EXTERNAL Presenter Logo Large Scale Subsurface and Surface Integrated Capacity Modeling - Implementation & Lessons Learned Shaikha Al Jenaibi
Transcript
Page 1: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

EXTERNAL

Presenter

LogoLarge Scale Subsurface and Surface

Integrated Capacity Modeling -

Implementation & Lessons Learned

Shaikha Al Jenaibi

Page 2: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

2EXTERNAL

DISCLAIMER 2019

The contents of this presentation are for informational purposes only. Halliburton**

makes no representation or warranty about the accuracy or suitability of the

information provided in this presentation and any related materials. Nothing in this

presentation constitutes professional advice or consulting services. No contractual

relationship with Halliburton is established by attending or viewing this

presentation. No rights to intellectual property of Halliburton are granted through this

presentation. The opinions expressed in this presentation are those of the author

and do not necessarily represent the views of Halliburton. **Halliburton means

Halliburton Energy Services, Inc., Landmark Graphics Corporation, and their

affiliates.

Page 3: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

3EXTERNAL

Agenda

• Motivation

• Solution Highlights

• Challenges

• Solution Description

• Leading Technical Features

• Typical User Interfaces

• ICM Business Value

• Conclusions and Lessons Learned

Responding faster and more efficiently to support decision making…

Page 4: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

4EXTERNAL

Before ICM After ICM

Production shortfall identification and

management

1-2 weeks 1-2 hours

High value products (i.e. C2, API) optimization NA 1-2 days

Production ramp-up validation & optimization 1-2 Months 1-2 days

Respond to downstream demand changes 1-2 weeks 1-2 days

5-years Business plan validation NA 2-5 days

Integration with long term portfolio planning NA 2-5 days

Future capacity planning optimization NA 2-5 days

Future unplanned shutdown and well availability NA 2-5 days

Production Allocation 1 Month 1 day

• Compensation of production shortfalls (e.g. 10% of base)

• Quick response to market conditions

• Ranking actions for production increase

• Improving synergy among assets (e.g. gas use, resources, etc.)

• Delivering optimized products (e.g. C2, API..) to downstream

• CAPEX optimization

• Increasing and optimizing field operations and activities over next decades

Responding faster and more efficiently to support decision making…

Motivation

Page 5: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

5EXTERNAL

Solution Highlights

Knowledge Sharing

• SPE paper presented in ADIPEC 2018

• ADNOC Digital Twin component (ADIPEC 2018)

Support compensation opportunities > 1 M$/day

Capacity model from Rock to Stock

• >12 Assets >20 Fields

• >100 Reservoirs > 4000 Oil & Gas Strings

• >8,000 surface nodes (Pipelines, pumps)

Technical Features

• 6 Daily production scenarios

• Integrated forecasting scenarios for production maximization

• Opportunities identification including Capacity and Cost

• Unplanned Availability prediction

• Production Allocation

• Compositional tracking from well to delivery point

Patent filed in July 2018

• First Integrated Country-wide Capacity Model in Upstream World

Wide of this scale

Responding faster and more efficiently to support decision making…

Page 6: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

6EXTERNAL

Decades-Years Years-Months Quarters-Months Days-Hours

Asset

pote

ntial t

o b

e d

evelo

ped

Develo

ped a

sset

pote

ntial

Eff

ective c

apacity

Insta

lled p

ote

ntial

Opera

ting p

ote

ntial

Additio

nal

investm

ent

Desig

n

Guid

elines

Pla

nned

dow

ntim

e

Opera

tional

Eff

icie

ncy

Planning and Development

Maintenance and Logistics

Production Operations

Wo

rk

Pro

cesses

Implementation Challenges

Integration of different available models and data

Different technologies and providers

Different type of models (Reservoir, Wells, Network, Economics, etc.)

Gaps in consistency between models and data

Integrated Business Planning

Plan and Economics @ different time horizons

Different Fields / Assets

Production / Facilities expansion / New wells

Operations vs Maintenance plans

Scenario Analysis

Responding faster and more efficiently to support decision making…

Page 7: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

7EXTERNAL

Well Surface IPR

Lookup table

Model and

Simulation

Parameters

Scenarios

Facilities

Model

Results

Upstream Data

Hub

OUTPUTS:

Integrated Capacity Assessment

Production Compensation

Production Ramp Up

Production Plan Review/UpdateReservoir Simulation

Lookup table

Future Conditions

Well

Performance

(t)

Integrated

Capacities

>100

reservoirs

Completions

PVT

Well tests

Business

Plan DB

User Interfaces

>4,000 oil

strings

Scenarios

Solution Description

An integrated hydraulic model with economics from well to point of delivery…

Daily

performance

calc

6 Hydraulic

Scenarios

>8,000 pipelines

>12 Assets

>20 Fields

Page 8: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

8EXTERNAL

Solution Description - Downstream-Upstream Integration

Well Surface IPR

Lookup table

Model and

Simulation

Parameters

Scenarios

Facilities

Model

Results

Upstream

Data Hub

OUTPUTS:

Integrated Capacity Assessment

Production Compensation

Production Ramp Up

Production Plan Review/Update

Reservoir

Simulation

Lookup table

Future

Conditions

Well

Performance

(t)

Integrated

Capacities

Completions

PVT

Well tests

Business

Plan DB

User

Interfaces

Scenarios

Reserves and Portfolio

Management SystemIntegrated Capacity Model (ICM)

Integrated Production Planning

(Downstream)

Gas Plants

RefiningGas Distr.

An integrated hydraulic model with economics from well to point of delivery…

Page 9: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

9EXTERNAL

Data

Layer

Upstream

Data Hub

Application

Layer

Modeling Components

Solution Description - Functional Architecture

Production

Integration Platform (DSIS®)

Completions Business

Plan

Res. Sim. Lookup Table Well Performance Proxy Network Model

(Nexus®)

Presentation

Layer

PVT

Calculation and Workflow

Orchestration Engine

(AssetConnect®)

Maintenance

An integrated hydraulic model with economics from well to point of delivery…

Page 10: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

10EXTERNAL

Solution Description - Additional Functionality

Additional AssetsInjection

Artificial LiftAllocation

Surrogate Models

Well Surface IPR

Lookup table

Model and

Simulation

Parameters

Scenarios

Facilities

Model

Results

Upstream

Data Hub

OUTPUTS:

Integrated Capacity Assessment

Production Compensation

Production Ramp Up

Production Plan Review/UpdateReservoir

Simulation

Lookup table

Future

Conditions

Well

Performance

(t)

Integrated

Capacities

Completions

PVT

Well tests

Business

Plan DB

User

Interfaces

Scenarios

Alternate Scenario

An integrated hydraulic model with economics from well to point of delivery…

Reservoir Sectors

Page 11: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

11EXTERNAL

Data Quality / Integration Indicator

0

1000

2000

3000

4000

5000

0 5000 10000 15000 20000

Well Performance Sensitivity

Leading Technical Features

Leading Technical Features

Assets Potential and Technical rate calculation

Automatic Reservoir Guidelines Compliance at sector level

Country-wide production maximization

Forecast analysis

Unplanned Availability prediction

Production Allocation

Mobile ICM access

Integration features

Oil and Gas Assets integration

Production Compensation

Business plan validation

Shutdown Plan integration

Data Quality/Integration Indicator

Business Process Management

An integrated hydraulic model with economics from well to point of delivery…

Page 12: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

12EXTERNAL

Typical User Interfaces

Production Allocation

Page 13: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

13EXTERNAL

Typical User Interfaces

Quota Validation

Page 14: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

14EXTERNAL

Typical User Interfaces

Waterfall Capacity Analysis

Page 15: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

15EXTERNAL

Typical User Interfaces

Delivery Nodes – Rates and Composition

Page 16: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

16EXTERNAL16

Ensure 100% Business Plan

Adjust Quota to meet

targets

Production

Assurance

Shortfall & Opportunities

tracking

6 daily scenarios

Proactive Opportunity

identification within

guidelines

Ensure Guidelines

Compliance

Opportunity by well

Automatic Calculation

of Well Technical Rate

Opportunities without

Additional CAPEX

Optimized Business Plan

Unlock Production

Potential Effectively

Limiting factors identified

Integrated

Value Chain

Downstream Integration

Full oil & gas

composition

Maximize UAE value

Adapt to market changes

ICM Business Value

An integrated hydraulic model with economics from well to point of delivery…

Page 17: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

17EXTERNAL

Conclusions and Lessons Learned

Sustainable platform to generate self-updated models combining:

First principle models

Available data

Effective Business Plan Validation and Quota Generation Honoring Guidelines

Short Term Opportunity Identification and Validation

Efficient way to model the production value chain:

From reservoir to Point of Sales

Leverage existing modeling infrastructure and available data

Integrating information from different sources

Effective Solution to Improve Data Quality

Viable platform to collaborate Upstream and Downstream to optimize capacity utilization

An integrated hydraulic model with economics from well to point of delivery…

Page 18: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

18EXTERNAL

Acknowledgements / Thank You / Questions

The authors recognize the support from Abu Dhabi

national Oil Company Upstream Directorate and

thank management for allowing sharing the

experiences of building the Country-wide Integrated

Capacity Model of Abu Dhabi

Page 19: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

19EXTERNAL

Your feedback is very important to us.

Please open the LIFE2019 app to answer a

few short questions on this presentation.

Page 20: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

21EXTERNAL

ICM Solution description

Patented and self updated Model, which includes

» Over 4000 oil & gas wells, 100 reservoirs

» Over 8000 surface nodes (flow lines, pumps)

» Main Oil lines from Assets to Terminal Network

Integrates to Downstream through fully compositional model

Integrates to OPCO’s Models

» Reservoir Model through proxy well models

» Integrated Asset Models (IAM)

System functionality includes

» Model calibration and data quality diagnostics

» Potential, shortfall and opportunity identification

» Stakeholder call-for-action issue and tracking

Opportunities Performance

Efficiency

Shortfalls

Asset Status well by well

FTR, FSOPR Plan vs ActualFilter

Page 21: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

22EXTERNAL

22

Now

OPCO Process

Work Process Alignment

User Validation

Quality Assurance

5YBP Integration

RPPM Integration

Panorama Integration

Downstream Integration

Artificial Intelligence

Data Analytics

Computing power

Surrogate Models

Short

TermMid

Term

Sustainable

Value

Creation

Integration with IAMs and

Business Process Management

BP Assurance, planning and

production optimization

Predicting and prescribing

actions by leveraging big data

Assuring model predictive quality

with latest real-time status

Fast scenarios for development

projects ranking and prioritizationOptimize the value chain for

supply and demand variations

Page 22: Presenter Large Scale Subsurface and Surface Logo ......Production Plan Review/Update Reservoir Simulation Lookup table Future Conditions Well Performance (t) Integrated Capacities

23EXTERNAL

Production Plan

Call for Action

Solution Description

An integrated hydraulic model with economics from well to point of delivery…


Recommended