UNDER SUPERVISION OF Prof. Dr. Hj. Amiruddin Ismail Prepared by : HAMZAH ALI P 63147 HOOMAN P ZURINDA BT MAT RABU P OPTIMIZATION OF TRAFFIC FLOW BY USING SIDRA INTERSECTION
Transcript
Page 1: Presentation sidra

UNDER SUPERVISION OF Prof. Dr. Hj. Amiruddin Ismail

Prepared by : HAMZAH ALI P 63147HOOMAN PZURINDA BT MAT RABU P

OPTIMIZATION OF TRAFFIC FLOW BY USING

SIDRA INTERSECTION

Page 2: Presentation sidra

Contents

Introduction

Input

Output

Conclusion

Page 3: Presentation sidra

INTRODUCTION

INTERSECTION

Allow the change of

route directions of traffic flows.

Traffic control

systems are capable to

reduce delays and crashes on

intersection

Problem of delay still

occurs

An area which shared

by two or more roads.

Page 4: Presentation sidra
Page 5: Presentation sidra

SIDRA

• Estimate of capacity and performance characteristics

• Analyze and optimize the intersections

• Determine signal timing

• Carry out a design life analyze for traffic growth

Page 6: Presentation sidra

SIDRA INTERSECTION User

Page 7: Presentation sidra

Advantages of using sidra

Use the parameter sensitivity

Use a lane-by-lane analysis method

Consistent with the US Highway capacity manual

Provide a Excel application to support model comparison

Estimate operation cost , fuel consumption , co2 & other emission

Page 8: Presentation sidra

Study objective

• The main objective of the Study is to prepare low cost

solutions to an existing intersection

Page 9: Presentation sidra

Study area

• The intersection is located in front of the main entrance of UKM.

• North side :Toll Bangi/Bandar Baru Bangi

• South side : UKM

• West side come from Bangi and will end to Kajang at East .

Page 10: Presentation sidra

N

To KajangTo

Bangi

Page 11: Presentation sidra

Data's 8-9 am & 6 – 7 pm

• Duration 15min => extended to 1hour

• Considerations : Vehicle types, direction, speed (to gain mean speed)

Page 12: Presentation sidra

PCU / UNIT

Page 13: Presentation sidra

Input Part OF SIDRA INTERSECTION Software

Page 14: Presentation sidra

Creating a new site and select an intersection type

First, to create our site, we select signals type

according to our case study

Page 15: Presentation sidra

Intersection Input dialog and insert data

We use the Intersection input dialog to establish the basic intersection configuration

Page 16: Presentation sidra

Intersection Input dialog and insert data

To Insert or delete an intersection leg we

should just click the leg

Page 17: Presentation sidra

Intersection Input dialog and insert data

Title: Four way intersection/grop 7

Page 18: Presentation sidra

Intersection Input dialog and insert data

Intersection ID: UKM

Page 19: Presentation sidra

Intersection Input dialog and insert data

Signal analyze method: fixed-time/pretimed

Page 20: Presentation sidra

Intersection Input dialog and insert data

These data apply to intersection as a whole.

Unit Time for Volumes: 60 minutesPeak Flow Period : 30 minutes

Page 21: Presentation sidra

Geometry Input dialog

Geometry node and Geometry Input dialog

The Geometry input dialog is used to configure approach and exit lanes, modify movements and insert other characters

Page 22: Presentation sidra

Geometry Input dialog (Lane & movements tab)

we should click a desirable leg to select it

To select a desirable lane, we should just click the lane

Page 23: Presentation sidra

Geometry Input dialog (Lane & movements tab)

we should click a desirable leg to select it

We can insert one approach and exit lane by clicking these

buttons for the selected leg

Page 24: Presentation sidra

Geometry Input dialog (Lane & movements tab)

we should click a desirable leg to select it

We can allocate desirable movements by clicking these buttons to

the selected lane

Page 25: Presentation sidra

Geometry Input dialog (Lane & movements tab)

we should click a desirable leg to select it

In this boxes we can input lane type, short lane, and lane length

Page 26: Presentation sidra

Geometry Input dialog (Lane & movements tab)

we should click a desirable leg to select it

To specify a Median for the selected leg, we should click the

Median check box and then insert the width of Median

Page 27: Presentation sidra

Geometry Input dialog (Lane data tab)

we input 3.3m for the width of lanes and 0 for

grads

we should click a desirable leg to select it

We choose1800 PCU/h for Basic

Saturation Flow

And accept the other defaults for this part

Page 28: Presentation sidra

Volume Input dialog

We choose separate LV & HV method to insert vehicle volume

We input the collected volume data for the selected

direction according to separate LV & HV method

Page 29: Presentation sidra

Figure of Volume Summary (volume summary node)

Page 30: Presentation sidra

PATH DATA dialog

We insert MOVEMENT PATH DATA for the

selected direction

For example for our site, approach cruise speed is 30km/h

Negotiation Speed, Negotiation Distance, and Downstream Distance will

be calculated by the program

Page 31: Presentation sidra

Specify the items in PATH DATA dialog

Vehicle’s speed at this point is Approach Crouse Speed

(Vac)

Approach travel Distance

Vehicle reaches Exit Crouse

Speed (Vec) at this point

APPROACH under consideration

Page 32: Presentation sidra

MOVEMENT DATA input dialog

The defaults of program for Movement

data are Accepted

Page 33: Presentation sidra

Priorities input dialog

Priorities dialog establishes Opposing movements for the selected movement

Select movement to be defined as

opposed movement

Click desirable movements to define them as opposing/not opposing

movements

Page 34: Presentation sidra

GAP-ACCEPTANCE DATA dialog

The

For GAP-ACCEPTANCE DATA We give the default values to the

program

Page 35: Presentation sidra

Phasing & Timing input dialog

In Phasing & Timing input dialog We use command buttons to edit

We must click this box in order to designate it as the Current Sequence , Which is analyzed by the program

Page 36: Presentation sidra

Phasing & Timing input dialog

Clone Sequence button is used to create a new Sequence for editing

Page 37: Presentation sidra

Phasing & Timing input dialog

Clone Phase button is used to create a new Phase for editing

The UKM Intersection is a Four Phase Intersection

Page 38: Presentation sidra

Phasing & Timing input dialog

For Vehicle Movement Timing Data we accept the defaults

Page 39: Presentation sidra

Phasing & Timing input dialog

In Phase Data dialog, we insert the Phase Time for each phase

Page 40: Presentation sidra

Model Settings input dialog

The parameters of MODEL SETTING affect the results significantly. However,

the defaults of parameters are appropriate generally

Page 41: Presentation sidra

Input Report node

We can get the summery of input data in the Input Report node

Page 42: Presentation sidra

Output Part OF SIDRA INTERSECTION Software

Page 43: Presentation sidra
Page 44: Presentation sidra
Page 45: Presentation sidra
Page 46: Presentation sidra
Page 47: Presentation sidra
Page 48: Presentation sidra

Total delay (average)

4640.7

Page 49: Presentation sidra

Level of Service

LOS Signalized Intersection

Unsignalized Intersection

A ≤10 sec ≤10 secB 10-20 sec 10-15 secC 20-35 sec 15-25 secD 35-55 sec 25-35 secE 55-80 sec 35-50 secF ≥80 sec ≥50 sec

A= Free flowB=Reasonably free flowC=Stable flowD=Approaching unstable flowE=Unstable flowF=Forced or breakdown flow

Page 50: Presentation sidra
Page 51: Presentation sidra
Page 52: Presentation sidra
Page 53: Presentation sidra
Page 54: Presentation sidra
Page 55: Presentation sidra
Page 56: Presentation sidra
Page 57: Presentation sidra
Page 58: Presentation sidra
Page 59: Presentation sidra
Page 60: Presentation sidra
Page 61: Presentation sidra

16500.6

Total cost

Page 62: Presentation sidra

970

Total fuel

Page 63: Presentation sidra

2430.4

Total CO2

Page 64: Presentation sidra
Page 65: Presentation sidra
Page 66: Presentation sidra

Review:

what is our plan?

collecting data(input)

for simulation(output)

optimizing (output)current situation

OPTIMIZING THE UKM INTERSECTION

CHOOSING OPTIMUM CYCLE TIME

CHANGING CURRENT PHASE TIME

ADDING SLIP LANE ON ALL APPROACHES

ADDING ONE APPROACH & EXIT LANE IN ALL DIRECTIONS

Page 67: Presentation sidra
Page 68: Presentation sidra

OPTIMIZING CYCLE : TIMECHANGIN G CYCLE TIME FROM 164 TO 150

Page 69: Presentation sidra
Page 70: Presentation sidra

SECOND MODIFICATION : CHANGING CURRENT FOUR PHASE TO TWO PHASE

Page 71: Presentation sidra
Page 72: Presentation sidra
Page 73: Presentation sidra

THIRD MODIFICATION : ADDING SLIP LANES INTO THE ALL APPROACHES

Page 74: Presentation sidra
Page 75: Presentation sidra
Page 76: Presentation sidra
Page 77: Presentation sidra

FOURTH MODIFICATION : ADDING LANE INTO EACH APPROACH & EXIT WAY

Page 78: Presentation sidra

ADDING LANE INTO EACH APPROACH & EXIT WAY

Page 79: Presentation sidra
Page 80: Presentation sidra
Page 81: Presentation sidra

1 2 3 40

500

1000

1500

2000

2500

3000

co2 (kg/h)

co2 (kg/h)

MODIFY 2 MODIFY 3CURRENT MODIFY 2

1 2 30

10

20

30

40

50

60

70

80

DECREASING OF CO2 (%)

DECREASING CO2 (%)

MODIFY 1 MODIFY 2 MODIFY 3

74 %

Page 82: Presentation sidra

1 2 3 40

2000

4000

6000

8000

10000

12000

14000

16000

18000

COST (RM)

COST (RM)

MODIFY 2 MODIFY 3CURRENT MODIFY 1

1 2 30

10

20

30

40

50

60

70

80

90

DECREASING OF COST (%)

DECREASING CO (%)

MODIFY 1 MODIFY 2 MODIFY 3

82.68 %

Page 83: Presentation sidra

1 2 3 40

200

400

600

800

1000

1200

FUEL (LITRE)

FUEL (LITRE)

MODIFY 2 MODIFY 3CURRENT MODIFY 1

1 2 30

10

20

30

40

50

60

70

80

DECREASING OF FUEL (%)

DECREASING FUEL (%)

MODIFY 1 MODIFY 2 MODIFY 3

74 %

Page 84: Presentation sidra

1 2 3 40

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

AVERAGE DELAY (SECOND)

AVERAGE DELAY (SECOND)

MODIFY 1 MODIFY 3CURRENT MODIFY 2

1 2 30

10

20

30

40

50

60

70

80

90

100

DECREASING OF AVERAGE DELAY (%)

DECREASING AVERAGE DELAY (%)

MODIFY 1 MODIFY 2 MODIFY 3

93.38 %

Page 85: Presentation sidra

Thank you