“Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import Terminal Design Angel Lim, S.E. & John Posadas, P.E.
Transcript
Page 1: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

“Structural Design of the Marine Terminal”

Prevention First 2006September, 2006Long Beach, CA

POLA / Pacific Energy Berth 408Crude Oil Import Terminal Design

Angel Lim, S.E. & John Posadas, P.E.

Page 2: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Berth 408 Crude Oil Import Terminal

Angel Lim, S.E. & John Posadas, P.E.

POLA/Pacific Energy Berth 408 Crude Oil Import Terminal Design

Structural Design of the Marine Terminal

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 3: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

OUTLINE

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Unique Features

Facility Description

Structural Design per MOTEMS

Mooring & Berthing per MOTEMS

Structural Details

Design Innovation

Page 4: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Unique Features

• 1st New Oil Terminal Designed to MOTEMS• Designed to meet new MOTEMS and POLA

Seismic Code• 81 ft of water depth• Designed to accommodate VLCC’s• 3-D analysis between structure and pipes

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 5: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Facility Description

• POLA Map• Faults• Structural Components

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 6: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

POLA Map

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 7: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

POLA Map

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 8: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Faults in Southern California

STRUCTURAL DESIGN OF THE MARINE TERMINAL

POLA

Page 9: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Structural Component - Unloading Platform

STRUCTURAL DESIGN OF THE MARINE TERMINAL

• 60 ft wide x 100 ft long x 4 ft deep reinforcedconcrete slab

• 12-48” steel piles• Steel piles rigidly connected to underside of slab• 4-16” unloading arms

Page 10: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Structural Component - Breasting Dolphin

STRUCTURAL DESIGN OF THE MARINE TERMINAL

• 4-40 ft sq. x 4 ft deep reinforced concrete slab• 4-48” steel piles• Piles rigidly connected to underside of slab

Page 11: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Structural Component - Mooring Dolphin

STRUCTURAL DESIGN OF THE MARINE TERMINAL

• 6-25 ft sq. x 5 ft deep reinforced concrete slab• 4-54” battered steel piles• Piles rigidly connected to underside of slab

Page 12: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Structural Component - North & South Trestles

STRUCTURAL DESIGN OF THE MARINE TERMINAL

• 244 ft long x 22 ft wide South Trestle• 33” deep pre-cast concrete box girders • Combined cast-in-place and pre-cast

concrete bent caps at 40 ft o.c.• 2-42” steel piles at each bent

• 214 ft long x 37 ft wide North Trestle• 33” deep pre-cast concrete box girders• Combined cast-in-place and pre-cast

concrete bent caps at 40 ft o.c.• 2-42” steel piles at each bent

Page 13: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Structural Design per MOTEMS

• MOTEMS Risk Classification• Seismic Performance Criteria• Minimum Required Analytical Procedure

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 14: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

MOT Risk Classification

Purpose is to establish minimum seismic analysis and structural performance.Structural performance is evaluated at a two level criteria:Level 1 and Level 2MOTEMS risk classification (Table 31-F-4-1)All new MOTS are classified as high risk.1. Exposed oil ≥ 1200 bbls

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 15: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

MOTEMS Seismic Performance Criteria

Design Earthquake Motions:Level 1• Minor or no structural damage• Temporary or no interruption in operationsLevel 2• Controlled inelastic structural behavior with repairable damage• Prevention of structural collapse• Temporary loss of operations, restorable within months• Prevention of major spill ( ≥ 1200 bbls)

Seismic Performance Criteria:Select: High risk classification:Seismic Performance Level: Level 1 Level 2Probability of Exceedance: 50% in 50 years 10% in 50 yearsReturn Period: 72 years 475 years

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 16: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Response Spectra

STRUCTURAL DESIGN OF THE MARINE TERMINAL

POLA CLE

MOTEMS LEVEL 2

Page 17: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

MOTEMS Minimum Required Analytical Procedures

• Minimum Required Analytical Procedures:• Select: High / Moderate:• Configuration: Irregular• Substructure Material: Concrete/Steel• Displacement Demand Procedure: Linear Model• Displacement Capacity Procedure: Non Linear Static

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 18: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Minimum Analytical Procedure

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Minimum Analytical Procedure Design Approach

Basic Classification

Seismic Performance Level

Displacement Based Design

Develop Computer Model

Calculate Displacement Demand

Calculate Displacement Capacity

Check Pile Shear

Design for Shear Key Forces

CheckP-Δ

Page 19: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Displacement Capacity Flow Chart

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Develop 2-D Models

Pile P-M Curve

Non-linear Hinge Properties

GeometrySection Properties:E, A and Ieff

Soil Springs Seismic Mass

Lower Bound Upper Bound

Pile Moment-Curvature Curves

Page 20: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Seismic Mass

STRUCTURAL DESIGN OF THE MARINE TERMINAL

10% Live Load Added Dead Load

Dead Load

Pile Mass

Page 21: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

DIFFERENT POSSIBLE MODELS FOR DETERMINING DISPLACEMENT CAPACITY

INELASTIC FE (SOIL + PILE) MODEL

EQUIVALENT DEPTH TO FIXITY MODEL

Too complex! Too simplistic!

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 22: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

SAP2000 2-D Model Layout

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Typical top hinge

Pile

p-y soil springs

Deck

Typical in-ground hinge

1 23

45

6

Page 23: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Pushover Curves

Total

0

50

100

150

200

250

300

0.0 4.0 8.0 12.0 16.0 20.0 24.0 28.0

Displacement, inches

Base

She

ar, k

ips

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Level 1

Level 2B

ase

She

ar, k

ips

Displacement, inches

Page 24: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Displacement Demand Flow Chart

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Displacement Demand = Transverse Displacement

Demand x DMF

Calculate Displacement Demand

Initial Stiffness MethodFor Initial Check

Substitute Structure Method (Iterative)

Page 25: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Displacement Demand Flow Chart

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Initial Stiffness Method for initial check

Calculate Displacement Demand

Initial stiffness from pushover curve

Damping = 5%

gKWT π2=

Read displacement demandform displacement

spectra for 5% damping

Page 26: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Demand-to-Capacity Ratio (DCR)

• Demand x DMF / Capacity < 1.0

• DCR < 1.0

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 27: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Mooring & Berthing per MOTEMS

• Mooring/Berthing Risk Classification• Mooring Analysis• Berthing Analysis

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 28: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

MOTEMS Mooring/Berthing Risk Classification

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Based on site specific parameters:

1. Wind

2. Current

3. Hydrodynamic effects of passing vessels

4. Change in vessel draft

Page 29: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Mooring Analysis

Load Generated By• Wind• Wave• Passing Vessel• Seiche• Tsunami

STRUCTURAL DESIGN OF THE MARINE TERMINAL

MOTEMS Ref.• 3105F.3.1• 3105F.3.1• 3105F.3.2• 3105F.3.3• 3105F.3.4

Page 30: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

MOTEMS Windspeed Conversion Factor

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 31: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

MOTEMS Current Velocity Correction Factor

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 32: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Berthing Analysis

• Fender DesignBerthing Energy DemandEvessel = ½(W*Vn

2/g)Berthing Energy CapacityEfender = Cb*Cm*Evessel

• Tanker Contact LengthLc = 2r Sin α

• Longitudinal or Vertical Berthing ForcesF = μN

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 33: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

MOTEMS Berthing Velocity, Site Conditions& Max. Berthing Angle Tables

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 34: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Structural Details

• Ship Design Parameters• General Layout & Elevation• Mooring Layout for VLCC• Section at Unloading Platform• ULP Rigid Frame Joint Detail• ULP Reinforcing• MD Deck & Pile Reinforcing• MD Deck Reinforcing Plans• N & S Trestle Box Girder Layout• N & S Pier Layout & Cap Bm Details

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 35: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Ship Design Parameters

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 36: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

General Layout Plan & Waterside Elevation

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 37: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Mooring Layout for VLCC

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 38: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Section at Unloading Platform

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 39: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

North & South Trestle Box Girder Layout

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 40: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Design Innovations

• 1st New Oil Terminal Designed to MOTEMS• Optimized Seismic Design Analysis• Modularization of Structural Components• Advance Design-Build Process• Environmental Technologies

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 41: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Project Photos

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 42: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

Project Photos

STRUCTURAL DESIGN OF THE MARINE TERMINAL

Page 43: Prevention First 2006€¦ · “Structural Design of the Marine Terminal” Prevention First 2006 September, 2006 Long Beach, CA POLA / Pacific Energy Berth 408 Crude Oil Import

“Structural Design of the Marine Terminal”

Thank [email protected]

[email protected]

POLA / Pacific Energy Berth 408Crude Oil Import Terminal Design