+ All Categories
Home > Documents > productionplanning-110409060343-phpapp02

productionplanning-110409060343-phpapp02

Date post: 04-Jun-2018
Category:
Upload: sampathgsk
View: 216 times
Download: 0 times
Share this document with a friend
20
8/13/2019 productionplanning-110409060343-phpapp02 http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 1/20 PRODUCTION PLANNING Introduction Activities Process Outcome
Transcript
Page 1: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 1/20

PRODUCTION PLANNINGIntroduction

ActivitiesProcessOutcome

Page 2: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 2/20

Start of Production Planning• Forecasting Decision: Based on Sales Estimates.• Management Decision : Based on Demand

Estimates, product design, etc.•

Engineering Decision : Based on manufacturingdesign, process design, materials required, etc.• Capacity Decision : Based on existing resources of

plant, machinery, tools, Planning the facility, etc.•

Financial Decision : Based on funds, profitability.• Resource availability :Employee workflow,

availability of skilled labour, etc.

Page 3: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 3/20

ACTIVITIES OF PRODUCTION PLANNING

Materials Machines Men

Planning, Routing, Scheduling, Dispatching

Sales Order orStock to order

Page 4: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 4/20

OBJECTIVES

• Maximise utilisation of materials andhuman resources

• Minimise costs• Timely supply of finished goods•

Effective control of productionprocess

Page 5: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 5/20

PROCESS OF PRODUCTION PLANNING

• Materials Planning

• Operations Planning

• Cost Planning

Page 6: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 6/20

MATERIALS PLANNINGMaster

Production Schedule Bill of

Materials Material

Requirements Planning System

Inventory Status

Planned Order & Other Reports

Item Master Purchasing

Data

Page 7: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 7/20

Bill of Materials

• Bill of Materials – Parent-child diagram thatshows what goes into what.

Frame Assy

Wheel Assy

Wheel Tires

Hubs &Rims

Spokes

Frame

Bike

Components

Page 8: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 8/20

BOM (contd.)

Used to make sure enough parts are availablethroughout production plan.Each part has Lead Time and ordering process.One BOM for every end product to arrive atcost per product.

Types of BOMSingle Level BOM – One level downIndented BOM – More than one level

Page 9: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 9/20

Inventory Classifications

Inventory

Processstage

DemandType

Number& Value Other

Raw MaterialWIP Finished

Goods

IndependentDependent

A ItemsB ItemsC Items

MaintenanceDependentOperating

Page 10: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 10/20

Output of Materials Planning

• Planned Production report• Planned Purchases report•

Master Schedule report• Sales Forecasts Listing• Materials Handling report

Page 11: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 11/20

OPERATIONS PLANNING

MasterProductionSchedule

ForecastMedium term

Long termShort term

Sales OrderCapacity

Constraints

Production Plan

Lead TimeProduct :

What

Time:When

Quantity:

HowMuch

Page 12: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 12/20

How it is done

EngineeringDiagram

StandardProcessSheet

Route Sheet

CostTime

Labour

PERTCPM

OperationsPlanning

Page 13: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 13/20

Page 14: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 14/20

COST PLANNINGCost

MATERIALS LABOUROTHER EXPENSES

DIRECTDIRECTINDIRECT INDIRECTDIRECT INDIRECT

OVERHEADS

FOH AOH SOH DOH

DirectDi

Page 15: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 15/20

Examples of Indirect material

• At factory level – lubricants, oil, consumables,etc.

• At office level – Printing & stationery, Brooms,Dusters, etc.

• At selling & distribution level – Packingmaterials, printing & stationery, etc.

Page 16: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 16/20

Examples of Indirect labour

• At factory level – foremen’s salary, worksmanager’s salary, gate keeper’s salary,etc.

• At office level – Accountant’s salary, GM’s

salary, Manager’s salary, etc. • At selling and distribution level – salesmen

salaries, Logistics manager salary, etc.

Page 17: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 17/20

Examples of other expenses

• At factory level – factory rent, factoryinsurance, lighting, etc.

• At office level – office rent, office insurance,office lighting, etc.

• At sales & distribution level – advertising,show room expenses like rent, insurance, etc.

Page 18: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 18/20

Output of Cost Planning

• Know the value addition at each stage ofproduction.

• Break up of material, production andoverhead costs. Know the direct / indirectcosts.

• Know the cheapest production line.•

Analyse the profitability of make / buydecision.• Know the reason for rise in costs.

OUTCOME OF PRODUCTION

Page 19: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 19/20

OUTCOME OF PRODUCTIONPLANNING

• Production Data• Inspection Data• Pay roll Data• Cost Data

Page 20: productionplanning-110409060343-phpapp02

8/13/2019 productionplanning-110409060343-phpapp02

http://slidepdf.com/reader/full/productionplanning-110409060343-phpapp02 20/20

ERP inProduction Planning

MRP by period report

MRP by date report

Planned orders report

Purchase requirements

Cost reports

MRPPrograms

Master ProductionScheduleBOM

Lead Times

(Item Master File )

(Bill-of-Material )

Inventory Data

Purchasing data CostData


Recommended