*** Jodhpur Discom
*AG,DL & BPL CONNECTIONS
Status of AG. DN deposited & connections Released (2011-12)*
Name GOR-D
GOR-D
1 TO 11 For The Month of June, 2011
Jodhpur Discom
GOR-D-01
Progress of Distribution Companies ( JODHPUR DISCOM) REVISED
Status of AG. DN deposited & connections Released
Upto the Month:-June,11GOR-D-01
Sr. No.Name of DistrictNo of DN issued During 2011-12DN depositedAg. Connections released During 2011-12 out of Colmn. 8% Connection Released of Col.8Cancelled after D.N. Deposited During 2011-12Balance Pending for connection
As on 31.03.11During 2011-12Total DN Deposited
GENERAL CATEGORYOTHERSDuring the monthUpto the monthDuring the monthUpto the month
12345678910111213
1Jodhpur448948449736493781174182322731717.39161490796
2Pali582366186317341447713367.555436241
3Sirohi44319563825427044770111415.853657177
4Jalore17571111868229718987121643826.74121122269
5Barmer10924781570227368618845159911.723743250
6Jaisalmer3944343715511214530022227.33027833
Jodhpur Zone8757134710104157720193785536233159711.133947261766
7Bikaner16451064270929280714100618737537.280631634
8HMH9968310792052024036084814123.190467201
9SGNR524238762117253653715397.260498364
10Churu126178320446626780487016718821.610682537
1115116111314000.0001412
Total Churu Cir.127678420606726881788416718821.610696549
Bikaner Zone4441216966105657222470303541774324.48022921748
Total Discom131983516167142142274162558397748134015.963970183514
DN ISSUEDDN DEPOSITEDCANCELLEDPENDING
JLRBMRJSMRJLRBMRJSMRJLRBMRJSMRJLRBMRJSMR
86RE-7 SC18532261133325473006719734
1393RE-9 GEN0548576711485218010701295819
RE-10 SPL00025
RE-11 FH000000000000
RE-11A DRIP8118532671473300027525
RE-11B DIGGI000
TOTAL2665121417761183565248011891544858
CONNECTION
JLRBMRJSMR
RE-7 SC14923573
RE-9 GEN880807344
RE-10 SPL1700
RE-11 FH000
RE-11A DRIP4010330
RE-11B DIGGI00
TOTAL10861145447
DN ISSUEDDN DEPOSITEDCANCELLEDPENDING
DCPALISIROHIDCPALISIROHIDCPALISIROHIDCPALISIROHI
RE-7 SC426751594707216900010349179
RE-8 TSP11645073
RE-9 GEN80615144213116031421252402696
RE-10 SPL10
RE-11 FH212611180120114
RE-11A DRIP323367030035380002474
RE-11B DIGGI
TOTAL831129366221324942031541379469966
CONNECTION
DCPALISIROHI
RE-7 SC50760144
RE-8 TSP536405
RE-9 GEN22703442906476
RE-10 SPL171
RE-11 FH1108
RE-11A DRIP2763334
RE-11B DIGGI
TOTAL3054447530
GOR-D-2
JODHPUR DISCOM
Status of release of DL connections during FY 2011-12
Upto the Month :-June,11GOR-D-02
S.NoName of Distt./CircleApplication for DL connections pendingApplication for DL connections pendingconnections released During 2011-12Cancelled up the month out of (3) & (4)Pending at the end of Reporting month
As on 31.03.11Received during FY 2011-12RuralUrbanTotalRuralUrbanTotal released
RuralUrbanRuralUrbanDuring the monthup to the monthDuring the monthup to the monthDuring the monthup to the monthRuralUrbanRuralUrbanBPL DURING monthAPL DURING monthBPL DURING 2011-12APL DURING 2011-12
123456345678910111212131415
1City Circle021101523017341734005091372509137279.120003620000
2Distt. Circle176201243494126211142502136491721503891955224110.72457718507152318861951955
Total JU Distt.176203353494164921114198423098917215054714631464361315.96457718507514318861951955
3Pali Distt.3858510352179373791303868289827172367351134345243.10622504040518089802717
4Sirohi Distt.653101736292138939317822145485522826977644.8646679515902140548
5Jalore Circle625112620742508325376870116452658811771726283537.05102920463817912815172732385
6Barmer Distt375392561352345388916013949259920798821068722895.84262103655038192507921987
7Jsm. Distt.357615202863576438401473127801751533027.531534482580730127
Jodhpur Zone6949714801117736158067450958576943461027910872988543313267154.3347077592241798679782009251409505609719
8Bikaner73606499636518323130096235891268205786794205421.381267043508058901268
9Hanumangarh222631325137834739109658356842359228623912298254.06284352096438068402359
10Sriganganagar3371204225899956291203683288719192988671185278643.7842841328229522865771842
11Churu3751815178410535535186874034931417282892775230933.173351063783870049301417
12127221326141159816217602285163412026263637.4658410243802280516
Total Churu Cir.502383621101194713320309163721193331610121037294534.013931104807908072101933
Bikaner Zone17980200278443627258245629314532881747910473288392810767153.2369160211117192172282149222859777402
Total Discom8747734821902172421064981072411722272271775821346276936124034307.57162378023534290852064158273695463717121
GOR-D-03
Progress of Distribution Companies ( JODHPUR DISCOM)
Status of release of BPL connections FY 2011-12
Upto the Month:-June,11GOR-D-03
Sr. NoName of DistrictBPL families as per Notification of GoR 2002Total BPL/Kutir Jyoti connections released as on 31.03.11Progress of release of BPL Connections FY 2011-12BPL AS ONRURAL DURING MONTH
TargetReleasedBalanceTOTAL GoR-D-2APLBPL
During the monthUpto the monthMMSLVYOTHER
12345678
1Jodhpur3565827928031195-195281239179778931
2Pali531404823300004823389808980
3Sirohi297091355200001355221402140
4Jalore58655429770128273-273432501645603914128
5Barmer74843225285091592925082322620599552-4592
6Jaisalmer1593110433000010433730730
Jodhpur Zone2679361656515091525156050355166211434612522843251
7Bikaner84842408410000408415893182710
8Hanumangarh43386367611101900110193676168406840
9SGNGR634564653092482277917146607887086522
10Churu656505087200005087249304930
11328833170000331722802280
Total Churu Cir.689385418900005418972107210
Bikaner Zone260622178321202672277201901783982881318254122
Total Discom5285583439727118227363770545344609722715705384273
* Recently sanctioned by REC
** Pending for sanction with REC183949
APRIL,102023
852
GOR-D-04(a) Dist. Wise
Progress of Distribution Companies ( JODHPUR DISCOM)
RGGVY Financial Status
Upto the Month:-June,11GOR-D-04 (a)
S.No.Name of Distrcit/DiscomNo. of SchemesSanctioned Cost (Rs. Lacs)Amount Released (in Lacs Rs.)Utilisation (in Lacs Rs.) (Tentavive)% Utilised
1234567
A. Sanctioned Before to Feb-08
1HN.Garh (AREP)1222.85133.72211.95158.50
2SG.Nagar (AREP)1681.69409.01520.84127.34
3Jaisalmer (AREP)1603.53181.06593.00327.52
4Jaisalmer11338.781144.251377.01120.34
5Bikaner12333.901851.602047.76110.59
6Sirohi11236.92963.30998.34103.64
7Jalore12367.411805.321856.00102.81
8Jodhpur12853.852385.922454.84102.89
9Churu11962.481457.311583.14108.63
101116.0687.5780.0091.36
Jodhpur Discom(A)1013717.4710419.0611722.88112.51
B. Sanctioned After Feb-08
1Hanumangarh13256.161634.391560.0095.45
2Sriganganagar13498.462042.10913.3944.73
3Pali (PGCIL)12981.292377.792787.00117.21
4Barmer (PGCIL)120995.8611272.6612055.00106.94
Jodhpur Discom(B)430731.7717326.9417315.3999.93
G.Total (A+B)1444449.2427746.0029038.27104.66
1Jodhpur12853.852385.922454.84102.89
2Pali12981.292377.792787117.21
3Sirohi11236.92963.3998.34103.64
4Jalore12367.411805.321856102.81
5Barmer120995.8611272.6612055106.94
6Jaisalmer21942.311325.311970.01148.65
Jodhpur Zone732377.6420130.322121.19109.89
7Bikaner12333.91851.62047.76110.59
8Hanumangarh23479.011768.111771.95100.22
9SGNGR24180.152451.111434.2358.51
10Churu11962.481457.311583.14108.63
11Nagaur (Ps. Ladnu)1116.0687.578091.36
Total Churu Cir.22078.541544.881663.14107.65
Bikaner Zone712071.67615.76917.0890.83
Total Discom1444449.242774629038.27104.66
GOR-D-04(b) Dist. Wise
Progress of Distribution Companies ( JODHPUR DISCOM)
Coverage & Progress under AREP & RGGVY Progress
Upto the Month:-June,11GOR-D-04 (b)
S.No.Name of DiscomNo. of SchemesCoverage ( Nos)Progress As on Month (Nos)% Achievement
Electrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.DhaniesElectrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.DhaniesElectrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.Dhanies
123456789101112131415161718
A. Sanctioned Before to Feb-08
1HN.Garh (AREP)14605163760460313322730100.000.00607.17604.520.00
2SG.Nagar (AREP)1111012964701110400031620100.000.003100.78488.720.00
3Jaisalmer (AREP)16002561237055035326091.670.0013.6726.350.00
4Jaisalmer19834810112839869983227094690662100.0092.5370.1582.2389.86
5Bikaner120558741481109513718055830744155603787.8095.0674.12142.09100.00
6Sirohi1844724666899151844782461122350100.00100.0033.43124.8298.04
7Jalore13066754217195821630524365892794016100.0078.5667.49142.68100.00
10Jodhpur117388530365396731251738702119856399125100.0098.3169.81142.16100.00
9Churu11184351488244787683135298319538754.5598.5868.561305.80100.00
81097281426090962638505390.0098.9793.751943.46100.00
Jodhpur Discom(A)10742387421604492562394707364814897516079538695.2894.1768.96173.7297.97
B. Sanctioned After Feb-08
1Hanumangarh1132157639319317042132525283002341532100.0033.3171.98738.6476.19
2Sriganganagar1179250544133217253715262034940170902684.9224.7579.1778.6770.27
3Pali (PGCIL)12191529334805517315913366583134713071.4399.78124.97389.1675.14
4Barmer (PGCIL)1668123060124587313782071679363160012230.9913.5815.57272.451.60
Jodhpur Discom(B)41000622617291038823163050622251092618785321050.6035.7463.19226.2912.88
G.Total (A+B)1417421010038895413138520241213587325823624864859669.6358.1566.39189.2529.45
Note:-Figures shown in shaded of column No. 6 (Coverage of Conn. to BPL) have been changed due to actual survey.
1Jodhpur117388530365396731251738702119856399125100.0098.3169.81142.16100.00
2Pali12191529334805517315913366583134713071.4399.78124.97389.1675.14
3Sirohi1844724666899151844782461122350100.00100.0033.43124.8298.04
4Jalore13066754217195821630524365892794016100.0078.5667.49142.68100.00
5Barmer1668123060124587313782071679363160012230.9913.5815.57272.451.60
6Jaisalmer215834810368963569153322712972326296.8492.5368.7675.0689.86
Jodhpur Zone710584492209074918091812586324311918315014240555.3972.2057.01163.5422.35
7Bikaner120558741481109513718055830744155603787.8095.0674.12142.09100.00
8Hanumangarh2178157639835354642178525314332568832100.0033.3178.91724.4276.19
9SGNGR2290250544262223723726362038940202522690.6924.7587.9890.5270.27
10Churu11184351488244787683135298319538754.5598.5868.561305.80100.00
11Nagaur (Ps. Ladnu)1097281426090962638505390.0098.9793.751943.46100.00
Total Churu Cir.21194054302270796692737936370069654.5598.6269.861367.05100.00
Bikaner Zone768456081798803957621262726301390539850619191.6746.9077.30248.9090.09
Total Discom1417421010038895413138520241213587325823624864859669.6358.1566.39189.2529.45
GOR-D-05
Progress of Distribution Companies (JODHPUR DISCOM)
Electrification of Villages & Dhanies FY 2011-12
Upto the Month:-June,11GOR-D-05
S.No.District & CircleElectrification of Dhanies & House Hold under MMSLVY
DhaniesHouseholds
Expected Dhanies less than 100 populationApplicationsDhanies SanctionedConnections CoveredDhanies ElectrifiedConnections Released
Upto 31.3.11FY 2011-12TOTAL% ElectrifiedUpto 31.3.11FY 2011-12TOTAL% OF CONN. ELECT.CANCELLEDBALANCE
During the Monthup to the MonthDuring the Monthup to the MonthGROUPAPPL.GROUPAPPL.
12344567896.16666666676.66666666677.166666666710111213
1Jodhpur54243843939972544229821538302075.5620436972372067381.266835710253617853
2Pali232254321725501630016375.12165500165564.9069888WORK COMPLETED
3Sirohi384153122522002270.9724100241107.1116174WORK COMPLETED
4Jalore1337136531186109305168012764354.224526603956548250.1652862443623338
5Barmer54073558718391142214559191154684.079138552552969084.841931256438328883
6Jaisalmer50245592144681450014567.761110001110237.18223953793526
Jodhpur Zone12940951967484510375283186256553974.0100037106125217453885176.12151114667766053600
7Bikaner276717128125954749095395100479.7557713185706341115.84950556010566764
8Hanumangarh959129589483008387.377800078087.2512132WORK COMPLETED
9SGNGR ***10592810576799009994.2986300863112.52665WORK COMPLETED
10Churu427267630115302410024180.07142500142593.14185124430187
111347066831559005986.7633100331105.0875375110
Total Churu Cir.561338236918453000030081.301756001756198.2166199813260161931197
Bikaner Zone3528223501828898013915395148681.2900091703185709740513.81974870781228737611187158
Total Discom164681175469312600176674239351702575.4400046276157023154859180.96273922043877860758
16468117546924160017667400667472.2216210367000462760046276
BKNR34942
13649
GOR-D-06
Progress of Distribution Companies (JODHPUR DISCOM)
Status of Consumers Grievances Redressal in Chhaupals FY 2011-12
Upto the Month:-June,11GOR-D-06
S.No.Name of Discom/District33/11 KV S/SProgress of Chhaupals organised during the monthProgress of Chhaupals organised upto the month
No of chhaupals heldGrievances receivedRedressalNo of chhaupals heldGrievances receivedRedressal
Related to billsOthersRelated to billsOthers% redressed (7+8)/(5+6)Related to billsOthersRelated to billsOthers% redressed (13+14)/(11+12)
123456789101112131415
1Jodhpur336601117511175100.0015830121130121100000100.00
2Pali1074090419041100.0011022512222512200000100.00
3Sirohi502550135013100.0076137461374600000100.00
4Jalore169581305713057100.0014929211929211900000100.00
5Barmer1681112017512016094.92333774853774500000095.94
6Jaisalmer5235510555110103.1391702951702850000097.85
Jodhpur Zone88219755646655645699.0253515021278150212330000098.38
7Bikaner19115361628971.1537973777250000076.12
8Hanumangarh89219835953597.745824774227720000093.15
9SGNGR1084464316431100.00122178771787700000100.00
10Churu111343710237102100.00101892648926400000100.00
111145959100.00121220122000000100.00
Total Churu Cir.122384211142111100.00113101284101284100.00
Bikaner Zone51011824019322918695.843306234725834580000095.07
Total Discom139231579665978564298.0886521251750208516910000097.45
00000000000000000
16993667557736545428
-1699-3667-5577-3654-542800000000
JPR (During)
GOR-D-07
Progress of Distribution Companies (JODHPUR DISCOM)
Progress of Vigilance Checking
Upto the Month:-June,11GOR-D-07
S. No.Name of DiscomTotal CheckingTheft DetectedRs. In lacs.No .of Complaint/FIRsNo .of Arrests
AssessmentRealisation
Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.
1234567891011121314151617181920
1Jodhpur25932065-20.36713681-4.49118.39123.314.1659.7955.10-7.849518089.47121525.00
2Pali127213324.72105219108.5745.5147.554.4817.2233.4093.96141828.5700
3Sirohi566399-29.51304136.678.269.1310.532.193.5562.10524380.0001
4JALORE664509-23.342825-10.7132.6545.1538.2810.2413.9436.1321224.7612100.00
5Barmer1284212765.65162135-16.6767.59102.2351.2525.0717.46-30.36233343.48110.00
6Jaisalmer141121-14.18375445.9513.7418.8837.417.318.4315.321024140.0000
Jodhpur Zone652065530.51107511557.44286.14346.2521.01121.82131.888.2616830179.17141935.71
7Bikaner76491219.374544815.9549.1363.2228.6822.4543.4993.7249122148.9849125.00
8HMH103611097.05372256-31.1854.2037.78-30.3037.7529.33-22.30233030.43312300.00
9SGNGR13691221-10.81909802-11.7778.1079.341.5935.0041.1617.60445320.45166-62.50
10Churu1070124716.54729107247.0559.5753.65-9.9415.3516.356.5123472-69.2303
11316-80.65252-92.001.400.04-97.140.120.04-66.670000
Bikaner Zone427044955.27248926134.98242.4234.03-3.45110.67130.3717.80350277-20.86233030.43
Other326101-69.0217057-66.4767.9110.12-85.1028.4011.55-59.33517-86.2700
Total11116111490.30373438252.44596.45590.40-1.01260.89273.804.955695852.81374932.43
GOR-D-08
Progress of Distribution Companies (JODHPUR DISCOM)
Progress of feeder Renovation Programme FY 2011-12
Upto the Month:-June,11GOR-D-08
S.No.Name of DiscomFeeders Renovated up to the monthExpected date of completion for feeders convert from B to APhysical ProgressExpenditure (Rs in Crs)% of UtilisationFeeders Renovated up 31.03.09Feeders Renovated during 2009-10Feeders Renovated up 31.03.10Feeders Renovated during 2010-11Feeders Renovated up 31.03.11Feeders Renovated during 2011-12
TargetA- typeB typeTotal (A+B)% Completion
FeedersVillagesFeeders (4+5)Villages getting supply at par with nearby urban TownFeeders (7/3)*100Villages (8/4)*100Installation of small new type 3-phase Xformers (with Mtrs. MCCB etc) in nosInstallation of small new type 1-phase Xformers in nosLaying of AB Cable in Kms.Installation of pushfit type mtrs. In no.SanctionedUtilised Up to the month
123456789101112131415161718
1Jodhpur7771058687907771058100.00100.00195415053458432970406824881966843
2Pali3359153350335915100.00100.001169422019117954618414532963350
3Sirohi1294551290129455100.00100.0055071352107513530345791381290
4Jalore4806974800480697100.00100.001907833751580296911421583001804800
5Barmer4781264417614781264100.00100.001400531863836195602145927311038334
6Jaisalmer1275021270127502100.00100.00178540843732757038108191270
JODHPUR ZONE23264891217515123264891100.00100.0061085175941342317857210505391589549213837
7Bikaner3686623680368662100.00100.0060641112121051960130210340283680
8Han.garh229162922902291629100.00100.0033974287245253402229022902290
9SGNGR214262321402142623100.00100.0050053987404150943214021402140
10Churu24094622713240946100.00100.008352281755897340882371199821710
1130973003097100.00100.0094137958278011301317300
BIKANER ZONE1081595710681310815957100.00100.00237591258213874237514668247915143105810
Discom3407108483243164340710848100.00100.0084844301762729741608617187862504692319647
A type :- Where 1 Phase & 3 Phase transformer work is completed.
B type:- Where 1 Phase transformer work 100 % completed but 3 phase transformer work partially complete.
GoR-D-08(b)
Progress of Distribution Companies (JODHPUR DISCOM)
Statement of Progress of 3 PhaseTransformers under FRP
Upto the Month:-June,11GOR-D-08(b)
S.NoName of Discom / DistrictTotal no of 3 phase transformers to be installed under FRPTotal no of 3 phase transformers installed up to last MonthTotal no of 3 phase transformers installed during the MonthTotal no of 3 phase transformers installed up to the MonthBalance transformers to be installedTotal no of 3 phase transformers installed up to 31.03.09Total no of 3 phase transformers installed during 2009-10Total no of 3 phase transformers installed up to 31.03.10Total no of 3 phase transformers installed during 2010-11Total no of 3 phase transformers installed up to 31.03.11Total no of 3 phase transformers installed during 2011-12
1234567
1Jodhpur204381941812319541897586338909753900118754787
2Pali116911690116904027671169011690
3Sirohi55075507055070144716813128237955070
4JALORE1907819078019078083755312136875391190780
5Barmer145631375025514005558476125947355611213467538
6Jaisalmer178517850178502151325154024517850
JOD.ZONE625406070737861085145521063155693663223128597601325
7Bikaner6064606406064020303781581125360640
8Hanumangarh33973397033970339703397033970
9SGNGR*50055005050050500505005050050
10Churu8384834578352323211183850493276832527
11Nagaur (Ps. Ladnu)94194109410181982796629410
Total B.Z.2379123752723759321382457171954141912373227
Total Discom863318445938584844148734887212865617327319834921352
*Note:- Revised Progress by per SE (Plan) during the month Jan-10
GoR-D-09(a)
JDOHPUR VIDYUT VITRAN NIGAM LTD., JODHPUR
Progress of Distribution Companies
Circle Wise Revenue Analysis
Information Upto :- May,11Reporting Month :- June,11GOR D 09 (A)
S.No.NAME OF CIRCLEFor theAssessment in Lacs Rs.Realisation in Lacs Rs.% RealisationOutstanding in Cr. Rs.
MonthLast YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.Mar.11This Year% Diff.
1C.C. JOD.During3889.353954.641.683599.853982.6610.6392.56100.718.15
Upto May7414.047628.182.896088.316971.2414.5082.1291.399.27109.02115.596.03
2D.C.JOD.During3374.563681.479.092804.063062.369.2183.0983.180.09
Upto May7085.047590.447.135697.915818.302.1180.4276.65-3.7784.51101.7320.37
3JALOREDuring2188.412131.17-2.621565.771726.9210.2971.5581.039.48
Upto May4007.624341.968.342795.873188.9914.0669.7673.453.6827.6939.2041.56
4PALIDuring4765.434585.75-3.774661.764714.931.1497.82102.824.99
Upto May8982.579193.292.357782.367473.36-3.9786.6481.29-5.3513.9230.85121.65
5BARMERDuring2752.592996.118.852289.932532.5210.5983.1984.531.34
Upto May5507.086022.529.364009.934328.727.9572.8171.88-0.9458.8975.8428.79
TOTAL JU. ZONEDuring16970.3417349.142.2314921.3716019.397.3687.9392.344.41
Upto May32996.3534776.395.3926374.3827780.615.3379.9379.88-0.05294.03363.2223.53
6BIKANERDuring3307.043805.4115.073068.733593.6217.1092.7994.431.64
Upto May6361.617295.0914.675607.196027.087.4988.1482.62-5.52150.98163.668.40
7HMHDuring1601.081672.224.441374.291729.7625.8785.84103.4417.61
Upto May3221.393591.1511.482173.032754.4126.7567.4676.709.2412.1720.5368.77
8SGNRDuring2310.312397.313.772161.322456.2613.6593.55102.468.91
Upto May4414.264830.119.423673.473996.388.7983.2282.74-0.4825.2333.5733.04
9CHURUDuring1845.192061.1111.701539.201931.6125.4983.4293.7210.30
Upto May3529.103990.0413.062760.923101.4412.3378.2377.73-0.5079.2488.1311.21
BKN.ZONEDuring9063.629936.059.638143.549711.2519.2589.8597.747.89
Upto May17526.3619706.3912.4414214.6115879.3111.7181.1080.58-0.52267.62305.8914.30
JU.DISCOMDuring26033.9627285.194.8123064.9125730.6411.5688.6094.305.71
Upto May50522.7154482.787.8440588.9943659.927.5780.3480.14-0.20561.65669.1119.13
GoR-D-09(b)
JDOHPUR VIDYUT VITRAN NIGAM LTD., JODHPUR
Progress of Distribution Companies
Circle Wise Revenue Analysis
Information Upto :-May,11Reporting Month :- June,11GOR D 09 (B)
S.No.NAME OF CIRCLEFor theEnergy Available (in LU)Energy Sold (in LU)T&D LossesEnergy Realised in LU% AT&C
MonthLast YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.
1C.C. JOD.During895.08904.201.02835.58844.421.066.656.61-0.04773.38850.409.9613.65.95-7.6592.56100.71
Upto May1917.441920.270.151577.931619.372.6317.7115.67-2.041295.771479.9114.2132.4222.93-9.4982.1291.39
2D.C.JOD.During2596.063238.3224.741628.341953.1719.9537.2839.692.411353.051624.7120.0847.8849.831.9583.0983.18
Upto May4877.375647.6015.793480.223826.499.9528.6532.253.602798.852933.124.8042.6248.065.4480.4276.65
3JALOREDuring1227.081216.38-0.871056.461075.231.7813.9011.60-2.30755.88871.2815.2738.428.37-10.0371.5581.03
Upto May2392.012317.17-3.132011.142059.972.4315.9211.10-4.821403.051512.967.8341.3434.71-6.6369.7673.45
4PALIDuring1248.941598.8228.011101.441190.528.0911.8125.5413.731077.481224.0613.6013.7323.449.7197.82102.82
Upto May2538.503026.3919.222135.822502.8817.1915.8617.301.441850.442034.639.9527.132.775.6786.6481.29
5BARMERDuring1120.201309.7516.92815.45886.118.6727.2032.355.14678.39749.0010.4139.4442.813.3783.1984.53
Upto May2188.502341.436.991756.001891.857.7419.7619.20-0.561278.621359.786.3541.5841.930.3572.8171.88
TOTAL JU. ZONEDuring7087.368267.4716.655437.275949.459.4223.2828.044.764780.785493.4514.9132.5433.551.0187.9392.34
Upto May13913.8215252.869.6210961.1111900.568.5721.2221.980.768761.359506.598.5137.0337.670.6479.9379.88
6BIKANERDuring2121.572712.0327.831420.541730.3721.8133.0436.203.151318.171634.0723.9637.8739.751.8892.7994.43
Upto May3668.744466.2121.742640.793296.4924.8328.0226.19-1.832327.622723.5017.0136.5639.022.4688.1482.62
7HMHDuring628.79581.20-7.57476.15474.83-0.2824.2818.30-5.97408.70491.1720.183515.49-19.5185.84103.44
Upto May1112.691042.74-6.291036.161119.548.056.88-7.37-14.24698.96858.6922.8537.1817.65-19.5367.4676.70
8SGNRDuring661.04656.83-0.64587.39581.70-0.9711.1411.440.30549.51596.008.4616.879.26-7.6193.55102.46
Upto May1376.841349.82-1.961117.431132.701.3718.8416.09-2.76929.91937.180.7832.4630.57-1.8983.2282.74
9CHURUDuring1052.551257.8119.50711.32858.7920.7332.4231.72-0.70593.36804.8335.6443.6336.01-7.6283.4293.72
Upto May1858.082177.7117.201309.151580.5120.7329.5427.42-2.121024.191228.5219.9544.8843.59-1.2978.2377.73
BKN.ZONEDuring4463.955207.8716.673195.43645.6914.0928.4230.001.582871.023563.2124.1135.6831.58-4.189.8597.74
Upto May8016.359036.4812.736103.537129.2416.8123.8621.11-2.764950.225744.7116.0538.2536.43-1.8281.1080.58
JU.DISCOMDuring11551.3113475.3416.668632.679595.1411.1525.2728.793.537648.159048.4718.3133.7932.85-0.9488.6094.30
Upto May21930.1724289.3410.7617064.6419029.8011.5222.1921.65-0.5313709.4115249.5811.2337.4937.22-0.2780.3480.14
GoR-D-09(c)
Progress of Distribution Companies (JODHPUR DISCOM)
Circle wise T&D Losses
Information Upto:-May,11Reporting the Month:-June,11GOR-D-09 (C)
S.No.Name of CircleT & D Loss for previous year 2010-11T & D Loss for current year 2011-12
T & D loss for the MonthT & D loss up to the MonthT & D loss for the MonthT & D loss up to the Month
Energy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D loss
1234567891011121314
1City Jodhpur1022.36835.5818.271917.441577.9317.711016.07844.4216.891920.271619.3715.67
2Distt. Jodhpur2281.311628.3428.624877.373480.2228.652409.281953.1718.935647.603826.4932.25
4Jalore1164.931056.469.312392.012011.1415.921100.791075.232.322317.172059.9711.10
3Pali1289.561101.4414.592538.502135.8215.861427.571190.5216.613026.392502.8817.30
5Barmer1068.30815.4523.672188.501756.0019.761031.68886.1114.112341.431891.8519.20
Total Ju.Zone6826.465437.2720.3513913.8210961.1121.226985.395949.4514.8315252.8611900.5621.98
6Bikaner1547.171420.548.183668.742640.7928.021754.181730.371.364466.213296.4926.19
7Hanumangarh483.90476.151.601112.691036.166.88461.54474.83-2.881042.741119.54-7.37
8SGNGR715.80587.3917.941376.841117.4318.84692.99581.7016.061349.821132.7016.09
9Churu805.53711.3211.701858.081309.1529.54919.90858.796.642177.711580.5127.42
Total Bik. Zone3552.403195.4010.058016.356103.5323.863828.613645.694.789036.487129.2421.11
Total Discom10378.868632.6716.8221930.1717064.6422.1910814.009595.1411.2724289.3419029.8021.65
GoR-D-10
Progress of Distribution Companies (JODHPUR DISCOM)
33 KV Sub-Stations Works Progress
Upto the Month:-June,11GOR-D-10
S.No.Name of Distt. / CircleNo of Gram PanchyatNo of Sub-Station to be installedNo of Sub-Station work order IssuedNo of Sub-Station Commissioned
Rural AreaUrban AreaRural AreaUrban AreaRural AreaUrban Area
Under GPVVYUnder STPUnder GPVVYUnder STPUnder GPVVYUnder STP
123456789101112
1Jodhpur33934171333130000
2Pali31831142911000
3Sirohi14914101310000
4Jalore26812201020000
5Barmer40223201810000
6Jaisalmer12815211421000
Total J.Z.16041292518117202000
7Bikaner21918311551000
8Hanumangarh25116121701000
9SGNGR*3203104903000
10Churu24930501640000
1132300100000
Total B.Z.107198975895000
Total Discom26752273425175297000
No of Gram PanchyatNo of Sub-Station to be installedNo of Sub-Station work order IssuedNo of Sub-Station Commissioned
26752862110
GoR-D-11
Progress of Distribution Companies (JODHPUR DISCOM)
Status of connection pending to release to Government Schools (FY 2011-12)
Upto the Month:-June,11GOR-D-11
S.No.Name of CircleName of DistrictNo. of applications pendingNo. of Demand Notes issued out of col(5)No. of DN depositedNo. of Demand Notes to be issued Col (5-6)No. of connections released up to the monthNo. of connections pending whose D.N. DepositedRemarks (reasons of pendency)Expenditure(Rs in Crs)% of Utilization
As on 31.03.2011 but DN not issuedReceived during FY 11-12Total(3+4)DN deposited as on 31.03.11DN deposited during FY 11-12 out of col(5)
123456789101111121314151617
1CITYJODHPUR000000000
2DISTRICTJODHPUR583896825938143859
TOTAL JODHPUR DISTT.5838968259381438590
3PALIPALI12132515141371512
4SIROHISIROHI21719187151164
5JALOREJALORE4232721272361634
6BARMERBARMER0000301201824
7JAISALMERJAISALMER000084093
JODHPUR ZONE7691167136145105281121360
8BIKANERBIKANER448544353
9HNGH.HNGH.336454181
10SGGNR.SGGNR.088706160
CHURUCHURU1326393584243317
P.S. LADNU314318118
11TOTAL CHURU CIRCLE16274338950534250
BIKANER ZONE2342655418641053290
TOTAL DISCOM99133232190163169381651650
GoR-D-11 E
JODHPUR VIDHYUT VITRAN NIGAM LIMITED,JODHPUR.
STATUS OF CONNECTIONS PENDING TO RELEASE TO GOVT. SCHOOLS
Upto the Month:-June,11
S.noName of CircleName of DistrictSTATUS AS ON 1.4.2011APPL. RECD./ RE-OPEN DURING 2011-12TOTALD.N. ISSUED UPTO REPORT MONTH 2011-12D.N. DEPO. UPTO REPORT MONTH 2011-12APPLI. CANCEL UP TO REPORT MONTH PRIOR D.N. ISSUEDAPPLI. CANCEL UP TO REPORT MONTH PRIOR D.N. DEPO.APPLI. CANCEL UP TO REPORT MONTH AFTER D.N. DEPO.CONNE. RELEASED UPTO REPORT MONTH 2011-12APPLICATIONS PENDING AT THE END OF THE MONTH
D.N. DEPO. BUT CONN. NOT RELE.D.N. ISSUED BUT NOT DEPO.D.N. TO BE ISSUEDTOTALD.N. DEPO. BUT CONN. NOT RELE.D.N. ISSUED BUT NOT DEPO.D.N. TO BE ISSUEDTOTAL
D.N.DEP.D.N.D.N.TOTAL(10+11)(10+11)
12345678910111213141516171819
1CITYJODHPUR0000000000000000
2DISTRICTJODHPUR595858175382138238063038593914112
TOTAL JODHPUR DISTT.595858175382138238063038593914112
3PALIPALI14212281341151330015124723
4SIROHISIROHI7321217291815052164116
5JALOREJALORE2774382361212304016341641
6BARMERBARMER301204204201200018240024
7JAISALMERJAISALMER840120120400093003
JODHPUR ZONE14586763079139813610537221121364528209
8BIKANERBIKANER4541341754000536312
9HNGH.HNGH.51393124410081113
10SGGNR.SGGNR.03038117600060415
CHURUCHURU82213432669354209033176427
P.S. LADNU15391103800018019
11TOTAL CHURU CIRCLE92716522779385009034256536
BIKANER ZONE183623774211954641905329171056
TOTAL DISCOM1631229938413351719016948121651656238265
Sheet1
Gen.AG connections 1st Phase DN. Issue Status FY 2011-12*
sheet 1 (2)
JODHPUR VIDHYUT VITRAN NIGAM LIMITED,JODHPUR
DISTRICTWISE AGRICULTURE(GENERALCAT.)D.N. ISSUED DURING 1ST PHASE
S.N.Name of CircleName of DistrictD.N. TO BE ISSUED IN 1ST PHASE (APPLICATIONS RECEIVED JAN.08 TO SEPT.08)D.N. ISSUED IN 1ST PHASE (16.04.11 TO 15.05.11) 25%D.N. ISSUED IN 1ST PHASE (16.05.11 TO 15.06.11) 25%
123478
1CITY CIRCLEJODHPUR000
2DISTT.CIRCLEJODHPUR732430821406
TOTALJODHPUR732430821406
4PALI CIRCLEPALI1061340242
SIROHI833243196
3JALORE CIRCLEJALORE3458196704
5BARMER CIRCLEBARMER2188549547
JAISALMER700171175
TOTAL JODHPUR ZONE1556445813270
6BIKANER CIRCLEBIKANER3281824783
7HANUMANGARHHNGH1766443462
8SRIGANGANAGARSGGNR906229229
9CHURU CIRCLECHURU1813468466
PS LADNU18211
TOTAL CHURU CIRCLE1831470477
TOTAL BIKANER ZONE778419661951
TOTAL DISCOM2334865475221
Information included Re-opened and specify Priorty Applications.
Applications received January 2008 to September 2008(of which DN to be issued ) will be revised by adding overridig priorty Applications.
sheet 1
JODHPUR VIDHYUT VITRAN NIGAM LIMITED,JODHPUR
DISTRICTWISE AGRICULTURE(GENERALCAT.)D.N. ISSUED DURING 1ST PHASE
S.N.Name of CircleName of DistrictD.N. TO BE ISSUED IN 1ST PHASE (APPLI. RECEIVED JAN.08 TO SEPT.08)Re-opened/ specified overriding priorty filesTOTALD.N. ISSUED IN 1ST PHASE (16.04.11 TO 15.05.11) 25%D.N. ISSUED IN 1ST PHASE (16.05.11 TO 15.06.11) 25%Total Upto 15.06.11Total DN Issued Up to 30.6.11
122345678910
1CITY CIRCLEJODHPUR000000
2DISTT.CIRCLEJODHPUR562417007324308214064488549344893924
TOTALJODHPUR562417007324308214064488549344893924
3PALI CIRCLEPALI968931061340242582796582875
4SIROHI78449833243196439625443735
5JALORE CIRCLEJALORE33331253458196704900259417573208
6BARMER CIRCLEBARMER2188021885495471096164110922188
7JAISALMER7000700171175346525394700
TOTAL JODHPUR ZONE1359719671556445813270785111673875711630
8BIKANER CIRCLEBIKANER3281032818247831607246116453281
9HANUMANGARHHNGH172343176644346290513259961680
10SRIGANGANAGARSGGNR9060906229229458680524906
11CHURU CIRCLECHURU1783301813468466934136012611753
12PS LADNU99182111314150
TOTAL CHURU CIRCLE1792391831470477947137312761753
TOTAL BIKANER ZONE7702827784196619513917583844417620
TOTAL DISCOM212992049233486547522111768175111319819250
Information included Re-opened and specify Priorty Applications.
Applications received January 2008 to September 2008(of which DN to be issued ) will be revised by adding overridig priorty Applications.
Status of release of DL connections during FY 2011-12*
Name GOR-D
GOR-D
1 TO 11 For The Month of June, 2011
Jodhpur Discom
GOR-D-01
Progress of Distribution Companies ( JODHPUR DISCOM) REVISED
Status of AG. DN deposited & connections Released
Upto the Month:-June,11GOR-D-01
Sr. No.Name of DistrictNo of DN issued During 2011-12DN depositedAg. Connections released During 2011-12 out of Colmn. 8% Connection Released of Col.8Cancelled after D.N. Deposited During 2011-12Balance Pending for connection
As on 31.03.11During 2011-12Total DN Deposited
GENERAL CATEGORYOTHERSDuring the monthUpto the monthDuring the monthUpto the month
12345678910111213
1Jodhpur448948449736493781174182322731717.39161490796
2Pali582366186317341447713367.555436241
3Sirohi44319563825427044770111415.853657177
4Jalore17571111868229718987121643826.74121122269
5Barmer10924781570227368618845159911.723743250
6Jaisalmer3944343715511214530022227.33027833
Jodhpur Zone8757134710104157720193785536233159711.133947261766
7Bikaner16451064270929280714100618737537.280631634
8HMH9968310792052024036084814123.190467201
9SGNR524238762117253653715397.260498364
10Churu126178320446626780487016718821.610682537
1115116111314000.0001412
Total Churu Cir.127678420606726881788416718821.610696549
Bikaner Zone4441216966105657222470303541774324.48022921748
Total Discom131983516167142142274162558397748134015.963970183514
DN ISSUEDDN DEPOSITEDCANCELLEDPENDING
JLRBMRJSMRJLRBMRJSMRJLRBMRJSMRJLRBMRJSMR
86RE-7 SC18532261133325473006719734
1393RE-9 GEN0548576711485218010701295819
RE-10 SPL00025
RE-11 FH000000000000
RE-11A DRIP8118532671473300027525
RE-11B DIGGI000
TOTAL2665121417761183565248011891544858
CONNECTION
JLRBMRJSMR
RE-7 SC14923573
RE-9 GEN880807344
RE-10 SPL1700
RE-11 FH000
RE-11A DRIP4010330
RE-11B DIGGI00
TOTAL10861145447
DN ISSUEDDN DEPOSITEDCANCELLEDPENDING
DCPALISIROHIDCPALISIROHIDCPALISIROHIDCPALISIROHI
RE-7 SC426751594707216900010349179
RE-8 TSP11645073
RE-9 GEN80615144213116031421252402696
RE-10 SPL10
RE-11 FH212611180120114
RE-11A DRIP323367030035380002474
RE-11B DIGGI
TOTAL831129366221324942031541379469966
CONNECTION
DCPALISIROHI
RE-7 SC50760144
RE-8 TSP536405
RE-9 GEN22703442906476
RE-10 SPL171
RE-11 FH1108
RE-11A DRIP2763334
RE-11B DIGGI
TOTAL3054447530
GOR-D-2
JODHPUR DISCOM
Status of release of DL connections during FY 2011-12
Upto the Month :-June,11GOR-D-02
S.NoName of Distt./CircleApplication for DL connections pendingApplication for DL connections pendingconnections released During 2011-12Cancelled up the month out of (3) & (4)Pending at the end of Reporting month
As on 31.03.11Received during FY 2011-12RuralUrbanTotalRuralUrbanTotal released
RuralUrbanRuralUrbanDuring the monthup to the monthDuring the monthup to the monthDuring the monthup to the monthRuralUrbanRuralUrbanBPL DURING monthAPL DURING monthBPL DURING 2011-12APL DURING 2011-12
123456345678910111212131415
1City Circle021101523017341734005091372509137279.120003620000
2Distt. Circle176201243494126211142502136491721503891955224110.72457718507152318861951955
Total JU Distt.176203353494164921114198423098917215054714631464361315.96457718507514318861951955
3Pali Distt.3858510352179373791303868289827172367351134345243.10622504040518089802717
4Sirohi Distt.653101736292138939317822145485522826977644.8646679515902140548
5Jalore Circle625112620742508325376870116452658811771726283537.05102920463817912815172732385
6Barmer Distt375392561352345388916013949259920798821068722895.84262103655038192507921987
7Jsm. Distt.357615202863576438401473127801751533027.531534482580730127
Jodhpur Zone6949714801117736158067450958576943461027910872988543313267154.3347077592241798679782009251409505609719
8Bikaner73606499636518323130096235891268205786794205421.381267043508058901268
9HMH222631325137834739109658356842359228623912298254.06284352096438068402359
10SGNR3371204225899956291203683288719192988671185278643.7842841328229522865771842
11Churu3751815178410535535186874034931417282892775230933.173351063783870049301417
12127221326141159816217602285163412026263637.4658410243802280516
Total Churu Cir.502383621101194713320309163721193331610121037294534.013931104807908072101933
Bikaner Zone17980200278443627258245629314532881747910473288392810767153.2369160211117192172282149222859777402
Total Discom8747734821902172421064981072411722272271775821346276936124034307.57162378023534290852064158273695463717121
GOR-D-03
Progress of Distribution Companies ( JODHPUR DISCOM)
Status of release of BPL connections FY 2011-12
Upto the Month:-June,11GOR-D-03
Sr. NoName of DistrictBPL families as per Notification of GoR 2002Total BPL/Kutir Jyoti connections released as on 31.03.11Progress of release of BPL Connections FY 2011-12BPL AS ONRURAL DURING MONTH
TargetReleasedBalanceTOTAL GoR-D-2APLBPL
During the monthUpto the monthMMSLVYOTHER
12345678
1Jodhpur3565827928031195-195281239179778931
2Pali531404823300004823389808980
3Sirohi297091355200001355221402140
4Jalore58655429770128273-273432501645603914128
5Barmer74843225285091592925082322620599552-4592
6Jaisalmer1593110433000010433730730
Jodhpur Zone2679361656515091525156050355166211434612522843251
7Bikaner84842408410000408415893182710
8Hanumangarh43386367611101900110193676168406840
9SGNGR634564653092482277917146607887086522
10Churu656505087200005087249304930
11328833170000331722802280
Total Churu Cir.689385418900005418972107210
Bikaner Zone260622178321202672277201901783982881318254122
Total Discom5285583439727118227363770545344609722715705384273
* Recently sanctioned by REC
** Pending for sanction with REC183949
APRIL,102023
852
GOR-D-04(a) Dist. Wise
Progress of Distribution Companies ( JODHPUR DISCOM)
RGGVY Financial Status
Upto the Month:-June,11GOR-D-04 (a)
S.No.Name of Distrcit/DiscomNo. of SchemesSanctioned Cost (Rs. Lacs)Amount Released (in Lacs Rs.)Utilisation (in Lacs Rs.) (Tentavive)% Utilised
1234567
A. Sanctioned Before to Feb-08
1HN.Garh (AREP)1222.85133.72211.95158.50
2SG.Nagar (AREP)1681.69409.01520.84127.34
3Jaisalmer (AREP)1603.53181.06593.00327.52
4Jaisalmer11338.781144.251377.01120.34
5Bikaner12333.901851.602047.76110.59
6Sirohi11236.92963.30998.34103.64
7Jalore12367.411805.321856.00102.81
8Jodhpur12853.852385.922454.84102.89
9Churu11962.481457.311583.14108.63
101116.0687.5780.0091.36
Jodhpur Discom(A)1013717.4710419.0611722.88112.51
B. Sanctioned After Feb-08
1Hanumangarh13256.161634.391560.0095.45
2Sriganganagar13498.462042.10913.3944.73
3Pali (PGCIL)12981.292377.792787.00117.21
4Barmer (PGCIL)120995.8611272.6612055.00106.94
Jodhpur Discom(B)430731.7717326.9417315.3999.93
G.Total (A+B)1444449.2427746.0029038.27104.66
1Jodhpur12853.852385.922454.84102.89
2Pali12981.292377.792787117.21
3Sirohi11236.92963.3998.34103.64
4Jalore12367.411805.321856102.81
5Barmer120995.8611272.6612055106.94
6Jaisalmer21942.311325.311970.01148.65
Jodhpur Zone732377.6420130.322121.19109.89
7Bikaner12333.91851.62047.76110.59
8Hanumangarh23479.011768.111771.95100.22
9SGNGR24180.152451.111434.2358.51
10Churu11962.481457.311583.14108.63
11Nagaur (Ps. Ladnu)1116.0687.578091.36
Total Churu Cir.22078.541544.881663.14107.65
Bikaner Zone712071.67615.76917.0890.83
Total Discom1444449.242774629038.27104.66
GOR-D-04(b) Dist. Wise
Progress of Distribution Companies ( JODHPUR DISCOM)
Coverage & Progress under AREP & RGGVY Progress
Upto the Month:-June,11GOR-D-04 (b)
S.No.Name of DiscomNo. of SchemesCoverage ( Nos)Progress As on Month (Nos)% Achievement
Electrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.DhaniesElectrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.DhaniesElectrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.Dhanies
123456789101112131415161718
A. Sanctioned Before to Feb-08
1HN.Garh (AREP)14605163760460313322730100.000.00607.17604.520.00
2SG.Nagar (AREP)1111012964701110400031620100.000.003100.78488.720.00
3Jaisalmer (AREP)16002561237055035326091.670.0013.6726.350.00
4Jaisalmer19834810112839869983227094690662100.0092.5370.1582.2389.86
5Bikaner120558741481109513718055830744155603787.8095.0674.12142.09100.00
6Sirohi1844724666899151844782461122350100.00100.0033.43124.8298.04
7Jalore13066754217195821630524365892794016100.0078.5667.49142.68100.00
10Jodhpur117388530365396731251738702119856399125100.0098.3169.81142.16100.00
9Churu11184351488244787683135298319538754.5598.5868.561305.80100.00
81097281426090962638505390.0098.9793.751943.46100.00
Jodhpur Discom(A)10742387421604492562394707364814897516079538695.2894.1768.96173.7297.97
B. Sanctioned After Feb-08
1Hanumangarh1132157639319317042132525283002341532100.0033.3171.98738.6476.19
2Sriganganagar1179250544133217253715262034940170902684.9224.7579.1778.6770.27
3Pali (PGCIL)12191529334805517315913366583134713071.4399.78124.97389.1675.14
4Barmer (PGCIL)1668123060124587313782071679363160012230.9913.5815.57272.451.60
Jodhpur Discom(B)41000622617291038823163050622251092618785321050.6035.7463.19226.2912.88
G.Total (A+B)1417421010038895413138520241213587325823624864859669.6358.1566.39189.2529.45
Note:-Figures shown in shaded of column No. 6 (Coverage of Conn. to BPL) have been changed due to actual survey.
1Jodhpur117388530365396731251738702119856399125100.0098.3169.81142.16100.00
2Pali12191529334805517315913366583134713071.4399.78124.97389.1675.14
3Sirohi1844724666899151844782461122350100.00100.0033.43124.8298.04
4Jalore13066754217195821630524365892794016100.0078.5667.49142.68100.00
5Barmer1668123060124587313782071679363160012230.9913.5815.57272.451.60
6Jaisalmer215834810368963569153322712972326296.8492.5368.7675.0689.86
Jodhpur Zone710584492209074918091812586324311918315014240555.3972.2057.01163.5422.35
7Bikaner120558741481109513718055830744155603787.8095.0674.12142.09100.00
8Hanumangarh2178157639835354642178525314332568832100.0033.3178.91724.4276.19
9SGNGR2290250544262223723726362038940202522690.6924.7587.9890.5270.27
10Churu11184351488244787683135298319538754.5598.5868.561305.80100.00
11Nagaur (Ps. Ladnu)1097281426090962638505390.0098.9793.751943.46100.00
Total Churu Cir.21194054302270796692737936370069654.5598.6269.861367.05100.00
Bikaner Zone768456081798803957621262726301390539850619191.6746.9077.30248.9090.09
Total Discom1417421010038895413138520241213587325823624864859669.6358.1566.39189.2529.45
GOR-D-05
Progress of Distribution Companies (JODHPUR DISCOM)
Electrification of Villages & Dhanies FY 2011-12
Upto the Month:-June,11GOR-D-05
S.No.District & CircleElectrification of Dhanies & House Hold under MMSLVY
DhaniesHouseholds
Expected Dhanies less than 100 populationApplicationsDhanies SanctionedConnections CoveredDhanies ElectrifiedConnections Released
Upto 31.3.11FY 2011-12TOTAL% ElectrifiedUpto 31.3.11FY 2011-12TOTAL% OF CONN. ELECT.CANCELLEDBALANCE
During the Monthup to the MonthDuring the Monthup to the MonthGROUPAPPL.GROUPAPPL.
12344567896.16666666676.66666666677.166666666710111213
1Jodhpur54243843939972544229821538302075.5620436972372067381.266835710253617853
2Pali232254321725501630016375.12165500165564.9069888WORK COMPLETED
3Sirohi384153122522002270.9724100241107.1116174WORK COMPLETED
4Jalore1337136531186109305168012764354.224526603956548250.1652862443623338
5Barmer54073558718391142214559191154684.079138552552969084.841931256438328883
6Jaisalmer50245592144681450014567.761110001110237.18223953793526
Jodhpur Zone12940951967484510375283186256553974.0100037106125217453885176.12151114667766053600
7Bikaner276717128125954749095395100479.7557713185706341115.84950556010566764
8Hanumangarh959129589483008387.377800078087.2512132WORK COMPLETED
9SGNGR ***10592810576799009994.2986300863112.52665WORK COMPLETED
10Churu427267630115302410024180.07142500142593.14185124430187
111347066831559005986.7633100331105.0875375110
Total Churu Cir.561338236918453000030081.301756001756198.2166199813260161931197
Bikaner Zone3528223501828898013915395148681.2900091703185709740513.81974870781228737611187158
Total Discom164681175469312600176674239351702575.4400046276157023154859180.96273922043877860758
16468117546924160017667400667472.2216210367000462760046276
BKNR34942
13649
GOR-D-06
Progress of Distribution Companies (JODHPUR DISCOM)
Status of Consumers Grievances Redressal in Chhaupals FY 2011-12
Upto the Month:-June,11GOR-D-06
S.No.Name of Discom/District33/11 KV S/SProgress of Chhaupals organised during the monthProgress of Chhaupals organised upto the month
No of chhaupals heldGrievances receivedRedressalNo of chhaupals heldGrievances receivedRedressal
Related to billsOthersRelated to billsOthers% redressed (7+8)/(5+6)Related to billsOthersRelated to billsOthers% redressed (13+14)/(11+12)
123456789101112131415
1Jodhpur336601117511175100.0015830121130121100000100.00
2Pali1074090419041100.0011022512222512200000100.00
3Sirohi502550135013100.0076137461374600000100.00
4Jalore169581305713057100.0014929211929211900000100.00
5Barmer1681112017512016094.92333774853774500000095.94
6Jaisalmer5235510555110103.1391702951702850000097.85
Jodhpur Zone88219755646655645699.0253515021278150212330000098.38
7Bikaner19115361628971.1537973777250000076.12
8Hanumangarh89219835953597.745824774227720000093.15
9SGNGR1084464316431100.00122178771787700000100.00
10Churu111343710237102100.00101892648926400000100.00
111145959100.00121220122000000100.00
Total Churu Cir.122384211142111100.00113101284101284100.00
Bikaner Zone51011824019322918695.843306234725834580000095.07
Total Discom139231579665978564298.0886521251750208516910000097.45
00000000000000000
16993667557736545428
-1699-3667-5577-3654-542800000000
JPR (During)
GOR-D-07
Progress of Distribution Companies (JODHPUR DISCOM)
Progress of Vigilance Checking
Upto the Month:-June,11GOR-D-07
S. No.Name of DiscomTotal CheckingTheft DetectedRs. In lacs.No .of Complaint/FIRsNo .of Arrests
AssessmentRealisation
Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.
1234567891011121314151617181920
1Jodhpur25932065-20.36713681-4.49118.39123.314.1659.7955.10-7.849518089.47121525.00
2Pali127213324.72105219108.5745.5147.554.4817.2233.4093.96141828.5700
3Sirohi566399-29.51304136.678.269.1310.532.193.5562.10524380.0001
4JALORE664509-23.342825-10.7132.6545.1538.2810.2413.9436.1321224.7612100.00
5Barmer1284212765.65162135-16.6767.59102.2351.2525.0717.46-30.36233343.48110.00
6Jaisalmer141121-14.18375445.9513.7418.8837.417.318.4315.321024140.0000
Jodhpur Zone652065530.51107511557.44286.14346.2521.01121.82131.888.2616830179.17141935.71
7Bikaner76491219.374544815.9549.1363.2228.6822.4543.4993.7249122148.9849125.00
8HMH103611097.05372256-31.1854.2037.78-30.3037.7529.33-22.30233030.43312300.00
9SGNGR13691221-10.81909802-11.7778.1079.341.5935.0041.1617.60445320.45166-62.50
10Churu1070124716.54729107247.0559.5753.65-9.9415.3516.356.5123472-69.2303
11316-80.65252-92.001.400.04-97.140.120.04-66.670000
Bikaner Zone427044955.27248926134.98242.4234.03-3.45110.67130.3717.80350277-20.86233030.43
Other326101-69.0217057-66.4767.9110.12-85.1028.4011.55-59.33517-86.2700
Total11116111490.30373438252.44596.45590.40-1.01260.89273.804.955695852.81374932.43
GOR-D-08
Progress of Distribution Companies (JODHPUR DISCOM)
Progress of feeder Renovation Programme FY 2011-12
Upto the Month:-June,11GOR-D-08
S.No.Name of DiscomFeeders Renovated up to the monthExpected date of completion for feeders convert from B to APhysical ProgressExpenditure (Rs in Crs)% of UtilisationFeeders Renovated up 31.03.09Feeders Renovated during 2009-10Feeders Renovated up 31.03.10Feeders Renovated during 2010-11Feeders Renovated up 31.03.11Feeders Renovated during 2011-12
TargetA- typeB typeTotal (A+B)% Completion
FeedersVillagesFeeders (4+5)Villages getting supply at par with nearby urban TownFeeders (7/3)*100Villages (8/4)*100Installation of small new type 3-phase Xformers (with Mtrs. MCCB etc) in nosInstallation of small new type 1-phase Xformers in nosLaying of AB Cable in Kms.Installation of pushfit type mtrs. In no.SanctionedUtilised Up to the month
123456789101112131415161718
1Jodhpur7771058687907771058100.00100.00195415053458432970406824881966843
2Pali3359153350335915100.00100.001169422019117954618414532963350
3Sirohi1294551290129455100.00100.0055071352107513530345791381290
4Jalore4806974800480697100.00100.001907833751580296911421583001804800
5Barmer4781264417614781264100.00100.001400531863836195602145927311038334
6Jaisalmer1275021270127502100.00100.00178540843732757038108191270
JODHPUR ZONE23264891217515123264891100.00100.0061085175941342317857210505391589549213837
7Bikaner3686623680368662100.00100.0060641112121051960130210340283680
8Han.garh229162922902291629100.00100.0033974287245253402229022902290
9SGNGR214262321402142623100.00100.0050053987404150943214021402140
10Churu24094622713240946100.00100.008352281755897340882371199821710
1130973003097100.00100.0094137958278011301317300
BIKANER ZONE1081595710681310815957100.00100.00237591258213874237514668247915143105810
Discom3407108483243164340710848100.00100.0084844301762729741608617187862504692319647
A type :- Where 1 Phase & 3 Phase transformer work is completed.
B type:- Where 1 Phase transformer work 100 % completed but 3 phase transformer work partially complete.
GoR-D-08(b)
Progress of Distribution Companies (JODHPUR DISCOM)
Statement of Progress of 3 PhaseTransformers under FRP
Upto the Month:-June,11GOR-D-08(b)
S.NoName of Discom / DistrictTotal no of 3 phase transformers to be installed under FRPTotal no of 3 phase transformers installed up to last MonthTotal no of 3 phase transformers installed during the MonthTotal no of 3 phase transformers installed up to the MonthBalance transformers to be installedTotal no of 3 phase transformers installed up to 31.03.09Total no of 3 phase transformers installed during 2009-10Total no of 3 phase transformers installed up to 31.03.10Total no of 3 phase transformers installed during 2010-11Total no of 3 phase transformers installed up to 31.03.11Total no of 3 phase transformers installed during 2011-12
1234567
1Jodhpur204381941812319541897586338909753900118754787
2Pali116911690116904027671169011690
3Sirohi55075507055070144716813128237955070
4JALORE1907819078019078083755312136875391190780
5Barmer145631375025514005558476125947355611213467538
6Jaisalmer178517850178502151325154024517850
JOD.ZONE625406070737861085145521063155693663223128597601325
7Bikaner6064606406064020303781581125360640
8Hanumangarh33973397033970339703397033970
9SGNGR*50055005050050500505005050050
10Churu8384834578352323211183850493276832527
11Nagaur (Ps. Ladnu)94194109410181982796629410
Total B.Z.2379123752723759321382457171954141912373227
Total Discom863318445938584844148734887212865617327319834921352
*Note:- Revised Progress by per SE (Plan) during the month Jan-10
GoR-D-09(a)
JDOHPUR VIDYUT VITRAN NIGAM LTD., JODHPUR
Progress of Distribution Companies
Circle Wise Revenue Analysis
Information Upto :- May,11Reporting Month :- June,11GOR D 09 (A)
S.No.NAME OF CIRCLEFor theAssessment in Lacs Rs.Realisation in Lacs Rs.% RealisationOutstanding in Cr. Rs.
MonthLast YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.Mar.11This Year% Diff.
1C.C. JOD.During3889.353954.641.683599.853982.6610.6392.56100.718.15
Upto May7414.047628.182.896088.316971.2414.5082.1291.399.27109.02115.596.03
2D.C.JOD.During3374.563681.479.092804.063062.369.2183.0983.180.09
Upto May7085.047590.447.135697.915818.302.1180.4276.65-3.7784.51101.7320.37
3JALOREDuring2188.412131.17-2.621565.771726.9210.2971.5581.039.48
Upto May4007.624341.968.342795.873188.9914.0669.7673.453.6827.6939.2041.56
4PALIDuring4765.434585.75-3.774661.764714.931.1497.82102.824.99
Upto May8982.579193.292.357782.367473.36-3.9786.6481.29-5.3513.9230.85121.65
5BARMERDuring2752.592996.118.852289.932532.5210.5983.1984.531.34
Upto May5507.086022.529.364009.934328.727.9572.8171.88-0.9458.8975.8428.79
TOTAL JU. ZONEDuring16970.3417349.142.2314921.3716019.397.3687.9392.344.41
Upto May32996.3534776.395.3926374.3827780.615.3379.9379.88-0.05294.03363.2223.53
6BIKANERDuring3307.043805.4115.073068.733593.6217.1092.7994.431.64
Upto May6361.617295.0914.675607.196027.087.4988.1482.62-5.52150.98163.668.40
7HMHDuring1601.081672.224.441374.291729.7625.8785.84103.4417.61
Upto May3221.393591.1511.482173.032754.4126.7567.4676.709.2412.1720.5368.77
8SGNRDuring2310.312397.313.772161.322456.2613.6593.55102.468.91
Upto May4414.264830.119.423673.473996.388.7983.2282.74-0.4825.2333.5733.04
9CHURUDuring1845.192061.1111.701539.201931.6125.4983.4293.7210.30
Upto May3529.103990.0413.062760.923101.4412.3378.2377.73-0.5079.2488.1311.21
BKN.ZONEDuring9063.629936.059.638143.549711.2519.2589.8597.747.89
Upto May17526.3619706.3912.4414214.6115879.3111.7181.1080.58-0.52267.62305.8914.30
JU.DISCOMDuring26033.9627285.194.8123064.9125730.6411.5688.6094.305.71
Upto May50522.7154482.787.8440588.9943659.927.5780.3480.14-0.20561.65669.1119.13
GoR-D-09(b)
JDOHPUR VIDYUT VITRAN NIGAM LTD., JODHPUR
Progress of Distribution Companies
Circle Wise Revenue Analysis
Information Upto :-May,11Reporting Month :- June,11GOR D 09 (B)
S.No.NAME OF CIRCLEFor theEnergy Available (in LU)Energy Sold (in LU)T&D LossesEnergy Realised in LU% AT&C
MonthLast YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.Last YearThis Year% Diff.
1C.C. JOD.During895.08904.201.02835.58844.421.066.656.61-0.04773.38850.409.9613.65.95-7.6592.56100.71
Upto May1917.441920.270.151577.931619.372.6317.7115.67-2.041295.771479.9114.2132.4222.93-9.4982.1291.39
2D.C.JOD.During2596.063238.3224.741628.341953.1719.9537.2839.692.411353.051624.7120.0847.8849.831.9583.0983.18
Upto May4877.375647.6015.793480.223826.499.9528.6532.253.602798.852933.124.8042.6248.065.4480.4276.65
3JALOREDuring1227.081216.38-0.871056.461075.231.7813.9011.60-2.30755.88871.2815.2738.428.37-10.0371.5581.03
Upto May2392.012317.17-3.132011.142059.972.4315.9211.10-4.821403.051512.967.8341.3434.71-6.6369.7673.45
4PALIDuring1248.941598.8228.011101.441190.528.0911.8125.5413.731077.481224.0613.6013.7323.449.7197.82102.82
Upto May2538.503026.3919.222135.822502.8817.1915.8617.301.441850.442034.639.9527.132.775.6786.6481.29
5BARMERDuring1120.201309.7516.92815.45886.118.6727.2032.355.14678.39749.0010.4139.4442.813.3783.1984.53
Upto May2188.502341.436.991756.001891.857.7419.7619.20-0.561278.621359.786.3541.5841.930.3572.8171.88
TOTAL JU. ZONEDuring7087.368267.4716.655437.275949.459.4223.2828.044.764780.785493.4514.9132.5433.551.0187.9392.34
Upto May13913.8215252.869.6210961.1111900.568.5721.2221.980.768761.359506.598.5137.0337.670.6479.9379.88
6BIKANERDuring2121.572712.0327.831420.541730.3721.8133.0436.203.151318.171634.0723.9637.8739.751.8892.7994.43
Upto May3668.744466.2121.742640.793296.4924.8328.0226.19-1.832327.622723.5017.0136.5639.022.4688.1482.62
7HMHDuring628.79581.20-7.57476.15474.83-0.2824.2818.30-5.97408.70491.1720.183515.49-19.5185.84103.44
Upto May1112.691042.74-6.291036.161119.548.056.88-7.37-14.24698.96858.6922.8537.1817.65-19.5367.4676.70
8SGNRDuring661.04656.83-0.64587.39581.70-0.9711.1411.440.30549.51596.008.4616.879.26-7.6193.55102.46
Upto May1376.841349.82-1.961117.431132.701.3718.8416.09-2.76929.91937.180.7832.4630.57-1.8983.2282.74
9CHURUDuring1052.551257.8119.50711.32858.7920.7332.4231.72-0.70593.36804.8335.6443.6336.01-7.6283.4293.72
Upto May1858.082177.7117.201309.151580.5120.7329.5427.42-2.121024.191228.5219.9544.8843.59-1.2978.2377.73
BKN.ZONEDuring4463.955207.8716.673195.43645.6914.0928.4230.001.582871.023563.2124.1135.6831.58-4.189.8597.74
Upto May8016.359036.4812.736103.537129.2416.8123.8621.11-2.764950.225744.7116.0538.2536.43-1.8281.1080.58
JU.DISCOMDuring11551.3113475.3416.668632.679595.1411.1525.2728.793.537648.159048.4718.3133.7932.85-0.9488.6094.30
Upto May21930.1724289.3410.7617064.6419029.8011.5222.1921.65-0.5313709.4115249.5811.2337.4937.22-0.2780.3480.14
GoR-D-09(c)
Progress of Distribution Companies (JODHPUR DISCOM)
Circle wise T&D Losses
Information Upto:-May,11Reporting the Month:-June,11GOR-D-09 (C)
S.No.Name of CircleT & D Loss for previous year 2010-11T & D Loss for current year 2011-12
T & D loss for the MonthT & D loss up to the MonthT & D loss for the MonthT & D loss up to the Month
Energy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D loss
1234567891011121314
1City Jodhpur1022.36835.5818.271917.441577.9317.711016.07844.4216.891920.271619.3715.67
2Distt. Jodhpur2281.311628.3428.624877.373480.2228.652409.281953.1718.935647.603826.4932.25
4Jalore1164.931056.469.312392.012011.1415.921100.791075.232.322317.172059.9711.10
3Pali1289.561101.4414.592538.502135.8215.861427.571190.5216.613026.392502.8817.30
5Barmer1068.30815.4523.672188.501756.0019.761031.68886.1114.112341.431891.8519.20
Total Ju.Zone6826.465437.2720.3513913.8210961.1121.226985.395949.4514.8315252.8611900.5621.98
6Bikaner1547.171420.548.183668.742640.7928.021754.181730.371.364466.213296.4926.19
7Hanumangarh483.90476.151.601112.691036.166.88461.54474.83-2.881042.741119.54-7.37
8SGNGR715.80587.3917.941376.841117.4318.84692.99581.7016.061349.821132.7016.09
9Churu805.53711.3211.701858.081309.1529.54919.90858.796.642177.711580.5127.42
Total Bik. Zone3552.403195.4010.058016.356103.5323.863828.613645.694.789036.487129.2421.11
Total Discom10378.868632.6716.8221930.1717064.6422.1910814.009595.1411.2724289.3419029.8021.65
GoR-D-10
Progress of Distribution Companies (JODHPUR DISCOM)
33 KV Sub-Stations Works Progress
Upto the Month:-June,11GOR-D-10
S.No.Name of Distt. / CircleNo of Gram PanchyatNo of Sub-Station to be installedNo of Sub-Station work order IssuedNo of Sub-Station Commissioned
Rural AreaUrban AreaRural AreaUrban AreaRural AreaUrban Area
Under GPVVYUnder STPUnder GPVVYUnder STPUnder GPVVYUnder STP
123456789101112
1Jodhpur33934171333130000
2Pali31831142911000
3Sirohi14914101310000
4Jalore26812201020000
5Barmer40223201810000
6Jaisalmer12815211421000
Total J.Z.16041292518117202000
7Bikaner21918311551000
8Hanumangarh25116121701000
9SGNGR*3203104903000
10Churu24930501640000
1132300100000
Total B.Z.107198975895000
Total Discom26752273425175297000
No of Gram PanchyatNo of Sub-Station to be installedNo of Sub-Station work order IssuedNo of Sub-Station Commissioned
26752862110
GoR-D-11
Progress of Distribution Companies (JODHPUR DISCOM)
Status of connection pending to release to Government Schools (FY 2011-12)
Upto the Month:-June,11GOR-D-11
S.No.Name of CircleName of DistrictNo. of applications pendingNo. of Demand Notes issued out of col(5)No. of DN depositedNo. of Demand Notes to be issued Col (5-6)No. of connections released up to the monthNo. of connections pending whose D.N. DepositedRemarks (reasons of pendency)Expenditure(Rs in Crs)% of Utilization
As on 31.03.2011 but DN not issuedReceived during FY 11-12Total(3+4)DN deposited as on 31.03.11DN deposited during FY 11-12 out of col(5)
123456789101111121314151617
1CITYJODHPUR000000000
2DISTRICTJODHPUR583896825938143859
TOTAL JODHPUR DISTT.5838968259381438590
3PALIPALI12132515141371512
4SIROHISIROHI21719187151164
5JALOREJALORE4232721272361634
6BARMERBARMER0000301201824
7JAISALMERJAISALMER000084093
JODHPUR ZONE7691167136145105281121360
8BIKANERBIKANER448544353
9HNGH.HNGH.336454181
10SGGNR.SGGNR.088706160
CHURUCHURU1326393584243317
P.S. LADNU314318118
11TOTAL CHURU CIRCLE16274338950534250
BIKANER ZONE2342655418641053290
TOTAL DISCOM99133232190163169381651650
GoR-D-11 E
JODHPUR VIDHYUT VITRAN NIGAM LIMITED,JODHPUR.
STATUS OF CONNECTIONS PENDING TO RELEASE TO GOVT. SCHOOLS
Upto the Month:-June,11
S.noName of CircleName of DistrictSTATUS AS ON 1.4.2011APPL. RECD./ RE-OPEN DURING 2011-12TOTALD.N. ISSUED UPTO REPORT MONTH 2011-12D.N. DEPO. UPTO REPORT MONTH 2011-12APPLI. CANCEL UP TO REPORT MONTH PRIOR D.N. ISSUEDAPPLI. CANCEL UP TO REPORT MONTH PRIOR D.N. DEPO.APPLI. CANCEL UP TO REPORT MONTH AFTER D.N. DEPO.CONNE. RELEASED UPTO REPORT MONTH 2011-12APPLICATIONS PENDING AT THE END OF THE MONTH
D.N. DEPO. BUT CONN. NOT RELE.D.N. ISSUED BUT NOT DEPO.D.N. TO BE ISSUEDTOTALD.N. DEPO. BUT CONN. NOT RELE.D.N. ISSUED BUT NOT DEPO.D.N. TO BE ISSUEDTOTAL
D.N.DEP.D.N.D.N.TOTAL(10+11)(10+11)
12345678910111213141516171819
1CITYJODHPUR0000000000000000
2DISTRICTJODHPUR595858175382138238063038593914112
TOTAL JODHPUR DISTT.595858175382138238063038593914112
3PALIPALI14212281341151330015124723
4SIROHISIROHI7321217291815052164116
5JALOREJALORE2774382361212304016341641
6BARMERBARMER301204204201200018240024
7JAISALMERJAISALMER840120120400093003
JODHPUR ZONE14586763079139813610537221121364528209
8BIKANERBIKANER4541341754000536312
9HNGH.HNGH.51393124410081113
10SGGNR.SGGNR.03038117600060415
CHURUCHURU82213432669354209033176427
P.S. LADNU15391103800018019
11TOTAL CHURU CIRCLE92716522779385009034256536
BIKANER ZONE183623774211954641905329171056
TOTAL DISCOM1631229938413351719016948121651656238265
Sheet1
Status of release of BPL connections *
Name GOR-D
GOR-D
1 TO 11 For The Month of June, 2011
Jodhpur Discom
GOR-D-01
Progress of Distribution Companies ( JODHPUR DISCOM) REVISED
Status of AG. DN deposited & connections Released
Upto the Month:-June,11GOR-D-01
Sr. No.Name of DistrictNo of DN issued During 2011-12DN depositedAg. Connections released During 2011-12 out of Colmn. 8% Connection Released of Col.8Cancelled after D.N. Deposited During 2011-12Balance Pending for connection
As on 31.03.11During 2011-12Total DN Deposited
GENERAL CATEGORYOTHERSDuring the monthUpto the monthDuring the monthUpto the month
12345678910111213
1Jodhpur448948449736493781174182322731717.39161490796
2Pali582366186317341447713367.555436241
3Sirohi44319563825427044770111415.853657177
4Jalore17571111868229718987121643826.74121122269
5Barmer10924781570227368618845159911.723743250
6Jaisalmer3944343715511214530022227.33027833
Jodhpur Zone8757134710104157720193785536233159711.133947261766
7Bikaner16451064270929280714100618737537.280631634
8Hanumangarh9968310792052024036084814123.190467201
9SGNGR524238762117253653715397.260498364
10Churu126178320446626780487016718821.610682537
1115116111314000.0001412
Total Churu Cir.127678420606726881788416718821.610696549
Bikaner Zone4441216966105657222470303541774324.48022921748
Total Discom131983516167142142274162558397748134015.963970183514
DN ISSUEDDN DEPOSITEDCANCELLEDPENDING
JLRBMRJSMRJLRBMRJSMRJLRBMRJSMRJLRBMRJSMR
86RE-7 SC18532261133325473006719734
1393RE-9 GEN0548576711485218010701295819
RE-10 SPL00025
RE-11 FH000000000000
RE-11A DRIP8118532671473300027525
RE-11B DIGGI000
TOTAL2665121417761183565248011891544858
CONNECTION
JLRBMRJSMR
RE-7 SC14923573
RE-9 GEN880807344
RE-10 SPL1700
RE-11 FH000
RE-11A DRIP4010330
RE-11B DIGGI00
TOTAL10861145447
DN ISSUEDDN DEPOSITEDCANCELLEDPENDING
DCPALISIROHIDCPALISIROHIDCPALISIROHIDCPALISIROHI
RE-7 SC426751594707216900010349179
RE-8 TSP11645073
RE-9 GEN80615144213116031421252402696
RE-10 SPL10
RE-11 FH212611180120114
RE-11A DRIP323367030035380002474
RE-11B DIGGI
TOTAL831129366221324942031541379469966
CONNECTION
DCPALISIROHI
RE-7 SC50760144
RE-8 TSP536405
RE-9 GEN22703442906476
RE-10 SPL171
RE-11 FH1108
RE-11A DRIP2763334
RE-11B DIGGI
TOTAL3054447530
GOR-D-2
JODHPUR DISCOM
Status of release of DL connections during FY 2011-12
Upto the Month :-June,11GOR-D-02
S.NoName of Distt./CircleApplication for DL connections pendingApplication for DL connections pendingconnections released During 2011-12Cancelled up the month out of (3) & (4)Pending at the end of Reporting month
As on 31.03.11Received during FY 2011-12RuralUrbanTotalRuralUrbanTotal released
RuralUrbanRuralUrbanDuring the monthup to the monthDuring the monthup to the monthDuring the monthup to the monthRuralUrbanRuralUrbanBPL DURING monthAPL DURING monthBPL DURING 2011-12APL DURING 2011-12
123456345678910111212131415
1City Circle021101523017341734005091372509137279.120003620000
2Distt. Circle176201243494126211142502136491721503891955224110.72457718507152318861951955
Total JU Distt.176203353494164921114198423098917215054714631464361315.96457718507514318861951955
3Pali Distt.3858510352179373791303868289827172367351134345243.10622504040518089802717
4Sirohi Distt.653101736292138939317822145485522826977644.8646679515902140548
5Jalore Circle625112620742508325376870116452658811771726283537.05102920463817912815172732385
6Barmer Distt375392561352345388916013949259920798821068722895.84262103655038192507921987
7Jsm. Distt.357615202863576438401473127801751533027.531534482580730127
Jodhpur Zone6949714801117736158067450958576943461027910872988543313267154.3347077592241798679782009251409505609719
8Bikaner73606499636518323130096235891268205786794205421.381267043508058901268
9Hanumangarh222631325137834739109658356842359228623912298254.06284352096438068402359
10Sriganganagar3371204225899956291203683288719192988671185278643.7842841328229522865771842
11Churu3751815178410535535186874034931417282892775230933.173351063783870049301417
12127221326141159816217602285163412026263637.4658410243802280516
Total Churu Cir.502383621101194713320309163721193331610121037294534.013931104807908072101933
Bikaner Zone17980200278443627258245629314532881747910473288392810767153.2369160211117192172282149222859777402
Total Discom8747734821902172421064981072411722272271775821346276936124034307.57162378023534290852064158273695463717121
GOR-D-03
Progress of Distribution Companies ( JODHPUR DISCOM)
Status of release of BPL connections FY 2011-12
Upto the Month:-June,11GOR-D-03
Sr. NoName of DistrictBPL families as per Notification of GoR 2002Total BPL/Kutir Jyoti connections released as on 31.03.11Progress of release of BPL Connections FY 2011-12BPL AS ONRURAL DURING MONTH
TargetReleasedBalanceTOTAL GoR-D-2APLBPL
During the monthUpto the monthMMSLVYOTHER
12345678
1Jodhpur3565827928031195-195281239179778931
2Pali531404823300004823389808980
3Sirohi297091355200001355221402140
4Jalore58655429770128273-273432501645603914128
5Barmer74843225285091592925082322620599552-4592
6Jaisalmer1593110433000010433730730
Jodhpur Zone2679361656515091525156050355166211434612522843251
7Bikaner84842408410000408415893182710
8Hanumangarh43386367611101900110193676168406840
9SGNGR634564653092482277917146607887086522
10Churu656505087200005087249304930
11328833170000331722802280
Total Churu Cir.689385418900005418972107210
Bikaner Zone260622178321202672277201901783982881318254122
Total Discom5285583439727118227363770545344609722715705384273
* Recently sanctioned by REC
** Pending for sanction with REC183949
APRIL,102023
852
GOR-D-04(a) Dist. Wise
Progress of Distribution Companies ( JODHPUR DISCOM)
RGGVY Financial Status
Upto the Month:-June,11GOR-D-04 (a)
S.No.Name of Distrcit/DiscomNo. of SchemesSanctioned Cost (Rs. Lacs)Amount Released (in Lacs Rs.)Utilisation (in Lacs Rs.) (Tentavive)% Utilised
1234567
A. Sanctioned Before to Feb-08
1HN.Garh (AREP)1222.85133.72211.95158.50
2SG.Nagar (AREP)1681.69409.01520.84127.34
3Jaisalmer (AREP)1603.53181.06593.00327.52
4Jaisalmer11338.781144.251377.01120.34
5Bikaner12333.901851.602047.76110.59
6Sirohi11236.92963.30998.34103.64
7Jalore12367.411805.321856.00102.81
8Jodhpur12853.852385.922454.84102.89
9Churu11962.481457.311583.14108.63
101116.0687.5780.0091.36
Jodhpur Discom(A)1013717.4710419.0611722.88112.51
B. Sanctioned After Feb-08
1Hanumangarh13256.161634.391560.0095.45
2Sriganganagar13498.462042.10913.3944.73
3Pali (PGCIL)12981.292377.792787.00117.21
4Barmer (PGCIL)120995.8611272.6612055.00106.94
Jodhpur Discom(B)430731.7717326.9417315.3999.93
G.Total (A+B)1444449.2427746.0029038.27104.66
1Jodhpur12853.852385.922454.84102.89
2Pali12981.292377.792787117.21
3Sirohi11236.92963.3998.34103.64
4Jalore12367.411805.321856102.81
5Barmer120995.8611272.6612055106.94
6Jaisalmer21942.311325.311970.01148.65
Jodhpur Zone732377.6420130.322121.19109.89
7Bikaner12333.91851.62047.76110.59
8Hanumangarh23479.011768.111771.95100.22
9SGNGR24180.152451.111434.2358.51
10Churu11962.481457.311583.14108.63
11Nagaur (Ps. Ladnu)1116.0687.578091.36
Total Churu Cir.22078.541544.881663.14107.65
Bikaner Zone712071.67615.76917.0890.83
Total Discom1444449.242774629038.27104.66
GOR-D-04(b) Dist. Wise
Progress of Distribution Companies ( JODHPUR DISCOM)
Coverage & Progress under AREP & RGGVY Progress
Upto the Month:-June,11GOR-D-04 (b)
S.No.Name of DiscomNo. of SchemesCoverage ( Nos)Progress As on Month (Nos)% Achievement
Electrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.DhaniesElectrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.DhaniesElectrification of Villages (DE/UE)Intensive ElectrificationConn. To BPLGen.Dhanies
123456789101112131415161718
A. Sanctioned Before to Feb-08
1HN.Garh (AREP)14605163760460313322730100.000.00607.17604.520.00
2SG.Nagar (AREP)1111012964701110400031620100.000.003100.78488.720.00
3Jaisalmer (AREP)16002561237055035326091.670.0013.6726.350.00
4Jaisalmer19834810112839869983227094690662100.0092.5370.1582.2389.86
5Bikaner120558741481109513718055830744155603787.8095.0674.12142.09100.00
6Sirohi1844724666899151844782461122350100.00100.0033.43124.8298.04
7Jalore13066754217195821630524365892794016100.0078.5667.49142.68100.00
10Jodhpur117388530365396731251738702119856399125100.0098.3169.81142.16100.00
9Churu11184351488244787683135298319538754.5598.5868.561305.80100.00
81097281426090962638505390.0098.9793.751943.46100.00
Jodhpur Discom(A)10742387421604492562394707364814897516079538695.2894.1768.96173.7297.97
B. Sanctioned After Feb-08
1Hanumangarh1132157639319317042132525283002341532100.0033.3171.98738.6476.19
2Sriganganagar1179250544133217253715262034940170902684.9224.7579.1778.6770.27
3Pali (PGCIL)12191529334805517315913366583134713071.4399.78124.97389.1675.14
4Barmer (PGCIL)1668123060124587313782071679363160012230.9913.5815.57272.451.60
Jodhpur Discom(B)410006226172910388231630506222510926121050.6035.7463.190.0012.88
G.Total (A+B)14174210100388954131385202412135873258236059669.6358.1566.390.0029.45
Note:-Figures shown in shaded of column No. 6 (Coverage of Conn. to BPL) have been changed due to actual survey.
1Jodhpur117388530365396731251738702119856399125100.0098.3169.81142.16100.00
2Pali12191529334805517315913366583134713071.4399.78124.97389.1675.14
3Sirohi1844724666899151844782461122350100.00100.0033.43124.8298.04
4Jalore13066754217195821630524365892794016100.0078.5667.49142.68100.00
5Barmer1668123060124587313782071679363160012230.9913.5815.57272.451.60
6Jaisalmer215834810368963569153322712972326296.8492.5368.7675.0689.86
Jodhpur Zone710584492209074918091812586324311918315014240555.3972.2057.01163.5422.35
7Bikaner120558741481109513718055830744155603787.8095.0674.12142.09100.00
8Hanumangarh2178157639835354642178525314332568832100.0033.3178.91724.4276.19
9SGNGR2290250544262223723726362038940202522690.6924.7587.9890.5270.27
10Churu11184351488244787683135298319538754.5598.5868.561305.80100.00
11Nagaur (Ps. Ladnu)1097281426090962638505390.0098.9793.751943.46100.00
Total Churu Cir.21194054302270796692737936370069654.5598.6269.861367.05100.00
Bikaner Zone768456081798803957621262726301390539850619191.6746.9077.30248.9090.09
Total Discom1417421010038895413138520241213587325823624864859669.6358.1566.39189.2529.45
GOR-D-05
Progress of Distribution Companies (JODHPUR DISCOM)
Electrification of Villages & Dhanies FY 2011-12
Upto the Month:-June,11GOR-D-05
S.No.District & CircleElectrification of Dhanies & House Hold under MMSLVY
DhaniesHouseholds
Expected Dhanies less than 100 populationApplicationsDhanies SanctionedConnections CoveredDhanies ElectrifiedConnections Released
Upto 31.3.11FY 2011-12TOTAL% ElectrifiedUpto 31.3.11FY 2011-12TOTAL% OF CONN. ELECT.CANCELLEDBALANCE
During the Monthup to the MonthDuring the Monthup to the MonthGROUPAPPL.GROUPAPPL.
12344567896.16666666676.66666666677.166666666710111213
1Jodhpur54243843939972544229821538302075.5620436972372067381.266835710253617853
2Pali232254321725501630016375.12165500165564.9069888WORK COMPLETED
3Sirohi384153122522002270.9724100241107.1116174WORK COMPLETED
4Jalore1337136531186109305168012764354.224526603956548250.1652862443623338
5Barmer54073558718391142214559191154684.079138552552969084.841931256438328883
6Jaisalmer50245592144681450014567.761110001110237.18223953793526
Jodhpur Zone12940951967484510375283186256553974.0100037106125217453885176.12151114667766053600
7Bikaner276717128125954749095395100479.7557713185706341115.84950556010566764
8Hanumangarh959129589483008387.377800078087.2512132WORK COMPLETED
9SGNGR ***10592810576799009994.2986300863112.52665WORK COMPLETED
10Churu427267630115302410024180.07142500142593.14185124430187
111347066831559005986.7633100331105.0875375110
Total Churu Cir.561338236918453000030081.301756001756198.2166199813260161931197
Bikaner Zone3528223501828898013915395148681.2900091703185709740513.81974870781228737611187158
Total Discom164681175469312600176674239351702575.4400046276157023154859180.96273922043877860758
16468117546924160017667400667472.2216210367000462760046276
BKNR34942
13649
GOR-D-06
Progress of Distribution Companies (JODHPUR DISCOM)
Status of Consumers Grievances Redressal in Chhaupals FY 2011-12
Upto the Month:-June,11GOR-D-06
S.No.Name of Discom/District33/11 KV S/SProgress of Chhaupals organised during the monthProgress of Chhaupals organised upto the month
No of chhaupals heldGrievances receivedRedressalNo of chhaupals heldGrievances receivedRedressal
Related to billsOthersRelated to billsOthers% redressed (7+8)/(5+6)Related to billsOthersRelated to billsOthers% redressed (13+14)/(11+12)
123456789101112131415
1Jodhpur336601117511175100.0015830121130121100000100.00
2Pali1074090419041100.0011022512222512200000100.00
3Sirohi502550135013100.0076137461374600000100.00
4Jalore169581305713057100.0014929211929211900000100.00
5Barmer1681112017512016094.92333774853774500000095.94
6Jaisalmer5235510555110103.1391702951702850000097.85
Jodhpur Zone88219755646655645699.0253515021278150212330000098.38
7Bikaner191000000.0022612149160000079.27
8Hanumangarh89000000.003714939132370000089.89
9SGNGR108000000.0078114461144600000100.00
10Churu111000000.0067521625216200000100.00
1111000000.00871171100000100.00
Total Churu Cir.122000000.00755917359173100.00
Bikaner Zone510000000.002123832793542720000094.56
Total Discom139219755646655645699.0274718851557185615050000097.65
00000000000000000
16993667557736545428
-1699-3667-5577-3654-542800000000
JPR (During)
GOR-D-07
Progress of Distribution Companies (JODHPUR DISCOM)
Progress of Vigilance Checking
Upto the Month:-June,11GOR-D-07
S. No.Name of DiscomTotal CheckingTheft DetectedRs. In lacs.No .of Complaint/FIRsNo .of Arrests
AssessmentRealisation
Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.Last Year.This Year.% Incr.
1234567891011121314151617181920
1Jodhpur1767886-49.86522404-22.6175.2865.59-12.8740.1232.11-19.97729227.7881475.00
2Pali557500-10.2348126162.5029.0028.02-3.3812.9518.6844.2581025.0000_
3Sirohi195156-20.002316-30.434.322.11-51.161.271.5421.26022_01_
4JALORE198184-7.071810-44.4422.3213.81-38.135.857.3425.47182116.6712100.00
5Barmer840542-35.4814217-88.0354.6911.55-78.8821.249.22-56.59212519.05110.00
6Jaisalmer9752-46.39233552.178.629.9014.854.202.15-48.811024140.0000_
Jodhpur Zone36542320-36.51776608-21.65194.23130.98-32.5685.6371.04-17.0412919450.39101880.00
7Bikaner5165639.113033226.2732.0931.16-2.9013.3222.0765.6938101165.7902_
8HMH60370416.75224182-18.7527.9226.15-6.3419.5920.494.59122391.6738166.67
9SGNGR875751-14.17567494-12.8754.9942.45-22.8027.2121.56-20.76354940.00112-81.82
10Churu58580036.7539669174.4940.4327.29-32.5011.119.03-18.7221963-71.2302_
1190-100.0080-100.000.160.00-100.000.000.00_00_00_
Bikaner Zone258828188.891498168912.75155.59127.05-18.3471.2373.152.70304236-22.3714140.00
Other22258-73.8712240-67.2150.585.47-89.1919.246.94-63.93467-84.7800_
Total64645196-19.6223962337-2.46400.40263.50-34.19176.1151.13-14.18479437-8.77243233.33
GOR-D-08
Progress of Distribution Companies (JODHPUR DISCOM)
Progress of feeder Renovation Programme FY 2011-12
Upto the Month:-June,11GOR-D-08
S.No.Name of DiscomFeeders Renovated up to the monthExpected date of completion for feeders convert from B to APhysical ProgressExpenditure (Rs in Crs)% of UtilisationFeeders Renovated up 31.03.09Feeders Renovated during 2009-10Feeders Renovated up 31.03.10Feeders Renovated during 2010-11Feeders Renovated up 31.03.11Feeders Renovated during 2011-12
TargetA- typeB typeTotal (A+B)% Completion
FeedersVillagesFeeders (4+5)Villages getting supply at par with nearby urban TownFeeders (7/3)*100Villages (8/4)*100Installation of small new type 3-phase Xformers (with Mtrs. MCCB etc) in nosInstallation of small new type 1-phase Xformers in nosLaying of AB Cable in Kms.Installation of pushfit type mtrs. In no.SanctionedUtilised Up to the month
123456789101112131415161718
1Jodhpur7771058687907771058100.00100.00195415053458432970406824881966843
2Pali3359153350335915100.00100.001169422019117954618414532963350
3Sirohi1294551290129455100.00100.0055071352107513530345791381290
4Jalore4806974800480697100.00100.001907833751580296911421583001804800
5Barmer4781264417614781264100.00100.001400531863836195602145927311038334
6Jaisalmer1275021270127502100.00100.00178540843732757038108191270
JODHPUR ZONE23264891217515123264891100.00100.0061085175941342317857210505391589549213837
7Bikaner3686623680368662100.00100.0060641112119051935130210340283680
8Han.garh229162922902291629100.00100.0033974267243153164229022902290
9SGNGR214262321402142623100.00100.0050053987404150943214021402140
10Churu24094622713240946100.00100.008352281155347192382371199821710
1130973003097100.00100.0094137958074171301317300
BIKANER ZONE1081595710681310815957100.00100.00237591255613776235382668247915143105810
Discom3407108483243164340710848100.00100.0084844301502719941395417187862504692319647
A type :- Where 1 Phase & 3 Phase transformer work is completed.
B type:- Where 1 Phase transformer work 100 % completed but 3 phase transformer work partially complete.
GoR-D-08(b)
Progress of Distribution Companies (JODHPUR DISCOM)
Statement of Progress of 3 PhaseTransformers under FRP
Upto the Month:-June,11GOR-D-08(b)
S.NoName of Discom / DistrictTotal no of 3 phase transformers to be installed under FRPTotal no of 3 phase transformers installed up to last MonthTotal no of 3 phase transformers installed during the MonthTotal no of 3 phase transformers installed up to the MonthBalance transformers to be installedTotal no of 3 phase transformers installed up to 31.03.09Total no of 3 phase transformers installed during 2009-10Total no of 3 phase transformers installed up to 31.03.10Total no of 3 phase transformers installed during 2010-11Total no of 3 phase transformers installed up to 31.03.11Total no of 3 phase transformers installed during 2011-12
1234567
1Jodhpur204381941812319541897586338909753900118754787
2Pali116911690116904027671169011690
3Sirohi55075507055070144716813128237955070
4JALORE1907819078019078083755312136875391190780
5Barmer145631375025514005558476125947355611213467538
6Jaisalmer178517850178502151325154024517850
JOD.ZONE625406070737861085145521063155693663223128597601325
7Bikaner6064606406064020303781581125360640
8Hanumangarh33973397033970339703397033970
9SGNGR*50055005050050500505005050050
10Churu8384834578352323211183850493276832527
11Nagaur (Ps. Ladnu)94194109410181982796629410
Total B.Z.2379123752723759321382457171954141912373227
Total Discom863318445938584844148734887212865617327319834921352
*Note:- Revised Progress by per SE (Plan) during the month Jan-10
GoR-D-09(a)
GoR-D-09(b)
GoR-D-09(c)
Progress of Distribution Companies (JODHPUR DISCOM)
Circle wise T&D Losses
Information Upto:-May,11Reporting the Month:-June,11GOR-D-09 (C)
S.No.Name of CircleT & D Loss for previous year 2010-11T & D Loss for current year 2011-12
T & D loss for the MonthT & D loss up to the MonthT & D loss for the MonthT & D loss up to the Month
Energy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D lossEnergy SuppliedEnergy Billed% T&D loss
1234567891011121314
1City Jodhpur1022.36835.5818.271917.441577.9317.711016.07844.4216.891920.271619.3715.67
2Distt. Jodhpur2281.311628.3428.624877.373480.2228.652409.281953.1718.935647.603826.4932.25
4Jalore1164.931056.469.312392.012011.1415.921100.791075.232.322317.172059.9711.10
3Pali1289.561101.4414.592538.502135.8215.861427.571190.5216.613026.392502.8817.30
5Barmer1068.30815.4523.672188.501756.0019.761031.68886.1114.112341.431891.8519.20
Total Ju.Zone6826.465437.2720.3513913.8210961.1121.226985.395949.4514.8315252.8611900.5621.98
6Bikaner1547.171420.548.183668.742640.7928.021754.181730.371.364466.213296.4926.19
7Hanumangarh483.90476.151.601112.691036.166.88461.54474.83-2.881042.741119.54-7.37
8SGNGR715.80587.3917.941376.841117.4318.84692.99581.7016.061349.821132.7016.09
9Churu805.53711.3211.701858.081309.1529.54919.90858.796.642177.711580.5127.42
Total Bik. Zone3552.403195.4010.058016.356103.5323.863828.613645.694.789036.487129.2421.11
Total Discom10378.868632.6716.8221930.1717064.6422.1910814.009595.1411.2724289.3419029.8021.65
GoR-D-10
Progress of Distribution Companies (JODHPUR DISCOM)
33 KV Sub-Stations Works Progress
Upto the Month:-June,11GOR-D-10
S.No.Name of Distt. / CircleNo of Gram PanchyatNo of Sub-Station to be installedNo of Sub-Station work order IssuedNo of Sub-Station Commissioned
Rural AreaUrban AreaRural AreaUrban AreaRural AreaUrban Area
Under GPVVY