implementing 454 km on BOT (Annuity) and MoRT&H /BRO/PWD is implementing 432 km ** 776 km , MoRTH is implementing on Hybrid BOT (Annuity)
Performance of SARDP-NEYear Sanctions/ Award Length
completed (km)
Financial (Rs. Crore)
Length (km) Cost (Rs in crore)
Allocation Expenditure
2006-07 501 1321 Preliminary 550 450
2007-08 240 615 150 700 652
2008-09 187 857 290 1000 637
2009-10 188 1079 156 1200 676
2010-11 1615 9439 146 1500 1065
2011-12 983 4752 150 1950 1940
2012-13 69 334 260 2000 1844
2013-14 55.58 317.86 3300 337
Total 3838.58 18715 1152 8745 7601
(i) Programme Phase ‘A’ of SARDP-NE
Arunachal Pradesh Package for Roads and Highways of
SARDP-NE(ii) Length included (NH*/SR**/GS***) 264 2181(iii) Length Sanctioned 198 1229(iv) Balance length for DPR preparation 66 845(v) Length Completed 43 62(vi) Length under implementation 155 1167(vii) No. of packages under implementation by (a) State PWD 3 11 (b) BRO 8 13 (c) NHAI 0 0 (d) MoRT&H 0 3
State : ARUNACHAL PRADESH
* NH – National Highways** SR – State Roads** * GS – General Staff Roads
State-wise Status of SARDP-NE
(i) Programme Phase ‘A’ of SARDP-NE
Arunachal Pradesh Package for Roads and Highways of SARDP-
NE
(ii) Length included (NH*/SR**) 1356 138(iii) Length Sanctioned 885 112(iv) Balance length for DPR preparation 471 0(v) Length Completed 611 7(vi) Length under implementation 274 105(vii) No. of packages under implementation by
(a) State PWD 22 2(a) BRO 8 1(a) NHAI 0 0(a) MoRT&H 0 1
State-wise Status of SARDP-NE (contd/…….)
* NH – National Highways** SR – State Roads
State : ASSAM
(i) Programme Phase ‘A’ of SARDP-NE
(ii) Length included (NH*/SR**) 213
(iii) Length Sanctioned 150
(iv) Balance length for DPR preparation 63
(v) Length Completed 130
(vi) Length under implementation 20
(vii) No. of packages under implementation by
(a) State PWD 0
(b) BRO 9
(c) NHAI 0
(d) MoRT&H 0
State : MANIPUR
* NH – National Highways** SR – State Roads
State-wise Status of SARDP-NE (contd/…….)
(i) Programme Phase ‘A’ of SARDP-NE
(ii) Length included (NH*/SR**) 785
(iii) Length Sanctioned 376
(iv) Balance length for DPR preparation 409
(v) Length Completed 159
(vi) Length under implementation 217
(vii) No. of packages under implementation by
(a) State PWD 1
(b) BRO 0
(c) NHAI 2
(d) MoRT&H 0
State : MEGHALAYA
* NH – National Highways** SR – State Roads
State-wise Status of SARDP-NE (contd/…….)
(i) Programme Phase ‘A’ of SARDP-NE
(ii) Length included (NH*/SR**) 321
(iii) Length Sanctioned 295
(iv) Balance length for DPR preparation 0
(v) Length Completed 65
(vi) Length under implementation 230
(vii) No. of packages under implementation by
(a) State PWD 8
(b) BRO 0
(c) NHAI 0
(d) MoRT&H 0
State : MIZORAM
* NH – National Highways** SR – State Roads
State-wise Status of SARDP-NE (contd/…….)
(i) Programme Phase ‘A’ of SARDP-NE
(ii) Length included (NH*/SR**) 423
(iii) Length Sanctioned 329
(iv) Balance length for DPR preparation 0
(v) Length Completed 0
(vi) Length under implementation 329
(vii) No. of packages under implementation by (a) State PWD 1
(b) BRO 0
(c) NHAI 0
(d) MoRT&H 0
State : NAGALAND
* NH – National Highways** SR – State Roads
State-wise Status of SARDP-NE (contd/…….)
(i) Programme Phase ‘A’ of SARDP-NE
(ii) Length included (NH*/SR**/GS***) 585
(iii) Length Sanctioned 238
(iv) Balance length for DPR preparation 347
(v) Length Completed 75
(vi) Length under implementation 163
(vii) No. of packages under implementation by
(a) State PWD 5
(b) BRO 13
(c) NHAI 0
(d) MoRT&H 0
State : SIKKIM
* NH – National Highways** SR – State Roads** * GS – General Staff Roads
State-wise Status of SARDP-NE (contd/…….)
(i) Programme Phase ‘A’ of SARDP-NE
(ii) Length included (NH*/SR**) 152(iii) Length Sanctioned 25(iv) Balance length for DPR preparation 127(v) Length Completed 0(vi) Length under implementation 25(vii) No. of packages under implementation by (a) State PWD 0 (b) BRO 1 (c) NHAI 0 (d) MoRT&H 0
State : TRIPURA
* NH – National Highways** SR – State Roads
State-wise Status of SARDP-NE (contd/…….)
Reasons and Mitigation measures for slow progress
Reasons for slow progress Mitigation measures for slow progress
Departmental Execution by BRO Delay in Environmental /Forest Clearance Hilly area and High rain fall regionNon availability of Construction material Extended monsoon period (8-9 months) Lack of technical know how with PWD Tough terrain Dearth of local good contractors and consultants
BRO to switch over to EPC Mode
PWD and BRO to pursue matter vigorously with concerned department
Need to develop innovative technology for alternative material.
Ministry is providing Training at Indian Academy of Highway Engineers to the Officers of State PWD.
Thereis need to develop local contracting industry by imparting proper training.
EPC Mode for effective implementation
Switching over to EPC Mode instead of conventional item rate contract
MORTH has decided that all works by PWD and BRO will be implemented under EPC mode.
The contractor would be responsible for the design and construction for a fixed tender amount.
90% of Land acquisition, shifting of utilities and statutory clearances like environment clearance, forest clearances etc. have to be completed at the time of award of the work.
This will avoid time and cost overrun as witnessed in the case of item rate contract.
Monitoring mechanismOne Chief Engineer has been posted at
Kolkata to look after the works of Tripura, Manipur and Mizoram
In addition to this Regional Officers, at Itanagar and Guwahati, who are officer of the rank of Superintending Engineer, Ministry of Road Transport& Highways are already in existence for monitoring of all works sanctioned by the Ministry.
In addition to the above, regular review of the programme is being done at various level in the Ministry from time to time to identify and sort out the bottlenecks in implementing the programme with PWD’s and BRO.
Major Road Development Programs in North East Region
LEGEND :-1. Arunachal Package2. SARDP NE, Phase- A3. SARDP NE, Phase- B4. East West Corridor5. NHDP III5. NH/Roads (In-Progress under SARDP-NE )
6. Completed stretches) NH Network with PWD with BRO NH yet to be Entrusted
TawangVijaynagar
Panchao
Golaghat
Chandel
Tura
Lunglei
Seling
Champai
Palel
Peren
Kailasahar
Seppa
Balipara
Koloriang
Yingkiong
Pasighat
Anini
HawaiAlong
Ziro
Bishing
Jido
Singa
Sarkam Point
Jorging
Rowta
Maram
Theriat
Tuipang
Saiha
Ukhrul
Mokokchung
Migging
Bile
Tato
Taliha
Pango
AIZAWL
Mangan
Sivoke
Baghmara
SIKKIM
MIZORAM
NAGALAND
ARUNACHAL PRADESH
CHINA
BHUTAN
BANGLADESH
MYANMAR
Mahadevpur
NATHULA
Srirampur
Silchar
GUWAHATI
IMPHAL
GANGTOK
ITANAGAR
AGARTALA
AIZAWL
MEGHALAYA
Boxirhat
Pangsu Pass
Kajiranga
Jhanji
Dimapur
Tuensang
Moreh
Sabroom
150
31C
155
Daboka
Paikan
31A
54B
54A
Roing
Barapani
Namchik
61Nagaon
Dhola
Makum
Bimlapur
52B
52B
Dhubri
Kokrajhar Barpeta
BaskaUdalguri
Morigaon
Diphu
Tamenglong
Lumla
Tashigaon
Silghat
Longleng
Mon
Zunheboto
Zhamai
Goalpara
BaihataCharali
Dudhnai
Dalu
Gyalshing
Namchi
Melli
Singtam
`
Yupia
Road serving Kaladan Project
Daporijo
Bame
TezpurNumaligarh
Merangkong
Kanubari
Mawthabah
Chaigaon
ASSAM
Demagiri
TRIPURA
Manu
JowaiBypass
ShillongBypass
SilcharBypass
Haflong
Nongstoin
DibrugarhBypass
Athibung
Khelema
6251
31
3637
37
61
39
54
39
40
44
5339
54
44
44
155
151
150
152
229 52
52
52
37
229
38153
44E
SHILLONG
44A
150
Nechipu
Hoj
Potin
Pahumara
Lumding
KhonsaChanglang
Sadia
NorthLakhimpur
Jonai
KOHIMA
154
54
54
37
Kumarghat
Wakhaji
Pangin
Akajan
Jorabat
Wokha
Kukital
Phek
Williamnagar
Rangpo
BagdograSilliguri
Naya Bazar
Chalsa
WESTBENGAL
Bogibeel bridge with NHAI
Menla
Jaldhaka
31
Ranipul
CHINA
Shankshak
Tengnoupal
Yaingpokpi
MANIPUR
31B
37
62
40 40
36
37A
52A
52A
52
52
52B
150
53Badarpur
Jiribam
36 54
153
Km 95 – 118 of NH 54
Km 10 – 18 of NH 154
Boko
Mawshynrut
`
NH-52
NH-52
NH-37
LEGEND :-
A. Roads under Arunachal Package Road stretches proposed on Annuity basis
B. Roads under Phase ‘A’C. Roads under Phase ‘B’ Work is on-going in stretch Other National Highways East West Corridor
DISTRICT HEADQUARTER TOWN
BaihataCharali
To Srirampur
ITANAGAR
ZORAM
NH-52B
NH-37A
MAHADEVPUR
BIMLAPUR
BALIPARA
RUPAI
AKAJAN
NECHIPU
SADIA
DHOLA
NUMALIGARH
DIBRUGARH
Roads covered for Roads covered for improvement inimprovement inArunachal Pradesh Arunachal Pradesh under SARDP-NEunder SARDP-NE
GOHPUR
SILGHAT
TINSUKIA
Tawang
Bomdila
Seppa
Koloriang
Daporijo
Aalong
Yingkiong
Anini Roing
Tezu
HawaiZiro
Yupia
Khonsa
Changlang
Pasighat
SIBSAGAR
NAMCHIK
MARIYUNG
JONAI
PANGSU PASS
JAIRAMPUR
GUWAHATI
KANUBARI
TOSILCHAR
Hoj
NAGAON
NORTHLAKHIMPUR
BANDER DEWA
Potin
PAKA BAME
PANGINBOMJIR
CHOWKHAM
Being improved to 2 lane by BRO under China Study Group(CSG)
Aalong
PANGIN
Koronu
Paya
Lalpul
TASHIGAONG
LUMLA
TAHILA
TATO
LUNGTE
PONGO
MIGGING
GORGING
BILE
BISHING
JIDO
SINGA
SAKRAM POINT
229
229
52
52
52B
153
52B52B
229
HOLONGI
ROUTE OF 4 LANE CONNECTIVITY OF ITANAGAR WITH EAST WEST CORRIDOR AT NAGAON
37 Ext
Quarterly Targets for 2013-14 for SARDP-NE including Arunachal Pradesh Package.
26
`
Sl. No.
Description Item Performance in 2012-13
Cumulative upto
31.3.2013
2013-14 (cumulative)
Qrt 1 Qrt 2 Qrt 3 Qrt 4
1 Sanction of works
Target 1980 6702 131 450 815 2000
Achievement 69 3783 56 - - -
2 Award of works
Target 1991 6702 131 450 815 2000
Achievement 57 3771 56 - - -
3 Completion of
construction
Target 300 1282 0 25 150 550
Achievement 260 1152 - - - -
Details of sanctions in the North Eastern States entrusted to State PWDs under NH(O) in the last four years
27
States 2009-10 2010-11 2011-12 2012-13No. Amount
(Rs. In Crores)
No. Amount (Rs. In Crores)
No. Amount (Rs. In Crores)
No. Amount (Rs. In Crores)
Arunachal Pradesh
- - - - - - - -
Assam 17 292.06 3 79.88 3 430.65 11 155Manipur 9 132.22 - - 10 34.57 4 107
Meghalaya7 137.55 - - 3 21.72 14 112
Mizoram 11 63.82 - - 4 45.89 5 35Nagaland 1 8.42 1 93.68 - - 9 60
Sikkim - - - - - - - -Tripura - - - - - - - -
Allotment and expenditure in the North Eastern States entrusted to State PWDs under NH(O) in the last five years
28
States 2009-10 2010-11 2011-12 2012-13 2013-14Allot-ment
Expen-diture
Allot-ment
Expen-diture
Allot-ment Expen-diture
Allot-ment
Expen-diture
Allot-ment
Expen-diture
Arunachal Pradesh
- - 7.00 - - - 6.00 - - -
Assam 172.00 200.51 172.00 171.67 230.0 197.04 225.22 137.16 198.004.58
Manipur 19.65 19.65 55.00 64.08 78.00 47.09 61.61 54.91 32 5.26
Meghalaya60.00 64.08 65.00 79.08 83.50 82.76 101.77 62.60 47.00 3.40
Mizoram 28.00 5.42 43.00 24.22 60.00 40.81 107.51 38.42 57 3.4
Nagaland 40.00 31.68 47.00 26.94 54.00 19.63 85.15 6.29 48 0.00
Sikkim - - - - - - - - - -
Tripura - - - - - - - - - -
Allotment and expenditure in the North Eastern States under CRF in the last five years
States 2009-10 2010-11 2011-12 2012-13 2013-14Allot-ment
Expen-diture
Allot-ment
Expen-diture
Allot-ment Expen-diture
Allot-ment
Expen-diture
Allot-ment
Expen-diture
Arunachal Pradesh
31.38 18.44 45.47 45.47 40.24 33.53 46.05 46.05 41.49 -
Assam 35.05 32.87 45.47 45.47 43.62 33.53 46.02 32.04 46.02-
Manipur 8.90 2.20 10.07 2.28 11.43 5.84 11.56 5.95 11.79 -
Meghalaya10.40 3.04 16.76 16.76 16.50 16.50 13.83 13.83 14.06 -
Mizoram 8.20 6.73 9.29 3.10 10.55 6.90 10.88 3.63 10.88 -
Nagaland 6.61 4.63 7.35 2.17 11.53 11.53 15.55 15.55 8.84 -
Sikkim 2.99 3.41 3.48 2.48 3.96 1.44 4.08 2.56 4.08 -
Tripura 4.62 5.27 7.95 7.95 9.81 9.81 6.12 5.24 6.14 -