+ All Categories
Home > Documents > Privatisation and Regulation of Business

Privatisation and Regulation of Business

Date post: 03-Apr-2018
Category:
Upload: tarakeshwar-allamsety
View: 220 times
Download: 0 times
Share this document with a friend

of 24

Transcript
  • 7/28/2019 Privatisation and Regulation of Business

    1/24

    Privatisation and Regulation of Business

    Assignment

    Done By

    1101101-1101120

  • 7/28/2019 Privatisation and Regulation of Business

    2/24

    TABLE OF CONTENTS

    TABLE OF CONTENTS......................................................................................2

    ANNEX 5-2: CONCESSION CONTRACTS & PUBLIC-PRIVATE

    PARTNERSHIPS.....................................................................3

    1. WHATISA CONCESSION?.................................................................................3

    1.1 Definition & application framework...........................................................3

    1.2 Particularities in the application of concessions.......................................4

    2. PUBLIC-PRIVATE PARTNERSHIPS.......................................................................8

    2.1 What is a Public-Private Partnership (PPP)?...........................................8

    2.2 Forms of Public-Private Partnerships (PPPs)..........................................9

    2.3 PPPs compared to other types of contract.............................................14

    2.4 Critical success factors for PPP contracts.............................................15

    2.5 Advantages and drawbacks of the application of PPPs.........................16

    2.5.1 Advantages of the application of PPPs .............................................16

    2.5.2 Potential drawbacks of the application of PPPs.................................19

    2.6 Steps in awarding and implementing a PPP contract............................20

    2.7 PPP Projects in the EU and examples of sectors where PPPs are

    applied..........................................................................................22

  • 7/28/2019 Privatisation and Regulation of Business

    3/24

    on0242.ico

    ANNEX 5-2: CONCESSION CONTRACTS & PUBLIC-PRIVATE PARTNERSHIPS

    1. WHATISA CONCESSION?

    1.1 Definition & application frameworkConcessions are not defined in the EU Treaty. The only relevant definition is found in the

    secondary legislation (Community Directives etc.), where a special status is foreseen in

    particular for public works concessions, together with a general reference regarding service

    concessions.

    The concept of concession is in principle defined by the Community legislator on the

    basis of the concept of public contracts. In this context:

    A public works concession is defined as a contract of the same type as a public

    works contract, except for the fact that the consideration for the works to be carried out

    consists either solely in the right to exploit the work or in this right together with

    payment (Directive 2004/18/EC, Article 1, and Law 12(I)2006, Chapter VII).

    Similarly:

    A service concession is defined as a contract of the same type as a public service

    contract, except for the fact that the consideration for the provision of services consists

    either solely in the right to exploit the service or in this right together with payment

    (Directive 2004/18/C, Article 1, par. 4).

    This, however, does not mean that concessions are exempted from the rules of the Treaty.

    As pointed out in the Commission Interpretative Communication on Concessions under

    Community Law (2000/C121/2, p. 3), works or service concessions are subject to the rules

    and principles of the Treaty.

    Regarding public works concessions, Community Directive 2004/18 and Law 12(I)2006 of

    the Republic of Cyprus contain specific provisions (Title III, Chapter I, and Chapter VII,

    respectively).

    Regarding service concessions, the Community and the national law provide that the

    provision under these rules do not apply to service concessions (Directive 2004/18?EC,

    Article 17, and Law 12(I)/2006, Article 16).

    According to this definition, the main distinctive feature of a works concession is that a right

    to exploit a construction is granted as a consideration for having erected it. This right may

    also be accompanied by payment.

    In general, if the contract is principally concerned with the construction of a work onbehalf of the Contracting Authority, then the Community legislator holds that it should be

    considered to be a works concession.

    n1398

  • 7/28/2019 Privatisation and Regulation of Business

    4/24

    con0242.ico

    on0242.ico

    In contrast, a concession contract in which the construction work is incidental or which

    only involves operating an existing work, is regarded as a service concession.

    In a works concession, the risks inherent in exploitation are transferred to the

    Concessionaire.

    If recovery of expenditure were guaranteed by the Contracting Authority without the

    risk involved in the management of the work, there would be no element of risk andthe contract should be regarded as a works contract rather than a concession contract.

    Moreover, if the Concessionaire receives, whether directly or indirectly, during the course of

    the contract or even when the contract comes to an end, payment (by way of reimbursement,

    covering losses etc.) other than connected with exploitation, the contract could no longer be

    regarded as a concession. In this situation, the compatibility of any subsequent financing

    should be considered in the light of any relevant Community law.

    The definition of a concession allows the Contracting Authority to make a payment in return

    for work carried out, provided that that this does not eliminate a significant element of the risk

    inherent in exploitation.By specifying that there may be payment in addition to the right to exploit the work, the

    Community legislator states that operation of the structure must be the source of the

    Concessionaire's revenue.

    The determining factor in concessions continues to be the existence of the exploitation

    risk in connection with the investment made or the capital invested, particularly when

    the awarding authority has paid a sum of money. This applies as a general principle, even

    though in most concessions the origin of the resources comes from payments made directly

    by the users of the work (such as for example in the case of motorway tolls).

    In concessions, the risks arising from the operation of the concession are transferred to theConcessionaire with the right of exploitation.

    The division of specific risks between the Contracting Authority and the Concessionaire takes

    on a case by case basis, according to their respective ability to manage the risk in question.

    If the Contracting Authorities undertake to bear the risk arising from managing the work by,

    for example, guaranteeing that the financing will be reimbursed, there is no element of risk

    and the Community legislator considers such cases to be public works contracts and not

    concessions.

    In general, the correct approach to interpreting the above provisions requires, in order

    for a contract to be designated as a concession contract, the assessment of its duration and

    of the collection of a consideration from the operation of the work; this, however, should be

    combined with the transfer to the contractor of the investment risk and operating risk which,

    were they to remain within the sphere of control competence of the Contracting Authority,

    might be indicative of a classic public works contract.

    1.2 Particularities in the application of concessionsAs already mentioned, insofar as concessions result from acts of the Contracting Authority

    the purpose of which is to provide economic activities or the supply of goods, they aresubject to the relevant provisions of the Treaty and to the principles which derive from

    the Court case law in the respective areas.

    n1398

    n1398.

  • 7/28/2019 Privatisation and Regulation of Business

    5/24

    on0242.ico

    These rules and principles are already known and have been mentioned in several Chapters

    of this Guide: they are the principle of equality of treatment, the principle of transparency, the

    principle of proportionality, and the principle of mutual recognition.

    In awarding concessions, the Contracting Authorities must adhere to the above principles of

    the Treaty. More in particular:

    The principle of equality of treatment

    The application ofthe principle of equality of treatment to concessions (which is obviously

    only possible when the Contracting Authority negotiates with more than one economic

    operators as potential concessionaires) means that the Contracting Authority is free to

    choose the most appropriate award procedure, especially in relation to the characteristics of

    the particular project, and to lay down the requirements which candidates must meet

    throughout the various phases of the relevant tendering procedure.

    However, this implies that the choice of candidate(s) must be made on the basis of objective

    criteria and the procedure must be conducted in accordance with the procedural rules and

    basic requirements originally set by the Contracting Authority.

    Where these rules have not yet been set, the application of the principle of equality of

    treatment requires in any event that the candidates be chosen objectively.

    The Court of Justice of the European Communities (ECJ) had the occasion to set out

    the scope of the principle of equality of treatment in the area of public contracts, by

    asserting on the one hand that this principle requires that all tenders conform to the terms of

    the contract, so as to guarantee an objective comparison between tenders (Judgement of 22

    June 1993, Case C-243/89, Storebaelt, point 37), and, on the other hand, that when an

    Contracting Authority takes account of changes to the initial tenders of only one tenderer,

    who thereby obtains an advantage over his competitors, then the principle of equality of

    treatment of the tenderers is violated and the transparency of the procedure is impaired.

    Moreover, the Court notes that the procedure for comparing tenders has to comply at every

    stage with both the principle of the equal treatment of tenderers and the principle of

    transparency, so as to afford equality of opportunity to all tenderers when formulating their

    tenders (Judgment of 25 April 1996, Case C-87/94, Walloon Buses. See also Judgment of

    the Court of First Instance of 17 December 1998, T-203/96, Embassy Limousines &

    Services).

    In certain cases, the Contracting Authority may be unable to specify its requirements

    in sufficiently precise technical terms, and will look for alternative tenders likely toprovide various solutions to a problem expressed in general terms. In such cases, however,

    in order to ensure fair and effective competition, the documents issued by the Contracting

    Authority must always state in a non-discriminatory and objective manner what is asked of

    the candidates and above all the way in which they must draw up their tenders.

    In this way, each candidate knows in advance that he has the possibility of proposing various

    technical solutions.

    More generally, the documents issued by the Contracting Authority must not contain

    elements that infringe the abovementioned rules and principles of the Treaty.

    The requirements of the Contracting Authority may also be determined in

    collaboration with economic operators, provided that this does not restrict competition.

    n1398

  • 7/28/2019 Privatisation and Regulation of Business

    6/24

    on0242.ico

    on0242.ico

    on0242.ico

    The principle of transparency

    The principle of transparency can be ensured by any appropriate means, including

    advertising, taking into account the particularities of each project.

    For example, transparency can be ensured, among other means, by way of

    publishing a Concession Notice or a pre-information notice in the daily Press or in

    specialist journals, or by posting appropriate notices

    This type of advertising generally contains the information necessary to enable

    potential concessionaires to decide whether they are interested in participating

    (selection and award criteria, etc.). This information also includes the subject of the

    concession and the nature and scope of the services expected from the Concessionaire.

    The principle of proportionality

    According to the principle of proportionality, any measure chosen should be both

    necessary and appropriate in the light of the objectives sought.

    When applied to concessions, this principle allows Contracting Authorities to define the

    objective to be reached, especially in terms of performance and technical

    specifications. This implies that any measure chosen must be both necessary and

    appropriate in relation to the objective set.

    Thus, for example, when selecting candidates, a Contracting Authority may not

    impose technical, professional or financial conditions which are excessive and

    disproportionate to the subject of the concession.

    The principle of proportionality also requires that competition and financial stability be

    reconciled. Therefore, the duration of the concession must be set so that it does not limit nor

    restrict open competition beyond what is required to ensure that the investment is paid off

    and there is a reasonable return on invested capital, whilst maintaining a risk inherent in

    exploitation by the concessionaire.

    The principle of mutual recognition

    The principle of mutual recognition has been laid down by the Court Case law andgradually defined in greater detail in a large number of judgments on the free circulation of

    goods, persons and services.

    According to this principle, a Member State must accept the products and services

    supplied by economic operators in other European Union countries, if the products

    and services meet in like manner the legitimate objectives of the recipient Member State.

    The application of this principle to concessions implies that the Member State in which the

    service is provided must accept the technical specifications, checks, diplomas, certificates

    and qualifications required in another Member State, if they are recognised as equivalent to

    those required by the Member State in which the service is provided.According to the Community Directive and the national transposition law on public works

    concessions, the following also apply within the framework of the principles of the Treaty:

    I n0728.i

  • 7/28/2019 Privatisation and Regulation of Business

    7/24

    In terms of advertising, Contracting Authorities wishing to award a public works

    concession contract shall make known their intention by means of a relevant notice.

    Such notices shall be published in the OJEU and in the national Press.

    Notices concerning public works concessions contain the information listed in Annex

    VIIC of Directive 2004/18/EC, and any other information which the Contracting

    Authority may consider necessary, and are submitted using the standardised forms of

    the European Commission.

    In terms of time limits, when Contracting Authorities resort to a public works

    concession, the time limit for the presentation of applications for the concession usually

    cannot be less than 52 days from the date of dispatch of the notice.

    Chapter VII of Law 12(I)/2006 presents in detail the rules applicable to public works

    concessions. These rules concern, inter alia, time limits, subcontracting, awarding of

    additional works to the concessionaire, contracts awarded by the concessionaire to third

    parties etc.

  • 7/28/2019 Privatisation and Regulation of Business

    8/24

    on0242.ico

    on0242.ico

    2. PUBLIC-PRIVATE PARTNERSHIPS

    2.1 What is a Public-Private Partnership (PPP)?A Public-Private Partnership (PPP) is a public contract concluded for a long period oftime (usually 15 to 30 years) between a public sector entity and a private sector entity

    for the construction of infrastructure works and the provision of services of a public nature.

    This type of contract is increasingly applied in the European market, and also in the market

    of the new EU Member States.

    PPPs refer to various forms of cooperation of private investors with the public authorities,

    which also include Local Authorities, for ensuring all or part of the financing, construction,

    renovation, management and maintenance of an infrastructure, or the provision of a service,

    in sectors where full deregulation of the market is either unfeasible or undesirable.

    On the basis of the contract entered into, the private partner undertakes to finance,design and construct the project and operate it for the period of time agreed in the

    relevant contract. When the contract expires, the operation of the project is undertaken by

    the Public Authority on whose behalf the contract was entered into. The Contracting Authority

    of the public partner determines the framework and the requirements of the tendering

    procedure (tender documents), and the private partner assumes the construction risk and

    operation risk for the project and, is remunerated during the projects operation phase by way

    of a consideration (monetary or otherwise) which it receives either from the Contracting

    Authority or the public authority on whose behalf the project is put out to tender, or directly

    from the users, or in some cases by both (the public sector & the users). If the

    consideration is paid directly from the users, then the private partner undertakes theexploitation risk.

    The participation of the private sector in the implementation of works and services is either in

    the form of an associated partner for their implementation, or in the form of service provider

    to the public sector.

    The key distinction that can be made in terms of the contractual contents of PPPs is

    their distinction in compensatory contracts, where the use of the infrastructure/service

    is borne directly by its users, and in non-compensatory contracts, where usage costs are

    assumed by the public sector through regular payments, on the basis of concrete

    specifications regarding service quality and availability.Through PPPs, the public authorities aim to improve the quality of the services provided to

    the citizens, achieve savings in the resources of the public sector and of the local authorities

    which may be channelled to the implementation of additional projects and programmes, and

    utilise the advantages, experience, know-how and operation methods of the private sector.

    The international experience has shown that PPPs make possible the provision of high-

    quality services and goods that meet the requirements of citizens in a cost-efficient and

    effective manner. Indicatively, from the efforts and contracts entered into to this date, it has

    been found that the successful implementation of PPPs has lead to reductions of 15-20% in

    the overall financial cost of the provision of the public service foreseen, compared to thetraditional procurement methods.

    n1398.

  • 7/28/2019 Privatisation and Regulation of Business

    9/24

    on0242.ico

    On the other hand, the use of PPPs should not be presented as the only one or the

    best solution for a public entity facing budget constraints. To proceed to the

    application stage, the financial and organisational choices made in setting up the partnership

    to carry out the project must offer real value added value compared with other options (such

    as the conclusion of a more traditional method).

    The success of a PPP in practice depends to a great extent on the completeness of

    the contractual framework to be agreed, and on the precision and clarity of the terms

    to govern its implementation. Clear separation of roles, precise assessment and, in

    particular, optimum distribution of risk between the two parties, together with the clear

    definition of the responsibilities undertaken by each one of them, are of decisive importance.

    The scope of the cooperation and the risks associated with it must be distributed between

    the parties according to the respective ability of each party to assess and control them more

    efficiently and thus achieve the best possible utilisation of its skills, capacities and

    experience.

    2.2 Forms of Public-Private Partnerships (PPPs)During the last 20 years, various contractual PPP forms (PPP contracts) have been

    developed and tried internationally.

    All these forms have a minimum common core:

    The relatively long duration of the contractual relationship.

    The total or partial funding of the project by the private partner, often through complex

    arrangements.

    The important role of the private partners, who ensure the projects financial

    parameters, as opposed to the role of the public partner, who ensures the publicinterest (objectives, quality, pricing policy etc.).

    The distribution of risks between the public sector and the private partners, in such a

    way that the latter assume management of inherent risk factors which, in the case of

    public works, are today assumed by the public sector.

    The Green Paper issued by the European Commission in 2004 (COM(2004) 327 final,

    Brussels, 30-04-2004), distinguishes between two forms of PPPs:

    PPPs of a purely contractual nature, in which the partnership between the public and

    the private sector is based solely on contractual links, with a further distinction between

    concession contracts, characterised by the direct relationship between the private

    partner and the end user, under the control of the public sector, with payment in the

    form of fees imposed on the users, and Public Finance Initiative (PFI) contracts, in

    which the private partner is required to implement and manage a public administration

    infrastructure (school, hospital etc.), with payment in the form of regular payments

    made by the public sector (availability fee), and

    PPPs of an institutional nature, involving cooperation between the public and the

    private sector within a distinct entity (Special Purpose Vehicle or SPV).

    There are many types of PPP contracts, which are adapted to each particular project.

    Their main advantages, provided that there are applied properly, are:

    The need to secure funds of the State budget,

    I n0728.i

  • 7/28/2019 Privatisation and Regulation of Business

    10/24

    The quality improvements in infrastructure construction and service provision,

    The mobilisation of private sector know-how on project design and implementation, and

    The significant curtailment of lifecycle costs for a project or service.

    The most widely used forms of PPP contracts are listed in the Table below:

    Table 1: Most widely used PPP forms

    B.O.T. (Build-Operate-Transfer) & BOOT (Build-Own-Operate-Transfer)

    D.B.F.O. (Design - Build - Finance - Operate)

    B... (Build - Transfer - Operate)

    B.O.O. (Build - Own - Operate)

    B.B.O (Buy - Build - Operate)

    L.R.O (Lease - Rehabilitate - Operate)

    B..L.T (Build - Own - Lease - Transfer)

    O.M. (Private Services Contract : Operation and Maintenance)

    O.M.M. (Private Services Contract : Operation, Maintenance and Management)

    In particular, these PPP forms involve the following:

    ... (Build Operate Transfer)and .... (Build Own-Operate Transfer)

    The private contractor constructs, maintains and operates the project, on the basis of the

    specifications agreed with the public sector. The project is either owned by State entities

    (B.O.T.) or assigned for a predetermined period of time to the private partner (B.O.O.T.), who

    upon expiry of the exploitation period (concession), transfers to the public sector the projects

    operation (BOT) or ownership (BOOT). In most cases, the private partner is responsible forpart or for the entirety of the financing for the project.

    This form, considered as the most widely used of all PPP forms, was for example adopted by

    Greece for the construction of large-scale infrastructure projects, such as the

    ELEFTHERIOS VENIZELOS airport, the Spata-Elefsina Freeway, the West Immitos Ring

    Road, and the Rion-Antirion Bridge.

    D.B.F.O. (Design-Build-Finance-Operate)

    The private partner is responsible for the design, construction, operation and financing of the

    asset, and recovers the capital invested through the payments made by the public sector forthe services provided during the contract. Upon expiry of the contract, ownership of the asset

    is transferred to the public sector. The DBFO model is the basic model for contracts involving

    the development of public sector infrastructures and assets, when the possibilities of parallel

    commercial exploitation are in principle unknown and may potentially be limited.

    ... (Build-Transfer-Operate)

    In this form, the private partner designs, finances and constructs the project. After

    completion, ownership of the project is transferred to the public sector, who then agrees to

    lease the project to the aforementioned private partner for a predetermined period of time.

    During this time, the private partner manages the project and collects the revenues from its

    operation.

    n1398

  • 7/28/2019 Privatisation and Regulation of Business

    11/24

    on0242.ico

    ... (Build-Own-Operate)

    In this form, the public sector approaches the private sector with a view to implementing a

    public utility project. The public sector grants a long-term operating license to the private

    partner, who assumes the responsibility for financing, designing, erecting and operating the

    project. In this particular form of PPP, the private partner owns the project, while the public

    sector establishes precisely the operating specifications regarding the services provided, the

    safety regulations and the maximum level of the fees, if any, for using the project (e.g. tolls).

    ... (Buy-Build-Operate)

    Within the framework of attracting private venture funds, the public sector sells existing public

    utility installations to private sector entities, with the aim of securing the realisation of

    additional investments for them (renovation-expansion), in order to take advantage of the

    construction and administration skills of the private sector, mitigate the risks resulting from

    owning and operating the project, and capitalising on the significant economic value of

    existing infrastructure works. The private partner operates these installations as a profitable

    utility project under State supervision.

    L.R.O. (Lease-Rehabilitate-Operate)

    In this form, the private partner leases existing facilities from the public sector, invests its own

    funds for modernising or expanding them, and then undertakes their operation and

    exploitation for a predetermined period of time, under a contract entered into with the public

    sector, who owns the project.

    B.O.L.T. (Build-Own-Lease-Transfer)

    In this form, the private partner finances and constructs the project, and then leases it to thepublic sector through a leasing agreement. The public sector makes regular payments to the

    private partner, through which ownership of the project is gradually transferred to it. At the

    end of this period, the public sector has full ownership of the facilities, or can purchase them

    for a price determined in the leasing agreement. During the term of the lease, operation of

    the facilities is undertaken either by the public sector or by the private partner.

    .. (Private Services Contract: Operation and Maintenance)

    By awarding an OM private services contract, the public sector assigns to the private partnerthe operation and maintenance of a project but retains ownership and management of it.

    ... (Private Services Contract: Operation, Maintenance and Management)

    This form concerns the award of an integrated private services contract, whereby the public

    sector assigns to the private partner the operation, maintenance and management of a

    project but retains ownership of it.

    The distinction between the above forms of PPPs is defined within the two extreme

    boundaries of concession and ownership, and is a function of the distribution of risks

    between the parties involved and of the financing arrangements between the contractingparties (public sector funding agencies / banks contractors/shareholders).

    This distribution is shown indicatively in the Figure below:

  • 7/28/2019 Privatisation and Regulation of Business

    12/24

    Figure 1: Types of contract as a function of the distribution of risks between the parties

    involved and of the financing arrangements

    The organisational chart that follows shows a typical organisation of a PPP contract,,

    where the core comprises the contract and the private party (Special Purpose Vehicle)

    entering into contract with the public sector. Payment for the project or for the service

    provided by the SPV takes place over the term of the contract, either through the exploitation

    of the facility or through regular payments by the public sector, in line with the attainment of

    predetermined quality and availability targets. The private partner usually undertakes,

    through a tender procedure, to design, finance, construct, operate and maintain the project

    for a period of 15 to 30 years.

    n1398

  • 7/28/2019 Privatisation and Regulation of Business

    13/24

    Figure 2: Typical organisation of a PPP contract

    The Figure below presents the parties involved in PPPs and their interrelationships.

    Central to a PPP structure is the Special Purpose Vehicle (SPV), which is established

    exclusively for the purposes of the project and enters into contract with the other project

    entities through a complex system of contracts that ensures the clear distribution of risks.

    Roles and responsibilities:

    Contractor : own funds, know-how;

    Construction Contractor : construction, maintenance, adherence to construction schedule;

    Market: the market to benefit from the development of an efficient and socially acceptable

    solution;

    Manager : assumes the risk of return on the investment made, and part of the long-term

    management of the asset;

    Public Sector : legal framework, main part of the contracts, contribution in money;

    Banks : financing structure, know-how, provision of funding through a financially viable

    arrangement.

  • 7/28/2019 Privatisation and Regulation of Business

    14/24

    on0242.ico

    Figure 3: Participants in PPP arrangements and their interrelationships

    It should be noted that where the Public Sector wishes to retain a shareholding interest in the

    Special Purpose Vehicle, its participation is limited to 49%.

    However, the most common practice is for the public sector not to participate in the share

    capital of the SPV. In this case, if the construction is made on a plot owned by the public

    sector, this is granted to the SPV together with the exploitation rights for the plot and for any

    buildings erected on it.

    2.3 PPPs compared to other types of contractPPPs can offer significant advantages to the implementation of a project with the best value

    for money, allowing public sector entities a relative fiscal flexibility, as it provides them with

    an opportunity for securing the public expenditure required for the project or for converting

    short-term obligations into a series of long-term regular payments while in parallel exploiting

    in terms of fiscal planning the resulting difference to improve their macroeconomic figures,

    but in practice also for other purposes, such as the creation of infrastructures which, because

    of fiscal restrictions, could not be financed directly.

    It is however clear that the complexity of the resulting contractual relationship, and the

    very fact of public assets and services being assigned through PPPs to economic

    operators who by default operate on the basis of, and are motivated by, business profit, do

    not leave much room for experimentation in the procedure followed for selecting this method

    as more advantageous in comparison to other options available. Thus, in order to opt for this

    implementation method, the difference in the value added should, in terms of the financial

    and social end result, be undisputed.

    The Table below summarises the conditions necessary for deciding on the initial

    suitability of a PPP solution and on the need to further investigate its adoption:

    Table 2: Conditions for investigating the award of a PPP

    Existence for the need to carry out an extensive investment programme that requires themanagement of risks associated with construction and with the provision of services.

    Banks / Funding Agencies

    Investor

    Special Purpose Vehicle

    (SPV)

    Market

    Guarantees

    Shares

    CashContribution in kind

    FundingGuarantees

    Shares

    Service ContractManagement Contract

    Manager

    Shareholding ourceP Contracts in terms ot time anc cost ...ncentive for the felivery s for servi

    Contractor

    Construction Contract

    Public Sector

    I n1310.ico

    Funding

  • 7/28/2019 Privatisation and Regulation of Business

    15/24

    The private sector know-how and specialisation required to implement the project exists, and it isestimated that it can offer good value for money for the project.

    The type of the service envisaged is such that the public sector entity may specify it on the basis ofoperating specifications for the duration of the contract.

    Whole Life Costing (WLC) can be established for the project/service.

    Demand for the project/service concerns a long period of time and a growing client base.

    The technology incorporated in the implementation of the project/service is not expected to bemodified significantly (and in any case, not beyond the possibility of adaptation) over the next years.

    In assessing PPPs as an option against other forms of contract, the criteria listed in

    the following Table may be used:

    Table 3: Criteria for assessing PPPs as an option against other forms of contract

    The techno-economic result of the project for the public sector entity. This involves issues related tothe costs for implementation and operation of the project and/or the provision of the servicethroughout its lifecycle compared to the implementation and provision of the service by the publicsector, to the quality operation specifications and the relevant checking procedures, to the required

    level of quality upon expiry of the contract etc.The expected compensatory nature and functionality of the project for its users (socio-economicresult) in terms of the provision of the particular service, but also in terms of its complementarity toother services of a public nature.

    Sufficient size, so that the project may be bankable for credit institutions, whose contribution (and theterms governing the relevant agreements) is a key element of the project. In the case of PPPs, animportant aspect which usually is underestimated is the cost of the award procedure, both for thepublic sector entity and for the tenderers, and its proportion to the cost of the project.

    Financial viability, so that the project is attractive to the private investors who will tender for it.

    In addition to the above criteria for assessing PPPs as an option against other forms of

    contract, the following Table lists some critical factors affecting their adoption:

    Table 4: Critical factors affecting the adoption of PPPs

    The expected development result of the project. The project should form part of, and contribute to,the public sector entitys development planning, in terms of its result at the level of the provision ofthe service to which it refers, as well as in terms of its overall impact on its operation, on socialdevelopment and on its economic environment.

    The long-term political will to implement the project.

    The social acceptance of the project, at least during a first period in the implementation of the PPP.In what regards Local Authorities, for example, the project must complement social andadministrative structures and acquired employment rights, rather than attempt to substitute them.

    The institutional and legal framework for implementation, which must ensure clear terms for theproject.

    The trade, financial or other rights regarding the provision of the envisaged service.

    2.4 Critical success factors for PPP contractsThe Table below lists the critical factors affecting the success of PPP contracts,

    grouped according to whether or not they are controlled or affected by the public or

    private sector, or by both.

    Table 5: Critical factors for successful development of PPP contracts

    Factors controlled or affected by the Public Sector

    Determination of political priorities in relation to the projects to be developed

    I n1310.ico

    I n1310.ico

    I n1310.ico

  • 7/28/2019 Privatisation and Regulation of Business

    16/24

    Commitment of the public sector to these forms of partnership

    Coordination between public services and entities

    Capability of the public sector to respond to the requirements of contracts of this form (negotiations,monitoring, checking, evaluation)

    Attracting interest from the market (viability and attractiveness of projects)

    Financial affordability of the project for the public sector

    Suitable economic, legal and institutional framework

    The environment within which the project is developed

    The projects particular characteristics

    The duration of the contract

    Standardisation for curtailing costs and determination of effective procurement procedures

    Factors controlled or affected by the Private Sector

    Capability of the market to respond to the requirements of the public sector and of the project

    Financial viability of project implementation from the viewpoint of the private sector

    Possibility for the private sector to achieve acceptable profit

    Factors controlled or affected by both

    Sufficient funding ensuring completion of the projects

    Compatibility of contracts with the applicable legal and institutional framework

    Structuring and Management of contracts (determination of minimum specifications, paymentmechanisms etc.)

    Identification, effective management and suitable distribution of risks

    Know-how and experience

    2.5 Advantages and drawbacks of the application of PPPsThe advantages and drawbacks of the application of PPPs are the following:

    2.5.1 Advantages of the application of PPPs

    The advantages of the application of PPPs for the public sectorare the following:

    Improvement of infrastructures and assets Flexibility

    PPPs can be developed in many key infrastructure activity areas, such as water supply,

    energy, telecommunications, roads, transport, hospitals, schools, prisons, accommodation of

    offices and departments, museums etc., as well as in the area concerning the development

    of the public sectors real estate property. In all these cases, PPPs help bring about

    improvements in innovation and in the quality and quantity of supplies/services/assets.

    High-quality services Improved project management

    The quality of the services provided through PPP contracts may be higher than that obtainedin the classic way, as a result of innovation, competition, performance incentives and

    planned maintenance throughout the project lifecycle.

  • 7/28/2019 Privatisation and Regulation of Business

    17/24

    Innovation Savings in time and money

    The specialisation and experience of corresponding projects available in the private sector

    offers an opportunity for developing innovative solutions, reducing project delivery cost and

    time, and improving functional design, construction, and process management. The

    processes to be developed can serve as standards for future projects, to which they could

    also be applied.

    Provision of services at a lower total cost

    The net present value of the total cost of the services provided through PPPs, if the

    corresponding arrangements and the contract have been structured and applied correctly, is

    lower than the cost borne by the public sector when the procurement of the corresponding

    supplies or services is made in the classic way. Although the financing of the project by

    private funds may involve additional costs, as the borrowing cost for the private sector is

    usually higher than that for the public sector, these costs may be compensated by the

    synergies developed by combining the design, construction and operation of the project

    under the same economic operator. These synergies may lead to reductions in operating andmaintenance costs and to improvements in the level of the services provided (value for

    money), resulting in a total cost for the development and operation of the project which is

    lower than that obtained through the classic procurement approach. Financing of the

    project by private funds and the transfer of the responsibility for operation to the private

    sector, usually results in the avoidance of cost overruns and in the adherence to the

    construction schedule, two factors which are very difficult to control under the conventional

    method followed for the procurement of supplies and services.

    The Figure below presents the differences, in terms of time and money, between public

    works contracts and PPP contracts.

    Cost

    overruns

    Estimated

    investmentcost

    Timeoverruns

    Estimated operation/maintenance cost

    Operation/maintenance cost overruns

    Payments

    Years

    0 5 10 15 20

    Construction

    Period Operation & Maintenance Period

    Public Works Contracts

    No payments

    made until theproject is

    completed

    Payments for availability

    Payments for usage

    Payments

    Years

    0 5 15 20

    Construction

    Period Operation Period

    PPP Contracts

  • 7/28/2019 Privatisation and Regulation of Business

    18/24

    Figure 4: Differences between Public Works Contracts and PPP Contracts in terms of time and

    cost (Source: IFS/PWC)

    Transfer of risks

    The identification of the risks associated with the project and their distribution between the

    public and the private sector on the basis of their respective ability to manage and control

    more effectively each risk, is perhaps the most important benefit of PPPs. This distribution

    usually involves the following risks: design, construction, operation, technological change,

    financing, market, legal etc.

    The Figure below shows the distribution of risks between public and private sector:

    Figure 5: Risk distribution between Private and Public Sector (Source: IFS / PWC)

    Improvement of the performance and effectiveness of the new services

    By allocating each risk to the entity best able to handle it, and by linking the payments for

    services provided to performance, PPP contracts may serve as clear incentive for thedelivery of projects on time and without cost overruns, and for ensuring adherence to the

    desired specifications throughout the duration of the contract. The public sector shall pay the

    entire amount of payments only when the services provided meet fully the desired level and

    the specifications (payment mechanism). In contrast, in the case of public contracts, the

    maintenance and operation of the asset depends on the availability of corresponding funds

    under the State budget, and on the effective implementation of relevant programmes by

    entities who do not always have available the infrastructure required.

    Clear commitment to the client/citizen

    The development of PPPs by the public sector is aimed at meeting its needs and

    requirements in connection with the services required, rather than managing the existing

    procedures for the provision of services. This shift in focus from the management of

    procedures to the quality of the produced result is a determining factor in the promotion and

    development of innovative solutions and in improving the relationship between the public

    sector and the citizens.

    Differentiation of services

    The development of PPPs enhances competition and, through the introduction of

    benchmarks, allows comparisons the quality and production costs for the services providedto be compared to those of similar services in the market, a development that helps improve

    productivity and effectiveness.

    Public Sector: Risk assumption Risk Transfer or Assumption Private Partner: Risk transfer

    Required licenses/permits

    Institutional framework(taxes, spatial planning etc.)

    Inflation

    Demand (usage / size)Residual ValueForce majored events

    Design

    ConstructionOperationFinancing

    Technology

  • 7/28/2019 Privatisation and Regulation of Business

    19/24

    Funding Development of more projects

    The use of private capital in the construction and development of projects can accelerate the

    infrastructure development programme and help keep public expenditure within the budgeted

    cost, eliminating overruns and the need for additional funds.

    Broader economic benefits

    By helping develop and bring to completion a significant number of projects during periods of

    budgetary restrictions, the development of PPPs may act as incentive for the private sector,

    mobilising resources that may help to increase employment and achieve economic growth.

    Know-how

    The application of PPPs assists the transfer of know-how to the public sector, through its

    cooperation with the private sector.

    The advantages of the application of PPPs for the privatesectorare the following:

    Participation in public projects and joint ownership of the assets.

    Attractive profit margins.

    Long-term contracts.

    2.5.2 Potential drawbacks of the application of PPPs

    Implementation complexity

    PPPs are characterised by increased complexity in their implementation, due to the

    necessary changes in the institutional framework and to the complex set-up of contractswhich should foresee all potential risks and the ways in which to address them, in order to

    achieve the distribution of each risk to the party best suited to manage it.

    High partnership structuring costs

    Because of their complexity, the cost associated with the development of PPPs during the

    stage of their formulation may be considerably higher than the costs to result through the

    conventional procurement methods for assets and services. Of course, this does not

    necessarily mean that the total cost of the project shall be higher compared to that of the

    conventional procurement method.

    Higher borrowing cost

    The borrowing for the private partner is usually higher than that for the public sector and,

    given that the private partner will seek a high borrowing rate, the financial cost of the project

    may be increased. Of course, this does not necessarily mean that the total cost of the project

    shall be higher compared to that of the conventional procurement method.

    Ineffective contract management

    Proper monitoring and checking of the contract may not be available, resulting in failure to

    achieve the desired results (level of services, payment mechanism, assumption of risks etc.).This may be due either to a lack of know-how or to the absence of suitable monitoring

    procedures.

  • 7/28/2019 Privatisation and Regulation of Business

    20/24

    on0242.ico

    Lack of competition

    In the case of a PPP contract, the presence of competition contributes to the development of

    innovative solutions and to the improvement of the effectiveness in the provision of services.

    However, the result intended may not be achieved in cases of weak or limited competition or

    where the number of private partners able to provide these services (i.e. having the

    knowledge, capacity, and resources required) is small..

    It is important to note here that several of the drawbacks of PPPs can be minimised

    through proper planning, structuring and implementation of the project. For example,

    the initial financial viability study should document that the total economic benefit from such a

    structure may exceed the higher cost of structuring the partnership and the financing cost

    (value for money). In addition, clear support by the State is required at the political, legislative

    and institutional level.

    2.6 Steps in awarding and implementing a PPP contractThe figure below presents the steps of a typical PPP procedure. The time required forcompletion of such a procedure, from the publication in the OJEU to the signature of the

    contract, varies from 14 to 24 months.

  • 7/28/2019 Privatisation and Regulation of Business

    21/24

    Figure 6: Steps of a typical PPP procedure

    The Table below summarises the key conclusions regarding the application of PPPs.

    Table 6: Conclusions regarding the application of PPPs

    PPPs are a reliable alternative for implementation of numerous infrastructures of the public sector, and

    of the management and operation services associated with them.

    Savings in time and cost may be achieved.

    Private financing may be more expensive than public funding, but in all cases the introduction of acompetitive procedure leads usually and under the right circumstances to solutions which are moreeconomic overall (construction, operation and maintenance).

    The legislative and institutional framework must be determined or enhanced.

    As a rule, the quality of the services provided through the development of PPPs is improved, while thepublic sector may specify and check the quality of the services provided. As the payments made to theprivate partner are linked clearly to the quality of the services provided and to the attainment of aspecific quality level, the achievement of the objective acts as an incentive driving the efficiency andeffectiveness of the private sector and the quality achieved is better than that obtained through thetraditional procurement approach.

    The public sector maintains control over public assets, as risks and responsibilities regarding the day-to-day management of the services provided are transferred to the private sector selectively. In any

    Preparation of TenderProcedure (Public Sector)

    Official Journal of the EuropeanUnion (OJEU)

    Prequalification Documents Invitation of Requests to

    Participate

    Prequalification of Candidates

    Tender Submission Documents

    Evaluation Selection of Candidate

    Contractor

    Contract Signature Contract Management

    Determination of business needAssessment of alternatives for project implementation and of the suitability of the

    project for developing PPP/PFI solutionsDocumentation of the overall economic benefit from the project (value for money)Initial market soundingSecuring of the approvals required to proceed with the solutionEstablishment of Project Team

    Publication in the OJEU

    Preparation of prequalification documentsDispatch of documents to the interested economic operatorsSubmission of requests to participate by the candidates

    Evaluation of requests to participatePrequalification of candidates (usually 5 6)

    Preparation of tender submission documentsDispatch of documents to the prequalified candidatesSubmission of tenders by the prequalified candidates

    Evaluation of submitted tenders on the basis of the specified technical, financialand legal criteria

    Selection of candidate Contractor

    Final discussions and negotiations for signature of the contractContract Management

  • 7/28/2019 Privatisation and Regulation of Business

    22/24

    case, the public sector maintains control over the possibility of adopting and imposing policies,specifications and regulatory interventions.

    2.7 PPP Projects in the EU and examples of sectors where PPPs areapplied

    The maps and tables in this section present applications and examples of PPPs in the EU.Source: European Investment Bank, Dexia Credit

    IrelandPPP Act 2002EducationHealthTransportWater Supply Networks

    BelgiumPPP Decree 2003TransportWater Supply NetworksEducationEducation

    NetherlandsPPP Task Force 1999TransportWater Supply NetworksHealthPrisons

    FinlandTransportEducationHealthWater Supply Networks

    FranceLOPSI, LOPJI 2004Ordonnance MatteiOrdonnance PPPEducationHealthTransportInfrastructuresPrisons

    PortugalPPP Law 2003

    TransportHealthPrisonsWater Supply NetworksEducation

    SpainPPP Law 2003TransportHealthEducationWater Supply Networks

    ItalyMerloni Law 2001-4TransportHealthWater Supply NetworksEducation

    GreeceTransportTourism

    GermanyPPP Task Force 2003DefenseWater Supply NetworksInfrastructuresRoads

  • 7/28/2019 Privatisation and Regulation of Business

    23/24

    PolandLegal framework under preparationWater Supply Networks

    Transport

    Czech RepublicPPP Taskforce 2004Legal framework under preparationWater Supply NetworksTransportMilitary CampsHealthEducation

    CroatiaTransportWater Supply Networks

    RomaniaTransportHealthWater Supply Networks

    HungaryPPP Committee 2003New Procurement Act 2004TransportPrisonsHealthEducationWater Supply Networks

    SlovakiaWater Supply NetworksTransport

    Building facilities

    Court HallsPrefectural/Municipal HallsRelocation servicesSocial welfare centresManagement of real estate

    property

    Environment

    Solid & liquid wastemanagement

    Provision of watersupply irrigationservices

    Management of energysources

    Entertainment

    Tourist facilitiesTheme parksMallsRecreation areasExhibition areasSports facilities

  • 7/28/2019 Privatisation and Regulation of Business

    24/24

    Source : Grand Thornton Presentation (Athens 2005)

    Source : Grand Thornton Presentation (Athens 2005)

    Education/Training

    Students residencehalls

    University campusesSchools

    Health

    HospitalsHealth CentresClinicsPatient Treatment

    Units

    TransportMotorwaysTramway, Underground

    rail (Metro), airportsPorts, marinasNational trunk roadsRoad network in cities

    Parking

    Security

    PrisonsTherapeutic

    CommunitiesPolice StationsFire Brigade Centres

    Defense

    Accommodation, officesConstruction of auxiliary

    facilitiesTraining Centres

    Technology

    IT Services andSystems forSchools,Universities,Ministries,Public Services


Recommended