MS PROJECT HW
Prof Ralph V. Locurcio, PECON 2001CVE 4070
WBS Instructions
Project TaskSequence
SequenceSingle Family House - 3,000 square feet
Duration
1 General Conditions 21
2 Apply for Permits 1
3 Site Work 3
4 Pour Foundation 19
5 Pour floor slab 8
6 Framing or masonry for walls 22
7 Construct roof & dry in 16
8 Complete exterior finishes 15
9 Rough-in plumbing & electrical& tel 14
10 Rough-in HVAC 4
11 Install insulation 4
12 Install drywall 5
13 Paint and wallpaper interior 10
14 Install kitchen & cabinets & trim 5
15 Install plumbing fixtures 4
16 Install electrical fixtures 4
17 Install HVAC equipment 3
18 Install carpet, tile and appliances 6
19 Install landscaping 3
20 Install driveway 2
21 Final inspection for CO 1
22 Make final repairs 2
23 Cleanup for occupancy 1
Total 173
Actual 140
House WBSWBS for Senior Design
Activity or Task Assigned Planned Actual Planned Actual Float % Done
person) Start Start Finish Finish Lag Comp
Phase-1 (5%)
General Conditions Engineer-1 21 23-Aug 3-Sep 0
Apply for Permits Engineer-2 1 23-Aug 29-Aug -5
Phase-2 (15%)
Site Work 3
Pour Foundation 19
Pour floor slab 8
Framing or masonry for walls 22
Construct roof & dry in 16
Phase-3 (50%)
Complete exterior finishes
15
Rough-in plumbing & electrical& tel 14
Rough-in HVAC 4
Install insulation 4
Install drywall 5
Phase-4 (95%)
Paint and wallpaper interior 10
Install kitchen & cabinets & trim 5
Install plumbing fixtures 4
Install electrical fixtures 4
Install HVAC equipment 3
Install carpet, tile and appliances 6
Phase-5 (100%)
Install landscaping 3
Install driveway 2
Final inspection for CO 1
Make final repairs 2
Cleanup for occupancy 1
Flow Chart
Schedule Instructions
Note: The following items are required for full credit:1. Schedule must use MS Project
2. Use Septemnber 1 as your starting date for the construction3. Calculate start & finish dates based on your flow chart & Sept 1 start4. Schedule must be on one page; landscape format5. Be sure to arrange the tasks in "logical" construction order6. Must use task sequencing & overlap per your Flow Diagram7. Add lead or lag to separate or overlap a task or sequence of tasks8. All activities must be labeled with activity names to the right of the bar9. All activities must show % complete to left of bar
10. Show % complete in the activity bar for all tasks11. All activities must be completed in less than 173 days12. All activity bars must be colored blue & use cross hatch pattern 13. Include the 3 "phase" activities with black bars as: (1) Planning (2) Foundation & Site (3) Vertical (4) Exterior & Finish14. Include a title & your name in the heading
MS Project Schedule