Alignment Determination / Survey Work – March 2019 Begin the Environmental Study (NEPA) and Preliminary Engineering - April 2019 Complete Environmental Study (NEPA) and Preliminary Engineering – January

2020 TDOT awards Design-Build Contract – September 2020 R.O.W. Acquisition begins - February 2021 Construction begins – November 2021 ALL WORK MUST BE COMPLETED BY SEPTEMBER 2025