PRESENTATION TO EAZ
LOAD-SHEDDING IN ZAMBIA:WHAT SHOULD BE THE PLAN
PRESENTED BY C CHITUNDU
MANAGING DIRECTOR
PRESENTATION OVERVIEW
1.0 BACKGROUND
2.0 CURRENT STATUS
3.0 ZESCO’S PLANS TO END LOAD-SHEDDING
3.1 GENERATION PROJECTS
3.2 TRANSMISSION PROJECTS
3.3 DISTRIBUTION PROJECTS
3.4 OTHER INITIATIVES TO REDUCE LOAD-SHEDDING
4.0 CONCLUSION
BACKGROUND
• ELECTRICITY IS A KEY DRIVER OF ECONOMIC GROWTH & MAJOR
INPUT IN ALL ECONOMIC SECTORS - AGRICULTURE, MINING,
MANUFACTURING AND TOURISM
• ZESCO’S ELECTRICITY GENERATING CAPACITY STANDS AT 2.2 GW
(99% HYDRO)
• NET EXPORTS ROUGHLY 5% OF TOTAL GENERATION (MOSTLY TO
NAMIBIA, BOTSWANA AND CONGO D.R.)
• CURRENT PEAK DEMAND FOR ELECTRICITY BARELY MEETS
GENERATION CAPACITY ESPECIALLY DURING PEAK TIMES
•
BACKGROUND CONT’D
• ZAMBIA HAS EXPERIENCED A SUSTAINABLE
ECONOMIC GROWTH OVER THE LAST FIVE YEARS
DESPITE GLOBAL RECESSION, RESULTING IN:
• INCREASED DEMAND FOR ELECTRICITY FROM ALL
SECTORS
• DEMAND OUTSTRIPPING AVAILABLE CAPACITY
DURING PEAK HOURS
• ZESCO MUST INVEST IN NEW INFRASTRUCTURE TO
COPE WITH GROWING DEMAND
BACKGROUND CONT’D
• HOWEVER DELAYED INVESTMENT IN GENERATION PLANTS HAS NOT MATCHED THE LOAD GROWTH• RESULTING IN DEFICIT IN POWER GENERATION CAPACITY
• FURTHER, DELAYED INVESTMENTS IN TRANSMISSION & DISTRIBUTION SYSTEMS HAS ALSO LED TO DEPLETING POWER TRANSMISSION & DISTRIBUTION CAPACITY
• ABOVE FACTORS LARGELY CONTRIBUTE TO LOAD-SHEDDING
• LOAD-SHEDDING IS DONE TO SAFEGUARD THE ELECTRICITY INFRASTRUCTURE
GENERATION STATUSPOWER STATION INSTALLED
CAPACITY (MW)
AVAILABLE CAPACITY (MW)
ZESCOKAFUE GORGE PS 990 960
KARIBA NORTH BANK PS 720 705
VICTORIA FALLS PS 108 103
SMALL HYDROS 13 10
KNBE 360 360
LUSIWASI 12 5
IPPsLUNSEMFWA 50 20
NDOLA HFO PLANT 50 48
TOTAL 2,303 2,211
GENERATION STATUS CONT’D
• THE TOTAL AVAILABLE CAPACITY IS 2,211 AGAINST A MAXIMUM NATIONAL DEMAND OF 1890.
• ZESCO HAS ADEQUATE CAPACITY TO MEET THE DEMAND AT PRESENT. LOAD-SHEDDING IS THEREFORE DUE TO BOTTLENECKS IN THE TRANSMISSION AND DISTRIBUTION INFRASTRUCTURE.
PROJECTED DEMAND
ELECTRICITY DEMAND
8
0
500
1000
1500
2000
2500
3000
MW
Years
Demand Forecast for Zambia
Demand
PROJECTED DEMAND CONT’D
• FROM THE GRAPH IT CAN BE SEEN THAT UNLESS THE PLANNED GENERATION PROJECTS COME ON STREAM, THERE WILL BE A GENERATION DEFICIT IN THE COMING YEARS.
• DAILY CONNECTION RATE: 300
• PENDING BACKLOG IN CONSTRUCTION AND NEW CONNECTIONS TO DATE: 20,000
PROJECTED GENERATION DEFICITS
Year 2008 2010 2015 2020 2025
FORECAST MAXIMUM DEMAND (MW) 1,579 1,592 2,389 2,595 3,029
FORECAST SHORTFALL(MW) 547 753 1,179
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING
GENERATION
REHABILITATION AND UPRATING OF THE THREE MAJOR HYDROPOWER STATIONS, I.E. KAFUE GORGE, KNBPS AND VICTORIA FALLS
VICTORIA FALLS POWER STATION – USD53.7MILLION
KAFUE GORGE POWER STATION - USD 85.5 MILLION
KARIBA NORTH BANK POWER STATION – USD81.4MILLION
THROUGH THE UPRATING OF KARIBA AND KAFUE GORGE 210MW WAS GAINED
TOTAL COST OF THE UPGRADE– USD 100 MILLION
ESTIMATED COST FOR A 210MW NEW HYDRO POWER STATION
– ABOVE US$600MILLION
GENERATION PROJECTSPOWER REHABILITATION PROJECT (PRP)
SCOPE INCLUDED REHABILITATION AND UPRATING OF THE THREE MAJOR HYDROPOWER STATIONS, I.E. KAFUE GORGE, KNBPS AND VICTORIA FALLS
OTHER WORKS INCLUDED REINFORCEMENT AND REHABILITATION OF SOME TRANSMISSION AND DISTRIBUTION INFRASTRUCTURE
THE MAJOR ACHIEVEMENTS OF THE PRP HAS BEEN THE UPRATING OF THE KAFUE GORGE POWER STATION FROM 900 TO 990 MW, THE REINSTATING OF THE VICTORIA FALLS POWER STATION TO ITS FULL GENERATING CAPACITY OF 108 MW AS WELL AS THE UP-RATING OF KARIBA NORTH BANK POWER STATION FROM 600 MW TO 720 MW. THE TOTAL GENERATION CAPACITY YIELDED FROM THE PRP IS 210 MW
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING
GENERATIONCONSTRUCTING & COMISSIONING OF THE 360 MW
KARIBA NORTH BANK EXTENSION PLANT.LOAD-SHEDDING USUALLY DONE AT PEAK TIMES, KNBE
CONSTRUCTED AS A PEAKING STATION TO MEET THE PEAK CAPACITY SHORTFALLS
KNBE PROJECT- OUTFALL TOWER WORKS
15
UNIT # 6 SPIRAL CASING - PREPARATIONS FOR WATER PRESSURE TESTING
NEW GENERATION PROJECTS
ITEZHI TEZHI HYDROPOWER PROJECT (120 MW)
Owner PPP (ZESCO/TATA)
Cost (Millions of US Dollars) 232
Duration (Years) 3.5
Operation 2015
Status 48% completed
ITEZHI TEZHI HYDROPOWER PROJECT
NEW GENERATION PROJECTS-SMALL HYDROS SHIWANG’ANDU 1 MW – USD4.15 MILLION COMPLETED IN 2012
NEW GENERATION PROJECTS-SMALL HYDROS
LUNZUA-15MW-US$52M- COMMISSIONING OF UNIT 1 SCHEDULED FOR END AUGUST 2014.
19
LUNZUA PROJECT
LUNZUA-15MW-US$52M- COMMISSIONING OF UNIT 1 SCHEDULED FOR END AUGUST 2014.
20
NEW GENERATION PROJECTS-SMALL HYDROS
LUSIWASI UPPER -15MW-US$47M AWAITS SITE INVESTIGATIONS, AWARD OF CONTRACT, PROJECT
FINANCING
REHABILITATION AND UPRATING OF CHISHIMBA FALLS: 6 -14.8MW – US$46M
PREPARATION BID DOCUMENTS IN PROGRESS, AWARD OF CONTRACT, PROJECT FINANCING
REHABILITATION AND UPRATING OF MUSONDA FALLS: 5-10MW – US$32M
CONTRACT AWARDED, ADVANCE PAYMENT MADE TO EPC CONTRACTOR, PROJECT FINANCING. WORKS TO CONCLUDE IN 2016
NEW GENERATION PROJECTS-SMALL HYDROS
MUJILA FALLS 1.4MW-US$25M
75% OF PREPARATORY WORKS DONE. PROJECT COMPLETION EXPECTED 2017.
LUSIWASI LOWER -86MW-US$164 EPC CONTRACT AWARDED BUT CANCELLED DUE TO POOR
PERFORMANCE RECORD
22
NEW GENERATION PROJECTS
KAFUE GORGE LOWER HYDROPOWER PROJECT (750 MW)
• OWNER:PPP (ZESCO/SINOHYDRO)
• COST:USD 2 BILLION
• DURATION: 6 YEARS
• OPERATION: 2019
• STATUS: PROJECT PREPARATORY ACTIVITIES UNDERWAY. CONSULTANTS ARE BEING HIRED. DISCUSSIONS WITH FINANCIERS UNDERWAY.
• GRZ HAS ALLOCATED US$ 186 M (ZMK930 TR) FROM THE EURO BOND FOR THE KGL PROJECT AS PARTIAL EQUITY CONTRIBUTION
OTHER SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING
GENERATION
CONTRACTING OF THE 50MW FROM NDOLA ENERGY. COMMERCIALLY AVAILABLE.
CONTRACTING OF THE 300MW FROM MAAMBA COLLIERIES TO BE AVAILABLE IN 2015
NEW GENERATION PROJECTS – POTENTIAL SITES
MPATA GORGE – 540 MW DEVIL’S GORGE – 500 MW BATOKA GORGE – 800 MW MUMBOTUTA FALLS - 300 MW MAMBILIMA FALLS SITE I – 202 MW MAMBILIMA FALLS SITE I – 124 MW KABWELUME FALLS - 62 MW KUNDABWIKA FALLS – 101 MW MUTINONDO - 40 MW LUCHENENE – 30 MW MKUSHI – 65 MW
TRANSMISSION PROJECTS ONGOING
CONNECTION OF NORTH WESTERN PROVINCE TO NATIONAL GRID
THE OBJECTIVE IS TO SUPPORT THE INCREASED ACCESS TO ELECTRICITY AND IMPROVED QUALITY OF SERVICE BY DISPLACING THE EXPENSIVE DIESEL GENERATORS
COST: APPX. USD150 MILLION
FUNDING: SECURED FROM NORDEA BANK (SWEDEN)
STATUS: CONTRACT AWARDED TO EL TEL, NOW MOBILIZING TO SITE. DESIGN WORKS IN PROGRESS.
CONSTRUCTION PERIOD 24 MONTHS. COMMISSIONING APRIL 2016
26
TRANSMISSION PROJECTS ONGOING
KARIBA NORTH BANK EXTENSION POWER EVACUATION PROJECT
THE OBJECTIVE IS TO INCREASE TRANSMISSION CAPACITY FROM KNBPS TO THE GRID FOR THE EVACUATION OF POWER FROM KNBE PROJECT
COST: USD62 MILLION
STATUS: EPC CONTRACTOR IS SINOHYDRO, TOWER ERECTION AND CONDUCTOR STRINGING ARE IN PROGRESS.
CONSTRUCTION PERIOD: 18 MONTHS, PROJECT HAS HOWEVER BEEN DELAYED.
27
TRANSMISSION PROJECTS ONGOING
KAFUE TOWN MUZUMA VICTORIA FALLS TRANSMISSION LINE UPGRADE
THE OBJECTIVE IS TO INCREASE TRANSMISSION CAPACITY SOUTHWARDS FOR EXPORT TO AND FROM SAPP AND PROVIDE EVACUATION PATH FOR NEW GENERATION PROJECTS
SCOPE: UPGRADE 348 KM OF 220 KV LINE TO 330 KV
COST: USD100 MILLION
STATUS: PROCUREMENT PROCESS ALMOST COMPLETE
FUNDING: WORLD BANK AND EUROPEAN INVESTMENT BANK
CONSTRUCTION PERIOD: 18 MONTHS28
OTHER TRANSMISSION PROJECTS ONGOING
PENSULO KASAMA AND PENSULO CHIPATA 330 KV PROJECT
THE OBJECTIVE IS TO IMPROVE POWER QUALITY IN EASTERN, MUCHINGA, NORTHERN AND LUAPULA PROVINCES AND TO INCREASE TRANSMISSION CAPACITY TO THESE AREAS
COST: USD335 MILLION CONSTRUCTION PERIOD: 30 MONTHS FROM AUGUST 2012
TRANSMISSION PROJECTS ONGOING
ITT MUMBWA LUSAKA WEST TRANSMISSION LINE PROJECT
THE OBJECTIVE IS TO PROVIDE POWER EVACUATION FOR THE ITT POWER STATION
COST: USD133 MILLION
FUNDING: EIB, AFDB AND AFD
STATUS: EPC PROCUREMENT PROCESS FOR SUBSTATION AND TRANSMISSION LINE COMPLETE.
CONSTRUCTION PERIOD: 18 MONTHS
30
TRANSMISSION PROJECTS ONGOING
SUPPLY TO KALUMBILA MINE
THE OBJECTIVE IS TO SUPPLY POWER TO THE PROPOSED FQM KALUMBILA MINE
SCOPE: 400KM OF 330 KV DOUBLE CIRCUIT LINE AND 66 KM OF 330 KV SINGLE CIRCUIT LINE AND ASSOCIATED SUBSTATION AT KALUMBILA
COST: USD300 MILLION
STATUS: TRANSMISSION LINE AND SUBSTATION WORKS IN PROGRESS
CONSTRUCTION PERIOD: COMMISSIONING IS EXPECTED END OF 2015 31
OTHER TRANSMISSION PROJECTS ONGOING
CONNECTION OF LUANGWA DISTRICT TO THE GRID
THE OBJECTIVE IS TO SUPPORT THE INCREASED ACCESS TO ELECTRICITY AND IMPROVED QUALITY OF SERVICE BY DISPLACING THE EXPENSIVE DIESEL GENERATORS
COST; USD63MILLION
STATUS: CONSTRUCTION WORKS ARE IN PROGRESS.
CONSTRUCTION PERIOD: COMMISSIONING IS EXPECTED DECEMBER 2014
32
TRANSMISSION PROJECTS ONGOING
LUSAKA TRANSMISSION & DISTRIBUTION REHABILITATION AND UPGRADING PROJECT
THE OBJECTIVE IS TO INCREASE THE TRANSMISSION CAPACITY OF THE LUSAKA TRANSMISSION AND DISTRIBUTION NETWORK
COST: USD210MILLION
FUNDING: WORLD BANK, EUROPEAN INVESTMENT BANK AND ZESCO LIMITED
STATUS: FINANCING BY WB, EIB. GOING THROUGH THE PROCESS.
CONSTRUCTION PERIOD: COMPLETION EXPECTED BY 201833
FUTURE TRANSMISSION PROJECTSZIZABONA THE OBJECTIVE IS TO INCREASE REGIONAL TRADE IN POWER BY INCREASING
TRANSMISSION CAPACITY FOR NORTH TO SOUTH AND EAST TO WEST POWER TRADING
PROJECT PROMOTED BY ZIMBABWE, ZAMBIA, BOTSWANA AND NAMIBIA
COST: USD230MILLION
FUNDING: DISCUSSIONS ONGOING WITH POTENTIAL FINANCIERS. DBSA, AFDB, KFW
STATUS: TECHNICAL AND MARKET STUDIES COMPLETED, PROJECT GOVERNANCE DOCUMENTS PREPARED
IUMOU, IGMOU SIGNED. JOINT DEVELOPMENT AGREEMENT TO BE SIGNED BY BPC. WILL LEAD TO SIGNING OF SHAREHOLDERS AGREEMENT
CONSULTANT ENGAGED AND SPV REGISTRATION IS UNDERWAY
CONSTRUCTION PERIOD: COMMISSIONING IS EXPECTED BY 201734
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING TRANSMISSION PROJECTS
UPGRADING (RE-CONDUCTORING) OF LUSAKA 132 KV
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING
MEASURES TO INCREASE TRANSMISSION CAPACITIES:INSTALLATION OF A SECOND 125 MVA 330/132 KV
TRANSFORMER AT LUSAKA WEST TO SUPPORT 132 KV SYSTEM. (COMPLETED IN 2012)
UPGRADE OF MAZABUKA SUBSTATION COMPLETED IN 2012INSTALLATION OF COMPENSATION EQUIPMENT IN THE
COPPERBELT
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING –DISTRIBUTION PROJECTS
DISTRIBUTION PROJECTS UNDER INCREASED ACCESS TO ELECTRICITY SERVICES.
SPONSORED BY WB, JICA AND OTHER FINANCIERS IN PROGRESS. PROJECT COST US$75MILLION
IAES –PROJECTS STATUSProject Name Project Description Project Cost
(USD)Project Status
Kanyama SubstationZESCO/IAES/W/002/ 12
Design, Supply & Installation of Kanyama 2 x 16/25MVA 33/11kV S/S in Lusaka
3,406,018.75
.Overall Progress 98%
Livingstone’s Lusaka Rd SubstationZESCO/IAES/W/001/ 12
Design, Supply & Installation of Lusaka Rd 2 X 15/20MVA 33/11kV S/S in Livingstone
4,020,411.00
Overall Progress 98%
Grid Reinforcement - IAES Procurement of and Works to Install Reinforcement Transformers at Roma 132/11kV; Figtree132(88)/33kV; Chibombo 132(88)/33kV Substations
12,637,654.52
Overall Progress 20%
Garden, Kanyama, Misisi Township Electrification (Integrated Approach)
Integrated Approach to Electrification in Garden, Kanyama & Misisi Townships
1,824,940.00
Progress 40%.
Intensification Works in the Copperbelt Region ZESCO/IAES/002/ 12
Construction of Total 32km of 11kV of lines, 39x200kVA,11/0.4kV Tx’s ; 45km of 400V lines and service connection (Intensification Works) in the Copperbelt Region ( ie Kabushi,Chipulukusu,New Kawama & Chibolya)
2,781,965.66
75% progress
Grid Extension Works in the Northern Region ZESCO/IAES/001/ 12
Construction of Total of 30km x 11kV and 8x200kVA,11/0.4kV Tx’s; 37km of 33kV Lines, 23x50kVA,33/0,4kV Tx’s and service connection (Grid Extension Works) in the Northern Region (ie Lukulu,Ipusukilo mission & Lukulu farm block)
2,315,061.76
Construction of lines is underway, with 80% progress
New Distribution Lines ZESCO/IAES/JICA/001/11
Construction of Distribution Lines in KapiriMposhi & Mumbwa; Azele1 & Lundazi; Mbereshi 1&2; Isoka1 & Luwingu; Vic Falls & Mazabuka; Senanga & Mongu; Mujila Falls Lower P/S
12,781,965
Construction of lines is underway, with 80% progress
Grid Extension Works in the Central Region ZESCO/IAES/W/008/12
Construction of Grid Extension lines in Central Region covering Mukonchi and Mangango
8,111,772.84
Line Surveys, Bush-clearing and pole pegging completed, in readiness for construction.
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING
NEW KANYAMA SUBSTATION
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING
WAYLEAVE ENCROACHMENT -NEW KANYAMA SUBSTATIONINCOMPLETE LINE
SHORT TERM MEASURES TAKEN TO REDUCE LOAD-SHEDDING
EUROBOND PROJECTS IN LUSAKA, KITWE AND NDOLA – COMMISSIONING TO START BY AUGUST 2014
PROJECT COST USD 69 MILLIONOVER 60% OF FUNDS ALREADY COMMITTED
DERP PROJECTS STATUS
Name of the project Scope of Work Project Status Progress Expected Commissioning
New Chalala 33/11kV Substation
Chalala 33/11kV new Substation with two 33/11kV 26 MVA TXs
Civil works completed. Installation in progress 98% August , 2014
Rehabilitation of Water Works 33kV busbarCivil works for half busbar completed & electrical works in progress for half
busbar.50% August , 2014
Rehabilitation of 33kV waterworks bay 1 at Woodland Sub
Civil works completed & electro-mechanical works snagging completed
33kV OHL, 18kM & 11kV OHL, 5kMErection and stringing work in
progress 95% August, 2014
New Bonaventure 33/11kV Substation
Bonaventure 33/11 KV new Substation with two 33/11 kV 26 MVA T/Fs
Civil works completed. Installation in progress 94% August, 2014
Rehabilitation of Chilanga 33kV busbar Civil & installation works in progress 80% August, 2014
33kV OHL, 25kM and 11kV OHL, 5kMErection and stringing work in
progress 98% July, 2014
Upgrade 33kV switchgear at Lusaka West Sub
new 33kV outdoor Switching Station Civil & electrical works in progress. 93% & 86% September, 2014
Chongwe 88/33kV Sub upgrade
Rehabilitation of Chongwe 88 / 33kV Substation and install 132/ 88/ 33kV, 52 MVA TXs
Civil works completed. Installation in progress. 90% September, 2014
Upgrade of 33kV switchgear at
Liverpool SubstationNew 33kV indoor GIS Switchgear Civil & electrical works snagging completed
Construction of two new Substations and
66kV transmission lines
New Scaw 66 /11kV Substation with two 66/11 kV 40 MVA TXs Civil & electrical works in progress. 97% & 72% September, 2014
New Mwambashi 66 /33kV Substation with two 66/33kV 26 MVA TXs Civil & electrical works in progress. 97% & 80% September, 2014
New 14kM 66kV transmission line from Chambishi Copper Smelter Sub to Mwambashi Sub
Civil & installation works in progress. 84% December, 2014New 28kM 66kV transmission line from Mwambashi Sub to New SCAW Sub
DERP PROJECTS STATUS CONT’D
Reinforce Makeni, Matero,
Chelstone, Kabulonga & L85
Substations
Chelstone 33/11kV new Substation with two 33/11kV 26 MVA TXs
Civil works, Installation & Testing and
Commissioning completed.
snagging completed
Kabulonga 33/11kV new Substation with two 33/11kV 26 MVA TXs
Civil, Installation, Testing & Commissioning
completed. snagging completed
Reinforce Makeni, Matero,
Chelstone, Kabulonga & L85
Substations
L85 33/11kV new Substation with two 33/11kV 26 MVA TXs
Civil & electrical works in progress. 99% & 94% August, 2014
Rehabilitation of Makeni and add two 33/11kV 26 MVA TXs
Civil works completed. Installation in progress. 99% & 98% August , 2014
Rehabilitation of Matero and add two 33/11kV 40 MVA TXs
Civil & electrical works in progress. snagging completed
Reinforcement of supply at Ndeke
Village in Mufulira
New 66/11kV Substation with two 66/11kV ,26 MVA TXs
Civil & Installation works in progress. 95% & 80% September ,
2014
New 24kM 66kV transmission line from Chambishi Copper Smelter and 10kM of 11kV OHL
Civil & installation works in progress. 85% December, 2014
Reinforcement of supply in Chongwe town
33/11 kV new Substation with two 33/11 kV 26 MVA TXs
Civil works completed. Installation in progress 98% August, 2014
33kV OHL, 25kM , and 11kV OHL, 5 KM 33kV & 11kV installation in progress 97% July, 2014
NEW KABULONGA SUBSTATION UNDER DERP
11KV BOARD AT KABULONGA SUBSTATION
PLANNED CAPITAL INVESTMENT 2014
ZESCO PLANS TO SPEND ZMK 5,634BN ON ASSETS AND INFRASTRUCTURE DEVELOPMENT IN 2014
OVER 45% ALREADY UTILIZED
PLANNED CAPITAL INVESTMENT (BREAKDOWN)
STRATEGIC BUSINESS UNIT
2014 CAPITAL EXPENDITURE
(ZMK’000)
GENERATION 1,342,371
TRANSMISSION 2,913,348
DISTRIBUTION 1,198,500
CORPORATE 179,898
TOTAL 5,634,117
TARIFFS IN THE REGIONCOUNTRY AVERAGE RETAIL TARIFF US$ CENTS/KWHTANZANIA 8.2
SWAZILAND 11.50
ZIMBABWE
9.80
SOUTH AFRICA
8.70
NAMIBIA
8.60
MOZAMBIQUE
7.50
BOTSWANA
7.00
MALAWI
6.80
ANGOLA
6.00 ZAMBIA 6.00
IPPS AND THEIR CAPACITIESGENERATION SOURCE CAPACITY MW ENERGY (MWH)
KNBE 360 488,978
ITPC 120 506,289
KGL 750 2,761,905
NDOLA ENERGY (HFO) 50 438,000
Maamba Collieries Ltd 300 2,362,205
EMCO 300 2,022,472
TOTAL 1880 8,579,849
ZESCO REVENUE DEFICITS DUE TO PRICE DIFFERENTIALS ON IPPS
DESCRIPTION USc/ KWH REVENUE (US$)
AVERAGE TARIFF - IPPs 12.75 883.7M
AVERAGE SELLING TARIFF 6.02 516.5M
TARIFF DIFERENTIAL 6.73 367.2M
REVENUE LOSS (US$ ) 367.2M
POWER PURCHASE AGREEMENTS WITH INDEPENDENT POWER PRODUCERS
TO ENSURE LOAD SHEDDING IS MINIMIZED ZESCO HAS CONTRACTED POWER FROM IPPS AT HIGHER COST COMPARED TO THE PREVAILING TARIFFS ON THE MARKET.
AVEARGE TARIFF USC/KWH -6.02
ANNUAL LOSS OF 367 MILLION USD
REASONS FOR LIMITED INVESTMENTS IN THE ELECTRICITY SECTOR
THE ELECTRICITY ENERGY SECTOR IN ZAMBIA HAS SUFFEREED LITTLE OR NO INVESTMENT DESPITE GOVERNMENTS INITIATIVE TO HAVE THE INDUSTRY DEREGULATED DUE TO LARGELY:
NON COST REFLECTIVE TARIFF LACK OF WILLINGNESS FROM CUSTOMERS TO PAY COST REFLECTIVE
TARIFFS
ZAMBIA HAS THE LOWEST TARIFFS IN THE REGION.
52
POWER PURCHASE AGREEMENTS WITH INDEPENDENT POWER PRODUCERS
DUE TO THE UNATTRACTIVE TARIFFS, THE ZAMBIAN ELECTRICITY SECTOR IS LARGELY DOMINATED BY ZESCO –SINGLE BUYER MODEL.
SOLAR ENERGY OPTION
• SOLAR ENERGY CAN ONLY BE HARNESSED WHEN IT IS DAYTIME AND SUNNY.
• LESS EFFICIENT AND COSTLY EQUIPMENT (EFFICIENCY FOR MOST PANELS BETWEEN 17-20%)
• RELIABILITY DEPENDS ON LOCATION, CLIMATE, POLLUTION E.T.C
• ENVIRONMENTAL IMPACT OF PV CELL PRODUCTION
• REQUIRES LARGE TRACTS OF LAND FOR SOLAR PANELS AND BATTERIES
• NO FEED-IN TARIFF IN PLACE –MUST BE DEVELOPED BY MEMWD AND ERB
SOLAR ENERGY OPTION
• COST OF SOLAR ENERGY VERY HIGH
• EXAMPLE TO PROCURE AND INSTALL A 25KWP IT COSTED ZESCO ABOUT
USD 300,000
OTHER INITIATIVES TO REDUCE LOAD-SHEDDING
• POWER PLANTS WILL TAKE TIME TO COME ON BOARD
• THEREFORE ZESCO MANAGEMENT STEPPED UP DSM ACTIVITIES TO ACCELERATE ENERGY EFFICIENCY INITIATIVES
• ENERGY SAVER LAMP (CFLS) DISTRIBUTION
• POWER ALERT SYSTEM
• ENERGY AUDIT AND POWER FACTOR CORRECTION
• SOLAR POWER TECHNOLOGY
• TIME OF USE TARIFF (TOU)
• RIPPLE CONTROL OF ELECTRIC GEYSERS
• PREPAYMENT METERING
DEMAND SIDE MANAGEMENT (DSM)
• DSM IS A UTILITY PROGRAM AIMING TO FINE TUNE CONSUMERS ENERGY CONSUMPTION PATTERN ACCORDING TO UTILITIES ENERGY PRODUCTION AND DISTRIBUTION CAPACITY
• TO REDUCE LOAD-SHEDDING
• TO RELEASE SYSTEM CAPACITY
• MAKE AVAILABLE ADDITIONAL POWER FOR NEW CONNECTIONS
• REDUCED ENERGY BILLS FOR CUSTOMERS
• PROMOTE ENERGY EFFICIENCY AND SAVE THE ENVIRONMENT
CFL DISTRIBUTION
CFL DISTRIBUTION
AN 87MW NEW POWER PLANT WILL COST NOT LESS THAN US$300MILLION WHILE ZESCO SPENT U$4.0MILLION ON THE PROCUREMENT AND DISTRIBUTION OF THE CFLS
Consignment Distributed Savings (MW) Efficacy (CFL/kW)
IAES (1 million) 913,056 57 16
ZEM (1 million) 595,832 29.79 20
Cumulative 1,508,888 86.79 17
POWER ALERT SYSTEM
• THE POWER ALERT SYSTEM IS ESSENTIALLY A COMMUNICATION TOOL THAT UTILIZES THE TELEVISION AND RADIO MEDIA AS THE CHANNEL TO INFORM ELECTRICITY CONSUMERS ON THE ENERGY SITUATION IN THE POWER NETWORK THEREBY PROMPTING CUSTOMER RESPONSE.
• THE SYSTEM THEREFORE TRIGGERS VOLUNTARY PARTICIPATION OF CONSUMERS IN ELECTRICITY DEMAND REDUCTION BY SWITCHING OFF UNNECESSARY LOADS IN RESPONSE TO THE BROADCAST POWER ALERT MESSAGE.
POWER ALERT SYSTEM
62
SOLAR POWER
• 305 OUT OF 1,000 SOLAR GEYSERS INSTALLED MOSTLY IN GOVERNMENT INSTITUTIONS AND TRANSIT HOMES (WITH 566KW POWER SAVINGS).
• REMAINING SOLAR GEYSERS TO BE INSTALLED IN ZESCO INSTITUTIONAL HOUSES MOSTLY AT POWER STATIONS & SERVICE CAMPS
• ZESCO HQ OFFICE LIGHTING AND PARLIAMENT EMERGENCY SUPPLY ALREADY ON SOLAR POWER
• AT ZESCO HQ 1,850 LEDS RETROFITTED IN FLUORESCENT FITTINGS
RIPPLE CONTROL SYSTEM
• MEANS OF LOAD SHAVING (INSTEAD OF LOAD SHEDDING)
• MAINLY TARGETED AT ELECTRIC GEYSER LOADS
• INITIALLY TARGETED AT 100,000 RESIDENTIAL CUSTOMERS IN LUSAKA
• PROJECTED LOAD OF ABOUT 135MW TO BE SAVED
• CAN BE IMPLEMENTED EVEN UNDER SYSTEM EMERGENCIES
• TECHNICAL SPECIFICATIONS DRAWN. FINANCING
ARRANGEMENTS UNDERWAY
ZESCO PROJECTS
CONCLUSION
• ZESCO LIMITED HAS EMBARKED ON VARIOUS PROJECTS FROM THE PRODUCTION SIDE THROUGH TO DISTRIBUTION TO REDUCE AND ULTIMATELY STOP LOAD-SHEDDING.
• GOVERNMENT BEING THE MAJOR SHAREHOLDER HAS GIVEN SUPPORT THROUGH PROVISION OF EQUITY AND GUARANTEES FOR DEBTS BEING CONTRACTED TO FINANCE THE PROJECTS.
• LOAD-SHEDDING IN ZAMBIA, THE PLAN IS THEREFORE TO ENSURE COST REFLECTIVE TARIFFS IN ORDER TO ATTRACT INVEST IN THE GENERATION, TRANSMISSION AND DISTRIBUTION ELECTRICITY INFRASTRUCTURE.
THANK YOU!!