Flood-CBA#2 Training Seminars Proforma B Évros River Case Study
Transcript
Page 1: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Flood-CBA#2 Training Seminars

Proforma B

Évros River Case Study

Page 2: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

A B C D E F

Collecting information regarding

the site that is to be assessed.

Collecting details about

(a) the current flood risk situation and (b) the key features at risk today and in the future from flooding at

the site.

Overview of the impacts

that are expected under the do-nothing

or the baseline scenario.

An assessment

of the possible future

changes and/or

interventions that may affect the

site

the potential of a range of

flood risk prevention measures and assess

their efficacy based on

CBA and/or MCA

methods

To be determined

1-4 5-11 12-15 16-18 19-23 24-27

5% 20% 25% 25% 10% 20%

Proforma

The rationale

Approx. % of the total

effort

Number of steps/tasks

Page 3: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

B

Collecting details about

(a) the current flood risk situation and (b) the key features at risk today and in the future from flooding at

the site.

5-11

20%

Proforma

The rationale

Approx. % of the total

effort

Number of steps/tasks

Task 5: For the site (in the past): Collect information on flood extent/history in the past (maps of flooding; numbers of properties

affected, and their types [e.g. residential; non-residential etc]; photos; etc)

Task 6: For the site (in the past): Collect information on any flood

damages and/or disruption to economic activities (i.e. traffic; railways; agriculture) in the past

Task 7: For the site (in the past): Collect details any injuries and loss

of life in floods in the past here.

Task 8: For the site (now and in the future): Collect data on Flood hydrology (flows; flood return periods; flood extents, etc) for the site.

Task 9: For the site (now and in the future): Collect data on modelled

or estimated future flood extents (geographical areas) by return period (e.g. for the 2; 5; 20; 50; 100 year floods).

Task 10: For the site (now and in the future): Collect data on property

numbers and types [e.g. residential; non-residential etc] in each of those areas identified above.

Task 11: For the site (now and in the future): Collect data on population numbers (estimated) in each of those areas.

Page 4: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and (b) the key features at risk today and in the future from flooding at the site.

Task 5 For the site (in the past): Collect information on flood extent/history in the past (maps of flooding; numbers of properties affected, and their types [e.g. residential; non-residential etc]; photos; etc)

It will be useful to know the extent to which the study location has a history of flooding, to inform both our assessment of damages and our elaboration of potential risk reducing measures. For example, it will be useful to know whether the area is affected very rarely by major events or

regularly by minor floods.

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 5: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 5 For the site (in the past): Collect information on flood extent/history in the past (maps of flooding; numbers of properties affected, and their types [e.g. residential; non-residential etc]; photos; etc)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 6: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 5 For the site (in the past): Collect information on flood extent/history in the past (maps of flooding; numbers of properties affected, and their types [e.g. residential; non-residential etc]; photos; etc)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

km2

Page 7: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 5 For the site (in the past): Collect information on flood extent/history in the past (maps of flooding; numbers of properties affected, and their types [e.g. residential; non-residential etc]; photos; etc)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 8: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and (b) the key features at risk today and in the future from flooding at the site.

Task 6 For the site (in the past): Collect information on any flood damages and/or disruption to economic activities (i.e. traffic; railways; agriculture) in the past

It will be useful to have an idea of the kind of damages that are caused in this location, not least so we can concentrate on those areas where damage is greatest.

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 9: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 6 For the site (in the past): Collect information on any flood damages and/or disruption to economic activities (i.e. traffic; railways; agriculture) in the past

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Primary sectors affected by flood events: • Agriculture. • Livestock. • Trade and Business. • Transport Infrastructure. • Properties (Public and Private). • Damaged pump station Flooded area

No archeological sites & monuments in Case Study Area.

Damaged pump station Flooded area

Page 10: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future from flooding at the site.

Task 7 For the site (in the past): Collect details any injuries and loss of life in floods in the past here.

It is important to stress within the case studies that economics using money values is not the whole story. Many intangible impacts from floods, and injury and loss of life are two of these.

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 11: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 7 For the site (in the past): Collect details any injuries and loss of life in floods in the past here.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 12: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future from flooding at the site.

Task 8 For the site (now and in the future): Collect data on Flood hydrology (flows; flood return periods; flood extents, etc) for the site

Any assessment of the benefits of flood risk reduction requires the assessment of the impact in the future of a range of events of different return periods. Taking a single event is likely to lead to

gross errors. See Annex B4

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 13: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future from flooding at the site.

Task 8 For the site (now and in the future): Collect data on Flood hydrology (flows; flood return periods; flood extents, etc) for the site

Any assessment of the benefits of flood risk reduction requires the assessment of the impact in the future of a range of events of different return periods. Taking a single event is likely to lead to

gross errors. See Annex B4

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 14: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 8 For the site (now and in the future): Collect data on Flood hydrology (flows; flood return periods; flood extents, etc) for the site

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Basin Area: 53,000 km2 • 66.2% in Bulgaria • 27.5% in Turkey • 6.3% in Greece

River Length: 528 km Estimated flow (annual average): 103 m3/s

EVROS RIVER

Page 15: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 8 For the site (now and in the future): Collect data on Flood hydrology (flows; flood return periods; flood extents, etc) for the site

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 16: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 8 For the site (now and in the future): Collect data on Flood hydrology (flows; flood return periods; flood extents, etc) for the site

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Main causes of flooding in Case Study Area: • Evros River

flooding.

• Stormwater flooding from streams vertical to Evros River.

Page 17: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 8 For the site (now and in the future): Collect data on Flood hydrology (flows; flood return periods; flood extents, etc) for the site

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 18: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future from flooding at the site.

Task 9 For the site (now and in the future): Collect data on modelled or estimated future flood extents (geographical areas) by return period (e.g. for the 2; 5; 20; 50; 100 year floods)

Each of the floods of different severities in the future, the return periods of which are estimated, needs to have a map showing the properties affected. The rare floods (e.g. 1:100 years) will affect more properties than the more common floods (e.g. 1:10 years). If this is not the case, the data is

likely to be flawed.

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 19: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 9 For the site (now and in the future): Collect data on modelled or estimated future flood extents (geographical areas) by return period (e.g. for the 2; 5; 20; 50; 100 year floods)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 20: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 9 For the site (now and in the future): Collect data on modelled or estimated future flood extents (geographical areas) by return period (e.g. for the 2; 5; 20; 50; 100 year floods)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 21: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 9 For the site (now and in the future): Collect data on modelled or estimated future flood extents (geographical areas) by return period (e.g. for the 2; 5; 20; 50; 100 year floods)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 22: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 9 For the site (now and in the future): Collect data on modelled or estimated future flood extents (geographical areas) by return period (e.g. for the 2; 5; 20; 50; 100 year floods)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 23: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 9 For the site (now and in the future): Collect data on modelled or estimated future flood extents (geographical areas) by return period (e.g. for the 2; 5; 20; 50; 100 year floods)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 24: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future from flooding at the site.

Task 10 For the site (now and in the future): Collect data on property numbers and types [e.g. residential; non-residential etc] in each of those areas identified above

This is a crucial ingredient, identifying properties and potential damage from events of different return periods. This is what will be used to calibrate the loss-probability curve (see Annex B4).

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 25: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 10 For the site (now and in the future): Collect data on property numbers and types [e.g. residential; non-residential etc] in each of those areas identified above

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Damage in buildings

Damage in cultivated areas

Page 26: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future from flooding at the site.

Task 11 For the site (now and in the future): Collect data on population numbers (estimated) in each of those areas.

It may be possible to assess the number of properties in the area from the population that lives there, in the absence of better information (i.e. divide population by c. 2.3 to identify the number of households/houses). In any case this information may be useful for assessing the potential loss

of life or injury during floods, related to the population living there.

Tasks 5-11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Page 27: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Évros River Case Study

Task 11 For the site (now and in the future): Collect data on population numbers (estimated) in each of those areas.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Population affected by the flood incidents

Population of Lavara: 1093 residents

Page 28: Proforma B - FLOOD-CBA 2 · Évros River Case Study Proforma B Collecting details about (a) the current flood risk situation and(b) the key features at risk today and in the future

Flood-CBA#2 Training Seminars

End of Proforma B