IFMS BRIEFING
TO THE STANDING COMMITTEE ON PUBLIC ACCOUNTS
06 MARCH 2018
PROGRESS ON ACTION TAKEN ON MATTERS RAISED SINCE LAST
SCOPA BRIEFING
2
MATTER PROGRESS
Report on services provided to NT by Bitz
Technologies Report submitted to Parliament as requested and provided as an
addendum
Finalisation of forensic investigation into
the IFMS
A Service Provider has been appointed and the investigation is
currently underway, after Audit Committee rejected the draft report
completed by the initial service provider
Investigating whether any employees of
NT were awarded contracts under IFMS No evidence has been found of any NT employee having received
remuneration outside of the public service in relation to the IFMS
Appointment of permanent staff in the
OAG IFMS unit Interviews have been conducted to appoint a permanent head of
IFMS unit.
Suspending IFMS related payments Payments processes reviewed and controls strengthened
Raising issues in respect of previous
forensic investigators On recommendation of Audit Committee, contract with service
provider terminated.
IFMS – THE BACKGROUND
3
Cabinet approved decision to replace IFMS1 (2000-2013) with IFMS 2 in Nov 2013, as
recommended by Ministers of Finance and Public Service and Administration
Process for IFMS 2 managed jointly by NT, DPSA and SITA
IFMS1 was a hybrid solution with IFMS2 shifting to an off-the-shelf COTS solution
– Objective was to replace governments legacy IT systems with an integrated system (BAS,
PERSAL and LOGIS)
– Includes Procurement, HR management, Financial management, Catalogue management,
payroll integrated data exchange
Procurement of COTS solution commenced in 2014, final award to Oracle in April 2016
– Favourable discounts negotiated on back of government committing to purchase licenses
and tech support over the first 5 years
Audit opinion for 2013/14, 2014/15 and 2016/17 did not raise any material issues related to the
award of the contract or its management
IFMS – ISSUES RAISED
4
Issues raised by AGSA audit opinion (2016/17) different from issues raised in May 2016 Internal
Audit Unit report
Audit opinion covers ICTworks settlement and payment of licenses, whilst IAU leaked report covers
weaknesses in controls, all of which management has responded to
In respect of the IA :
– NT acted promptly on request by audit committee for a forensic investigation.
– In the interest of good governance the audit committee was assigned to oversee the
investigation process
– Issues raised in the Internal audit Report has been addressed by management and is being
closely monitored by Internal Audit on a quarterly basis
– NT will act speedily and decisively if any corruption or wrongdoing identified by forensic
process
IFMS – ISSUES RAISED
5
In respect of AGSA
On matters relating to Oracle the necessary corrective steps will be taken once the investigation is
concluded however the key question is how the audit process treats such practice
NT believed it was cost-effective to pay every year for technical support rather than pay more in
later years and with penalties
Such support includes system upgrades and coding support, and NT believes led to an upfront
saving of R149 million and R719 million over 20 years
On matters relating to CSD and LOGIS/BAS enhancements/developments, the key question is how the
audit process differentiate between interpretations of enhancements and new systems
NT believes that the enhancement of the existing supplier master of government was provided for
in the existing SLA through a variation/expansion of the existing contract
On the matter relating to ICT-Works
Shifting from IFMS1 to IFMS2 required exit of contracts to be negotiated
ICT-Works demanded damages of approximately R800 million
This was negotiated down to R383 million with the settlement in lieu of cash assigning a specific
role to ICT-Works in IFMS2
IFMS - FORENSIC INVESTIGATION
6
As previously reported arising out of anomalies raised by the Audit Committee (AC) in respect of
actions taken and work performed by the then appointed service provider to conduct a forensic
investigation of IFMS, the DG in consultation with the AC and the then Minister approved on 31
August 2017 to invite an open bid to restart the process to conduct the IFMS Forensic Investigation
– Bid published on 22 September 2017 and closed on 13 October 2017
– New service provider was appointed on the 30 January 2018
– Contracted investigation period from 01 February 2018 – 30 April 2018
– Areas of investigation :
PMO, SCM process. Finance (payments), IFMS1 settlements and other (systems and
IT)
– Investigation is currently underway
– The draft report to the AC is expected by the first week of May 2018
– The Final report once completed will be made available to all stakeholders including Scopa,
the Public Protector and the Hawks as per their request
7
THE ROLE OF INTERNAL AUDIT
• In terms of the Standards for the Professional Practice of Internal Audit, it is an Independent
objective, assurance and consulting activity designed to add value and improve an
organisations operations. It helps an organisation by bringing a systematic and disciplined
approach to evaluate the effectiveness and efficiency of an organisations Internal controls,
Risk management and Governance processes .
• It is therefore an Internal Management tool that helps an organisations improve its internal
controls and governance. Internal Audit reports highlight findings in this regard with
recommendations for management consideration.
• Internal Audit reports are not meant for external distribution but for tabling in Audit Committee
where progress on the resolving of these internal control gaps is monitored
IFMS - IMPLEMENTATION PROGRESS
• Administration and payment has been streamlined for better control
• Revised IFMS Programme Base-line & Implementation Approach was
endorsed by IFMS Steering Committee
• Programme Risks are being monitored by project risk committee as well
as the National Treasury Risk Committee
• Interim IFMS PMO services have been sourced from SITA (value added
services) and processes are being strengthened continuously
8
IFMS - IMPLEMENTATION PROGRESS
9
REVISED IFMS PROGRAMME IMPLEMENTATION
APPROACH – NOVEMBER 2017
11
The following detail describes the phases and sub-phases in more detail:
3.1 Phase 1: Software agreement
Completed with contractual agreement with Oracle (software only).
3.2 Phase 2: Focuses on the development of the Generic Template (GT) that will be used for
implementation and roll-out (Pilot Sites & Lead Sites). Three sub-phases agreed: ( Nov 2017 – Feb 2021 )
• 2A: Design and Template Development (18 Months, ending in Nov 2018)
Planning, scope, objectives & approach;
Securing architecture and design services
Procurement of implementation services and hosting infrastructure
Develop generic solution baseline - GT0;
Policy owners and assigned business representatives to participate in GT0 design phases to be as
inclusive as possible
• Phase 2B - Pilot Site Implementation, (12 Months , ending Nov 2019)
Implement and Refinement of GT0 at Pilot Sites (DPSA & NT) into GT1;
Establish the Centre of Excellence (CoE) at SITA including capacitation for support, maintenance,
training, etc.
• Phase 2C - Lead Site Implementation, (18 months , ending June 2021)
Refinement of GT1 into GT2 at Lead Sites (Eastern Cape and Western Cape).
REVISED IFMS PROGRAMME IMPLEMENTATION APPROACH –
NOVEMBER 2017
3.3 Phase 3: National Roll-out (To commence in April 2021)
Long-term planning for Phase 3 is still not quantified, dependent on
strategy and resourcing.
Standard departments will implement GT2, additional requirements to
be considered through a formal change process.
Differentiated departments (E.g. DOD, SAPS, Education and Health)
GT2 will be expanded for the differentiated departments’ legislative
requirements, culminating in GT3,
GT3 locked down and formal change management process in place,
The implementation and hosting approach for the differentiated
departments to be clarified.
12
REVISED PROGRAMME IMPLEMENTATION APPROACH – NOVEMBER
2017
COST SUMMARY 2013/2014 – 2016/2017
13
2013/2014 2014/2015 2015/2016 2016/2017 TOTAL
R'000 R'000 R'000 R'000 R'000
REVENUE
Annual Appropriation 194 626 167 366 178 516 556 985 1 097 493
EXPENDITURE
Current Expenditure 194 626 167 366 180 273 162 207 704 471
Compensation of Employees - - 1 927 3 786 5 713
Goods and services 194 626 167 366 178 346 158 421 698 758
Capital Expenditure
Payments for Capital Assets - - - 394 243 394 243
Surplus/(deficit) for the year 0 0 1 757- 535 1 221-
IFMS - FINANCIAL SUMMARY
2017/2018 Planned Costs vs. Actual.
Breakdown of total spent for Goods and Services
14
FY2017/18 (YTD)
Total Budget allocation R 352 112 000.00
Total expenditure R 97 402 287.31
2 Compensation of employees R 2 600 783.47
3 Goods and Services R 94 801 143.84
4 Transfers and Subsidies R 0.00
5 Capital Assets R 360.00
Varience i.e. Actual vs Budget R 232 814 767.69
No. (Line Item 3 Goods & Services) Total Spend per item
1 Licence Fees R 1 455 472.52
2 Software and Maintenance costs R 79 280 020.24
3 SITA hosting and maintenance R 11 537 304.74
4 SITA website and consulting R 2 474 116.72
Total Good s & Services Costs R 94 746 914.22
Already committed expenditure for 2017/2018
• Note: The total committed expenditure above will be paid from the
variance of R233m which represents approximately 52% expenditure
Service Provider Committed Expenditure
Oracle R58 000 000
SAP (Annual licence fees) R11 000 000
SITA ( IFMS 1 Hosting & FAS) R17 699 566.80
TOTAL COMMITTED EXPENDITURE R 86 699 567
IFMS - COMMITTED EXPENDITURE FOR 2017/18
THANK YOU
TO THE STANDING COMMITTEE ON PUBLIC ACCOUNTS
06 MARCH 2018