+ All Categories
Home > Documents > Procurement 02

Procurement 02

Date post: 06-Oct-2015
Category:
Upload: gishan-sanjeewa
View: 3 times
Download: 0 times
Share this document with a friend
Description:
Procurement
6
 Contracts in Procurement MSc in Construction Law and Dispute Resolution 1 CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT BE 5402 BE 5402 BE 5402 BE 5402 BE 5402 BE 5402 BE 5402 BE 5402 Suranga Jayasena Suranga Jayasena 1 MSc in Construction Law and Dispute Resolution MSc in Construction Law and Dispute Resolution CONTRACTS CONTRACTS CONTRACTS CONTRACTS CONTRACTS CONTRACTS CONTRACTS CONTRACTS Day Two 2 Some Preliminaries • What is Pri ce?  Amount of payment (compens ation) given by one party to another in return for goods or services. Wha t i s Val ue?  V arious expl anations V al ue- in- use : what benefit provided to the buyer Exc han ge val ue: how much of other goods given up V alue = p rice: market mechanism 3 Value = Price if Pric e = Cost + Profit : for the seller/contractor Valu e = valu e-i n-use : for the buyer/client Value = e xchan ge val ue : for the buyer/client ? 4 In a Contract We sh ould be a ble to se e the lin k betwee n Value & Price 5 A Contract ...is a legal ly bindin g agree ment (usu ally ) between two parties. Usual ly a written (& some times not) • All agree ments are not contracts • Test  Offer an d acceptance  Intenti on to create legal relationship Thus, all co ntracts are a greeme nts 6
Transcript
  • Contracts in Procurement

    MSc in Construction Law and Dispute Resolution 1

    CONSTRUCTION PROCUREMENTCONSTRUCTION PROCUREMENTCONSTRUCTION PROCUREMENTCONSTRUCTION PROCUREMENTCONSTRUCTION PROCUREMENTCONSTRUCTION PROCUREMENTCONSTRUCTION PROCUREMENTCONSTRUCTION PROCUREMENTBE 5402BE 5402BE 5402BE 5402BE 5402BE 5402BE 5402BE 5402

    Suranga JayasenaSuranga Jayasena1

    MSc in Construction Law and Dispute ResolutionMSc in Construction Law and Dispute Resolution

    CONTRACTSCONTRACTSCONTRACTSCONTRACTSCONTRACTSCONTRACTSCONTRACTSCONTRACTS

    Day Two

    2

    Some Preliminaries

    What is Price? Amount of payment (compensation) given by

    one party to another in return for goods or services.

    What is Value? Various explanations

    Value-in-use: what benefit provided to the buyer Exchange value: how much of other goods given up Value = price: market mechanism

    3

    Value = Price

    if Price = Cost + Profit : for the seller/contractor

    Value = value-in-use : for the buyer/client Value = exchange value : for the buyer/client

    ?4

    In a Contract

    We should be able to see the link between

    Value&

    Price

    5

    A Contract

    ...is a legally binding agreement (usually) between two parties.

    Usually a written (& sometimes not) All agreements are not contracts Test

    Offer and acceptance Intention to create legal relationship

    Thus, all contracts are agreements6

  • Contracts in Procurement

    MSc in Construction Law and Dispute Resolution 2

    Contract Development

    Decision on type of contract, conditions of contract and contract documentation

    Selection of the contractor Establishment of contract price (or how the

    price will be arrived at)

    7

    Contracts in Procurement

    The focus is on Validity of Contracts Legal grounds for challenge Judicial precedents ...

    No It is on what is agreed by the parties.

    8

    What is agreed

    ...defines Rights and Obligations

    of parties under the agreement.

    Clients right: to get the project done. Contractors right: to get paid

    9

    Rights and Obligations

    Rather than what they are, we may also look how they are defined.

    Contract defines What is to be designed What is to be built and How much to be paid

    How these are defined maybe used to classify the contracts

    10

    Contract Classification

    Simplest maybe to look at design and build responsibilities, i.e. classification by responsibility. A design contract A building/construction contract A design and build contract

    This classification may not be deep enough for our purposes

    11

    Classification by Reward

    Looks at how reward (payment) is paid to the contractor by the client. >> What is agreed at the time of contract.

    Broadly, either Price Based, or Cost Based

    12

  • Contracts in Procurement

    MSc in Construction Law and Dispute Resolution 3

    Price Based Contracts

    Broadly Two

    Lump Sum Contracts

    Measurement Contracts

    13

    Lump Sum Contracts

    Contract Sum (for the total contract) is agreed before construction starts.

    Appropriate for most of contracts. Client has the maximum price certainty

    before contractor starts performing.

    14

    Measurement Contracts

    Agree for a mechanism to arrive at final sum based on actual quantities of work done.

    Price certainty only at the end of performance.

    Higher price risk compared to lump sum. Some, are re-measurement contracts.

    15

    Measurement Contracts Cont.

    Most effective when works are substantially designed but final details not yet completed.

    Client can shorten overall programme at the expense of price certainty.

    Fair Price ...?

    16

    Cost Based Contracts

    Agreed for mechanism for final price Price = Costs + Agreed Allowance Costs

    Actual costs (prime cost) incurred by the contractor in performing the contract >> labour, plant, material, fuel, etc.

    Allowance A fee: which needs to be agreed.

    17

    Cost Based Contracts Cont.

    Known as Cost Reimbursement Contracts Used When not appropriate to measure

    even approximate quantities: scope not clear, risk unreasonable to price, etc. Risk >>> Profit Margin

    Examples: emergency building repair after fire, Civil Engineering work under water.

    18

  • Contracts in Procurement

    MSc in Construction Law and Dispute Resolution 4

    Cost Based Contracts Cont.

    Provide for great flexibility for change Programme, scope, quantity of works, etc.

    Price risk to contractor is low; to client high Weakness in lack of incentive for

    contractor minimize his prime cost Few variants depending on the way the

    fee is applied.

    19

    Cost Reimbursement Contracts

    Cost + Percentage Fee

    Cost + Fixed Fee

    Cost + Fluctuating Fee

    Target Cost Reimbursement Contract20

    Alternative Classification

    Drawings and Specification Performance Specification Schedule of Rates Schedule of Prices Bills of Firm Quantities Bills of Approximate Quantities

    21

    Drawings and Specifications

    Simplest type Complete drawings and full specifications Comprises of large amount of tender

    information Most pricing risk to the contractor Tendency to overprice due above Known to be used with lump sum price

    (and no BoQ)22

    Drawings and Specification

    with Lump Sum Price

    Each bidder quantifies for pricing >> wasteful

    Difficult to evaluate bid prices Design needs to be fully completed for

    signing of the contract Variations might become problematic to

    value

    23

    Performance Specification

    Price based on employers brief and user requirements (documented as a performance spec)

    Within the parameters laid down, contractor chooses methods, materials and the design (often)

    Flexibility to the contractor Defined performance to be achieved

    24

  • Contracts in Procurement

    MSc in Construction Law and Dispute Resolution 5

    Performance Specifications Cont

    Lump sum price Natural to offer least expensive materials

    and construction methods Difficulty is to draft the Performance Spec

    perfectly Suits projects of any size.

    25

    Schedule of Rates

    Similar to BoQ but no quantities Principles of SMM used Bidders insert their rates Neither contract sum nor final price

    predictable Difficult to price in absence of quantities Used when not possible to predetermine

    the extent of proposed work26

    Schedule of Prices

    Similar to Schedule of Rates, but tender includes rates (from current market)

    Bidders offer discounts (+/-) for work sections

    Facilitate bid evaluation Usage of standard allows familiarity >>

    better pricing

    27

    Bills of Firm Quantities

    Both Quantities and Unit Rates form part of contract

    Design to be virtually completed Clear picture of commitment of both

    parties Detail breakdown of bid/tender sum >>

    better bid evaluation Unit rates >> basis for pricing variations

    28

    Bills of Firm Quantities Cont.

    Bid can be compared on bid sum alone Widely used, suits projects of any size

    Lot of time on design and bill preparation Risk of quantity errors in BQ is with bidder

    Bidder to rate strategically May cause problems in variations pricing

    29

    Bills of Approximate Quantities

    Used when not possible to measure work accurately

    Price certainty comparatively less than previous

    Entire work re-measured on completion Only Unit Rates form part of contract Quantities ...?

    30

  • Contracts in Procurement

    MSc in Construction Law and Dispute Resolution 6

    Bills of Approximate Quantities Cont

    Less pressure to fully complete the design Signing of contract before finalizing the

    design Lesser overall time No risk to bidder on quantity errors in the

    bill (what if for large deviations) Extra expense (time/money) on bill of firm

    quantities avoided >> but, what about remeasuring

    31

    Contracts

    Further Comments?

    Reflections?

    Summarizing?

    32

    Thank You

    33


Recommended