Procurement of IT- Fiduciary Forum 2008 – Page 1
Procurement of Information Technology
Fiduciary Forum 2008
Overview
Procurement of IT- Fiduciary Forum 2008 – Page 2
AGENDA
• Characteristics of ICT • packaging approach for IT components; • selection of Standard Bidding Documents (Goods
vs the SBD for Supply and Installation of Information Systems (SII; and single stage vs two-stage bidding);
• evaluation methodology and technical requirements, including establishing price/technical ratio
• Two stage bidding
Procurement of IT- Fiduciary Forum 2008 – Page 3
• Enormous level of continuing innovation
• Prices come down, performance increases
• Lifetime of “hard” investments potentially low
• Technology now permeates business processes, with heavy integration across all systems
• Private sector (as provider) remains key driving force
Characteristics of ICT
Procurement of IT- Fiduciary Forum 2008 – Page 4
Typical Parts of Major ICT Components
• General studies (BPR, IT strategy, establishing the linkage with project goals, establishing priorities, approach)
• Design studies (user requirements, functional specifications, designs, “blueprints”)
• Application software customization/development
• Hardware and standard software delivery
• Project management (often a complex task)
• Training (users, technical staff)
• Other services (e.g., digitization, data conversion, surveys)
Procurement of IT- Fiduciary Forum 2008 – Page 5
FAILURE FACTORS
Factor Percent
1 Incomplete requirements 13.1
2 No user involvement 12.4
3 Lack of resources 10.6
4 Unrealistic expectations 9.9
5 No support from senior management
9.3
6 Unstable requirements 8.7
7 Poor planning 8.1
8 System non-usable at finish 7.5
9 No IT management 6.2
10 No technical competence 4.3
Procurement of IT- Fiduciary Forum 2008 – Page 6
SUCCESS FACTORS
Factor Percent
1 User involvement 15.9
2 Support from senior management 13.9
3 Clearly defined requirements 13.0
4 Good planning 9.6
5 Realistic expectations 8.2
6 Phased approach 7.7
7 Competent personnel 7.2
8 User ownership 5.3
9 One vision and clear goals 2.9
10 Effective and goal oriented personnel 2.4
Procurement of IT- Fiduciary Forum 2008 – Page 7
Examples of ICT Components in Typical Bank-Financed Projects
Computer classrooms for schools Agency’s main e-mail and document handling system (e.g.,
Outlook/Exchange, Lotus Notes) Court administration system Financial Information System (e.g., Budget, Payroll, Integrated FMS) Geographical Information System (e.g., cadastre, forest management) Information System (laws, general statistics, highway accidents, etc.) Management Information System (e.g., health, education) Operational Information System (e.g., Railway, Central Bank RTGS) Social Insurance System (medical, pensions, unemployment) Revenue Management System (tax, customs administration) Treasury System (budgeting, expenditure control)
Procurement of IT- Fiduciary Forum 2008 – Page 8
Large IT projects
Procurement of IT- Fiduciary Forum 2008 – Page 9
Why IT Procurement Is Different
• IT Professional Mindset• Know chances of failure are high (US gov. study – 45% of projects
unusable)• Are experienced to eliminate ambiguity and uncertainty• Know who can do the job best• Fast technical changes
• Market• extremely competitive• becoming commodity driven
• Environment• Policy, legal and regulatory changes• Management change
It Is aLethal Mix
of Risks
Procurement of IT- Fiduciary Forum 2008 – Page 10
• IT frequently combines Goods and Services elements
• software pricing/licensing/IP presents an additional element needing special treatment, as do possible telecommunications facilities
• installed base and related staff skills may have considerable impact
• de-facto market monopolies may weigh heavily
Need for specialized Standard Bidding Documents (SBDs) and for skill in packaging the overall procurement
Procurement challenges presented by IT
Procurement of IT- Fiduciary Forum 2008 – Page 11
Low
Consulting Services ContractsLow
High
High
Service Content
Product Content
Low
Consulting Services ContractsLow
High
High
Service Content
Product Content
Consulting Services ContractsConsulting Services ContractsLow
High
High
Service Content
Product Content
Complexity diagram
Procurement of IT- Fiduciary Forum 2008 – Page 12
ICT toolset for Task Managers Guidance on SBD selection for ICT procurement Other IT Guidance Notes
SBD for Information Systems Supply and Installation (IS1STG SBD, Version 3a, March 2003)*
Two-stage (IS2STG SBD, Version 3a, March 2003)* Goods SBD (use only for IT products)* Shopping (only for well-defined IT products of small value) RFP approach (for strategy development, design studies, development
of user requirements and application software development)*
Appropriate overall approach may use all of these options to advantage* Versions in French and Spanish are available
The available instruments
Procurement of IT- Fiduciary Forum 2008 – Page 13
Services Content
Goo
ds C
onte
nt
High
High
Low
Low
RFP
Goods SBD
IS1STG SBD
IS1STG SBD
IS2STG SBD
Shopping
Which Approach to Use?
Procurement of IT- Fiduciary Forum 2008 – Page 14
Procurement Methods
• ICB is common for initial investment. Goods or Single-stage Supply and Installation of Information Systems SBDs are used.
• Two-stage Supply and Installation of Information Systems SBDs used for turnkey and complex procurements
• Pre-qualification for exceptional very specialized cases critical for project implementation. No standard pre-qualification document is available. LIB can be used in lieu of pre-qualification in some cases.
• Shopping may be necessary for start up activities, to fill gaps, for specialized tools, and minor purchase updates
Procurement of IT- Fiduciary Forum 2008 – Page 15
Practical suggestions
• Turnkey implementation SBD – only exceptional, high risk of failure.• Goods SBD – general purpose hardware and off-the-shelve software
(without customization).• Single-stage SBD – detailed requirements for system (hardware and
software) are known and the weight of technical scoring is no more than typically 25%.
• Two-stage SBD – the solution is known but the alternatives are allowed and there is need for the weight of technical scoring higher than typically 25 % (30%-50%), in the first stage.
• Technical assistance RFP – for design, development and integration of the system, or any combination of these activities (the suggested minimum is design and/or integration).
Procurement of IT- Fiduciary Forum 2008 – Page 16
• single responsibility (“turnkey”) contract(s) • separating the application software development• building on existing efforts if they hold promise• phasing application software development (prototyping,
RAD, piloting, partial and full “roll-out”)• splitting procurement and managing several suppliers
(splitting in time, and by type of procurement package)
Each approach has its own set of pros and cons.Actual approach needs to fit the situation.Should also reflect Borrower’s competence and will.
Approaches for dividing and packaging
Procurement of IT- Fiduciary Forum 2008 – Page 17
Use SBD for Goods…
• For ready-made equipment and materials, pre-installed
software packages and consumables only • Package contains only incidental services, such as
installation, LAN, standard training, etc. (15% of total contract value)
• Contract can be fully implemented in at most 6 months
• Recurrent costs comprise only the standard warranties and software licenses, up to 3 years
In other words, the procurement package resembles a typical Goods procurement.
Procurement of IT- Fiduciary Forum 2008 – Page 18
SHOPPING
The ITQ for Shopping (SH) may be used as an alternative when the procurement package is:
• only off-the-shelf IT and is small in value (consult thresholds in LA/DCA/PP) and can be handled by simple payment on Delivery (in any case max US$100,000);
• only incidental services are delivery and installation;
• must use the ECA Shopping Website:
Procurement of IT- Fiduciary Forum 2008 – Page 19
Use RFP…
• Typically for IS project management support, development of ICT strategies, user requirements, functional specifications, design of application software, and the assembly of ICT bidding documents
• For implementation: When the content comprises almost only services (e.g., development of an application system), and usually for pilot applications
• The size of the task is within the grasp of typical consultant or software engineering firms
• The hardware and packaged software content should be minimal, e.g., less than 20% of the estimated contract value
• Requires special customization to the standard contract (for intellectual property rights, support/warranty, testing and acceptance, and appropriate payment clauses
Purchaser assumes higher risk.Provides good scope for the use of competent local firms.
Procurement of IT- Fiduciary Forum 2008 – Page 20
Use the Single-Stage SBD…
• Especially if procurement package combines critical Goods and Services elements
• Sophisticated hardware requiring an informed performance comparison and special training requirements
• A dominating value of the software packages• Extra installation and support requirements for these • Software design, large-scale adaptation and/or
development • Requirements for the supplier to continue to operate the
equipment after installation • For contracts requiring pricing for both investment &
recurrent costs (life-cycle)Use as default for Information Systems
Procurement of IT- Fiduciary Forum 2008 – Page 21
Use the Two-Stage SBD…
• When it is unclear whether full solutions are available from potential bidders
• When the submission of technical alternatives is actively encouraged
• When it is important to gain confidence via the bidding process about acceptable and desirable solutions
• Includes the possibility to test proposed solutions prior to contracting
Requires more time than single-stage; entails the prospect of prejudicing the Purchaser.
Procurement of IT- Fiduciary Forum 2008 – Page 22
Typical Borrower Issues
• Reliance on inadequate IT expertise• Project management and implementation capacity often
lacking or unsustainable• Mindset fixed on obtaining specific brands• Eager to receive hardware, with little regard to use it
productively any time soon• Lack of attention to the effort and skills it takes to put
adequate BDs together• Desire to do everything with own staff• Poor communication with the World Bank
Procurement of IT- Fiduciary Forum 2008 – Page 23
Typical World Bank Issues
• Giving ICT components a separate life from the start
• No or inadequate reliance on IT expertise• Non-use of World Bank procurement expertise in
IT• Lack of problem appreciation by Task Manager
and Procurement Accredited Staff• Clearing BDs and BERs in frustration
Procurement of IT- Fiduciary Forum 2008 – Page 24
Preparation of Bidding Documents
• Clearly describe what is to be procured (Technical Specifications and IFB) ... can be complex
• Pay attention to how the global and local markets work in the areas of the technical requirements (what to include and what not, RFP vs. ICB, division into lots)
• Needing special attention: technical evaluation method (if any), recurrent cost table, schedule
• Also needing attention: investment price table, payment schedule, project management and approach to acceptance
• Capture required quality / performance for equitable competition
Procurement of IT- Fiduciary Forum 2008 – Page 25
Preparation of Bidding Documents
• To the extent possible, simplify bid evaluation. Define what is really wanted and make it mandatory
• Quality points reserved only for extra value offered by the Bidder, and the value is actually invited by the Purchaser
• The dilemma of the argument of Purchaser “wants” versus “needs”.
• Eliminate recurrent costs evaluation if at all possible. This is the most common cause of problems in bid evaluation.
TIP Use International
Consultants to assistthe Borrower
Procurement of IT- Fiduciary Forum 2008 – Page 26
Key areas needing attention
• Composition of evaluation team
• Letting evaluators do their job
• Expectation of non-conformities (bids are rarely perfect)
• Special issues in two-stage bids between stage one and two
• If technical merit is scored, BER must be informative to allow World Bank to review the scoring
• Review outcome as to being competitive in view of the expected market
Bidding and bid evaluation stages
Procurement of IT- Fiduciary Forum 2008 – Page 27
Key Areas Needing Attention
• Maintain focus on milestones, goals• Prevent premature delivery and payment of hardware and
user licenses for packaged software• Carefully assess proposed replacements of Supplier staff
and resist if appropriate, especially at the start of the contract
• World Bank involvement typically is a positive factor outside the contractual conflict resolution framework
• but, World Bank policies typically are very restrictive in times of contract implementation
Contract execution
Procurement of IT- Fiduciary Forum 2008 – Page 28
Software Rights
• STANDARD SOFTWARE– RIGHTS WITH OWNER
• CUSTOM (DEVELOPED) SOFTWARE– MUST BE SPECIFIED IN SCC
• A) FULLY VESTED IN PURCHASER• B) REMAIN VESTED IN SUPPLIER• C) ANY INTERMEDIATE APPROACH (BETWEEN A AND B)
• SOURCE CODE • SOFTWARE MONOPOLY – both Purchaser and
Supplier are SW owner with equal and separate rights to develop the software independently of each other after contract execution
Procurement of IT- Fiduciary Forum 2008 – Page 29
PAYMENT CONDITIONS
• PAYMENT IS DIVIDED AMONG 7 CATEGORIES– ADVANCE (USUALLY 10% excl. Recurrent Costs)
– INFORMATION TECHNOLOGIES, MATERIALS AND OTHER GOODS (not custom software or custom materials) usually 60% delivery, 10% installation, 10% Op. Accept.
– CUSTOM SOFTWARE AND CUSTOM MATERIALS usually 60% installation, 20% Op. Accept.
– SERVICES`OTHER THAN TRAINING (usually 80% monthly in arrears against services performed)
– TRAINING (usually 30% at start of training and 50% monthly in arrears)
– COMPLETE SYSTEM INTEGRATION (usually 10% of entire contract excl. Recurrent Costs)
– RECURRENT COSTS (100% monthly in arrears against services delivered)
Procurement of IT- Fiduciary Forum 2008 – Page 30
MAIN FEATURES
BIDDING MAY BE CONDUCTED AS A SINGLE OR TWO STAGE PROCESS
STG 1
STG 1 STG 2
Procurement of IT- Fiduciary Forum 2008 – Page 31
USE A SINGLE STAGE PROCESS
as default anytime, but especially if procurement package
combines critical Goods and Services elements and result is critical for production
operation
Requires comprehensive specifications; at a minimum functionally comprehensive
specifications.
MAIN FEATURES
Procurement of IT- Fiduciary Forum 2008 – Page 32
USE A SINGLE STAGE PROCESS WHEN:- Procurement is simple e.g. “supply and install”
- Technical requirements are well defined and can be defined by clear technical specifications
- Purchaser is clear what technical solution is required
- Solution can be met by products that are already available
- Procurement involves purchase and installation of large number of computers and off-the-shelf software
- Design risk is borne by the Purchaser
MAIN FEATURES
Procurement of IT- Fiduciary Forum 2008 – Page 33
Bidding Documents
(issued by Purchaser) Bid
(submitted by Bidder)
Contract Documents
SINGLE STAGE FLOWCHART
1. Pre-bid Conference
2. Questions & answers
3. Amendments
Procurement of IT- Fiduciary Forum 2008 – Page 34
PROCEDURE
Bidding Documents(issued by Purchaser)
Invitation for Bids (IFB)
1. Instructions to Bidders (ITB)
2. Bid Data Sheet (BDS)
3. Eligibility for the Provision of Goods, Works and Services in Bank-Financed Procurement
4. General Conditions of Contract (GCC)
5. Special Conditions of Contract (SCC)
6. Technical Requirements (TS)
7. Sample Forms
Procurement of IT- Fiduciary Forum 2008 – Page 35
PROCEDURE
Bid(submitted by Bidder)
Bid Form
Price Schedules
Bid Security
Authorization to sign (& any Joint Venture documents)
Attachments:
1. Bidder’s eligibility2. Bidder’s qualifications (incl. manufacturer’s authorizations)
3.Eligibility of goods and services4. Conformity of the information system (incl. technical bid and project plan) and deviations if any exists. 5. Proposed Subcontractors6. Intellectual property
[7. Alternative technical bids]
Procurement of IT- Fiduciary Forum 2008 – Page 36
PROCEDURE
Contract DocumentsNotification of AwardBid FormPrice SchedulesGeneral Conditions of ContractSpecial Conditions of ContractContract Agreement and Appendixes: 1.Supplier’s Representative 2.Adjudicator 3.Approved Subcontractors 4.Categories of Software 5.Custom Materials 6.Revised Price Schedules (if any) 7.Minutes of Contract Finalization 8. Change order procedures and forms Updated Technical Bid
Any other documents agreed as forming a part of the Contract
Procurement of IT- Fiduciary Forum 2008 – Page 37
ITB – Bidder Qualifications
• ITB 6.1• Ask bidders for:
– Experience, staffing, financial stability– Installed user base, references, site visits– Software history, development methodology,
maintenance, and stability`
• Set thresholds/hurdle targets• Subcontractors’ qualifications can be indicated
here, however note provisions of ITB 6.2• Manufacturer’s authorization (usually always)
Procurement of IT- Fiduciary Forum 2008 – Page 38
Bid evaluation
• Avoid technical scoring of mandatory requirements unless it concerns the method of implementation
• Select only few features – in the range 5-8 ; bidder capacity should be evaluated mostly as qualifications
• Describe the rules of assigning scores for each technical feature; predefined values for each feature
• Subjective scores should be assigned by consensus of the evaluation committee not by simple averaging
Procurement of IT- Fiduciary Forum 2008 – Page 39
Bid Evaluation
• Technical evaluation is complex to review, often requiring professional expertise - include IT specialists in evaluation committee
• Use pre-defined procedures for assigning scores and conclude with a consensus of the evaluation committee
• Bidders complain a lot• No perfect bids• Applying corrections• When are recurrent costs needed• When to use technical evaluation for
merit as opposed to technical compliance
Procurement of IT- Fiduciary Forum 2008 – Page 40
A material deviation, exception, objection, conditionality, or reservation is one
that limits in any substantial way the scope, quality, or performance of the Information System; or
that limits, in any substantial way that is inconsistent with the Bidding Documents, the Purchaser’s rights or the successful Bidder’s obligations under the Contract; or
the acceptance of which would unfairly affect the competitive position of other Bidders who have submitted substantially responsive bids.
MATERIAL DEVIATION
Procurement of IT- Fiduciary Forum 2008 – Page 41
AWARD OF CONTRACT TO THE LOWEST EVALUATED BIDDER WHO:
MEETS THE SPECIFICATIONS HAS CAPABILITIES AND RESOURCES HAS BEEN DETERMINED TO BE
SUBSTANTIALLY RESPONSIVE TO THE BIDDING DOCUMENTS
OFFERS THE LOWEST EVALUATED BID PRICE
AWARD
Procurement of IT- Fiduciary Forum 2008 – Page 42
ITB –Evaluation Methodology
• ITB 28
• Evaluation Formula (B=Evaluated Bid Score):
XT
TX
C
CB
high
low 1
C = Evaluated Bid PriceClow= Lowest of all Evaluated Bid Prices among responsive bidsT = Total Technical Score awarded to the bidThigh= Technical Score achieved by bid scored highestX = Weight for the Price as specified in the BDS
Bid with highest B will be termed “Lowest Evaluated Bid”
Procurement of IT- Fiduciary Forum 2008 – Page 43
ITB –Evaluation Methodology
• ITB 28.4• In most cases, you will assign a weight to
technical factors• Technical weight determined by degree of
professional judgment, project management, and risk management skills required from Supplier
• Range from 0% for well defined products to up to 60% could be justified for highly complex requirements of high intellectual input
• Typical 15%
Procurement of IT- Fiduciary Forum 2008 – Page 44
ITB – Evaluation Methodology
• Often very difficult to describe technical limits (i.e., server expansion or performance benchmarks, such as TPC-C)
• Purchaser would like to look at a spectrum of options in their investment decisions
• High divergence in functionality in the application software market
• Adequate evaluation of service elements of bids
Why use merit scoring…
Procurement of IT- Fiduciary Forum 2008 – Page 45
ITB – Evaluation Methodology
• Estimate the costs of major components and assign weight:C1 hardware and standard software c1 (0%)C2 application software package functionality c2 (50%)C3 custom application development, studies c3 (60%)C4 other services (training, project mgt., etc.) c4 (30%)
• C1+C1+C2+C4 must be total estimate for the procurement• c1, c2, c3, c4 represent technical “importance” within the
component (prior to bidding) • Compound merit weight is: Sum of Ci*ci/sum of Ci
Determining ‘1-X’ – Method for obtaining a composite merit weight
Procurement of IT- Fiduciary Forum 2008 – Page 46
ITB – Evaluation Methodology
• Estimate the costs of major components and assign weight:5m hardware and standard SW c1=0%1m application software package functionality c2=30%1m custom application development, studies c3=50%1m other services (training, project mgt., etc.) c4=20%
• C1+C1+C2+C4 = 8m• Compound merit weight is: Sum of 0+0.3+0.5+0.2 / 8
» = 12% technical merit weight
Determining ‘1-X’ – Example
Procurement of IT- Fiduciary Forum 2008 – Page 47
ITB – Evaluation Methodology
• ITB 28.5 (a),(b): Category merit sub-weights• Must list categories and list of preferred/Desirable
features within each category• Number of scored features should be kept to a
minimum• Scoring based on pre-specified assignment of
points• Operative goals is for a bidder to be able to
accurately forecast its own technical score
Procurement of IT- Fiduciary Forum 2008 – Page 48
ITB – Evaluation Methodology
• Score features which influence life-cycle cost and effectiveness of IS and exceed mandatory requirements
• Performance, capacity, or functionality features• Usability features (ease of use, administration,
expansion, etc.)• Quality of Bidder’s project/implementation plan,
staff experience, training, etc.
ITB 28.5 (a),(b) – What to score
Procurement of IT- Fiduciary Forum 2008 – Page 49
ITB – Evaluation Methodology
• ITB 28.5 (c), (e), (f): Category Weight
• Categories (i.e, SW, BQ) are given weights
• Features with each category may be given weights
Category Weight
Software (SW) 60%
Bidder Qual. (BQ) 20%
Training Plan (TR) 10%
Implementation Plan (IP) 10%
Procurement of IT- Fiduciary Forum 2008 – Page 50
ITB – Evaluation Methodology
• ITB 28.6: Evaluated Bid Price• C = Adjusted Bid Price (P)+Recurrent Cost (R)• P=total price for all goods/services less
adjustments• Adjustments include deviations as defined in ITB
28.6 (c)– Deviations to Implementation Plan– Deviations taken to contract payment schedule– Missing items (missing scored items are scored ‘0’)– Discounts
Procurement of IT- Fiduciary Forum 2008 – Page 51
ITB – Evaluation Methodology
• Recurrent Costs are reduced to net present value using the following formula:
Evaluated Bid Price – Recurrent Cost
MN
x xI
RR x
1 1
N = Number of years of Warranty Period (SCC 29.4)M = Number of years of Post-Warranty Period (SCC 1.1(e)(xii)x = Index from 1 to N+MRx = Total Recurrent Cost for year “x” as recorded in the Recurrent Cost FormI = Discount Rate, defined in the BDS 28.6 (d), typically 10%
Procurement of IT- Fiduciary Forum 2008 – Page 52
ITB – Bid Evaluation
• Price Weight X = 80%
• Technical Weight (1-X) = 20%
• T = 0.6*SW+0.2*BQ+0.1*TR+0.1*IP
• Three bidders, C evaluated as follows:
An Example Evaluation
Bidder 1 3.3 million
Bidder 2 4.7 million
Bidder 3 3.0 million
Procurement of IT- Fiduciary Forum 2008 – Page 53
ITB – Bid Evaluation
C - Evaluated Bid Price
Bidder 1 3.3 million
Bidder 2 4.7 million
Bidder 3 3.0 million
T – Total Technical Score
Bidder 1 65.0
Bidder 2 88.5
Bidder 3 46.0
Clow
Thigh
The T’s & the C’s
Procurement of IT- Fiduciary Forum 2008 – Page 54
ITB – Bid EvaluationDetermining B – Evaluated Bid Score
C - Evaluated Bid Price
Bidder 1 (3.0/3.3)* (0.8) + (65.0/88.5) * (0.2) = 0.87
Bidder 2 (3.0/4.7)* (0.8) + (88.5/88.5) * (0.2) = 0.71
Bidder 3 (3.0/3.0)* (0.8) + (26.0/88.5) * (0.2) = 0.66
Lowest Evaluated Bid
ITB 28.4: Highest Score (B) is termed Lowest Evaluated Bidder and is eligible for contract award, subject to ITB 32
Procurement of IT- Fiduciary Forum 2008 – Page 55
ITB – Schedule/Payment Deviations
• ITB 28.6 (c) (i) & (ii)
• Usually not used
• State maximum advance period and maximum delay period, in weeks
• 0.5% per week typical rate for delay, of bid price (none for advance)
Procurement of IT- Fiduciary Forum 2008 – Page 56
ITB – Post Qualification
• ITB 31• Use to specify specific tests on solutions provided
(i.e. performance tests, benchmarks)• Clear success criteria must be indicated• Site visits can be indicated • Clearly indicate how site visits will be conducted,
what evaluation methodology will be used, who will carry them
• Purchaser will bear cost of site visits
Procurement of IT- Fiduciary Forum 2008 – Page 57
ITB - Adjudicator
• ITB 38
• There should be an Adjudicator named (or agreed upon)
• Should play “honest broker” role (typically not from Purchaser’s country)
• Bidders can counter-propose an Adjudicator
Procurement of IT- Fiduciary Forum 2008 – Page 58
GCCPayment Terms – Example
Advance Payment
10 %
Information Technologies
(standard)
Delivery
60%
Installation
10%
Operational Acceptance
10%
Custom
Software
Installation
60%
Operational Acceptance
20%
ServicesPerformed
60%
Operational Acceptance 20%
TrainingMobilization
30%
Delivery
50%
Complete System Integration
10%
Procurement of IT- Fiduciary Forum 2008 – Page 59
GCC
• GCC 15.4 – Intellectual Property Rights (IPR) - Copyright
• Many possible approaches for custom software/materials– Purchaser retains all IPR– Supplier retains all IPR, and license Purchaser– An intermediate arrangement, with mutual benefit
• Seek Computer/Software Law expert when drafting these clauses
Procurement of IT- Fiduciary Forum 2008 – Page 60
GCC
• GCC 15.5 – Source Code Escrow• Source code is deposited with an “Escrow Agent”,
a neutral third party• Escrow agent keeps copy of source code secure
and safe• Source can be released to Purchaser based on pre-
set “release conditions”, such as:• Supplier goes bankrupt
• Supplier stops honoring software maintenance agreement
Procurement of IT- Fiduciary Forum 2008 – Page 61
GCC
• Language of Escrow agreement depend on laws of the country in which agreement is drawn
• Can be used to provide a level of protection for investments in custom software
• Can be costly to manage and administer, depending on level of verification required by the Purchaser
GCC 15.5 – Source Code Escrow - Continued
Procurement of IT- Fiduciary Forum 2008 – Page 62
Technical Requirements
• Technical requirements must be comprehensive and unambiguous
• Requirements must be stated clearly, with minimum room for differing interpretations
• Technical specifications must be vendor neutral and specified to elicit widest range of responses and competition, and not restrictive
• Brand names allowed in exceptional circumstance (Proc Tech Note #4), but always use “or substantially equivalent”
General Guidelines
Procurement of IT- Fiduciary Forum 2008 – Page 63
Technical Requirements
• Requirements should be definitive and offer quantifiable measure, and allow for comparable bids
• Use “not less than” or “greater than or equal” when specifying technical characteristics
• Standard performance benchmark can be used, except in cases where they become restrictive or un-economical
• Clearly identify items which are mandatory, and those that are preferred (scored)
General Guidelines - Continued
Procurement of IT- Fiduciary Forum 2008 – Page 64
Technical Requirements
• Clear, comprehensive
• Non-discriminatory
• Non-restrictive
• Up-to-Date
• Suitable to task
Specifications – in General Must be
Procurement of IT- Fiduciary Forum 2008 – Page 65
Technical Requirements
• Background
• Business Function & Performance Requirements
• Technical Specifications
• Testing Requirements
• Implementation Schedule
The Major Sections
Procurement of IT- Fiduciary Forum 2008 – Page 66
Technical Requirements
• Must clearly designate Mandatory vs. Preferred Specifications
• Use the following notation and enumerate specifications:
Technical Specifications
<M:cc-nnn>: Mandatory requirements which must be satisfied for a bid to be considered responsive (e.g., <M:HW-001> ). <P:cc-nnn>[score] Preferred specifications which will receive
points based on performance/functionality (e.g., <P:HW-001>[10] )
where cc indicates the Category (i.e., SW, BQ, etc.)
Procurement of IT- Fiduciary Forum 2008 – Page 67
Technical RequirementsTechnical Specifications –Mandatory Requirements Sample
Requirement No. Feature
<M:SW-001> Bilingual (Arabic/English)
<M:SW-002> Multi-platform hardware support
<M:HW-001> Processor performance benchmark
<M:HW-002> 60 GB Serial ATA Hard disk
Procurement of IT- Fiduciary Forum 2008 – Page 68
Processor benchmark
• Previously used clause:3.0GHz x86 CPU equivalent
• Present recommendation:Performance benchmarks such as
BAPCO Sysmark 2004 SE, or
SPEC (select appropriate one)
Procurement of IT- Fiduciary Forum 2008 – Page 69
Technical RequirementsTechnical Specifications –Preferred Requirements Sample
Requirement No. Feature
<P:SW-001>[30] Data replication
<P:SW-002>[20] Support for mobile device messaging
<P:SW-003>[40] Multi-class/course add & drop
<P:SW-004>[10] Self-serve kiosk operation
Procurement of IT- Fiduciary Forum 2008 – Page 70
Technical Requirements
• Service specifications typically are for:– Systems Integration elements– Training– Technical Support– Maintenance (Warranty & Post-Warranty)
Technical Specifications - Continued
Procurement of IT- Fiduciary Forum 2008 – Page 71
Recurrent Costs
• Hardware maintenance (post-warranty) for key technology
• Cost of keeping wear and tear-type of spare parts ready at hand and replacing these parts as needed
• Basic software bug correction and hot line service (post-warranty) for basic and application software
• Ongoing licensing costs of basic and application software
• Automatic supply of new versions/releases (for certain basic or application software packages)
Procurement of IT- Fiduciary Forum 2008 – Page 72
Recurrent Costs
• Cost of Supplier’s technical support staff for on-site and off-site support and software improvement work (staff-days or numbers)
• Cost to operate the information system for a specified period after operational acceptance
• Cost of consumables (toner for printers or copiers, special paper costs if and as needed)
• Telecommunications costs (if facilities will not be owned by Purchaser, or will directly be purchased, such as for one-time set-up fees, monthly rental charges, data volume charges based on expected average needs)
Continued…
Procurement of IT- Fiduciary Forum 2008 – Page 73
Two-Stage SBD
• For Two-Stage procurement of supply & installation of Information Systems.
• Developed from existing Single-Stage IS SBD, and…
• The Two-Stage SBD for Supply & Installation of Plant & Equipment
Procurement of IT- Fiduciary Forum 2008 – Page 74
Two-Stage SBD
• Complex business applications (e.g., Real-Time Gross Settlement Systems)
• Systems requiring extensive software development• Complex information technologies (e.g., GIS)• Systems involving extensive technical services for
design, development, customization , installation, training, operations and technical support
When to use
Procurement of IT- Fiduciary Forum 2008 – Page 75
Two-Stage SBD
• In the first-stage, Purchaser solicits non-priced technical proposals to address business/functional requirements
• By way of dialog, Purchaser arrives with each Bidder at a clear understanding of the aspects of the bid that:– (a) full-fill Purchaser’s requirements
– (b) do not conform to the requirements
– (c) are missing
General Approach
Procurement of IT- Fiduciary Forum 2008 – Page 76
Two-Stage SBD
• Bidders who offered sufficiently responsive first-stage bids are requested to submit second-stage bids
• Second-stage bids are priced bids, and are handled and evaluated in essentially the same manner as Single-Stage bids
General Approach - continued
Procurement of IT- Fiduciary Forum 2008 – Page 77
Two-Stage vs. Single-Stage SBD• Preface: provides rationale when to use two-stage• IFB: Two invitations, for first versus second stage,
respectively• ITB: Twelve clauses added after clause 12 of Single-Stage
SBD, to lay out first stage bid preparation, submission and evaluation
• BDS: Only one new entry related to hardware and software tests, but minor changes in other clauses too
• Sample Forms: Two bid forms (for first and second stage) instead of one such form in single-stage bidding
• GCC is unchanged• Fully detailed on IT Procurement Web Site in IS2STG
Publication Note
Procurement of IT- Fiduciary Forum 2008 – Page 78
Additional Provisions
• Content of first stage bid: Allows bidders to state exceptions to contract and technical requirements, and offer alternative components/bids
• Clarification meetings: Discuss bid deviations and agree on changes required in second stage bids
• Optional live tests: Mostly software tests; May include pass/fail tests; Purchaser must bear any own travel costs
• Invitation to second stage: Individual (bidder-specific) protocol of changes; perhaps general addendum for all bidders. Otherwise, bid must be updated first-stage bid.
Procurement of IT- Fiduciary Forum 2008 – Page 79
First-Stage Bid
• Similar to what is required as a full Single-Stage Bid, but without the Price Schedules
• Bidders are permitted to propose technical alternatives for components of their base bid or entire alternative bids (ITB 13.2)
• This would be in addition to, or in lieu of a base or main bid that meets the specified requirements
• Alternative bids maybe subject of discussion during the possible Clarification Meetings
Procurement of IT- Fiduciary Forum 2008 – Page 80
First-Stage Bid
• Bids are opened in public• Names of bidders who submitted bids will
be announced and recorded• Other information maybe recorded, as
considered by the Purchaser• Bid opening minutes to be distributed to all
Bidders that met the bid submission deadline
Procurement of IT- Fiduciary Forum 2008 – Page 81
First-Stage Bid
• First-Stage bids are examined for completeness, are in order, etc.
• Purchaser will determine if a bid substantially departs from the requirements
• If the departure is such that the bid cannot be reasonably expected to become fully responsive, Purchaser may exclude bid from further consideration
Procurement of IT- Fiduciary Forum 2008 – Page 82
First-Stage Bid – Technical Evaluation
• Purchaser will carry out detailed technical evaluation for non-rejected bids
• Purchaser must examine bids for:• Overall completeness and compliance with technical
requirements
• Suitability of the offered Information System
• Adherence to specified performance criteria
• Compliance with the Implementation Schedule
• Other factors, including maintenance services, that affect life-cycle of the Information System
Procurement of IT- Fiduciary Forum 2008 – Page 83
Bid Evaluation – Two-Stage
• Objective of first-stage is to refine the Purchaser’s specifications
• To allow Bidders to enhance their technical solutions to make them responsive
• In the second-stage, evaluation proceeds similar to the Single-Stage evaluation
Procurement of IT- Fiduciary Forum 2008 – Page 84
Bid Evaluation – Two-Stage
• Individual technical solutions are assessed to ascertain their acceptability in response to Bid specifications
• Alternative solutions should be evaluated on their own merit
• Determine if there are major deficiencies in the solutions and identify whether these deficiencies could be rectified by the Bidder
• This is when Clarification Meetings may be held
First-Stage Evaluation Process
Procurement of IT- Fiduciary Forum 2008 – Page 85
Bid Evaluation – Two-Stage
• In the first-stage, technical solutions should be evaluated with respect to mandatory criteria for reference purposes only
• Purchaser should work with Bidders to make the technical solutions responsive and to refine technical specifications if warranted
First-Stage Evaluation Process - Continued
Procurement of IT- Fiduciary Forum 2008 – Page 86
Bid Evaluation – Two-Stage
• Bids that cannot be made technically responsive, or
• If the Supplier cannot provide references or is not meeting qualification criteria, then
• Bid may be eliminated as being no-responsive
• Every attempt should be made to minimize the elimination of bidders at this stage
First-Stage Evaluation Process - Continued
Procurement of IT- Fiduciary Forum 2008 – Page 87
Bid Evaluation – Two-Stage
• All changes required in the second-stage bid will be listed in a bidder-specific memorandum entitled “Changes Required Pursuant to First Stage Evaluation”
• The memorandum also should include deviations with are unacceptable to the Purchaser
• Changes applicable to all Bidders invited to the second bidding-stage will be reflected in an Addendum to the initial Bidding Documents
Clarification Meeting
Procurement of IT- Fiduciary Forum 2008 – Page 88
First-Stage Clarification Meetings
• A Bidder-specific Clarification meeting may be conducted
• Used to clarify aspects of the Bid that require explanation or are not considered fully responsive by the Purchaser
• Purchaser needs to inform Bidder of any matters that would make the Bid conform to the requirements
Procurement of IT- Fiduciary Forum 2008 – Page 89
First-Stage Clarification Meetings
• Bidders are not required to attend a Clarification Meeting
• If Bidder elects not to attend, Purchaser will undertake reasonable effort to achieve required clarification by correspondence
• Bidders do this on their own risk
Procurement of IT- Fiduciary Forum 2008 – Page 90
First-Stage Clarification Meetings
• First-Stag Bid clarification stage may include live demonstrations and tests of Bidder’s proposed solution(s)
• BDS must clearly describe such test (ITB 23.3)• Purchaser must bear all staff, travel, and
subsistence costs associated with traveling to Bidder site
• Bidder is responsible for all costs in preparing, conducting, and dismantling tests
Procurement of IT- Fiduciary Forum 2008 – Page 91
First-Stage Clarification Meetings
• Purchaser must advise Bidder of any deviations the Bidder made, and which the Purchaser finds– Unacceptable and that must be withdrawn– Acceptable and will be incorporated into the
Bidding documents by way of an Addendum– Addendum would be sent to all Bidders invited
to submit second-stage bid
Procurement of IT- Fiduciary Forum 2008 – Page 92
First-Stage Clarification Meetings
• All changes required in the second-stage bid will be listed in a bidder-specific memorandum entitled “Changes Required Pursuant to First Stage Evaluation”
• The memorandum also should include deviations with are unacceptable to the Purchaser
• Changes applicable to all Bidders invited to the second bidding-stage will be reflected in an Addendum to the initial Bidding Documents
Procurement of IT- Fiduciary Forum 2008 – Page 93
Bid Evaluation – Two-Stage
• At end of first stage evaluation, Purchaser will either:– Invite Bidder to submit an updated technical &
commercial, priced bid, based on revisions as recorded in the Bidder-specific memo and/or Addenda
– Invite Bidder to submit alternative bid(s) in lieu of or in addition to the main First Stage Bid
– Notify Bidder that its bid has been rejected on grounds of being substantially non-responsive
Procurement of IT- Fiduciary Forum 2008 – Page 94
A substantially responsive bid is one that
(a) materially conforms with the First Stage Bid and/or any alternative components or alternative bids which the Purchaser invited the Bidder to offer in its Second Stage Bid,
(b) incorporates the modifications, if any, listed in the bidder-specific memorandum titled “Changes Required Pursuant to First Stage Evaluation” pursuant to ITB Clause 23.8, and
(c) reflects amendments, if any, to the Bidding Documents issued as Addenda together with or subsequent to the Invitation for Bids -- Second Stage, pursuant to ITB Clause 11.2.
Bid Evaluation – Two-StageSUBSTANTIALLY RESPONSIVE BID
Procurement of IT- Fiduciary Forum 2008 – Page 95
Evaluation of Bids - Forms
• Use Trial Standard Bid Evaluation Form for Supply & Installation of Information Systems, October 2004 Version
• IT Procurement Web Site
• Feedback welcome on the Trial Version
Procurement of IT- Fiduciary Forum 2008 – Page 96
Bid Evaluation – Two-Stage
• First-stage bid evaluation report should be formulated and sent to the Bank for review and issuance of “no objections”
• Report should include Bid opening minutes, and a copy of bidder-specific memorandum entitled “Changes Required Pursuant to First Stage Evaluation”
• The Draft “Invitation for Bids – 2nd Stage”• Amendments to the Bidding Document (if any)
First-Stage Evaluation Report
From that point on, it’s as if a Single-Stage Bid