Internship Report
1Page
Prince Mohammad Bin Fahd Universi t y
C o l l e g e o f E n g i n e e r i n g
Department of Electrical Engineering
Internship Report
at
[Sabic- Sharq]
R e p o r t i n g P e r i o d :
[16/6/2012 – 8/8/2012]
S u b m i t t e d b y :
[ K h a l i d A L - H u s s a i n ]
[ 2 0 0 7 0 0 2 6 3 ]
[ s u b m i s s i o n d a t e ( 1 5 / 9 / 2 0 1 2 ) ]
Electrical Engineering Department
Summer 2012
Internship Report
2Page
Abstract:
The importance of this internship is gaining experience, information, Knowledge and
Practical skills as much as I can for about two months. This report is demonstrating
my efforts in Sharq Company, its department, products, substations, Plants, my plan
for the internship, and the tasks and responsibilities. Further, its applications about
electrical engineering, plants and Substations are good for the engineer to relate the
theory to practical life. The information was from my experience at working in the
company, manuals, reliable books and some assistance from the engineers in Sharq.
The internship period was so beneficial that I covered the majority of the power
system information.
Internship Report
3Page
Table of Content
Introduction: 5
Acknowledgement: 6
Switch Gear: 7
Motor Control center (MCC): 7
Charger: 8
UPS: 8 a. Power Factor Study: 8
b. Load Flow Calculations: 8 c. Short Circuit & Voltage drop: 9
Conditions of calculations: 9
d. Cable Sizing Calculations: 9
Basic Training: 9
Fluorescent lights: 9
Mercury Vapor and Sodium: 11
Single Phase Motor: 11
Gas insulated switch gear (GIS): 11
Generators: 12
Cathodic protection: 12
The Impressive Current method (ICCP): 12
Sacrificial Anodes Cathodic protection: 12
VVVF: 13
Description about the component of VVVF 13
Protection System: 11
Some Protection devices in brief: 11 CT: 11 PT: 11
Differential relay (Relay 87): 11
Example for differential relay: 15 Synchronism Relay (Relay 25): 15
Fuses: 16
The Company: 16
Sharq Safety: 16
Root cause analysis: 17
RCA steps: 17
Internship Report
1Page
Heat Stress Announcements: 17
Conclusion: 21
Internship Report
5Page
Introduction:
During training at Sharq, I was assigned to visit substations and plants in order to
relate whatever in theory to practical life. The nature work of electrical engineering
needs some policies and cautions. Therefore, attending the safety lecture of the
company is for saving yourself and the environment. The importance of this
internship is learning and gaining experience to see how the practical life going about
my field, how to deal with some technical problems, how test emergency machines by
weekly or monthly. Ultimately, the engineer must seek for the information by himself,
so he won't forget it.
Internship Report
6Page
Acknowledgement:
Accomplishing this assignment was a very challenging goal in my life especially
being a first time at a workplace. It could not have been destined to become a reality
without those who have supported me throughout my way, for those I express the
below thanks:
Firstly, my appreciation to Almighty Allah for his endless blessings and for providing
me with health and strength to attain this degree.
Secondly, my utmost gratefulness and love to my mother who never cease or get
bored of blessing me with her prayers, may Allah reward her with the best in this life
and the life thereafter.
Last but not least, the engineers of Sharq company who assisted me a lot. First, my
supervisor Abdullah AL-Baghdadi was assisting me as much as he can, so I can get
benefits. Also, Mr. Pawan helped me in protection system. Sampath, was helping me
to understand the cathodic Protection. Jaber AL-Malki was helping me in
transformers.
.
Internship Report
7Page
Switch Gear:
Switch gear is combination of circuit breakers to feed whatever is needed. It can feed
transformers, substations, plants, etc. (See figure 1). There are three switch gears in
their substations in terms of voltage level in their substations such as Medium Voltage
Switch gear (4.16 KV), low voltage switch gear (480V) and High voltage switch gear
(13.8 KV). Each switch gear has GE Relays such as 750 relay for the feeders, 745 for
the transformers, and the 469 relay for the motors. Also, switch gears has ATS, and
Relay test blocks which used for testing the relays.
Figure 1
(Switch Gear)
Motor Control center (MCC):
It's the same as switch gear, but it has contactors instead of circuit breaker and fuses
for protecting over currents. Of course, the Multilin 469 is a part of it.
Figure 2
(MCC)
Internship Report
8Page
Charger:
a. Description: System which is useful to charge the dc controls during any
interruption. Further, the battery will charge the interrupted dc control switch
for a limited time during its interruption
b. Circuit: There is an input MCCB switch will make the rectifier to convert
from Ac to dc to charge a battery f. If any dc control switch fails, the battery
will feed it.
UPS:
Description: it’s uninterrupted power supply, which mainly used as a backup power
supply. If any interruption of ac equipments, motors, or valves, the UPS can feed
them when they are interrupted.
Circuit: The Rectifier will convert from ac into a dc for the battery, and then inverter
will convert from dc to ac again. If this operation fails, the bypass MCCB will work
by static switch. Then, it will send a signal to transformer and ultimately it will save
our plants from interruption.
Figure 3
(UPS & Charger)
a. Power Factor Study:
If the load is inductive, the capacitor enhances the voltage, reduces the current,
reducing line losses and reducing power bills and thus leading unity power factor.
Capacitor useful as a storage element and if it's a series with an inductor, it will
maintain the voltage.
b. Load Flow Calculations: Load flow calculation is about studying Voltage Profile, Power Flows, Current Flows,
Power Factors, Transformer LTC Settings, Voltage Drops, Generator’s Mvar Demand
(Qmax & Qmin), Total Generation & Power Demand, Steady State Stability Limits,
MW & Mar Losses.
Internship Report
9Page
c. Short Circuit & Voltage drop: Short circuit occurs between two phases or phase ad ground as a result of weak
insulation resistance.
Conditions of calculations:
1. Drawing the equivalent of per unit impedances for each element of the circuit.
2. Impedance of transformers, cables, bus ducts, etc. are required. But the
impedances of transformers, etc. are neglected.
3. Calculating mathematical equations to calculate the percentage drop. And
Ideal Circuit analysis theory for the calculating the short circuit current.
Note: Each of studies has its own calculations, but the most important point is to
convert the actual circuit into per unit and then calculates what is required.
d. Cable Sizing Calculations:
Procedure of calculations:
1. Calculating the continuous current.
2. Calculating the voltage drop across the cable.
3. Calculating the Maximum length of cable.
Basic Training:
I was assigned to attend the basic training course about my field in order to gain my
experience about electrical engineering. There are many information are very
impressive to learn in terms of practical life. This course covered street light and some
kinds of motors.
Fluorescent lights:
There are two types of fluorescent lights. The first is t is preheat type, when the circuit
is energized the current will flow from cathode A and then to cathode b through the
starter. Then, a heat will affect the gas inside the lamp and thus an arc will occur
across the fluorescent lamp. The second is the rapid type; the ballast will deliver a
small voltage to heat the cathodes. There isn't starter needed. Cathodes will heat the
gas, so the gas will be increased and higher current and lower resistance.
Internship Report
11Page
Figure 4
(Preheat Light)
Mercury Vapor and Sodium:
The ballast will deliver a voltage to the electrodes. The starter resistor will control the
current flowing. An arc will be struck between the starting electrode and the two main
electrodes. Therefore, the current will be high and resistance and that makes the
mercury vapor increased. Ultimately, the lamp is working. Sodium vapor doesn't have
the starting resistor and electrodes, but only two main electrodes. However, there is an
igniter that will deliver high voltage and high frequency to the electrodes and heat the
sodium vapor and arc will occur to make the lamp work. (See figure 5 & 6)
(Figure 5)
Mercury Vapor
(Figure 6)
Sodium Vapor
Internship Report
11Page
Single Phase Motor:
The supply voltage will deliver current which will go into two loads. The first load
has Capacitor, Centrifugal switch and starting winding. The second load has running
winding. The current will flow through the capacitor and centrifugal switch and then
starting winding. The starting winding will produce a magnetic field to make the rotor
rotate. When the rotor reaches the required speed, the centrifugal switch will open.
The running winding will make the rotor to continue rotating. The purpose of having
the capacitor in the circuit is maintain the wattage, voltage , and also to make phase
shift between the running period and starting period is 90. (See Figure 7)
(Figure 7)
Single phase motor
Gas insulated switch gear (GIS):
GIS is the upstream of the substations. A gas (SF6) insulated substation may have
underground feed lines and be nearly invisible to the average person. Distribution
circuits supplied by gas insulated substations normally have an alternate feed from
another substation, to allow maintenance work on the gas insulated site. For instance,
Sceco is feeding Voltage to Sabic Company, then GIS will feed transformer to feed
substations. Furthermore, the SF6 circuit breaker is available in the GIS because it's
useful for the high voltage sides. (See figure 8).
Internship Report
12Page
(Figure 8)
GIS in ABB Company
Generators:
There are many sources of generations such as Hydroelectric, nuclear, natural gas,
fossil fuel and diesel engine. Indeed, the generator is converting from mechanical
energy to electrical energy according to the first law of thermodynamic.
Cathodic protection:
Cathodic protection is technique which is useful to protect the buried pipelines, Metal
tank, and reinforced concrete structure from the corrosion. Usually the anode part "the
positive part" is for decaying and the cathode part for protecting the metal product and
that's why it's called Cathodic protection. Two methods are useful in cathodic
protection and these methods are the Impressive current and the sacrificial anode.
The Impressive Current method (ICCP):
The Impressive Current Cathodic Protection systems use anodes connected to a DC
power source. The rectifier bridge is useful to convert from ac source to dc powers
source. At the end of the rectifier bridge, there are two terminals. The positive
terminals for the anode for decaying and the negative terminal are for the cathode for
protection.
Sacrificial Anodes Cathodic protection:
There is something known as Fe and if it's added to a carbon, it will become hard
steel. In addition, the magnesium will be a good solution to avoid the corrosion. The
magnesium can be considered as the anode part for decaying, and the steel can be
considered as the cathode part for protection.
Internship Report
13Page
VVVF:
It’s a Power Electronics device, which generates a variable voltage and variable
frequency output from a fixed input that has constant voltage and frequency. If the
magnitude of maximum variable output voltage equals to the input voltage, the
maximum output frequency is as high as 8 to 10 times the input frequency. It’s crucial
to adjust the speed for some reasons, such as machine or Process Requirements,
Energy Savings, Automated Factory Concept and Productivity Increases. The main
purpose of the VVVF is controlling the speed of the motor.
Description about the component of VVVF
The transformer will step down the voltage to the rectifier. The rectifier is able to
convert from ac to dc signal and also have an output signal without any distortion.
The inverter will convert from dc to ac again. If the VVVF becomes heated from
inside, there are cooling fans able to cool it. The Display is comprised of a graphical
LCD with some tabs for the display that has a various functional data, eight keys,
three LED’s, and encoder. (See the following figures)
Figure 9
Inverter (Convert DC to AC with different frequency)
Figure 10
Control circuit
Internship Report
11Page
Figure 11
Cooling fans
There are two group fans and each group has two fans. Each group is redundant
Protection System:
It's crucial to protect our plants and substations from the damages, Arc hazards, Faulty
currents, over voltages, etc.
Some Protection devices in brief:
CT: The current transformer steps down a current to the relay, so the relay can read it and
will check if any fault occurs, then the breaker will open to clear the fault. (See
Figure12)
Figure 12
(CT)
PT: The voltage transformer will step down a voltage to relay and thus breaker will trip if
any fault occurs.
Differential relay (Relay 87): If there is two current transformers and a transformer between them, and a differential
relay will measure the difference between the primary current and the secondary
Internship Report
15Page
current. If the difference occurs, then the relay will make the breaker to trip. (See
Figure 13).
(See Figure 13)
(Differential Relay)
Example for differential relay:
There are two CT and one transformer between them. The two CT will take the ratio
to Differential relay to see the different current as previously mentioned. If the fault
occurs externally, the relay will not operate, but if it occurs internally the relay will
operate. For higher external fault, the biased differential relay which has two
retraining coils is Ideal solution.
(The one on the left is internal fault and the one on the right is external fault)
Synchronism Relay (Relay 25): This relay is Ideal for the ATS, especially in Substations if there are three breakers.
One in section A, the other in section B and the third is between. If you want to open
one of both manually by using the button, the indication will come from the relay to
demonstrate which Section has a problem. If there isn't any indication, there won't be
damage if you hold the execution button for three seconds.
Internship Report
16Page
Fuses: Fuses are helpful to clear a fault over current in the system. If it fails, the circuit
breaker can clear. (See figure 15)
(Figures 15)
Fuses
The Company:
The best company that produces the petrochemical in the Middle East is SABIC
Company, which is established in 1975 in Jubail industrial city. Furthermore, Sharq
Company is established on May 1981, which is one of SABIC companies. The most
crucial products of Sharq Company are Polyethylene and ethylene glycol. The two
types of poly ethylene are the low density and High density. The department that I
was working at is Electrical and control system (ECS) in the electrical department.
This department is banished by the time. After that, the department name is changed
to PE & OLIFAN. The objectives of this Company are several such as ensuring
safety, Health and environment management system, High reliability operation,
effectively employ Saudi nationalities train them to provide them career developed
programmed and quality.
Sharq Safety:
In 19/6/2012, I attended the safety lecture in order to know the safety rules that must
be followed to work safely in Sharq without any injuries. The following rules are:
Safe yourself in order to save the environment.
The prohibited items are: lighters, mobile phones, recorders, radio.
Smoking is not allowed.
If you're in a plant, you can go the other plant by specific bus.
Furthermore, I must wear Sharq shirt & trouser. Also, Safety helmets and safety shoes
in the plants, or substations are required.
Internship Report
17Page
Root cause analysis:
In 20/6/2012, I attended a lecture which is about root cause analysis "RCA". This
lecture is about analyzing the problem and gives solutions for it, then ideal decision
for the problem.
RCA steps:
Understanding the problem.
Gathered data related to incident.
Analyze (Logic Tree).
Verify.
Identify Cases.
Generate recommended actions.
Team review with a sponsor.
Presentation to responsible person departments.
Implement recondition.
Observe effectiveness.
Revisit RCA / reaction.
Heat Stress Announcements:
These warning for the workers and when you will hear" May I have your attention
please" then he will mention the heat stress number (1, 2, 3, 4)
Heat stress Working Stop Working
1 45 min 15 min
2 30 min 30 min
3 15 min 45 min
4 - No working
Internship Report
18Page
Sharq substations layout:
Activities and responsibility:
I was asked to attend the daily activity at the morning every day. In addition, the
technician are explaining the problems and the devices that needs to be fixed or
changed such as motors, Valves, UPS and measuring insulation resistance between
phases in order to check the short circuit. There wasn't any responsibility for me as a
student because I am participating. The electrical engineer at Sharq is responsible for
any problem that occurs at substation and plants such as trouble shooting, short
circuit, testing the generators and changing relays and any kind of electrical problems
as previously mentioned. The manager Nasser AL-Mutairy asked me to write weekly
report and monthly report about what I am learning from this Company. The weekly
230KV S/S
Recever from SECCO
SG TYPE: GIS SIEMENS
115KV S/S
V: P-230KV/S-115KV
SG TYPE: GIS MITSUBISHI
1 MAIN
1 S/S
V: P-115KV/S-34.5KV
SG TYPE: SF6 CB MITSUBISHI
3 S/S
1UTL
4 S/S
1EG
1EG COMPRESER
1KM-1201
5 S/S
1PE 1T.P.S
7 S/S
Administer + MTC + NEW WAREHOUSE
13 S/S
1PE 2T.P.S
2 MAIN
10 S/S
Voltage: P-115KV/S-34.5KV
SG TYPE: SF6 CB SCHNEIDER
11 S/S
2UTL
12 S/S
2EG
2EG COMPRESER
2KM-1201
21 S/S
3UTL
3 MAIN
20 S/S
V: P-230KV/S-34.5KV
SG TYPE: SF6 CB MITSUBISHI
23 S/S 2PE 3 T.P.S
3EG COMPRESER
3KM-1201
33 S/S
3PE
22 S/S
3EG
4 MAIN
30 S/S
V: P-230KV/S-34.5KV
SG TYPE: SF6 CB ABB
32 S/S 4EG
V:P-34.5KV/S-13.8+4.16+480
SQUER D
31 S/S 4UTL
V:P-34.5KV/S-4.16KV+480V
SQUER D
38 S/S 4UTL C.T
V:P-34.5KV/S-13.8+4.16+480
SQUER D
34 S/S 4PE
V:P-34.5KV/S-13.8+4.16+480
SQUER D
36 S/S OLF
V:P-34.5KV/S-4.16+480
SQUER D
4EG COMPRSER
4KM-1201
V:P-34.5KV/S-13.5KV
SQUER D
37 S/S OLF
V:P-34.5KV/S-4.16+480
SQUER D
Internship Report
19Page
reports must be submitted to my supervisor Abdullah Al-Baghdadi and the monthly
report must be submitted to the manager.
Major tasks:
In 27/6/2012, I was asked to go with one of the technician to see how to change of the
relays in substation 34. It's the relay multiline 750 for the feeders in the low voltage
switch gear (480V). To change the relay, there are some steps that must be followed:
Isolate the required relay from the system.
Download the settings from the old relay to a portable laptop.
Upload the settings to the new relay.
Replace the new relay
Connect the relay by closing the Isolators and ATS execution button buttons.
In 29/7/2012, I was asked to see how they test the emergency generator1-G-8001 A,
B; C. which is located near to substation 36. Usually they test the three generators,
weekly without loads, and monthly without loads. In addition, each generator are in
series with vacuum circuit breakers. (See the single line diagram in the appendices)
There is a DMC that has a touch screen for the three generators. Furthermore, the
generators are feeding the bus bar in the MV switch gear (4.16kv)
.
DMC Touch Screen
Internship Report
21Page
Conclusion:
In conclusion, the internship period in Sharq Company was excellent for me in terms
of knowledge, experience, and practical life. The major tasks that I was asked to study
and observe were good for me to gain experience and not commit any mistakes in the
future. The plan that they gave me was about power system analysis. The engineer
must seek for the information by himself, so he won't forget it. Ultimately, the
company supported me to see the world of electrical works.
Internship Report
21Page
References:
1. "Protection system" Maintenance procedures, Sharq Maintenance Department.
2. "Cathodic protection" Maintenance Procedures
3. ALmaliki, Jabir. Personal Interview, 25/6/2012.
4. Al-Mutairir, Nasser, Personal Interview, 8/7/2012.
5. "UPS & charger'' Manual, Sharq Maintenance Department
6. "VVVF" Maintenance procedures, Sharq maintenance department
Internship Report
22Page
Appendices:
Short circuit calculations:
a. Impedance for transformers:
R p.u= R%* (1-impedance of tolerance) */ Machine Kva *100
X p.u= X% * (1- impedance of tolerance) * Base KVA/ Machine * 100
b. Impedance data of cable and Bus ducts:
R p.u= R Actual * Base MVA / (base KV) ^2
X p.u = X Actual * Base MVA/ (Base KV) ^2
c. Short circuit current:
I sc = base MVA / (√3 * Base KV * Zp.u)
Voltage Drop Calculations:
a) Percent of impedance:
Z% = ZA * KVA base * 100 / KV^2 * 1000
Where,
Z% = impedance, in percent
(Same equation for % R and % X shall be applied)
ZA = Actual impedance, in ohms
KVA base = Base KVA (1000000 KVA)
KV = System base voltage (13.8Kv, 4.16 KV, 0.48 kV, respectively)
(b) Voltage drop is calculated as follows:
E% = KVA/ KVA base * (%R CosΩ + X % SinΩ)
Where,
E% = Voltage drop, in percent
KVA = Actual load apparent power, in KVA
KVA base= Base KVA (1000000 KVA)
% R= Resistance, in percent
Internship Report
23Page
% X = Reactance, in percent
cosΩ = Power factor, in decimal
SinΩ = reactive factor, in decimal
(c) Impedance Data of transformers:
% R= %R act * (1+ impedance tolerance) * Base KVA/ Machine KVA
% X = %X act * (1+ impedance tolerance)* Base KVA/ Machine KVA
(d) Impedance of date of cable and bus ducts:
% R= R act * Base KVA/ (Base KV) ^2 * 10
% X= X act * Base KVA/ (Base KV) ^2 * 10
(f) To calculate equipment rated voltage:
Voltage drop= e% *(Rated system voltage)/(100)
Equipment rated voltage = Rated System voltage- Voltage drop.
Cable sizing calculations:
Calculation Steps:
1. 1. Finding the continuous current:
I= P/ (Voltage * CosΩ)
2. Capacity of cable = Cable * Rating of cable
3. Voltage drop (VD) = I (%R CosΩ+ X% SinΩ) * L/ 1000
4. Maximum length of cable= VD * 1000/ I (R cosΩ+ X sinΩ)
Where:
I Current in Amps (A)
R cable Resistance in ohms per kilometer (Ω/ Km)
CosΩ power factor of equipment
L Length of cable
X Cable reactance at 60 HZ in Ohms per kilometer (Ω/ km)
Internship Report
21Page
Single line Diagram (From Sceco Side)
Emergency Generators
Internship Report
25Page
Appendix C: Industry Supervisor Report
Internship Report
26Page
Appendix D: Student Feedback Form
Internship Report
27Page
Appendix D: Student Log Sheet
Internship Report
28Page
Progress Report 1
Prince Mohammad Bin Fahd Univers i ty
C o l l e g e o f E n g i n e e r i n g
Department of Mechanical Engineering
Internship Report
at
Sabic- Sharq
R e p o r t i n g P e r i o d :
[16/6/2012 - 15/8/2012]
S u b m i t t e d b y :
K h a l i d A L - H u s s a i n
[ 2 0 0 7 0 0 2 6 3 ]
[ s u b m i s s i o n d a t e ( 9 / 7 / 2 0 1 2 ) ]
Electrical Engineering Department
Summer 2012
Internship Report
29Page
Summary:
Sabic Company is established in 1976 by royal decree. Its task is setting up operate
hydro carbon and mineral based industries in KSA and transferring them to good
value. This will assist the kingdom in terms of industrial base.
Back ground:
In 16/ 6/2012, I went to ALRazi to sign my papers to work in Sharq. Further, I went
to the maintenance building to meet my supervisor to know what I have to learn from
this training. The name of the company is Sabic and I am working in Sharq at ECS,
Electrical Department. Abdullah AL-Baghdadi is my supervisor and I can contact him
by the following information: email: [email protected], T: +966 (3)
357 5000-5862 Ext.5862, F: +966 (3) 357 5275, Job: Electrical engineering. P.O.
Box 10035, Mobile: +96655468875,
In the first week, the supervisor asked me to go through Power system by GE training
Software that is helpful for enhancing my Knowledge about my field. Also, I must
attend the safety orientation lecture to know the rules. The second week, I was asked
to go to substations to relate theoretical studies to practical life.
Progress:
First week:
1. Attending the SHE orientation to learn the following: (19- june-2012)
Safe yourself in order to save the environment.
The prohibited items are: lighters, mobile phones, recorders, radio.
Smoking is not allowed.
If you're in a plant, you can go the other plant by specific bus.
Moreover, I must wear the Sharq shirt and trouser. In the plants, the safety shoes and
helmet are significant.
2. Root Cause analysis lecture" RCA": (20-June-2012)
I learned the following steps:
Understanding the problem.
Gathered data related to incident.
Analyze ( Logic Tree).
Verify.
Identify Cases.
Generate recommended actions.
Internship Report
31Page
Team review with a sponsor.
Presentation to responsible person departments.
Implement recondition.
Observe effectiveness.
Revisit RCA / reaction.
3. GE training software:
I went through power system analysis and Distribution system.
Second week:
I went to the following substations:
Substation 38:
I saw the following:
Switch Gear:
There is a Medium Voltage Switch gear (13.8KV) and low voltage switch gear
(480V). Each switch gear has Protective Relays such as 750 relay for the feeders, 745
for the transformers, and the 469 relay for the motors. Also, switch gears has Circuit
breakers, ATS, and Relay test blocks which used for testing the relays.
Motor Control center (MCC):
It's the same as switch gear, but it has contactors instead of circuit breaker and fuses
for protecting over currents. 469 relay.
Charger:
There is an input MCCB switch will allow the rectifier to work to convert from Ac to
dc to charge a battery for emergency. If any dc control in fails, the battery will feed it.
UPS:
A UPS has rectifier and inverter. Rectifier will convert from ac into a dc to allow the
battery work, and then inverter will convert from dc to ac again. If it fails, the Bypass
MCCB will work, so the transformer will feed the load. If an ac device fails, the UPS
will feed it.
Substation 3:
It's the same as other substations, but the switch gears have an old relays such as relay
27(Under voltage relay), relay 49(Transformer thermal relay), relay 50(Over current
relay), 51 and (Over current) and 52 (Air circuit breaker). Also, a potential
transformer used for high voltage and low voltage.
Internship Report
31Page
Substation 31:
It has same things as substation 38, except that it doesn't has fixed capacitors and
UPS. But, there is an emergency ABB transformer.
Problems:
a. In substation 3, the problem is the GE Multilin 750 relay in switch gear
(480V-Low voltage) must be changed, which is for the feeder. The setting
must be downloaded to pc from the old one, then down load it into the new
relay.
b. In substation 31, there was short circuit for one of the three phase motors. The
technician used an insulation resistance device to measure the insulation
between two phases and also for each phase with ground. Ultimately, he
discovered short circuit between one phase and ground.
Plans:
The supervisor gave me a plan for two months. In addition, I must submit weekly
report and two monthly reports to him and attending daily activity.
Internship Report
32Page
Progress Report 2
Prince Mohammad Bin Fahd Universi t y
C o l l e g e o f E n g i n e e r i n g
Department of Electrical Engineering
Internship Report
at
Sharq Company
R e p o r t i n g P e r i o d :
[30/6/2012-11/7/2012]
S u b m i t t e d b y :
K h a l i d A L - H u s s a i n
2 0 0 7 0 0 2 6 3
s u b m i s s i o n d a t e ( 1 3 / 7 / 2 0 1 2 )
Electrical Engineering Department
Summer 2012
Internship Report
33Page
1. Summary:
Protection system is crucial in terms of protecting our equipments in substations. In
addition, Power System, calculation required for designing the system and this is I
suppose to know as electrical engineer.
Back Ground: 2.
Protection system is the ability of sensing a fault to take an appropriate action within a
time frame necessary to minimize damages, interruption power, and Safety issues.
Going to substations to see the devices in reality is helpful to understand.
Furthermore, Load flow studies, short circuit calculations, voltage drop calculations,
Cable sizing calculations and power factor study are significant in the world of power
electrical engineering. These are the things that my supervisor asked me to do in two
weeks.
Progress: 3.
According to my plan, the supervisor asked me to do the following tasks:
Week3:In
I was assigned to study the protection devices before going to the substations.
Protection devices:
First, the current transformer is used to step down a current to the relay to check if
any faults occur, so the breaker will open to clear the faults. Second, the Voltage
transformer that will step down a voltage to relay to do what previously mentioned.
Third, differential relay, which work by adding two current transformers and a
transformer between them, and thus a differential relay will see the difference
between the primary current and the secondary current. If the difference occurs, then
the relay will make the breaker to trip.
Other protection equipments such as fuses are helpful to clear a fault over current in
the system. If it fails, the circuit breaker can clear. Fuses are available, in the MCC,
and many places.
c transfer Switches):ATS (Automati
Useful for two sections in switch gears. For instance, breaker in section A and other
breaker in section B and the third is between. The two breakers in section A and B are
normally closed and the third is normally open. The ATS is able to close the third
Breaker manually or automatically and open A and thus B will feed the feeders. It is
also able to do the opposite and make A feeds the others. What is more, the
Internship Report
31Page
synchronism relay can sense to indicate which section has a problem, so we can stop
this operation.
Substations:
I went to substation 5 to see the VVF and what is it for, Relay 25 (Synchronism
relay), CT and VT, Relay 86(Differential relay), Relay 50G (Over Current Relay),
two neutral ground resistance (A &B) and Selector switch of RTD in MCC.
I went to substation 3 to see, Relay 50(Over current relay), Relay 51(AC Time Over
, Relay 25 (Synchronism Relay) Relay )current Relay), Relay 27(Under voltage Relay
86 (Differential relay) Two neutral ground resistance: 3GD-1A, 3GD-1B for (3TX-A)
and (3TX-1B).
Week 4:In
I was asked to study the following:
Short Circuit:
Short circuit is a fault over current that occurs between two phases or phase and
ground. Usually, the short circuit happens as result of week insulation or improper
wiring of broken insulation.
Conditions of calculations:
1. The actual circuit must be converted into per-unit impedance circuit.
2. The impedance of transformer, cables, bus ducts, etc. are required in per unit.
Other impedances such as breakers and CT are neglected.
3. Using an appropriate theory or analysis to calculate the short circuit faulty
current.
Voltage drop:
The purpose is observing the voltage difference between the supplied voltage and the
drop voltage at the bus bar or the load.
Conditions of calculations:
4. Drawing the equivalent of per unit impedances for each element of the circuit.
5. Impedance of transformers, cables, bus ducts, etc are required. Impedances of
transformers, etc. are neglected.
6. Applying mathematical equations to calculate the percentage drop.
Internship Report
35Page
Cable sizing calculation:
It's crucial to calculate the cable length and size to deliver appropriate current, voltage
and power flow to the motor.
Steps of calculations:
4. Finding the continuous current.
5. Finding the voltage drop across the cable.
6. Calculating the Maximum length of cable.
Power factor study:
When the load is inductive (Lagging power factor), the capacitor can enhance the
voltage conditions, reducing the current, reducing line losses and reducing power bills
and ultimately leading power factor. The perfect power factor is close to one.
Load Flow Calculations:
Load flow calculation is about studying Voltage Profile, Power Flows, Current Flows,
Power Factors, Transformer LTC Settings, Voltage Drops, Generator’s Mvar Demand
(Qmax & Qmin), Total Generation & Power Demand, Steady State Stability Limits,
MW & Mar Losses.
4. Plans:
I was assigned to attend daily activity and writing a weekly report about the work
done in these two weeks. The next two weeks will be about Transformers and VVF.
5. Conclusion:
In conclusion, protection system is helpful to avoid equipments damages, hazards, and
fault currents and thus the substations and plants are under control. Power system
calculations and studies are helpful in terms of designing perfect plants equipment.
Internship Report
36Page
Prince Mohammad Bin Fahd Universi t y
C o l l e g e o f E n g i n e e r i n g
Department of Mechanical Engineering
Internship Report
at
[Sabic-Sharq]
R e p o r t i n g P e r i o d :
[14/7/2012 - 25/7/1012]
S u b m i t t e d y :
[ K h a l i d A L - H u s s a i n ]
[ 2 0 0 7 0 0 2 6 3 ]
[ s u b m i s s i o n d a t e ( 2 7 / 7 / 2 0 1 2 ) ]
Mechanical Engineering Department
Summer 2012
Internship Report
37Page
Summary:
I was assigned these two weeks to study about transformers and VVF. My supervisor
noticed that it's hard to cover the requirements in two month. Therefore, it seems that
I will have a beneficial pressure, so he asked me to do other things. My assignments
in these two weeks are about transformers and Basics trainings.
Back ground:
According to my plan, I have to learn more about transformers in the fifth week, but
my supervisor asked me to seek for other details because of the short period. The
week after, I was assigned to see the basic trainings in the company. Though it's hard
to cover the majority of heavy, I was motivated to try to learn as much as I can from
them. Moreover, I am joining a small group in the basic training.
Progress:
My assignment in these two weeks:
Plan work Period
Transformers, Generators, GIS 14/7/2012-18/7/2012
Basic Training 21/7/2012-25/7/2012
Week 5:
Transformers:
The main purpose of transformers is either steeping down or stepping up. This
depends on the on what is needed for the load. Usually, transformers feed substations,
three phase motors, transmission lines, etc. there are two types of transformers. The
first type is the dry type transformer. The second type transformer is liquid filled type.
Dry type of transformer:
The dry type of transformer has limited size around 10 MVA because it relies on air
to provide cooling and its losses are high. Further, It can be designed to operate at
much higher temperature than Liquid-filled (temperature rises as high as 150oC,
whereas oil filled as 100oC to avoid acceleration of breakdown of oil).
Liquid filled type:
This type of transformer is relying on oil. There is sealed type and non- sealed type.
Sealed type:
Internship Report
38Page
The sealed type has a temperature gauge. When the temperature is increasing, the size
of the oil will be increased and thus the air will go out with the moisture. The nitrogen
gas and oil and oil will be inside the tank and that's why we call t sealed. On the other
hand, the non-sealed is not closed as the sealed one and it has there is a breather.
Brief description about oil filled type equipments:
The breather of the transformer absorbs the moisture by silica jell. The radiator of the
sealed type is for cooling the oil. The bushings are above the terminal box to hold the
cables, and insulate between the cables and the box to avoid short circuit. Tap changer
which is located in the primary windings to switch and control the voltages. There are
two types of tap changers. ON load tap changer and off load tap changer.
Gas insulated switch gear:
It is the upstream of the substations. A gas (SF6) insulated substation may have
underground feed lines and be nearly invisible to the average person. Distribution
circuits supplied by gas insulated substations normally have an alternate feed from
another substation, to allow maintenance work on the gas insulated site. For instance,
Sceco is feeding Sharq Company and the GIS will feed transformer to feed
substations. (See figure 1)
Generators:
The generator has an exciter which is series to the load will produce a magnetic field
to the stator windings. Then, the induced voltage in the stator winding that ends
currents will be delivered to the load. There is a prime mover will produce steam for
the turbine to rotate and ultimately the generator will rotate. Therefore, the generator
converts the mechanical energy into electrical energy. There are other sources of
generations such as hydro-electric, nuclear, fossil fuels, and diesel engine. (See
figure2)
Week 6:
There is a basic training that I have to attend in order to enhance my knowledge about
my major. It was interesting training that I've ever seen in my university life.
Furthermore, the instructor was expert to teach this course.
Fluorescent lights:
There are two types of fluorescent lights. The first is t is preheat type, when the circuit
is energized the current will flow from cathode A and then to cathode b through the
starter and there will heat the gas inside the lamp and thus an arc will occur across the
fluorescent lamp. The second is the rapid. The rapid start ballast will deliver a small
voltage to heat the cathodes. There isn't starter needed and cathodes will heat the gas,
so the gas will be increased and higher current and lower resistance.
Internship Report
39Page
Mercury Vapor and Sodium:
The ballast will deliver a voltage to the electrodes. The starter resistor will control the
current flowing. An arc will be struck between the starting electrode and the two main
electrodes. Therefore, the current will be high and resistance and that makes the
mercury vapor increased. Ultimately, the lamp is working. Sodium vapor doesn't have
the starting resistor and electrodes, but only two main electrodes. However, there is an
igniter that will deliver high voltage and high frequency to the electrodes and heat the
sodium vapor and arc will occur to make the lamp work.
Single Phase Motor:
The supply voltage will deliver current which will go into two loads. The first load
has Capacitor, Centrifugal switch and starting winding. The second load has running
winding. The current will flow through the capacitor and centrifugal switch and then
starting winding. The starting winding will produce a magnetic field to make the rotor
rotate. When the rotor reaches the required speed, the centrifugal switch will open.
The running winding will make the rotor to continue rotating. The purpose of having
the capacitor in the circuit is maintain the wattage, voltage , and also to make phase
shift between the running period and starting period is 90.
Plan:
I was supposed to learn about transformers and VVF this week. But the supervisor
asked me to do more as a result of the short period. The supervisor is a good person
who is helping for my future.
Conclusion:
In conclusion, the generator will generate power to the GIS, and the GIS will feed the
transformers that will step down voltages for the substations. The Basic training
course was helpful for me to enhance and improves my knowledge. The engineer
must seek for the information by himself to learn.
Internship Report
11Page
Appendices:
GIS in ABB:
Figure 1
Generators performance:
Figure 2
Internship Report
11Page
Prince Mohammad Bin Fahd Universi t y
C o l l e g e o f E n g i n e e r i n g
Department of Electrical Engineering
Internship Report
at
[Sabic-Sharq]
R e p o r t i n g P e r i o d :
[28/7/2012 - 8/8/2012]
S u b m i t t e d b y :
[ K h a l i d A L - H u s s a i n ]
[ 2 0 0 7 0 0 2 6 3 ]
[ S u b m i s s i o n D a t e ( 1 0 / 8 / 2 0 1 2 ) ]
Electrical Engineering Department
Summer 2012
Internship Report
12Page
Summary:
I was assigned in the last two weeks to study the Cathodic protection and VVVF.
Also, I was assigned to go with my supervisor to see the emergency Generators in
order to test them and How their performance.
Back ground:
The buried Pipelines are in the underground need to be protected from the corrosion
that leads to the erosion. By the cathodic protection methods, the metal pipes will be
in a safe situation from falling down and short circuits problems. In Sharq, they are
testing the emergency generator weekly without load and monthly with load. The
purpose of having VVVF is controlling the speed of the motor.
Progress:
Plan work Period
Cathodic protection, Testing Generators 28/7/2012- 1/8/2012
VVF 4/8/2012-8/8/2012
Table 1
Week 7:
Cathodic protection:
Cathodic protection is a technique which is useful to protect the metals such as,
Buried pipelines, Storage tanks and reinforced concrete from the corrosion. There are
two beneficial methods are useful to protect our sources from the corrosion. The first
method is impressive current method (ICCP). The second method is the sacrificial
anode method (SACP).
The Impressive Current Method:
For larger structures, galvanic anodes cannot deliver enough current to provide
complete protection. The Impressive Current method uses anodes connected to a DC
power source. The rectifier bridge is useful to convert from ac source to dc powers
source. At the end of the rectifier bridge circuit, there are two terminals. The positive
terminals for the anode for decaying and the negative terminal are for the cathode for
protection. Ultimately, we can protect the Pipe lines from the corrosion and avoiding
short circuit.
Sacrificial Anodes Cathodic protection:
If we add the Fe to a carbon, it will become hard steel. In addition, the magnesium
will be a good solution to avoid the corrosion. The magnesium can be considered as
Internship Report
13Page
the anode part for decaying, and the steel can be considered as the cathode part for
protection.
Problems:
I went with my supervisor to see him how is going to test the three generators in the
Emergency generators building which is near to Substation 36. There was a DMC that
controls the generators and it has Touch screen to control the Three Medium voltage
generators 1-G-8001 A, B; C. the three (4.16 KV) generators are in series with three
Vacuum circuit breakers to feed the bus bar MV switch gear . The switch gear is in
substation 36.
Week 8:
VVVF:
The variable voltage variable frequency is electronics power device which is able to
control the speed of the motor. Adjusting the speed is crucial for some reasons such as
machine or Process Requirements, Energy Savings, Automated Factory Concept and
Productivity Increases.
The components of the VVVF:
The components of the VVVF are many such as integral transformer, Rectifier,
inverter, control circuit, cooling fans, Display/ Key and Isolation. (See the
appendices).
Plan:
My supervisor asked me to see the emergency generators in week 7. Also, I went
with one of the technician to substation 5 to see the variable voltage variable
frequency.
Conclusion:
In conclusion, the cathodic protection is special technique to protect the buried
pipelines and other metals form the corrosion. Further, it's a good experience to for
me to see how they test the emergency generators. Variable Voltage Variable
frequency is panel is useful the control the speed of the motors.
Internship Report
11Page
Appendices:
Figures:
Figure 1
Inverter (Convert DC to AC with different frequency)
Figure 2
Control circuit
Figure 3
Cooling fans
There are two group fans and each group has two fans. Each group is
redundant.
Internship Report
15Page
Single Line Diagram :
Figure 4
Emergency Generators