Manufacturing of Epichlorohydrin
Production via GTE Process
Group 1
Alejandro Lopez Perez
Dragana Stojanovic
Kostantinos Papanikolaou
Priyanka Vaiude
Eindhoven 27/3/2015
GTE Process Design
List of Acronyms
EPH Epichlorohydrin
GLY Glycerol
HCl Hydrogen chloride
GTE Glycerol to epichlorohydrin
HOCl Hypochlorous acid
1,3-DCP 1,3-dichloro propan-2-ol
2,3-DCP 2,3-dichloro propan-1-ol
NaOH Sodium hydroxide
a-MCH a-Monochlohydrin
b-MCH b-Monochlorohydrin
GLUA Glutamic acid
DCP Dichloropropanols
PFD Process flow diagram
HPS High pressure steam
LPS Low pressure steam
MPS Medium Pressure steam
AA Adipic acid
CAPEX Capital expenditure
OPEX Operating expenditure
NaCl Sodium chloride
CSTR Continuous Stirred Tank Reactor
*DCP’s are referred as dichlorohydrins in the text in some instances, expressing the same compounds (1,3-DCP, 2,3-DCP).
GTE Process Design
Nomenclature
Units
r1 EPH formation reaction rate mol/m3 s
R Gas constant J/mol K
k1 Reaction rate constant of EPH formation mol s/m3
[OH-] Concentration of hydroxide ions mol/m3
[EPH] Concentration of EPH mol/m3
[DCP] Concentration of DCP mol/m3
T Temperature K
k2 Hydrolysis reaction rate constant mol s/m3
r2 Reaction rate of hydrolysis mol/m3 s
SGLY/1,3-DCP Selectivity of GLY toward 1,3-DCP -
Cp Specific heat capacity kJ/kg K
F Molar flow kmol/s
FCp Flow heat capacity kW/K
Qinterval Heat available in a temperature interval kW
ΔTinterval Temperature difference of interval K
NHE,AP Number of heat exchange units above pinch -
NHE,BP Number of heat exchange units below pinch -
NS,BP Number of streams below pinch -
NS,AP Number of streams above pinch -
ΔTCW Temperature difference of cooling water K
Δhvap Latent heat kJ/kg
Qutility Heat provided by utility kW
Cpo Free on board cost of equipment $
CBM Installed equipment cost $
FBM Design correction factor -
Fm Material correction factor -
FP Pressure correction factor -
M&S Marshall and Swift indices -
Executive Summary
GTE Process Design
Epichlorohydrin is a valuable fine chemical, mainly dedicated to the manufacturing of epoxy resins.
Currently, several routes are available for the production of this chemical with the predominant one
to be the allylic chlorination of propylene, referred also as conventional process route in this text.
The extensive formation of undesired chlorinated organics from this process that are difficult to be
disposed of and the escalating cost of petrochemical raw materials such as propylene postulate the
investigation of alternative routes for epichlorohydrin manufacturing.
The above disadvantages of the conventional process in combination with the growing availability of
glycerol, as consequence of the increase of biodiesel production have played decisive role in the
rapid development of the glycerol to epichlorohydrin route (known as GTE process) which was
historically prevented due to the high cost of glycerol.
GTE route is divided into two steps; chlorination of glycerol is the first and dehydrochlorination of
dichloropropanols the second one. In the present study both steps have been examined thoroughly
and the entire process has been simulated on Aspen Plus V8.6 software.
Two reactor configurations have been proposed for the first step, utilising adipic acid as a liquid
catalyst, whilst a reactive distillation column has been designed for the second step accompanied by
a separation train for production of almost 99% pure final product.
Sizing of process equipment and economic evaluation of the process have been performed, revealing
strong potential of GTE route compared to the conventional technology. China has been chosen as
the location of the plant and the payback period has been estimated to endure 3 years for 1800 $/ton
selling price of epichlorohydrin. Heat integration by Pinch point analysis showed 0.167 M$/year
savings from utilities and finally a preliminary control scheme has been suggested for the process.
GTE Process Design
Design Considerations
The basis of design considered in the current project is specified in this section. The topics
considered in the Basis of Design are the plant capacity, plant location, composition and prices of
materials (i.e. raw material), physical and chemical properties of the substances involved in the
process and storage information about some of these materials.
Plant capacity
The capacity of the GTE process in order to produce epichlorohydrin (EPH) is given to be 100
kton/year.
Plant location
The location of the glycerol (GLY) to EPH plant is assumed to be in China.
Compositions and prices
The raw materials used in this process are GLY, hydrochloride (HCl) gas and sodium hydroxide
(NaOH) solution. The GLY is assumed to be obtained from a nearby biodiesel production plant. The
HCl gas is assumed to be obtained from a plant nearby producing HCl gas as one of the byproducts
of that plant and is assumed to be fed to the plant via pipelines. The raw material composition and
purchase price is listed in Table 1.
The scope of the project claims that the feedstock composition is 99.9% glycerol with 0.1%
impurities that may be present due to processing parameters involved in the previous plant. The
following table contains the classification of the most important substances involved in the process
and their purity and price.
Table 1 Composition and price of the main raw materials present in the GTE process
Name Formula Purity wt.% Purchase price
$/ton
Glycerol C3H8O3 99.9 800
Hydrogen
chloride gas
HCl 100 360
Sodium
hydroxide
NaOH 99.99 120
GTE Process Design
Table of Contents1. INTRODUCTION........................................................................................................................................2
2. Literature Review..........................................................................................................................................5
2.1. First Step –Chlorination of Glycerol.....................................................................................................8
2.2. Second Step –Dehydrochlorination of DCP.......................................................................................13
2.3. General Process Considerations and Operation Conditions...............................................................14
2.4. Literature Review Conclusions...........................................................................................................15
3. Aspen Simulation of GTE process..............................................................................................................17
3.1. Chlorination of GLY Reactor Selection.............................................................................................18
3.2. Dehydrochlorination of DCP..............................................................................................................31
4. Equipment sizing and cost..........................................................................................................................37
4.1. Reactors and columns.........................................................................................................................37
4.2. Pumps and Compressors.....................................................................................................................38
4.3. Heat exchangers and decanters...........................................................................................................39
5. Economic evaluation...................................................................................................................................41
5.1. ASPEN Economics Input....................................................................................................................41
5.2. Results.................................................................................................................................................42
6. Conclusions and Recommendations...........................................................................................................46
Appendix.............................................................................................................................................................46
Heat Integration of GTE Process-Pinch Point Analysis.....................................................................................49
GTE Heat Exchanger Network Design above Pinch Point.............................................................................52
GTE Heat Exchanger Network Design below Pinch Point............................................................................54
Annual Savings Estimation.............................................................................................................................56
Control Scheme of GTE Process........................................................................................................................58
Control of Reactors.........................................................................................................................................58
Control of Distillation columns......................................................................................................................59
Heat Exchangers and Decanters......................................................................................................................59
References...........................................................................................................................................................63
GTE Process Design
This page intentionally left blank
GTE Process Design
Introduction
1
1. INTRODUCTION
Several routes are known to manufacture EPH, most is made in a two-step process from allyl
chloride and hypochlorous acid procuring a mixture of two chlorinated alcohols which can be
converted into EPH by treating with a base sodium hydroxide.
In the different reactions occurring in the above process, large amount of undesired organic
compounds which are very expensive to be discarded resulting to a high required selling price. In
combination with the high price of propylene, which is used a raw material, this route of EPH
production becomes less attractive leading to a need for alternative routes.
Owing to the disadvantages mentioned above, other routes have been investigated and GTE is
highlighted as the most promising technology representing an economically and environmentally
advantageous process. The commercial development of the process was obstructed until recently,
because of the high cost of glycerol. The recent advances in the technology related to biofuels have
caused the GLY price to drop dramatically since it can be obtained as a biodiesel by-product. This
new development and subsequent reduction in prices of GLY has indicated a great potential for the
feasibility of GTE process.
In 2007 Solvay, a traditional GLY and EPH manufacturer was the first to start GTE process.
Previously in the early 2000s the company was producing GLY from EPH but after the glycerol
price drop, it reversed its process to produce EPH from GLY. The picture below taken from the
company website represents this reversal trend in the process of production of EPH and glycerol.
Figure 1.1 Trend reversal in the processes concerning Glycerol and EPH from Solvay.
2
Solvay has acquired many patents in this regard and the innovative process is registered as
Epicerol®, characterized as the most important patented process for the production EPH. The
company claims that this process is very environment friendly and reduces the carbon footprint by
60% as compared to the conventional route. GTE process of EPH production has been patented by
other well-known chemical industries like DOW chemicals.
The aim of this project is the evaluation of technical as well as economic feasibility of GTE process
and comprehensive comparison with the conventional process. To that end, GTE process has to be
thoroughly designed with subsequent estimation of Capital Expenditure (CAPEX) and Operating
Expenditure (OPEX). ASPEN PLUS (version 8.2) will be used for that purpose and the efficiency of
GTE will be established.
3
Literature Review
4
2. Literature Review
EPH is a liquid epoxide being used as an intermediate chemical for the production of epoxy resins
for coatings paintings and electronic circuits but also for non-epoxy applications such as paper
chemicals, water treatment and health care products [1]. China is highlighted as the leading market in
EPH production. Almost 97 % of the annual production is being consumed in the production of
epoxy resins and ca. 5% increase in annual production rate is predicted until 2018 [2].
Many different routes for EPH manufacture have been suggested in the literature; however the
predominant one in industry is the allylic chlorination of propylene to allyl chloride, starting from
propylene and chlorine as primary raw materials in a multi-step process as indicating in Figure 2.1.
Figure 2.1 The conventional route to EPH production in a multi-step process [3].
The first reaction is the allylic chlorination of propylene to allyl chloride. In parallel hypochlorous
acid (HOCl) being produced via dissolving of chlorine into water and subsequently reacts with the
produced allyl chloride from the first step to yield a mixture of 1,3-dichloropropan-2-ol (1,3-DCP)
and 2,3-dichloropropan-1-ol (2,3-DCP). The last step of the process includes the reaction between
dichloropropanols (DCP) and a base (e.g. NaOH or Ca(OH)2) for the formation of the final product.
The described process can yield EPH of very high purity but suffers from numerous undesirable
features such as very low chlorine atom efficiency (i.e. only one of the four chlorine atoms
participating in the reaction is retained in the product molecule), significant inefficiencies in the
5
chlorination and hypochlorination steps, resulting to the formation of unwanted chlorinated organics
(ca. 0.5t/tEPH) and finally the continuous increase in the cost of petrochemical raw material like
propylene. [4]. In order these problems to be addressed different routes were examined in the past
based on less expensive raw materials. One such a route relies on the conversion of GLY through
DCP to EPH, known as glycerine to epichlorohydrin process (GTE). The high cost of GLY
prevented the development and the consideration of this process previously. This situation has been
changed recently since GLY can be obtained as by-product of biodiesel production (ca. 0.1 tn/tn
Biodiesel), and investigation on this process being conducted extensively [5,6]. Figure 2.2 shows the
rise in biodiesel production from 2000 to 2008, implying the potential of GTE process in the near
future.
Figure 2.2 World biodiesel production rate 2000-2008 [2]
The GTE is a two-step process as it can be seen from Figure 2.3. In the first step (or first reaction)
chlorination of GLY is taking place by reaction with HCl in the presence of liquid catalyst providing
a rich stream to DCP. This stream subsequently is driven the next unit to react with a base for EPH
formation.
6
Figure 2.3. EPH production from GTE process [3].
Apart from the reaction steps also separation of the final product is included in the process. Thus a
block-flow diagram, such the one presented in Figure 2.4, can give insight into the different steps of
GTE process presenting the initial idea before the execution of the design part. Literature details and
findings on the different steps are discussed in the following sections.
Figure 2.4 GTE process block flow diagram.
7
2.1. First Step –Chlorination of Glycerol
The first step of the process is the chlorination of GLY as mentioned previously, where four
reactions in series and parallel (i.e. complex reactions) are taking place. The reaction of GLY with
HCl yields a mixture of a-Monochlorohydrin (a-MCH) and 2-Monochlorohydrin (b-MCH) as
indicated in Figure 2.5. Subsequently a-MCH reacts with HCl to produce the final product of the
first step, i.e. DCP. All the reactions involved in reaction network are reversible but kinetics studies
have shown negligible kinetic constants of the reverse reactions, thus they can be considered as
irreversible.
Figure 2.5 Chlorination of GLY reaction network.
Before the design of GLY chlorination system several aspects have to be considered such as:
Catalyst Selection
Catalyst Concentration
HCl state
Operating conditions
Reaction kinetics
2.1.1. Catalyst Selection and Concentration
Catalyst selection and concentration are very important aspects as the selectivity to the desired
product and GLY conversion are strongly influence by them. The suitability of the catalyst can be
judged from three factors, namely activity, selectivity and low volatility. Carboxylic acids are
commonly utilised for the reaction, with acetic acid to be the usual choice owing to its very high
activity and selectivity towards 1,3-DCP; however its high volatility (ca. B.P. 117 oC) renders it as
8
inappropriate choice for large scale production due to significant losses at the reaction temperature
(ca. 120 oC).
E. Santacesaria [4] tested different carboxylic acids by using an apparatus operating in continuous
mode for HCl and batch for GLY in an effort to define catalysts with similar performance as acetic
acid but significantly lower volatilities. In this study the crucial role of pKa value in relation to the
performance of the catalyst was fortified. Specifically catalysts with pKa greater than 4 showed high
selectivity to DCP, while those with less than 1.2 demonstrated high selectivity to a-MCH and b-
MCH. The experiments were conducted at 100 oC and 5.5 bar HCl pressure and the downstream
composition was measured after 3 h. Adipic acid (AA) found to be very selective to 1,3-DCP, with
molar concentration of 72.23 % mol and complete conversion of GLY. This performance in
combination with high boiling point of AA (337.5 oC) highlights it as a promising catalyst.
R. Vitello et. Al [5] performed experiments with two series of catalysts, specifically glycolic acid
series and amminoacid series. The runs conducted at 100 oC for different pressures of gaseous HCl
and different concentration of catalysts. Glutamic acid (GLUA) found to be the best one in terms of
performance and further investigation followed. Higher concentration of catalyst proved to be very
beneficial regarding the selectivity to the desired product as seen in Figure 2.6, as from 2% catalyst
loading to 8%, a rise of 40% to selectivity towards 1,3-DCP is noted.
Figure 2.6 Effect of catalyst loading in selectivity for GLUA catalyst at P=4.5bar and T=100 oC [5]
9
Propionic acid has been discussed as another alternative [6] but with no good perspective because of
its slightly lower volatility than AA.
2.1.2. Hydrogen Chloride State and Reaction Conditions
The chlorination agent can be introduced in the reactor as a solution of hydrochloric acid with water
or as a gaseous hydrogen chloride. The big disadvantage of the first case is the presence of large
amount of water in the reactor and therefore larger reactor volumes because of slower kinetics.
Dimitriev et.al [7] investigated the effect of water concentration in regards to a-MCP formation at a
range of temperature between 80-117 oC. As it can be concluded from Figure 2.7 increase in water
concentration implies significant decline to the reaction rate constant and consequently slow kinetics.
Figure 2.7 Effect of water concentration to the reaction rate constant of a-MCP production [7].
10
Apparently, hydration degree strongly affects the reaction rates, resulting to smaller amount of
products formed and consequently to large reaction volumes. This problem can be tackled by feeding
gaseous HCl in the reactor. The feed pressure of HCl is a critical parameter as influences strongly the
conversion of GLY but also the selectivity toward 1,3-DCH which can react 20 times faster than 2,3-
DCP for EPH production.
Bruce M. et. al [3] demonstrated the effect of HCl pressure on product molar composition by
utilising 2 wt% acetic acid catalyst. Three different values of pressure were tested, 20, 30 and 50 psi.
The formation of 1,3-DCP in the case of 20 psi was observed to be negligible, while for 50 psi it has
the highest concentration in the reactor outlet. This behaviour can be explained by the reaction
nature. The reaction seems to be equilibrium limited at low HCl pressures resulting to very low
conversions and after 1 h run the concentrations of a-MCP and GLY reach a limit and no change can
be observed afterwards. Additionally, in the same study proved that the absorption of HCl to GLY is
higher working at higher pressures, indicating that higher conversion of GLY can be achieved.
Figure 2.8 demonstrates product evolution for different HCl pressures [3].
Similar results presented by R. Tesser et. al. [8] where monochloro-acetic acid catalyst tested under
2, 5.5 and 9 bar pressures. At 9 bar pressure complete conversion of GLY achieved after almost 3 hr
of experiment and 30 % rise of selectivity appeared after 225 min as shown in Figure 2.9.
11
Figure 2.9 Selectivity to dichlorohydrins (i.e. DCP) as a function of HCl partial pressure [8].
S.H. Lee et al. [9] highlighted the importance of proper mixing of the GLY and HCl for good yields
and selectivity. Experiments were conducted in a batch reactor revealing that at low stirrer speed
chlorination of GLY is mass transfer limited but above 600 rpm HCl is dissolved effectively in the
liquid phase providing higher yields of 1,3-DCP. This a critical observation that should be taken into
account for the reactor design and proper mixing will be required.
12
Figure 2.10 DCP yield as function of stirrer rotation speed [9].
2.1.3. Reaction Kinetics
The reaction kinetics were retrieved from the literature [10]. AA referred as promising catalyst for
industrial production and the kinetics by utilising this catalyst are presented in Table 2.1 for
temperature equal to 120 oC. In this a study a model developed for describing kinetics of DCP
production assuming 1st order kinetics for all the reactions and found quiet reliable compared to the
experimental results. These kinetic values were used later from us for simulation of the process.
Table 2.1 Reaction kinetic values of chlorination of GLY at 120 oC [10].
Reaction Rate Constant k (min-1) Activation Energy Ea(kJ/mol)
1 2.56 30.7
2 9.07 41.8
3 5.03 29.4
4 11.37 45.9
2.2. Second Step –Dehydrochlorination of DCP
In the second step of the process dehydrochlorination of DCP occurs for the production of the final
product EPH. The base to be used is defined from the formulation of the problem as sodium
hydroxide (NaOH). The reaction taking place are the main one but also in parallel hydrolysis of DCP
occurs resulting to the consumption of value product as illustrated from Reaction 1 and 2.
1. C3 H 6 Cl2O+NaOH yields→
C3 H 5 ClO+NaCl+H 2 O
2. C3 H 5 ClO+NaOH+H 2 O yields→
C3 H 8O3+NaCl
Apparently, to avoid undesired consumption of the valuable product from hydrolysis reaction it
should be removed promptly. This can be achieved by performing the reaction in a reactive
distillation column with instantaneous removal of EPH. Reactions conditions are relatively mild at
around 60 oC and atmospheric pressure [11] and the optimal ration of base to DCP is defined at
0.89:1 obtaining 97 % selectivity to EPH and 88 % of DCP [12].
13
MA et.al [13] showed that both reactions can be well represented by 2nd order kinetics using titration
technique as seen from Equations (2.3) and (2.4). These kinetic parameters were used from us for
the simulation of the reaction unit afterwards.
For temperature in the range: 313 - 333 K
Main Reaction
r1=8.97∗1020e−123200
RT [ DCP ]¿ (2.3)
Side Reaction
r2=5.66∗1010 e−70790
RT [ EPH ]¿ (2.4)
Where [OH-] the concentration of hydroxide ions and [EPH] the one for EPC.
2.3. General Process Considerations and Operation Conditions
Production of Dichlorohydrins :
In this process the catalyst, glycerol and HCL are fed to a reactor where the chlorohydrination
reaction takes place. The products are subjected to distillation to remove impurities like unreacted
raw materials and undesired products. The top product from this operation is subjected to decantation
where the DCP’s are separated from water [15].
Operating conditions of DCP production
Reaction temperature: 120 ⁰C
Reaction pressure: 5 bar
Separation (distillation) temperature: 130 - 195⁰C
Separation (distillation) pressure: 1 bar
Condenser temperature: 25 ⁰C
Residence time: 7-11 hours
14
Production of EPH:
The EPH is manufactured in two steps: the first step is reaction and extraction followed by
distillation separation train. The distillation operation can be in combination with adsorption, but this
is not the most preferred option. The reactor has to be equipped with stream stripping to remove the
EPH from the reaction environment as soon as it is formed to avoid the side reaction.
Operating conditions of EPH production [16]:
REACTORS
Excess of DCP as compared to NaOH: 0.89 effective equivalent (in order to reduce EPH
degradation reactions especially hydrolysis)
Reaction temperature: 60-90 ⁰C
Pressure range: 1– 1.5 bar
Reactor type: Reactive distillation column
Residence time: 7 – 10 min
2.4. Literature Review Conclusions
Regarding to the first step of the process (chlorination of GLY), the catalyst can strongly influence
the efficiency of the reaction. A catalyst is characterised as successful when is active, selective to
1,3-DCP and non-volatile. According to the above criteria AA seems to be the optimal choice at a
concentration around 8 % mol. HCl should be fed as a gas inside the reactor to avoid accumulation
of water and therefore slow kinetics. Water is also produced as a product of chlorination of GLY,
thus a combination of reaction and intermediate separation might be a promising solution for water
removal and lower reactor volume. The pressure of HCl and mixing intensity are highlighted as very
important parameters in relation to yield and selectivity toward DCP. HCl at 5 bar pressure can
provide very good results, whilst good mixing should be provided to overcome mass transfer
limitations. Upon the dehydrochlorination of DCP, EPH produced should be removed instantly from
the reaction system, and to that end a reactive distillation column has to be utilised. The optimum
ratio between the base and DCP was found to be 0.89:1 giving high selectivity on EPH and
conversion of DCP. Finally the kinetics of both reactions were found in the literature and will be
used for the simulation of the process on Aspen Plus.
15
GTE Aspen Simulation
16
3. Aspen Simulation of GTE process
In the present chapter the simulation and conceptual design of GTE process by Aspen Plus software
are presented. As it can be seen from Figure 3.1 GTE process is composed of four different steps.
The first step is chlorination of GLY, where HCl, AA and GLY are fed to the first reactor producing
mainly DCP’s and water, but also a-MCH and b-MCH. In the next step water with
monochlorohydrins are removed giving a stream rich in DCP’s which react with NaOH in the
dehydrochlorination unit to produce EPH and water. At the same time a solution of sodium chloride,
one of the products of the reaction, is removed from the bottom of the unit. Finally the separation of
EPH from water is performed in the purification unit. For the simulation Electrochemical NRTL has
chosen as base method due to the presence of electrolytes in the process, such as HCl and NaOH.
Figure 3.1 Block diagram of the GTE process
17
3.1. Chlorination of GLY Reactor Selection
The reaction is taking place in liquid phase and HCl decided to be fed in gas phase. As pointed out in
the previous chapter effective mixing is required in order to increase the yield and selectivity to
DCP. The most commonly used reactors on bench scale apparatus are either batch or semi-batch;
however these types of reactors are inappropriate for large scale production and particularly when the
annual capacity of the product is 100 kt. In industrial scale the previous types can be replaced by
continuous stirred tank reactors (CSTR’s), retaining the capability of intense mixing in a continuous
mode. Initially, the reaction system was simulated on Aspen only with one CSTR but an extremely
large reactor volume was needed , ca. 360 m3, in order to obtain the desired conversion of GLY and
at the same time the necessary mole flow of DCP for 100 kt/yr production of EPH. This result most
likely is attributed to the fact that CSTR operates at the same operating conditions (i.e. temperature
and concentration) as the exit stream. To reduce the reactor volume, CSTR’s in series were simulated
in order to approximate plug flow behaviour but at the same time retaining perfect mixing. The
following configurations are based on the same principle, but lower volumes for the same conversion
can be achieved in the second case making them the preferred option.
3.1.1. First Reactor Configuration Proposal-CSTR Model
The process flow diagram of the first proposed configuration is seen in Figure 3.2. 285 kmol/hr of
gaseous HCl at Stream 1 are driven to the compressor C-1, where they compressed at 5 bar and
afterwards the stream is moving towards HE-1 where it is cooled down to 90 oC. The stream is
splitted by S-1 to four streams, HCl-1, HCl-2, HCl-3 and HCl-4 for distribution into the first four
reactor units. Stream 2 contains pure GLY in a mole flow rate of 140 kmol/hr. After heating at 90 oC
by HE-2 the stream is pumped toward S-2. After splitting into two streams, GLY-1 and GLY-2,
GLY is fed to the first two reactor units follows CSTR-1 and CSTR-2.
18
Figure 3.2 PFD of GLY chlorination step.
The first reactor block is focused on the production of monochlorohydrins (a-MCH, β-MCH), whilst
the second block is dedicated to the production of DCP (1,3-DCP and 2,3-DCP). This can be better
understood by the definition of selectivity as given by Equation 3.1 and the kinetics of the reaction
[17].
The production of a-MCH and 1,3-DCH are 1st order reactions as mentioned before and they occur in
series. Thus by formulating the selectivity of GLY toward 1,3-DCH becomes clear that for high
concentration of GLY high selectivity to a-MCH can be achieved and this occurs in the first reaction
block where the entire stream of GLY is distributed. After the first reaction unit high concentration
of a-MCH has been obtained and therefore the process is primarily selective to 1,3-DCH in the
second reaction unit. Feed of GLY is interupted after CSTR-2 so as to speed up the kinetics of 1,3-
DCH formation and at the last unit the feed of HCl is stopped where the remaining a-MCH reacts
with the unreacted HCl. The distribution of HCl is targeting to complete consumption of GLY in the
first block, preventing 1,3-DCH formation.
Water removal has been pointed out as very beneficial for the kinetics of GLY chlorination and to
that end DC-1 unit is present between the two reaction blocks where 177 kmol/hr out 186 kmol/hr of
19
water are removed from the top stream, while the bottom stream composed of MCP, DCP and GLY
moves to the next reaction unit (CSTR-3). This amount of water removal can be achieved with a
column of 25 bubble cap trays and reflux ratio around 1.3. The downstream of the reactor is
composed of large amount of DCP, around 126 kmol/hr and therefore the yield of GLY to DCP is
estimated around 90 %. Also water (ca. 77 kmol/hr) and small amount of monochlorohydrins (ca.12
kmol/hr) are present, with negligible amounts of GLY and HCl. Table 3.1 and Table 3.2 show the
moleflow of HCl and GLY after S-1 and S-2 respectively.
Table 3.1 Stream 3 (HCl) splitting.
Stream 3 HCl-1 HCl-2 HCl-3 HCl4
Molar Flow (kmol/hr) 285 107.99 107.99 53.9 15.02
Table 3.2 Stream 6 (GLY) splitting.
Stream 6 GLY-1 GLY-2
Molar Flow (kmol/hr) 140 70 70
The volumes of the reaction units with the corresponding dimensions by assuming cylindrical vessel
geometries are tabulated in Table 3.3.
Table 3.3 Reaction units diamensions.
Unit Volume (m3) Diameter (m) Height (m)
CSTR-1 31.5 3 4.4
CSTR-2 36.3 3 5.1
CSTR-3 47 3 6.6
CSTR-4 40 3 5.6
CSTR-5 24.2 3 3.4
Total Volume 179
3.1.2. Second Reactor Configuration Proposal-PFR Model
As discussed in the previous chapter, using a CSTR in series improves the yields of DCP and reduces
the overall volume of reaction respect a conventional CSTR. The next logical step is to improve this
20
configuration by developing a custom model of a real PFR reactor. The main idea behind this model
is to overcome some of the difficulties still present in the previous configurations:
-Elevated residence times.
-High water production.
-Two mol of Hydrogen chloride in gas phase is needed for each mol of GLY.
As it is shown in Figure 3.3, in the reaction between HCl and GLY, the production of 1,3-DCP is
increased significantly for high residence times (8-9 h). This is exactly the same relation obtained in
the simulation with ASPEN plus.
Figure 3.3 Kinetics Comparison between experimental results and the developed model for
chlorination of GLY [10].
As a consequence, the reactors needed for the DCP production have very high volumes. In each
CSTR, water is being generated in the system reducing the concentration of GLY, there is non-
reacted HCl and very high pressure is needed to reduce the overall volume of the gas phase for the
non-reacted HCl.
The first solution to deal with these problems is working at very high pressures (>20 bar) therefore
the volumetric flow of HCl is reduced. However, the residence times are still high and the volume
21
cannot be further reduced. The idea to decrease the residence time and achieve high yields was to
increase the number of CSTR in series until the configuration assembled a more realistic PFR.
Figure 3.4 Absorption of HCl as a function of time for different pressures [3].
The model of the real PFR is developed by using many CSTR in series. As described in the literature
review chapter, the HCl is not participating on the kinetics, the flow of HCl introduced is optimized
to be the exact amount that can react in each reactor. Introducing more than required increases the
overall volume significantly and an additional separation is needed. Splitters are used to distribute
the flows of HCl. The split ratio is optimized so the outlet of each reactor does not contain unreacted
HCl, this ensures that the correct amount is used. The custom model of this reactor is shown in
Figure 3.5.
Introducing the exact amount of HCl in each reactor decreased the overall volume of reaction and
allowed to decrease the pressure of operation from 20 bar to 5 bar. All the amount of HCl has reacted
and therefore there is no gas phase in the reactor. Increasing the number of CSTRs used has shown to
improve the distribution of HCl among the reactor and reduces the overall volume and residence
times required to achieve the required yield of DCP.
22
Figure 3.5 Custom model of PFR with multi-injection of HCl.
In the real PFR, each CSTR reactor of the model is considered as one injection of HCl in the bottom.
The gas flow must consist of very thin bubbles to ensure optimum dispersion of HCl and increase the
mass transfer to be similar to each CSTR of the simulation and a depiction of the bubbling HCl into
the reaction mixture is illustrated in Figure 3.6. At the beginning higher amount of HCl is needed
because the reaction occurs faster and each CSTR was modelled with identical residence time.
Figure 3.6 Representation of HCl bubbling into the reaction mixture.
The model of the reaction part in Aspen is as shown in Figure 3.8 and 3.9. The model is equivalent
to use a total of four PFR. The hierarchies A and B are equivalent. These blocks are composed of
two PFR in series. They are interconnected with a distillation column in the middle that extracts all
the water formed during the reaction in the first reactor and sends back the products and unreacted
species to the second reactor.
23
Figure 3.7 PFD of DCP production.
Figure 3.8 Water extraction from PFR reactors.
24
B1B2B3
W1 W2
PFRB1OUT38(IN)
PFRA1OUT39(IN)PFRA2IN 40(OUT)
PFRB2OUT 41(OUT)
C-1
HE-1
HE-2 P-1
B5
HIERARCHY
PFR2
B3
HIERARCHY
PFR1
B2
HE-3
V-1
DC-1DC-2
HE-4
HCL
1HP
GLY 1HT S32
1HC
PFR2OUTGLY2
HCL2
GLY1
HCL1PFR1OUT
PRODUCTS
PL
PLTL
17
16
19
DICHL
2118
The water extraction step reduced the overall volume of the reactors by 40%. Both identical reactors
A1 and B1 are connected to the column. Water is removed from the tops, and the products and
unreacted species are sent back to reactors A2 and B2 respectively.
Figure 3.9 PFR Reactor 1 and 2 in series (blocks A and B equivalents) with water extraction.
The injection point was arithmetically determined according to the volume of each CSTR respect the
total volume of the PFR. Table 3.4 and 3.5 show the injection point of HCl, the exact flows of HCl
needed to completely react, the total length of the reactors, and the total volume of each reactor.
The diameter of the PFRs is fixed at 2.5m. As can be checked in bold letters in the following tables,
the first reactor has 24 m3 and 4.89 m of length, and the second reactor has 44 m3 and 9 m of length.
25
Table 3.4 Injection points of HCl for the first PFR.
Reactor 1
VCSTR t / h VPFR(L) / cc L / m Injection / m HCl / kg/h HCl / L/s
1567 0.25 1567 0.02 0.01 799 36.23
1701 0.50 3268 0.05 0.04 608 27.53
1806 0.75 5074 0.07 0.06 480 21.74
1891 1.00 6965 0.10 0.09 384 17.39
1971 1.25 8936 0.13 0.12 288 13.04
2036 1.50 10972 0.16 0.14 352 15.94
2085 1.75 13057 0.19 0.17 224 10.14
2127 2.00 15184 0.22 0.21 192 8.70
2162 2.25 17346 0.25 0.24 160 7.25
2193 2.50 19539 0.28 0.27 144 6.52
2221 2.75 21760 0.32 0.30 128 5.80
2245 3.00 24005 0.35 0.33 96 4.35
Table 3.5 Injection points of HCl for the second PFR
Reactor 2
26
t / h V(Length) / cc PFR2Length / m Injection / m HCl / kg/h HCl / L/s
3.25 1762 0.37 0.19 13.5 0.61
3.50 3545 0.40 0.39 9.6 0.44
3.75 5347 0.43 0.41 12.5 0.57
4.00 7167 0.45 0.44 10.6 0.48
4.25 9002 0.48 0.47 8.3 0.38
4.50 10853 0.51 0.49 8.2 0.37
4.75 12716 0.53 0.52 57.6 2.61
5.00 14591 0.56 0.55 54.4 2.46
5.25 16477 0.59 0.58 48.0 2.17
5.50 18372 0.62 0.60 41.6 1.88
5.75 20275 0.64 0.63 36.8 1.67
6.00 22186 0.67 0.66 38.4 1.74
6.25 24105 0.70 0.69 35.2 1.59
6.50 26031 0.73 0.71 32.0 1.45
6.75 27963 0.76 0.74 28.8 1.30
7.00 29901 0.78 0.77 25.6 1.16
7.25 31843 0.81 0.80 22.4 1.01
7.50 33790 0.84 0.83 19.2 0.87
7.75 35741 0.87 0.86 22.4 1.01
8.00 37697 0.90 0.88 16.0 0.72
8.25 39656 0.93 0.91 19.2 0.87
8.50 41618 0.95 0.94 16.0 0.72
8.75 43583 0.98 0.97 12.8 0.58
9.00 44369 0.99 0.99 0.5 0.02
Plotting the injection ratio of HCl/GLY mole ratio against the normalized length of reaction (PFR1
and PFR2 length), it is obtained a logarithmic expression that relates the optimized HCl injection
divided by the GLY mole flow (140 kmol/h of GLY at the inlet of the reactors) and the inject zones
across the reactor. This would be an advantage for designing the real reactor, where the nozzles
27
could be distributed evenly and it can even be extrapolated to other reactor size and other production
requirements.
0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.000.00
0.01
0.02
f(x) = − 0.0155410550078427 ln(x) + 0.00144716881721868R² = 0.983599034486075
f(x) = NaN ln(x) NaNR² = NaN Normalized injection
Reactor 1 Logarithmic (Reactor 1)Reactor 2 Logarithmic (Reactor 2)
L/Lreactor (m)
HCl/G
Ly ra
tio
Figure 3.10 Plotting of HCl injection points across PFR1 and PFR2.
3.1.3. DCP Separation-1st Train
DCP are obtained on removal of water, unreacted GLY, HCl and intermediate compounds α and β-
MCH from the product stream exiting the reactors. As can be checked on Table 3.6, the difference in
volatilities allows to separate all the components easily.
Table 3.6 Boiling points of components in the system
28
Components Boiling points (°C)
Glycerol 289
HCL -85.05
α -MCH 213
β-MCH 220.35
1:3 DCP 174.3
2:3 DCP 184
The extraction of these undesired products from the mix is done by employing two distillation
columns as seen in Figure 3.11. In the first column DC-1, water and traces of HCl are extracted from
the product mix. The inlet stream of the column stream 15 is at 130oC and at 1 bar. A partial
condenser has been used on the column to flash remaining HCl before the condenser (stream-16).
The bottom stream is heated up by HE-4 and is sent to the second column DC-2, the desired product
of the first reaction, DCP, are retrieved on stream 20 with 99.5 % purity.
C-1
HE-1
HE-2 P-1
B5
HIERARCHY
PFR2
B3
HIERARCHY
PFR1
B2
HE-3
V-1
DC-1DC-2
HE-4
HCL
1HP
GLY 1HT S32
1HC
PFR2OUTGLY2
HCL2
GLY1
HCL1PFR1OUT
PRODUCTS
PL
PLTL
17
16
19
DICHL
2118
Figure 3.11 DCP separation-1ST separation train.
Optimization first separation train
The important criteria considered for obtaining the optimal dimensions of the column are:
Number of stages
Feed stage
Mole recovery
29
Sensitivity analysis was done to find the optimal parameters considering the above criteria.
Optimization was performed by varying number of stages, feed stage and reflux ratio, the minimum
duties are found (iterative process). The composition profile of the components of interest must
reveal a changing profile across the column, without pinches (feed stage not optimal) or stages at
constant compositions (excess of stages). For the recovery, the bottoms/distillate rate was varied to
obtain maximum recovery of desired product.
Sieve trays are used for the columns due to their low cost, low maintenance requirements, low
fouling tendency. The design specs were applied to mole recovery and mole purity of 1,3-DCP in the
first column and second column respectively, since that is most desired product. The Table 3.7 and
3.8 give information about the design specs and dimensions of the columns.
Table 3.7 Design spec of the columns
Column Design Spec
DC1 Recovery and purity of 1,3-DCP in the
Bottom: 0,999
DC2 Recovery and purity of 1,3-DCP in
Distillate: 0,99
Table 3.8 Dimensions of distillation columns
Column Parameters DC1 DC2
Reflux ratio 0.5 0.5
Number of stages 10 25
Feed stage 5 18
The energy consumption of the columns were minimized is to be noted since it is an important
factor considering the overall economics of the process. The Table 3.9 shows the condenser and
reboiler duties of the columns.
Table 3.9 Energy Requirements of the columns
Column Qc Qreb Tc Tr
(MW) (MW) (°C) (°C)
C1 -0.80 1.22 98.88 174.52
C2 -2.61 0.60 172.52 215.75
30
3.2. Dehydrochlorination of DCP
Dehydrochlorination of GLY dichlorohydrin is the process in which the DCP’s react with a base to
form EPH, salt and water. In industry this process is carried out with lime milk. It creates many
ecological problems caused by waste water containing calcium chloride. It is advisable to replace the
lime milk by NaOH or catholyte. The waste water after the concentration and purification could be
recycled to electrolysis [26].
DC-2B1
RDISTILL
DICHL
21
DCHLFEED
NAOH
TPROD
BTM
Figure 3.12 Process flow diagram of reactive distillation column
The reactive distillation column is fed with the DCP from column DC-2 (cooled down to the reaction
temperature of 60°C) and NaOH solution (30 mol% concentrated). The column specifications are as
follows:
Table 3.20 Column Parameters
Column Parameters
Pressure 1 bar
Number of stages 10
31
Feed stage 5
Distillate rate 365 kmol/hr
Reflux ratio 0.1
Reboiler duty 6.11 MW
Condenser duty -4.7 MW
Temperature (feed) 63°C
Temperature (top) 88 °C
Temperature (bottom) 148.8 °C
Reaction zone (stage
numbers)
Stages 4-6
Residence Time 10 mins.
In the reactive distillation model, either the residence time or the liquid hold up can be specified. The
reaction stages are from 4 to 6, with 10 minutes of residence time [16]. The thermodynamic property
method used to carry out this reactive distillation is Electro-NRTL. The separation of EPH and water
is an important aspect of this process since EPH forms an azeotrope with water at about 88 °C and
101.3kPa. Aspen database’s does not include the binary interaction for this mixture. In order to
achieve a proper simulation the parameters for the azeotropic distillation have to be introduced in the
properties environment.
Table 3.11 Binary parameters for NRTL method for EPH-water azeotropic distillation [23]
The top of this column i.e. the top product consist mainly of water and EPH. Sodium chloride
solution was obtained at the bottom. Design specifications were employed to achieve maximum
recovery of EPH at the top by varying the distillate rate. The yield of EPH was found to be 99%.
Almost no GLY was formed in the system.
3.2.1. EPH Purification-2nd Separation Train
The last part of GTE process is the separation of water from the final product, EPH. As mentioned
previously these two components form an azeotrope at 88 oC, atmospheric pressure. The traditional
techniques to tackle with azeotrope via using distillation are pressure swing, when the equilibrium is
32
sensitive to pressure changes, entrainers or to resort to modern types of separation such as
membranes [18]. After assigning the binary NRTL parameters to Aspen plus, T-x-y diagram
retrieved as illustrated in Figure 3.13, whilst Figure 3.14 shows the corresponding graph derived
from experimental results. Apparently, the two graphs are almost identical indicating the azeotrope
composition to be at 0.34 mole fraction of water and 0.66 for EPH. This observation leads to the
conclusion that a promising separation can be simulated on Aspen Plus, but besides this fact , it is
evident that the forming azeotrope is heterogeneous with the formation of two liquid phases, one
organic and one aqueous.
Figure 3.13 T-x-y EPH/Water diagram obtained from Aspen Plus simulator after the assignments of
binary parameters.
For the simulation of the 2nd separation train NRTL base method employed since is capable of
predicting vapour-liquid-liquid equilibrium. After the above observation the separation becomes
simpler due to ability to cross distillation boundaries in the case of heterogeneous azeotropic
distillation. The proper piece of equipment in order to achieve this is a simple decanter while phase
splitting is not constrained by distillation boundaries.
33
Figure 3.14 T-x-y EPH/Water diagram from experimental work [23].
Figure 3.16 shows the PFD of the 2nd separation train. The total mole flow rate of stream 28 is 216
kmol/hr with 90 kmol/hr water and 126 kmol/hr EPH and it is fed at the fifth stage of DC-3 column.
At the top of the column the azeotropic composition of the mixture is obtained while the bottom
stream contains pure EPH (ca. 83 kmol/hr).
Figure 3.16 PFD of 2nd separation train.
Pure EPH can be retrieved at the bottom of the column because of the significant difference of its
boiling point (118 oC) and the azetrope temperature (88 oC). From the liquid mole fraction of EPH
throughout the column in Figure 3.17, it is seen that after stage six pure EPH is present in the liquid
phase, whilst at the top of the column (Stage 1) EPH exists in its azeotropic composisiton.
34
Block DC-3: Composition Profiles
Stage Number
Liqu
id M
ole
fra
ctio
n o
f EPH
1 2 3 4 5 6 7 8 9 100,30
0,35
0,40
0,45
0,50
0,55
0,60
0,65
0,70
0,75
0,80
0,85
0,90
0,95
1,00
Liquid mole fraction ALPHA-01
Figure 3.17 EPH liquid mole fraction per stage in unit DC-3.
The distillate of DC-1 is driven to the first decanter where significant amount of water (73.5 kmol/hr)
is removed due to the immiscibility of the two liquid phases. With utilisation of one more column
(DC-2) and a second decanter complete separation of EPH, retrieving 123.5 kmol/hr out of 125
kmol/hr of product with 99.1% purity. In such a way the principle of crossing the distillation
boundaries with decanters in the case of azeotrope is verified and the separation becomes simple
without any need of introduction of new materials (e.g. entrainers) to the process or pressure change.
Finally the relatively high difference in the boiling point of the azeotrope and EPH allows the usage
of small columns and therefore low capital cost.
Table 3.12 Column Input Specifications
Parameter DC-1 DC-2
Number of stages 10 10
Distillate rate(kmol/hr) 133 25
Reflux ratio 0.1 0.5
Feed stage 5 5
Feed Temperature (°C) 65 65
Pressure (bar) 1 1
35
Equipment Sizing and Cost
36
4. Equipment sizing and cost
In order to evaluate the total capital costs, it is first necessary to size the equipment. After
introducing the desired parameters, ASPEN Plus can estimate the sizing of most of the equipment
used in the simulation.
4.1. Reactors and columns
The reaction unit for the chlorination of GLY was simulated by many CSTR’s in series as presented
on Chapter 3; however in reality four PFR’s will be utilised and thus the installed equipment cost
should be estimated accordingly. For that purpose Guthrie method has been employed by using
Marshall and Swift (M&S) indices and costing was carried out by considering every PFR as
horizontal pressure vessel. M&S indices could not be retrieved from the literature for 2015 and a
sufficiently high value (1800) was assumed compared to M&S indices in 2007 (ca. 1363) [19] in
order to avoid underestimation of the cost. Moreover, 30 % of the calculated cost was added to the
final price, taking into account the coating (i.e. glass line coating) as well as additional charges for
piping and construction. The total installed cost of the reactor found to be 1.04 M$ and the installed
cost of each individual unit is shown in Table 4.1, whilst the sizing and the installed cost of the
columns is demonstrated in Table 4.2.
Table 4.1 Dimensions PFR reactors for Chlorination of glycerol.
PFR1A PFR2A PFR1B PFR2B
Volume (m3) 24 44 24 44
Residence Time (hr) 3 5.7 3 5.7
Diameter (m) 2.5 2.5 2.5 2.5
Length (m) 4.8 9.0 4.8 9.0
Installed Equipment
Cost (k$)
15.2 24.8 15.2 24.8
Table 4.2 Costs and sizing of distillation columns and reactive distillation (RDC-1).
DCW-1 DC-1 DC-2 RDC-1 DC-3 DC-4
Diameter (m) 1.22 0.91 1.37 1.83 1.37 0.76
37
Number of trays 33 12 12 12 12 12
Tray spacing (m) 0.61 0.61 0.61 0.61 0.61 0.61
Height (m) 20.13 7.32 7.32 7.32 7.32 7.32
Reboiler duty (MW) -2.86 -0.80 -2.61 -4.70 -1.72 0.55
Condenser duty MW 1.97 1.22 0.60 6.12 2.10 0.55
Equipment cost (k$) 586 520 557 724 557 442
4.2. Pumps and Compressors
It is assumed that the raw materials enter the plant at 30ºC and 1 bar. They need to be compressed to
the working pressure of the reactor (5 bar). The details for the equipment needed is shown in Table
4.3 and 4.4.
Table 4.3 Costs and sizing of pressure changers for raw materials
Isoentropic compressor HCl Centrifugal pump GLY
Net work required 478 kW Electricity 1.5 kW
Efficiency 0.8 Flow 3 l/s
Outlet pressure 5 bar Outlet pressure 5 bar
Outlet temperature 250 C NSPHa 8.5 m
Isentropic outlet
temperature
207 C Head 34 m
Equipment cost 1.1 M$ Equipment cost 80 k$
Installed cost 5.1 M$ Installed cost 140 k$
Table 4.4 Costs and flows of other pumps
Flow rate (m3/s) Installed cost / $ Capital cost / $
SW.DW-reflux pump 2.85 32500 5300
38
SW.B1 pump 4.62 90300 66200
DC-1-reflux pump 0.83 28200 5100
DC-2-reflux pump 13.21 43900 6123
DC-3-reflux pump 3.49 33900 5900
DC-4-reflux pump 0.89 31700 5100
RDC-1-reflux pump 10.00 40100 8100
4.3. Heat exchangers and decanters
The results for required heat exchangers and decanters are shown in the tables below.
Table 4.5 Costs and flows of additional pumps.
HE-1 HE-2 HE-3 HE-4 HE-5 HE-6 HE-7 SW.HE
Heat exchange area / m2 13.9 6.2 3.8 53.2 12.4 36.8 4.7 56.5
Capital cost / $ 10900 10800 8500 8400 10800 15200 9600 24800
Installed cost / $ 61600 63200 61300 61200 60700 74300 58800 103200
Energy / kW -432 504 128 162 658 -1485 213 1925
Table 4.6 Costs and flows of additional pumps
D-1 D-3 D-2
Liquid volume m3 170 170 170
Vessel diameter / m 9.8 9.8 9.8
Design gauge pressure / bar 3 3 3
Heat duty / kW 148 278 1.2
Design temperature / C 122 121 157
Operating temperature / C 88 87 130
Capital cost / $ 15400 15400 15400
Installed cost / $ 119900 116200 117600
39
GTE Aspen Economics
40
5. Economic evaluation
The selling price for conventional EPH ranges from 1700 to 2200 $/ton in the Asian market. In this
section, this prices will be compared to the required selling price and to recommended selling price.
5.1. ASPEN Economics Input
As the required amount of hydrogen chloride is very high (85848 kton/year) for the production of
100kton/year of EPH, ideally a neighbour plant which produces HCl may be required. However, in
order to make an economic evaluation it is necessary make assumptions to establish a price for each
stream. This price was extrapolated from the price of 36% hydrochloric acid (100$/ton), dividing by
0.36 (concentration), the price per ton HCl is extracted (277$/ton). Assuming a factor of 30% for the
separation of hydrogen chloride from water, the value of the HCl stream was obtained (360$/ton).
The price of solid pearls of pure NaOH (300$/ton) was used to extract the price of the NaOH (aq)
30% mol (120$/ton). The refined vegetal glycerol price ranges from 700-800$/ton [24] in the Asian
market. The summary of the prices introduced is shown in the following table:
Table 5.1 Raw materials price
Raw materials price
HCl 360 $/ton
GLY 800 $/ton
NaOH 30% vol 120 $/ton
Another additional parameters where needed to be introduce:
Rate return of the total costs is 20%/year.
The life expectancy of the plant is assumed equal to 30 years.
41
5.2. Results
After introducing the raw materials price, extracting the price of the CSTR in series and adding the
price for the PFR reactors it is possible to use ASPEN economics to obtain all the desired economic
information.The utility costs are found in Table 5.2.
Table 5.2 Raw materials price
Utility Fluid Rate Units Cost per
Hour
Cost
Units
Electricity 690.5 kW 77.1 $/ hr
Cooling Water Water 1065.6 m3/hr 33.7 $/ hr
Steam @690KPA Steam 19.7 ton/hr 353 $/ hr
Steam @1135KPA Steam 5.74 ton/hr 123 $/ hr
Steam @2760KPA Steam 5.20 ton/hr 134 $/ hr
The summary of the economic results is the following:
Table 5.3 Raw materials price
Parameter Price
Total Capital Cost [M$] 30.0
Total Operating Cost [M$/Year] 163.3
Total Raw Materials Cost [M$/Year] 140.8
Total Product Sales [M$/Year] 199.6
Total Utilities Cost [M$/Year] 6.3
Desired Rate of Return [Percent/'Year] 20
Equipment Cost [M$] 4.3
Total Installed Cost [M$] 10.7
Required selling price [$/ton] 1633
Asia market price [$/ton] 1800-2,500
42
The required selling price (1633 $/ton) was calculated by dividing the total operating cost of the
plant (163 M$/year) by the production capacity 100,000 ton/year.
The percentage of investment returned each year is calculated in aspen assuming the total cash flow
for each year. Taking into account the total expenses and the total income, the percentage of
investment returned each year is defined as return over investment. Assuming a final recommended
selling price for the EPH in Asia of 1800 $/ton [25], the return over investment (R.O.I) is
33%/year.
Results of ASPEN economics for cash flows and detailed revenues and costs are found in appendix.
Both EPH and GLY prices vary significantly over the time. In order to study the viability of the
project a sensitivity analysis was performed. This analysis is shown in “Figure 5.1”.
600 650 700 750 800 850 9001000
1200
1400
1600
1800
2000
f(x) = 1.34551428571429 x + 556.918571428572R² = 0.999999999549093
Sensitivity analysis: GLY price
Market price for GLY in ($/ton)Min
imum
req
uire
d se
lling
pri
ce f
or E
PH
($
/ton
)
Figure 5.1 Sensitivity analysis - GLY price with RSP of EPH
Using the relation found on “Figure 5.1”, it is possible to predict the minimum required selling price
for EPH. This process is economically viable when the price of GLY in the market is lower than
900$/ton. The price market trend for glycerol is shown in “Figure 5.2”.
43
Figure 5.1 Sensitivity analysis - GLY price with RSP of EPH
Figure 5.1 shows that glycerol price has decreased significantly over the years, making the
alternative GTE process viable and very profitable. It is worth remarking that the crude glycerine
price is eight times lower than refined glycerine.
A further study of the economics for glycerine refining process is recommended in order to
determine if the GTE process can be even more profitable by refining in-situ the crude glycerine.
Crude glycerine price has sharply decreased over the last years as mass production of biodiesel is
continuously increasing over time.
44
Conclusions
45
6. Conclusions and Recommendations
Market price of GLY has sharply decreased over the years due to increased biodiesel production
making GTE process feasible. In the present report the economic feasibility of a plant with a capacity
100 kton/year for EPH manufacturing via GTE process has been investigated. The payback period
has been estimated 3 years for 1800 $/ton EPH selling price, highlighting GTE process as
economically viable and a promising alternative.
For the first step of the process (i.e. chlorination of GLY) two reactor configurations have been
proposed and intermediate water removal is strongly recommended in order to achieve smaller
reaction volume. Custom PFR model is suggested for further reduction of residence times and
therefore reaction volume. For the second step, a reactive distillation column is used for fast removal
of EPH and improved yields. The purification of EPH has been done with consecutive decanters and
distillation column in order to tackle the heterogeneous azeotrope, giving 99% pure product (EPH).
The overall yield of GLY to EPH found to be 89%.
Pinch point analysis including only the heat exchanger units of the process showed annual savings
ca. 168 k$/year in the utility costs. More thorough heat integration including the column of the
process is recommended for further reduction.
Appendix
The following figures (Figure 1, Figure 2 and Figure 3) represent the 3D design regarding the first
proposal of the reaction system for chlorination of GLY from two different perspectives. The first
reaction block is composed of two CSTR’s in series, focusing on the production of a-MCH. GLY is
fed only to the first reaction unit after Splitter-1, whilst HCl is fed to the first five reactors for the
reasons explained on Chapter 3. In order to reduce the number of units, reaction towers with stages
will be utilised. In each stage a downcomer will be designed for the flow of the reaction mixture
from on stage to the other so as to achieve the required residence time for every reactor. GLY lines
are painted in red colour and HCl lines are in blue. In each reaction column a shaft is employed
having had multi-impellers incorporated.
46
Figure 1 Chlorination of GLY 3D reactor design.
47
Figure 2 Chlorination of GLY 3D reactor design.
Figure 3 Chlorination of GLY 3D reactor design.
PFR cost estimation – Guthrie method
The free on board cost (f.o.b.) for each reactor is estimated by Equation (1):
Where H is the length of the reactor, D the diameter and Cp0 the f.o.b. cost in 1968.
Then the installed cost can be calculated from Equation (2),
Where FBM is a correction factor equal to 4.23, Fm the material correction factor which is equal to 1
for Carbon Steel and FP the pressure correction factor equal to 1.05 for pressure less or equal to 6.7
bar. The calculated cost is for 1968 and by using Equation (3) the corresponding for 2015 can be
found.
48
Heat Integration of GTE Process-Pinch Point Analysis
Pinch point analysis was performed on GTE process targeting to the reduction of hot (QHmin) and cold
(QCmin) utilities as well as for defining the minimum number of the heat exchanger units. The
minimum temperature difference was chosen equal to 20 oC in order to achieve balance between the
capital and utility costs. In the process there are five cold stream and the same number of cold
streams which can be combined for minimising energy losses. Table 1 demonstrates the process
streams and their properties such as heat capacities, flows and heat capacities flowrates (FC p) as
obtained from the Aspen simulation. The number of each stream refers to the number of the stream
of the PFD while the letter indicates whether the stream is hot (i.e. able to transfer heat) or not.
Table 1 Hot and cold process streams properties
Stream Tin (K) Tout (K) Cp (kJ/kmol· K) F (kmol/sec) FCp (kW/K)
H2 523 363 28.8 268 2.1
H21 446 333 167.2 126 5.8
H28 472 338 141 217 8.5
H33 403 338 236.1 58 3.8
H35 361 353 183.9 25 1.2
C4 303 363 217.3 140 8.4
C14 393 403 137.9 198 7.6
C18 448 468 172.4 140 6.7
C25 361 472 54.3 365 5.5
C31 361 403 54.3 133 2
From the inlet and outlet temperatures of hot streams is evident that the requirements of cold utilities
are significantly higher than the requirements for hot utilities. Figure 4 represents the process
streams as vectors and the temperature scale for cold streams is shifted by ΔΤmin as pinch point
analysis dictates. The problem, as it can be observed is divided into fifteen temperature intervals (I1,
I2 etc.) where hot streams and cold streams are able to exchange heat and heat surplus can be
transferred from one interval to the other owing to the driving force or i.e. temperature gradient.
49
523 K 503 K
492 K 472 K
488 K
468 K
472 K 452 K
468 K 448 K
446 K 426 K
433 K 403 K
413 K 393 K
403 K 383 K
383 K 363 K
381 K 361 K
363 K 343 K
361 K 341 K
353 K 333 K
338 K 318 K
333 K 303 K
Figure 4 Stream population of GTE process.
50
I-1
I-3
I-2
I-4
I-7
I-5
I-6
I-8
I-9
I-10
I-11
I-13
I-12
I-15
I-14
H2
H35
C18
H28
H21
H33
C42
C25
C14
C31
The amount of heat of each interval is found by multiplying the total flow heat capacity of the
interval by the corresponding temperature difference as indicated from Equation 4 [18]:
Where FCH,i is the heat capacity of the hot stream i in the specific interval, FCC,i the heat flow
capacity of cold stream j and ΔΤinterval the temperature difference between the limits of the interval.
The heat duty of each interval was calculated and afterwards cascade calculations were performed so
as to define the minimum hot and cold utilities of the process as demonstrated in Table 2.
Table 2 Minimum hot and cold utilities estimation.
Interval FCp,interval ΔΤinterval (K) Qinterval (kW) Cascade
ΣQj (kW)
0 +113.8
1 2.1 31 +66.7 +66.7 180.6
2 -3.3 4 -13.4 +53.3 167.2
3 -10 16 -160.9 -107.6 6.2
4 -1.5 4 -6.2 -113.8 0
5 5.1 22 +113.3 -0.56 113.3
6 11 13 +143.2 +142.6 256.5
7 3.4 20 +67.9 +210.6 324.5
8 9 10 +90 +300.7 414.5
9 12.8 20 +256.5 +557.2 671.0
10 4.3 2 +8.7 +565.9 679.8
11 11.8 18 +214 +779.9 893.8
12 9.7 2 +19.4 +799.4 913.3
13 11 8 +88.1 +887.5 1001.4
14 9.7 15 +146 +1033.5 1147.4
15 -2.5 5 -12.9 +1020.6 +1134.5
As it can be observed the heat duty of each interval is calculated by Equation 4, and fourth column
is derived by cascade calculation of column 3. Negative values on column 4 imply heat transfer from
lower temperatures to higher temperatures, violating in such a way the second law of
51
thermodynamics. The most negative value (-113.8 kW) is observed in the fourth row and thus in
order to obstruct further violation of the second thermodynamic law this amount of heat should be
provided as an absolute value to the first interval (I-1) as being done in the sixth column. This
amount of heat simultaneously is the minimum requirements in hot utilities. The minimum amount
of cold utility is found by proceeding again with cascade calculations and it can be seen at the bottom
cell of the sixth column (+1134.5 kW). Finally by definition the point where the flux of heat equals
zero is the pinch point and it is located at interval 4 or at 472 K for hot streams and 452 K for cold
streams; because of the zero heat flux in the pinch point, the problem now is separated into two
different problems, namely above pinch point and below pinch point.
The minimum hot and cold utilities have been found; however further analysis is needed in order to
define the minimum number of heat-exchange units and also the way at which the different streams
should be combined together for the achievement of minimum utilities. To that end the problem is
separated to two sub-problems, namely above and below the pinch, and both of them are analysed on
the following sections.
GTE Heat Exchanger Network Design above Pinch Point
The minimum number of heat exchange units above pinch is given by Euler’s theorem as following
[19],
Where NHE,AP the number of heat exchange units and NS,AP the number of streams above pinch point.
Taking into account one more unit for the hot utility above pinch, the predicted number of units is
four. Figure 5 represents the problem above pinch. Stream H28 has 8.5 kW/K flow heat capacity, a
higher number than the two cold streams. Therefore, this stream cannot be utilized for heating up the
cold streams C25 and C18 which have lower flow heat capacities [20]. Splitting of stream H28 into
two streams with smaller flow heat capacities (8.5-x and x) is the necessary action to enable heat
transfer.
52
Figure 5 GTE heat integration above pinch point.
Only hot utility should be used above pinch point, thus the main goal is the full energy satisfaction of
the hot streams. HE-1 connects C25 and H2 fulfilling the energy requirements of H2. The necessary
heat duty can be calculated by multiplying the temperature difference of H2 and the flow heat
capacity of the stream (115 kW). Apparently C25 has not reached the target temperature (i.e. 472K),
and therefore the outlet temperature of the stream has to be found by performing an energy balance.
Stream H28 is divided into two streams with flow heat capacities 8.5-x and x. Presuming that we
want to satisfy stream C25 with the stream of x flow heat capacity. The value of x can be found from
the energy balance between the two streams as follows,
53
A heat exchanger with 16.5 kW heat duty is employed for that purpose and the other sub-stream
with flow heat capacity of 8-x (4.375 kW/K) can be combined with C18.
The outlet temperature is calculated in the same manner at 450 K and apparently 116.5 kW of hot
utility (High Pressure Steam) is needed for heating up the stream to the final target (i.e. 468K). This
value is slightly higher than the one calculated in Table 2 most likely due to propagation errors on
excel. Finally the number of heat exchange units verifies Euler’s theorem, since three units are
needed plus one more unit for the utility.
GTE Heat Exchanger Network Design below Pinch Point
Below the pinch point hot streams are more than cold streams (see Figure 4), rendering feasible heat
integration. The same procedure as the previous section was followed with the only difference that
here hot streams are able to exchange heat only with cold streams of lower flow heat capacity and
also the main goal is the full energy satisfaction of cold streams as only cold utilities can be utilised
below pinch [20]. Accordingly heat integration was performed as presented in Figure 6.
The minimum number of heat exchange units is estimated again by Euler’s theorem [19] as follows,
Therefore eight heat exchange units plus one unit for the utility are expected and this result can be
verified by Figure 6 where there are 9 units in total. The minimum cold utility requirements can be
found by summing up all the cold utility duties from Figure 6, and the total duty is found equal to
1134.1 kW, indicating optimum stream combination. Having performed pinch point analysis, the last
step is to provide some rough estimations of annual savings ($/year) achieved by applying the
technique in practice.
54
Figure 6 GTE heat integration below pinch point.
55
Annual Savings Estimation
Initially the total annual utility cost should be estimated for the case where there is no heat
integration and subsequently the corresponding cost with heat integration applied in order to
calculate the annual savings. To that end prices for different hot and cold utilities are provided in
Table 3.
Table 3 Utility properties and prices [20,21].
Utility Price ($/tn) Cp (kJ/kg K)
Cooling water (CW) 0.06 4.2
Cost ($/tn) Δhvap (kJ/kg)
High Pressure steam (HPS,42 bar-254 oC)
3.5 3.8
Medium Pressure steam (MPS,11 bar-
184 oC)
7 2.54
Low Pressure steam (LPS,6 bar-160 oC)
18 2.15
The heat content of each process stream can be estimated by Equation 5, depicting the amount of
heat that should be added or removed from the stream so as the target temperature to be reached. The
annual mass flow rate of water is calculated by Equation 6 and the one for steam from Equation 7
and subsequently the annual cost of utilities.
Where FCp the flow heat capacity of the stream, mcw the mass flow of cooling water, msteam the mass
flow of steam and Δhvap the latent heat of steam as given in Table 3.
Table 4 shows the calculation of the annual utility cost without heat integration of the process and it
is estimated around 287 k$/year. By performing pinch point and combining hot and cold streams this
cost can be reduced by ca. 56 % as demonstrating in Table 5.
56
Table 4 Annual utility cost before heat integration.
Stream Utility Qstream (kW) Utility Mass
Flowrates
(tn/year)
Cost ($/year)
H2 CW 344 258962 15537
H21 CW 662 497763 29865
H28 CW 1139 855827 51349
H33 CW 248 186247 11174
H35 CW 10 7672 460
C4 LPS 507 5898 20644
C14 LPS 76 885 3100
C18 HPS 134 1510 27197
C25 HPS 611 6890 124024
C31 LPS 84 980 3432
Total annual utility cost M$ 0.287
Table 5 Annual utility cost after heat integration.
Utility Qutility Utility Mass Flowrates
(tn/year)
Cost ($/year)
CW 1134.6 1703845 102230
HPS 116.5 1312.6 23626
Total annual utility cost M$ 0.12
57
Control Scheme of GTE Process
Any process flow diagram is incomplete without at least a basic control scheme to explain the
controls so the output of a specific process is maintained within a desired range. The critical factors
which can cause disturbances in the operating conditions of the process are [20]:
Changes in the feed flow rate – for example changes in the temperature or feed composition.
Changes in the conditions of utilities like steam or cooling water temperature fluctuations.
Ambient conditions in the environment like temperature fluctuations or moisture content.
The basic parameters under consideration for designing a control scheme for a process are:
Temperature
Pressure
Level
Flow
The process scheme under consideration consists of various equipment supposed to be working at
specified conditions. This equipment requires a control mechanism so that desired quality of product
is obtained. The main equipment under consideration for this case are the reactors, distillation
columns, the heat exchangers and the decanters.
Control of Reactors
The reactor system consists of the PFRs and the reactive distillation column (which is a hybrid vessel
consisting of a reactor and a distillation column in one equipment). As mentioned previously, the
main parameters considered for the control of the PFRs is the pressure in the vessel, and the level in
the vessel. The temperature of the vessel is controlled by using a jacketed vessel. The flow of the
coolant in the jacket is the manipulated variable used for the control of this parameter. The pressure
of the vessel is controlled by regulating the feed flow of the HCl gas in both the vessel, at the valve
after the splitter. The level of the vessels is controlled by the product outflow from the vessel. The
flow to these vessels is kept in a ratio which is already specified in the splitter equipment.
The reactive distillation column is slightly different equipment since it combines two unit operations
in a single vessel. The temperature of the reactive zone is regulated by the flow of dichlorohydrins to
the column. The composition of the product at the top is regulated by the flow of the NaOH to the
58
column. The control of this equipment is otherwise very similar to a normal distillation column
which is explained in the next section.
Control of Distillation columns
There are in totality six distillation columns in the EPCH production process scheme including the
reactive distillation column. The critical parameters for smooth operation of the columns are
controlled in the following ways:
Pressure:
The pressure of the column can be either controlled by manipulating the coolant flow of the
condenser in case of a total condenser or the vapor outflow of the reflux drum in case of a partial
condenser. In the EPH production process, the pressure in the columns C-2, RDistill, C-4 and C-5 is
controlled by regulating the coolant temperature. The column C-0 and C-1 has a partial condenser
and therefore the flow of vapor of the reflux drum is used to control the pressure in these columns.
Temperature:
The selection of the manipulated variable for the temperature control in a column depends on the
requirement of product quality of the top or bottom product. If the top product quality is required to
be high then the reflux ratio is to be regulated and if the bottoms product quality is the essential, the
temperature is regulated by varying the hot utility flow in the reboiler. The temperature and in turn
the quality of the top product of the columns RDistill and C-4 is controlled by manipulating the
reflux ratio. In the remaining columns the bottom product is important and thus the temperature is
controlled by varying the flow rate of the hot utility in the reboiler.
Level:
The level in all the columns at the top and bottom is controlled by varying the distillate rate and the
bottoms rate respectively. In our case, the level of all the columns at the bottom is controlled by the
bottoms flow rate. The level of the reflux drum is controlled by the distillate flow rate. The flow rate
of the reflux is controlled in the columns where the temperature is controlled at the bottom.
Heat Exchangers and Decanters
The temperature control of the heat exchangers is usually carried out by manipulating the utility flow
i.e the heating or the cooling fluid flow in the exchanger. The same has been done for all the heat
59
exchangers in this scheme. The level in the decanters is controlled by controlling the flow of one of
the liquids flowing out of the decanter, usually the liquid that is sent to the next unit.
60
61
DETAILED COSTS I (ASPEN DATABASE)
ITEM UNITS
TW (Number of Weeks per Period) Weeks/period 52
T (Number of Periods for Analysis) Period 20
DTEPC (Duration of EPC Phase) Period 0.846154
DT (Duration of EPC Phase and Startup) Period 0.929487
WORKP (Working Capital Percentage) Percent/period 5
OPCHG (Operating Charges) Percent/period 25
PLANTOVH (Plant Overhead) Percent/period 50
CAPT (Total Project Cost) Cost 3.06E+07
RAWT (Total Raw Material Cost) Cost/period 1.41E+08
PRODT (Total Product Sales) Cost/period 2.00E+08
OPMT (Total Operating Labor and Maintenance Cost) Cost/period 2.37E+06
UTILT (Total Utilities Cost) Cost/period 6.33E+06
ROR (Desired Rate of Return/Interest Rate) Percent/period 20
AF (ROR Annuity Factor) 5
TAXR (Tax Rate) Percent/period 40
IF (ROR Interest Factor) 1.2
ECONLIFE (Economic Life of Project) Period 30
SALVAL (Salvage Value (Percent of Initial Capital Cost)) Percent 20
DEPMETH (Depreciation Method) Straight Line
DEPMETHN (Depreciation Method Id) 1
ESCAP (Project Capital Escalation) Percent/period 5
ESPROD (Products Escalation) Percent/period 5
ESRAW (Raw Material Escalation) Percent/period 3.5
ESLAB (Operating and Maintenance Labor Escalation) Percent/period 3
ESUT (Utilities Escalation) Percent/period 3
START (Start Period for Plant Startup) Period 1
PODE (Desired Payout Period (excluding EPC and Startup Phases)) Period
POD (Desired Payout Period) Period
DESRET (Desired Return on Project for Sales Forecasting) Percent/Period 10.5
END (End Period for Economic Life of Project) Period 30
GA (G and A Expenses) Percent/Period 8
DTEP (Duration of EP Phase before Start of Construction) Period 0.326923
OP (Total Operating Labor Cost) Cost/period 2.06E+06
MT (Total Maintenance Cost) Cost/period 305714
62
CASH FLOW
Period
1st year 2nd year 3rd year 4th year 5th year 6th year 7th year 8th 10 10th year
R (Revenue) -4.50E+07 4.52E+07 5.02E+07 5.55E+07 6.11E+07 6.71E+07 7.36E+07 8.04E+07 8.77E+07
DEP (Depreciation Expense) 817172 817172 817172 817172 817172 817172 817172 817172 817172
E (Earnings Before Taxes) -4.58E+07 4.44E+07 4.94E+07 5.46E+07 6.03E+07 6.63E+07 7.27E+07 7.96E+07 8.69E+07
TAX (Taxes) 0 1.78E+07 1.97E+07 2.19E+07 2.41E+07 2.65E+07 2.91E+07 3.18E+07 3.48E+07
NE (Net Earnings) -4.58E+07 2.66E+07 2.96E+07 3.28E+07 3.62E+07 3.98E+07 4.36E+07 4.78E+07 5.21E+07
TED (Total Earnings) -4.50E+07 2.75E+07 3.04E+07 3.36E+07 3.70E+07 4.06E+07 4.45E+07 4.86E+07 5.30E+07
TEX (Total Expenses (Excludes
Taxes and Depreciation))
5.98E+07 1.75E+08 1.81E+08 1.87E+08 1.94E+08 2.00E+08 2.07E+08 2.15E+08 2.22E+08
CF (CashFlow for Project) -4.50E+07 2.75E+07 3.04E+07 3.36E+07 3.70E+07 4.06E+07 4.45E+07 4.86E+07 5.30E+07
FVI (Future Value of Cumulative
Cash Inflows)
1.48E+07 2.38E+08 5.16E+08 8.62E+08 1.29E+09 1.82E+09 2.46E+09 3.25E+09 4.20E+09
PVI (Present Value of Cumulative
Cash Inflows)
1.23E+07 1.65E+08 2.99E+08 4.16E+08 5.18E+08 6.08E+08 6.86E+08 7.55E+08 8.15E+08
PVOP (Present Value of
Cumulative Cash Outfows Prod.)
4.98E+07 1.84E+08 3.00E+08 4.01E+08 4.88E+08 5.64E+08 6.30E+08 6.87E+08 7.37E+08
PVO (Present Value of Cumulative
Cash Outfows)
4.98E+07 1.84E+08 3.00E+08 4.01E+08 4.88E+08 5.64E+08 6.30E+08 6.87E+08 7.37E+08
NPV (Net Present Value) -3.75E+07 -1.84E+07 -820491 1.54E+07 3.02E+07 4.38E+07 5.63E+07 6.76E+07 7.78E+07
ROI (Return over investment) 33%/year
63
References
[1] Solvay.http://www.solvaychemicals.com/EN/products/chlorinated/Allylicproducts/
Epichlorohydrin.aspx. http://www.solvaychemicals.com/. [Online] May 2013.
[2] Guan, Eric Linak with Akihiro Kishi and Maoshi. July 2014. CEH Report Epichlorohydrin:
IHS Chemicals, July 2014.
[3]
BruceM. Bell, John R. Briggs,RobertM. Campbell,Susanne M. Chambers,Phil D.
Gaarenstroom,Jeffrey G. Hippler,Bruce D. Hook,Kenneth Kearns,John M. Kenney,William J.
Kruper,D. James Schreck,Curt N. Theriault,Charles P. Wolfe. 2008. Glycerin as a Renewable
Feedstock forEpichlorohydrin Production. The GTE Process. Midland USA : Clean Journal , 2008.
657-661.
[4] R. Tesser, *,† M. Di Serio,† R. Vitiello,† V. Russo,† E. Ranieri,† E. Speranza,† and E.
Santacesaria†. 2012. Naples, Italy : American Chemical Society, 2012.
[5] R. Vitiello, V. Russo, R. Turco, R. Tesser *, M. Di Serio, E. Santacesaria. 2014. Glycerol
chlorination in a gas‐liquid semibatch reactor: New catalysts for chlorohydrin production.
Naples, Italy : Chinese Journal of Catalysis, 2014. 663–669.
[6] R. Tesser, † E. Santacesaria,*,† M. Di Serio,† G. Di Nuzzi,† and V. Fiandra‡. 2007. Kinetics
of Glycerol Chlorination with Hydrochloric Acid:A New Route to a,γ-Dichlorohydrin.
Milano, Italy : American Chemical Society, 2007.
[7] Georgy Dmitriev S.*, Leonid Zanaveskin N. 2011. Synthesis of Epichlorohydrin from
Glycerol.Hydrochlorination of Glycero. Moscow : Karpov Institute of Physical Chemistry,
2011.
[8] R. Tesser, *,† M. Di Serio,† R. Vitiello,† V. Russo,† E. Ranieri,† E. Speranza,† and E.
Santacesaria†. Glycerol Chlorination in Gas-Liquid Semibatch Reactor:An alternative Route
for Chlorination Production Naples, Italy : American Chemical Society, 2012.
64
[9] Sang Hee Lee a, Sun Ho Song a, Dong Ryul Park a, Ji Chul Jung a, Ji Hwan Song b, Sung
Yul Wooc,Won Seob Song c, Myong Suk Kwon c, In Kyu Song a,. 2008. Seoul : Catalysis
Communications, 2008.
[10] XIUQUAN LING1, DINGQIANG LU1,2*, JUN WANG1, MINGXIN LIANG1,SHUMIN
ZHANG1, WEI REN1, JIANHUI CHEN1 and PINGKAI OUYANG1. 2010. Investigation of
the kinetics and mechanism of the glycerol chlorination reaction using gas chromatography–
mass spectrometry. Nanjing : Journal of the Serbian Chemical Society , 2010.
[11] S. Carra, E. Santacesaria and M. Morbidelli. 1979. Synthesis of Epichlorohydrin by
Elimination of Hydrogen Chloride from Chlorohydrins simulation of the reaction unit.
Milano : Ind Eng. Chemical Process Design, 1979.
[12] Anna Krzyżanowska, Eugeniusz Milchert, Marcin Bartkowiak. 2014. Dehydrochlorination of
1,3-dichloropropan-2-ol by calcium and sodium hydroxide solutions. Szczecin : Polish
Journal of Chemical Technology, 2014.
[13] L. Ma, J. W. Zhu, X.Q. Yuan and Q. Yue. SYNTHESIS OF EPICHLOROHYDRIN FROM
DICHLOROPROPANOLS Kinetic Aspects of the Process. Shangai, China : Institution of
Chemical Engineers, 2007.
[14] WO2006/100320 method for converting polyhydroxylated aliphatic hydrocarbons into
chlorohydrins
[15] US20130032755 A1 Continuous process for preparing chlorohydrins
[16] WO2008/152045 Epichlorohydrin manufacturing process and use
[17] Fogler, Scott. Elements of Chemical Reaction Engineering. Michigan : Prentice Hall, 1989.
[18] Smith, Robin. 2005. Chemical Process Design and Integration. Manchester : Wiley , 2005.
[19] Koukos, Ioannis. 2009. Design of Chemical Plants. Athens,2009.
[20] Gavin Towler, Ray Sinnot and Gavin. 2010. Chemical Engineering Design. Oxford : BH
Elsevier, 2010.
[21] J.M. Smith, H.C.Van Ness, M.M. Abbott. 2005. Introduction to Chemical Engineering
Thermodynamics. New York : McGraw Hill, 2005.
[22]
65
Thielemans, Geert L.B. 2014. Lecture Notes Process Design. Eindhoven, 2014.
[23]
Qun Yue, Jia-wen Zhu∗, Yan-yangWu, Xiang-qian Yuan, Liang Ma. Liquid–liquid equilibria and
vapor–liquid equilibria for the binary system of epichlorohydrin and water. Shangai : Fluid Phase
Equilibria, 2009.
[24] ICIS Pricing. Glycerol ASIA Price. 2014
[25] Tecnom OrbiChem. CHEM-NET FACTS. Chemical market insight and foresight.
EPICHLOROHYDRIN. 1 November 2013
[26] Milchert E., Goc W.; Lewandowski G.; Myszkowski J. (1995). Dehydrochlorination of
glycerol dichlorohydrin to epichlorohydrin. Chem. Papers 49(3), 133–136.
66