+ All Categories
Home > Documents > PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

Date post: 02-Jun-2018
Category:
Upload: halimka
View: 217 times
Download: 0 times
Share this document with a friend

of 59

Transcript
  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    1/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 1 di 59

    GENERAL SPECIFICATIONS

    PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL

    INSTALLATIONS

    05221.VAR.ELE.SPC

    Rev. 4 December 2004

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    2/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 2 di 59

    FORWARD

    Rev. 1 Sheet 28June 1988

    Rev. 2 Sheet 20August 1997Computerized issue

    Rev. 3 Total number of pages 21July 2003Issue for normative references revision and contents conformity

    Rev. 4 Total number of pages 59December 2004General revision

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    3/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 3 di 59

    1. SCOPE OF PROGRAM............................................................................................................................................4

    2. DEFINITION OF TERMS........................................................................................................................................4

    3. PROGRAM DEFINITION CRITERIA...................................................................................................................4

    4. DUTIES AND RESPONSIBILITIES.......................................................................................................................7

    5. CHECK AND TEST RESULTS ......................................................... ............................................................. .........8

    6. MECHANICAL COMPLETION REQUIREMENTS ................................................................ ...........................8

    7. PRE-COMMISSIONING REQUIREMENTS ................................................................ ......................................41

    8. REFERENCE DOCUMENTS ................................................................ ........................................................ ........58

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    4/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 4 di 59

    1. SCOPE OF PROGRAM

    The program defines checks and tests to be carried out on individual materials and

    electrical system during installation or on completion.

    Checks and tests aim at determining any abnormalities that may have occurred during

    transport, installation and assembly and at establishing the efficiency of systems and

    circuits and feasibility of components.

    These checks and tests do not aim at repeating inspections carried out at the supplier's

    premises and, therefore, at verifying the performance and correct construction of

    materials.

    2. DEFINITION OF TERMS

    The following words and expressions shall have the meanings hereby assigned to

    them:

    - "COMPANY" (or Employer) shall mean the name of Company who has

    called for Tenders to provide and execute the works and who will employ the

    CONTRACTOR and the legal successors in title to the Employer but not (except

    with the consent of the CONTRACTOR) any assignee of the Employer;

    - CONTRACTOR" means the person or persons, firm or company whose tender

    has been accepted by the Employer and includes the CONTRACTOR's personnel

    representatives, successor and permitted assignees subject to Employer consent;

    - INSPECTION AUTHORITY, i.e. the organization nominated by COMPANY

    to supervise checks and tests.

    3. PROGRAM DEFINITION CRITERIA

    The program described on the following pages takes into account the Client's

    requirements and has been defined considering that every check and test has a specific

    intrinsic value with regard to data or characteristics to be established. However, this value

    varies depending on the role played by the system, circuit or component to which it

    applies and this role is linked to implications concerning malfunction and safety of

    personnel and equipment.

    Therefore, depending on the importance of the circuit, checks and tests may be carried

    out only on a sample of identical or similar circuit components (e.g. motor starters).

    The program has been prepared by subdividing checks and tests as follows:

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    5/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 5 di 59

    3.1 Checking of materials before installation

    Before being installed, materials must undergo a "visual examination" to determine any

    damage or breakage to prevent the installation of materials that will require replacement

    at a later stage.

    This check will, generally, be carried out at the warehouse.

    However, for some materials which must be transported to the place of installation in

    their packing (e.g. panels) it can be carried out on site.

    Note: In doubtful cases instrument checks and/or tests can be carried out.

    3.2 Mechanical Completion

    Mechanical Completion is defined as that point in the project when work to install, erect

    and fit out the facilities has been completed, and that fitting out work has been tested.

    Eg. Electric cables will have been installed, terminated, continuity and insulation

    resistance tested but not energised. Motors will similarly have been checked out but not

    run.

    Checks and tests must be carried out during construction or when systems or a constituent

    part of them are mechanically completed to ensure that the equipment and individual

    components are installed in accordance with design requirements, suppliers' instructions,

    technical codes and accident prevention codes and that there is no obvious damage orbreakage.

    Mechanical equipment will be installed, aligned and fitted with any temporary devices

    (strainers, etc.) required for commissioning. Initial fill of lubricants, etc., will be made.

    Mechanical completion will be done on a methodical system by system basis, and checks

    will be documented and compiled in a similar manner.

    In the case of areas with potentially explosive atmospheres, checks must be carried out to

    ensure that the whole system and individual components are installed in compliance with

    appropriate codes.

    More particularly, checks and tests listed below must be carried out.In the case of parts of systems or materials which are not indicated below, checks and

    tests must be carried out by analogy with those of materials indicated and in accordance

    with the supplier's instructions.

    3.3 Pre-commissioning

    Pre-commissioning is defined as the activities following Mechanical Completion carried

    out to facilitate safe and efficient commissioning of a system.

    Eg. Electrical switchgear relays will be tested and settings verified. Motors will be run for

    30 minutes without load (uncoupled). Cables will be energised as required.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    6/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 6 di 59

    Mechanical equipment will be prepared for operation by testing and running auxiliaries,

    by checking trips and other functions. Seal oil and lube oil systems will be flushed.

    These checks and tests must be carried out during construction or on completion and, in

    any case, before commissioning in order to:

    a) determine any abnormalities that may have arisen during installation;

    b) ensure the efficiency of systems and circuits;

    c) ensure that components operate under safe conditions.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    7/59

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    8/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 8 di 59

    5. CHECK AND TEST RESULTS

    5.1 Documentation

    Results of tests mentioned in paragraph 3.1 need not be recorded.

    Results of checks and tests mentioned in paragraphs 3.2 and 3.3 must be recorded on

    appropriate documents which must be attached to this PROGRAM so as to have complete

    and exhaustive file on the subject.

    For further information see the following chapter 8.

    6. MECHANICAL COMPLETION REQUIREMENTS

    6.1 General

    The main scope of Mechanical Completion inspections and tests is to ensure conformity

    with the project specifications and drawings and to prove that all equipment and materials

    are suited to the duties they are intended to perform.

    This procedure covers the general responsibilities of the electrical contractor during

    checkout of electrical equipment. Specific requirements are given for the following types

    of testing:

    - General checks

    - Grounding system tests

    - Insulation resistance tests

    - Protective relay system tests

    - Load tests

    - Noise tests

    - Temperature tests

    - Vibration tests (where appropriate)

    - Illumination level tests

    - DC system tests

    - Navigation Aids Tests

    All work shall be executed in strict accordance with project specifications and the

    approved drawings. The written approval of the COMPANY is required for any

    deviations.

    6.2 Conduct of Tests

    a) The Mechanical Completion program shall demonstrate the proper installation of the

    complete electrical system.

    b) Checkout tests shall be witnessed by the COMPANY as required.

    c) Checkout tests may be conducted concurrently with Pre-commissioning tests.

    d) Complete dossier shall be submitted to the COMPANY at completion of Mechanical

    Completion.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    9/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 9 di 59

    e) After the Mechanical Completion program has been completed and accepted by the

    Company, the Contractor shall be responsible for maintaining the equipment in a safeand protected conditions. All covers, doors and access plates shall be properly

    fastened. All wiring shall be completed..

    f) It should be noted that Mechanical Completion work may be carried out on adjacent

    equipment to live installations. The safety precautions listed must be observed.

    6.3 Safety

    a) General Safety Precautions

    The consequences of shock or burn from electrical systems are serious. Work onelectrical equipment shall, therefore, be carried out only when the equipment is de-

    energised, and by qualified personnel, and who fully understand the electrical system

    of the project.

    One-line diagrams shall be available at all times. All feeding equipment and circuits

    shall be tagged-out and locked-out. The test/check operatives own key or lock shall

    form part of the lock-out procedure.

    All equipment such as bus bars, circuit breakers, and motor shall be properly grounded

    as appropriate before any testing or other work is initiated.

    b) Equipment Isolation

    All equipment shall be physically disconnected from its power source to prevent

    accidental injury to personnel resulting from inadvertent re-energisation. Equipment

    isolation is necessary to ensure that voltages applied to the equipment under test are

    not allowed to feed-back into power transformers, generators and associated upstream

    synchronising and control circuits. The consequences of back-feeding voltages include

    danger to personnel and damage to equipment.

    c) Medium-Voltage Testing

    While any medium-voltage testing is being conducted shall be ensured that the test

    area is properly guarded to prevent unauthorised entry and that DANGER notices are

    posted adjacent to, and at all access ways to the test area during the period of the test.

    All cables must be discharged both before and after applying any test voltage. Any

    associated cables not being tested shall be grounded during the test, e.g., other phase

    conductors of a three-phase circuit.

    Temporary conductors used for test purposes shall not be sized less than the rating of

    the circuit under test.

    Caution notices shall be posted adjacent to, and at all access ways to the test area.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    10/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 10 di 59

    d) Portable Electrical Equipment

    Unless portable electrical equipment is double insulated or connected to ground fault

    interrupters, the equipment shall be grounded using flexible supply cable that

    incorporates a ground continuity conductor.

    6.4 Generators

    6.4.1 Installation and Mechanical Completion

    a) Ensure that the equipment meets the area classification and specification requirements.

    b) Note the nameplate ratings of the generators and compare with those given on the

    approved drawings.

    c) Ensure that the enclosure IP rating meets specification requirements.

    d) Ensure the mechanical integrity of all components.

    e) Ensure that any shaft blocking or transit packing has been removed.

    f) With the coupling removed ensure that the generator rotates freely and that the end

    play of the rotor is within tolerances.

    g) Without dismantling, inspect as far as possible oil rings, oil levels, grease packing and

    bearings. Inspect for leakage.

    h) Inspect the paint finish for damage. Any damaged areas shall be repainted.

    i) Inspect the earthing stud and the connection to the general earthing system, including

    those in the terminal box.

    j) Ensure that all terminal boxes are clean, dry and in good condition. Check that all

    spare entries are plugged.

    k) Check that cables are properly terminated, connected and supported, that the

    terminated box layout is satisfactory and that any current transformers are securely

    installed.

    l) Check that terminal boxes are properly phase segregated, where applicable.

    m) Ensure that anti-condensation heaters are correctly installed and terminated.

    n) Ensure that all vibration and temperature monitoring equipment is properly installed

    (if fitted).

    o) Ensure that internal are free from dust, debris, etc.

    p) Ensure that the installation and fixing of equipment is correct (level, alignment, etc).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    11/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 11 di 59

    q) Ensure that gaskets and seals are correctly installed and are in good condition.

    r) Ensure that the conductors are correctly connected to terminals (also in order to the

    direction of rotation) and that the insulation distance to earth is appropriate.

    s) Ensure that drains are correctly installed and effective;

    t) Ensure that there are not obvious damages to mounted instruments.

    u) Ensure that the air filters are correctly installed and clean.

    v) Ensure that the brushes, when existing, are transversally staggered on the surface of therings without, however, being in contact with ring corners so that they do not splinter.

    The distance between brushes and ring surface is that anticipated by the manufacturer

    and the inclination, if any, is correct, i.e. opposite to the direction of rotation.

    Brushes move freely, there is even contact with rings and the brush spring pressure is

    that specified by the manufacturer. Braided brush leads do not touch the brush gear

    w) Check that all mounting and holding down bolts are secure.

    6.4.2 Test Certificates

    a) Installation and Mechanical Completion shall be recorded on Check List CL-E001

    (MOD.ELE.FTC.002).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    12/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 12 di 59

    6.5 Power Transformers

    6.5.1 Installation and Mechanical Completion Checks

    a) Ensure that the equipment meets the area classification and specification requirements.

    b) Note the nameplate ratings of the generators and compare with those given on the

    approved drawings.

    c) Ensure that the enclosure IP rating meets specification requirements.

    d) Ensure the mechanical integrity of all components.

    e) Inspect the paint finish for damage. Any damaged areas shall be repainted.

    f) Ensure that the transformer is complete with all accessories and instruments.

    g) Ensure that there are not obvious damages to transformers, accessories and

    instruments.

    h) Ensure that the oil level (or other dielectric liquid) in the conservator corresponds to

    the level prescribed with regard to the oil temperature read on the dial thermometer. If

    the level is too low add new oil; if the conservator is fitted with a water collecting trap,

    drain it using the drain valve Only for oil transformer.

    i) Ensure that air bubbles have been evacuated by opening and closing appropriate

    breather plugs in the tank, radiators and insulators Only for oil transformer.

    j) Ensure that the thermometer bulb tube is full of oil Only for oil transformer.

    k) Ensure that the oil level in the air dryer sump corresponds to that marked Only for

    oil transformer.

    l) Ensure that silica gel (silicon oxide) of the air dryer is dry (if blue: dry; if purple:

    20-30% humidity; if pink: damp-saturated). It can be regenerated by removing the dryerwith the air intake pipe blocked: the silica gel must then be spread on to a metal sheet

    and heated to 180-200C until it turns blue. Before turning down the dryer to remove

    the silica gel, the oil sump at the bottom of the container must be unscrewed Only for

    oil transformer.

    m) Inspect tap change mechanism.

    n) Ensure that the pressure valve or bursting disk are not blocked in the "closed" position

    and can operate freely Only for oil transformer.

    o) Ensure that the level of the compound or oil in the cable terminal box corresponds to

    that prescribed Only for oil transformer.

    p) Ensure that insulators are clean.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    13/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 13 di 59

    q) Inspect the earthing stud and the connection to the general earthing system, includingthose in the terminal box.

    r) Check that cables or bus-bars are properly terminated, connected and supported;

    s) Ensure that all terminal boxes are clean, dry and in good condition. Check that all

    spare entries are plugged.

    t) Ensure that internal are free from dust, debris, etc.

    u) Ensure that bus-bar or cable terminal protection boxes are well closed.

    v) Ensure that there are not loose or missing screws or nuts. Accessories are well fixed.

    w) Ensure that rollers on rails are chocked.

    y) Ensure that gaskets and seals are correctly installed and are in good condition.

    x) Ensure that neutral connections are secure.

    z) Ensure that the padlocking facilities are satisfactory.

    a1) Ensure that enclosures suitable for protection against adverse weather conditions and

    sun are securely installed.

    a2) Ensure that warning labels (high voltage, high temperature, etc) are properly installed.

    a3) Inspect the transformer and auxiliary equipment for alignment and tightness of

    foundation bolts and fixings in general.

    6.5.2 Test Certificates

    a) Installation and Mechanical Completion shall be recorded on Check List CL-E002

    (MOD.ELE.FTC.003).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    14/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 14 di 59

    6.6 NEUTRAL EARTHING RESISTORS

    6.6.1 Installation and Mechanical Completion

    a) Ensure that the equipment meets the area classification and specification

    requirements.

    b) Note the nameplate ratings of the neutral earth resistors (NER's) and compare with

    the approved drawings.

    c) Ensure removal of any temporary weatherproofing and any drying agents

    (e.g. silica-gel).

    d) Inspect the neutral earthing resistors for alignment, tightness of foundation,

    bolts and fixings.

    e) Inspect the connections to the neutral earthing resistor.

    f) Inspect the frame earthing arrangement.

    g) Ensure all cable supports and glanding are satisfactory.

    h) Ensure all terminations are satisfactory.

    i) Ensure that all gaskets are installed correctly.

    j) Ensure that the internals of the NER are free from dust and debris.

    k) Ensure warning labels for sudden high temperature in the event of operation

    are in place.

    6.6.2 Test Certificates

    a) Installation and Mechanical Completion shall be recorded on Check List

    CL-E017 (MOD.ELE.FTC.030).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    15/59

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    16/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 16 di 59

    6.7.2 Test Certificates

    a) Installation and Mechanical Completion shall be recorded on Check List CL-E003

    (MOD.ELE.FTC.004).

    6.8 MV & LV Switchgear and Bus-bar

    6.8.1 Installation Completion

    a) Ensure that the equipment meets the area classification and specification requirements.

    b) Note the nameplate ratings of the equipment and compare with those given on the

    approved drawings.

    c) Ensure that the enclosure IP rating meets specification requirements.

    d) Inspect the switchboard assembly for alignment, level, tightness of foundation bolts

    and fixing in general. Ensure that circuit breaker trucks can be easily manoeuvred in

    and out of their cubicles - applicable to all withdrawable equipment.

    e) Compare the switchgear equipment with the Equipment Schedule, paying particular

    attention to the rating and any circuit changes.

    f) Inspect the switchboard earth bar and earth cable for electrical and mechanical

    continuity.

    g) Ensure that all panel doors and gland plates are bonded to the switchboard structure

    and that non-magnetic gland plates are fitted to single core cables.

    h) Ensure that all equipment installed in the switchboard is in good condition,

    particularly bus-bar insulation and bracing and joint insulation.

    i) Inspect bus duct connections.

    j) Inspect the inside of the switchgear for cleanliness, paying particular attention to the

    insulators.

    k) Ensure that all equipment (i.e. circuit breakers, contactors, fuse, switches, voltmeter,

    ammeter, protection relay, overload relay, current transformer, etc.) are in good

    condition and in particularly meet the drawings, data sheet and specification

    requirements.

    l) Ensure that there are not obvious damages to equipment and instruments.

    m) Ensure that the mechanical operation of equipment, in particular circuit-breakers and

    operating devices, is correct. In order to verify this, the circuit-breaker mechanismsand springs, if any, must be operated, mechanical locks must be checked and, if the

    breaker is withdrawable, this operation should also be checked.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    17/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 17 di 59

    n) Ensure that switchboards and equipment are securely fixed to supports.

    o) Ensure that doors and panels close properly and there are keys for all locks.

    p) Ensure that holes that are not used but are planned for future equipment or instruments

    are correctly plugged.

    q) Ensure that switchboards installed outdoors are protected against adverse weather

    conditions and sun with suitable canopy.

    r) Ensure that warning labels, fitted by the manufacturer for special indications, are

    intact.

    6.8.2 Mechanical Completion Certification Testing

    a) Prior to securely fitting the bus-bar covers, check the tightness of bus-bar joint bolts,

    measure the insulation resistance of the bus-bar. Ensure that cable and/or bus ducts are

    certified.

    b) Test the switchboard earth system for electrical and mechanical continuity. Measure

    the earth path resistance at the earth bar to the general earth system.

    c) Measure the insulation resistance of the bus-bar and control wiring after ensuring any

    sensitive equipment has been disconnected and also ensuring control wiring is not

    subjected to bus-bar test voltages. This test should be carried out prior to and

    immediately after the pressure test and before energising the switchboard. The

    minimum acceptable resistance, together with the relevant test voltage, is given in the

    table below.

    SWITCHGEAR

    VOLTAGE

    (V)

    TEST

    VOLTAGE

    (V)

    MIN INSULATION

    RESISTANCE

    (M)

    - Up to 1 kV

    - Up to 4.6 kV

    - Above 4.6 kV

    1000 Vdc

    2500 Vdc

    5000 Vdc

    10

    150

    200

    d) A DC high voltage test (pressure test) on both the main and auxiliary circuits shall be

    carried out between phases and phase-to-earth. The following conditions must be

    adhered to for the tests:

    (i) All current transformers secondaries will be short-circuited for the test.

    (ii) All voltage transformers shall be disconnected by removal of primary andsecondary fuses for the duration of the test.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    18/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 18 di 59

    (iii) One pole of the testing supply shall be connected to earth and to frame of the

    assembly for the phase to earth test.

    MAX SYSTEM VOLTAGE

    (kV)

    DC TEST VOLTAGE

    (FOR 1 MINUTE)

    (kV)

    - Up to 1

    - 3.6

    - 7.2

    - 12

    - 17.5

    - 24

    - 36

    1,5

    10 (*)

    20 (*)

    28 (*)

    38 (*)

    50 (*)

    70 (*)

    (*): or as recommended

    by Manufacturer

    e) Upon completion of testing, reconnect all cables and function test the circuit to ensure

    all links and fuses are replaced.

    6.8.3 Test Certificates

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E004 (MOD.ELE.FTC.005).

    b) All originals of test certificates generated by supplier must be attached to form

    CL-E004 (MOD.ELE.FTC.005) for inclusion in the system test dossier.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    19/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 19 di 59

    6.9 MV Power Cables

    6.9.1 Installation Completion

    a) Check that the cable installation is as per project specification and drawings.

    b) Ensure that the gland certificates meet the Area Classification and Specification

    requirements.

    c) Inspect the cable glands for tightness and good workmanship. Ensure that the correct

    type of gland has been used for the size and type of cable installed.

    d) Where conductors have been terminated using crimped connections, ensure that thecorrect size and type of crimping lug bas been used.

    e) Inspection the earth connections.

    6.9.2 Additional Installation Completion Checks (MV Cables)

    a) Ensure that cables have been glanded in accordance with Supplier's instructions.

    b) Check that any incorporated stress relief measures and termination kits are

    satisfactory.

    c) Ensure that the minimum cable bending radius has not been exceeded.

    6.9.3 Mechanical Completion Certification Testing

    Before any cables are tested, all cleaning, supports, etc. shall be completed.

    Intermediate insulation resistance tests will be carried out before cleaning. Before making

    any measurements, the Inspector shall ensure that both ends of the cable have been

    disconnected and are clean of any metal and that core continuity of jointed cables is

    correct.

    a) Measure the insulation resistance of the cable and record on the relevant test

    certificate. The table below gives the test voltages and minimum acceptance values of

    insulation resistance. Where necessary, measure the conductivity of the earth

    conductor.

    For all multicore cables, insulation resistance should be measured core-to-core, core-to-

    earth and screen-to-armour. Record only the lowest figure obtained.

    TEST VOLTAGE

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    20/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 20 di 59

    CABLE OPERATING

    VOLTAGE(V)

    (V)

    INSULATION

    RESISTANCE(M)

    (MINIMUM)

    U0/U 5000 200 (*)

    (*) For cable length above 1 km=200

    Cable lenght (Km)

    6.9.4 Additional Mechanical Completion Certification Testing (M.V. Cables)

    a) Apply a DC test voltage (pressure test) as per IEC code & regulations between the

    conductors of each high voltage cable and the copper tape screen of each conductor,

    also between each conductor and earth.

    Record test voltage and duration of test measure and record any leakage current.

    Each cable shall be discharged after the above tests and the conductors earthed until the

    cable is out into service. The test voltage and duration are as tabulated below:

    CABLE OPERATINGVOLTAGE

    (V)

    BETWEEN

    CONDUCTORS

    (V)

    BETWEENCONDUCTORS

    AND EARTH

    (V)

    TIME

    (min)

    U0/U 4 U0 4 U0 15

    b) As an alternative, and by agreement between the contractor and purchaser, an a.c.voltage test at power frequency, in accordance with the following points b1 and b2,

    can be used:

    b1) Test for 5 min with the phase-to-phase voltage of the system applied between theconductor and the metallic screen;

    b2) Test for 24 hours with the normal operating voltage of the system;

    Note that the tests above mentioned are for new installations only; electrical tests on

    repaired installations are subject to installation requirements.

    6.9.5 Test Certificates

    - MV cable check sheets and test certificates are for individual cables.

    - Mechanical completion certification testing of the M.V. cables shall be recorded on

    forms CL-E005 and CL-E006 (MOD.ELE.FTC.006 and 007).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    21/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 21 di 59

    6.10 L.V. Power & Control Cables

    6.10.1 Installation Completion

    a) Check that cable installation is as per project specifications and drawings.

    b) Ensure that the gland certificates meet the Area Classification and Specification

    requirements.

    c) Inspect the cable glands for tightness and good workmanship. Ensure that the correct

    type of gland has been used for the size and type of cable installed and that, where

    specified, insulating gland adapters have been installed. Particular attentions should be

    paid to barrier glands.

    d) Where conductors have been terminated using crimped connections, ensure that the

    correct size and type of crimping lug has been used.

    6.10.2 Mechanical Completion Certification Testing

    Before any cables are tested, all cleaning, supports, etc. shall be completed.

    Intermediate insulation resistance tests will be carried out before cleaning. Before making

    any measurements, the Inspectors should ensure that both ends of the cable have been

    disconnected and are clear of any metal and that core continuity of jointed cables is

    correct.

    a) Measure the insulation resistance of the cable and record on the relevant test

    certificate. The table below gives the test voltages and minimum acceptance values of

    insulation resistance. Where necessary, measure the conductivity of the earth

    conductor.

    For all multicore cables, insulation resistance shall be measured core-to-core, core-to-

    earth and screen-to-armour. Record only the lowest figure obtained.

    CABLE OPERATING

    VOLTAGE

    (V)

    TEST VOLTAGE

    (V)

    INSULATION

    RESISTANCE(M)

    (MINIMUM)

    500

    600 / 1000

    500

    1000

    1

    10

    6.10.3 Test Certificates

    Installation Completion and Mechanical Completion certification testing of cables shall

    be recorded on Forms CL-E006 (MOD.ELE.FTC.007).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    22/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 22 di 59

    6.11 DC Supply System: UPS, Battery Charger and Batteries

    6.11.1 Installation Completion

    a) Note the nameplate rating of the equipment and number, type and rating of batteries

    supplied. Compare with the ratings stated on the approved drawings for the

    equipment.

    b) Ensure that the equipment certificates meet the Area Classification and Specification

    Requirements.

    c) Inspect the chargers and battery stands for alignment, level and tightness of foundation

    bolts and fixing.

    d) Inspect the earthing bolts and connections to the earth system, where applicable.

    e) Check cleanliness. Where necessary clean the interiors of all control panel, chargers,

    etc. Remove any temporary silica-gel drying agents from the panels.

    f) Note the type, size and rating of all fuses and protective devices and compare with the

    values stated on the approved drawings.

    g) Inspect all batteries for cracks, damage, tightness and cleanliness of terminals and

    connections.

    h) Remove any transit bungs and store for possible future use.

    i) Inspect all bolted connections between individual cells in a bank of batteries. Ensure

    that all battery terminals have been coated with vaseline or equivalent.

    j) Inspect battery circuit breakers.

    k) Where batteries and battery chargers are housed in the same cubicle or suite of

    cubicles, check the integrity of the gas tight seal between the compartments.

    l) Ensure that there is not leakage of the electrolyte.

    m) Ensure that connections between cells and blocks are such as to prevent any short

    circuit.

    n) Ensure that connections from batteries to switchboards are well installed and suitably

    marked.

    o) Ensure that warning labels, fitted by the manufacturer for special indications, are

    intact.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    23/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 23 di 59

    6.11.2 Mechanical Completion Certification Testing

    a) Ensure that all cables have been certified.

    b) Measure the earth path resistance at the main earthing terminal. Note that special care

    must be taken when making tests on electronic equipment due to its susceptibility to

    damage by over voltage.

    6.11.3 Test Certificates

    a) Installation Completion and Mechanical Completion shall be recorded on forms CL-

    E007 and CL-E008 (MOD.ELE.FTC.008 and 009).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    24/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 24 di 59

    6.12 Lighting & Small Power Distribution System

    6.12.1 Installation Completion

    a) Ensure that the equipment meets the Area Classification and Specification

    requirements as laid down in the Design Specification and drawings.

    b) Note the distribution board circuit numbering and the fuse rating of the circuits and

    compare with the approved drawings. Verify the operation of any safety features, such

    as interlocks, padlocks and door switches.

    c) Note the location of the lighting fittings, sockets, etc. and compare with the approved

    drawings. Lighting equipment is correctly located and is no obstructed by pipes or

    other plant component thereby preventing the illumination of the areas

    d) Inspect the earthing bus-bar and cable earthing connections inside the distribution

    boards and the earthing connections from individual items of equipment to the

    earthing grid where detailed on drawing refer to the earthing/bonding procedure.

    e) Inspect lighting fittings, sockets and switches for neatness, weatherproofing, glanding,

    internal connections, general good workmanship and labelling.

    f) All equipment in hazardous areas should be inspected in accordance with the

    requirements of the procedure for the apparatus for use in hazardous areas.

    g) Carry out inspection of junction boxes in accordance with the junction box inspection

    procedure.

    h) Ensure that the circuits are correctly marked.

    i) Ensure that the safety lighting system is installed as per the design project.

    j) Ensure that glass and guards of lighting equipment are no broken.

    k) Ensure that local lighting panels are suitably welded to the support structure. The

    mechanical operation of circuit-breakers is satisfactory.

    l) Ensure that protection against corrosion has been provided and is complete or made

    good where necessary.

    m) Ensure that poles and floodlights are complete with accessories and are earthed.

    n) Ensure that road lighting equipment and floodlights are correctly orientated.

    6.12.2 Mechanical Completion Certification Testing

    a) Confirm that all cable certification is complete, including supply cable to distribution

    boards.

    b) Measure insulation resistance of distribution board phases to ground.

    c) Measure each distribution board and sub-circuit insulation resistance to earth.

    d) Check the earth continuity of each outgoing circuit.

    e) Check the operation of MCCB, ESD and RCD isolation, where applicable, on eachcircuit.

    f) Check that each circuit is correct to latest drawing revision.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    25/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 25 di 59

    g) As each sub-circuit from a distribution board is inspected, complete an inspection tag

    and attach it to the sub-circuit control switch in a prominent position.

    6.12.3 Test Certificates

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E009 (MOD.ELE.FTC.010).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    26/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 26 di 59

    6.13 Navigation AIDS

    6.13.1 Installation and Mechanical Completion

    a) Check that the equipment certification meets the Area Classification and Specification

    requirements.

    b) Note the nameplate rating of the supplied equipment and compare this rating with that

    on the approved drawings.

    c) Inspect the installation of equipment for alignment, level and tightness of foundation

    bolts and fixings.

    d) Ensure that the insides of any control panels, etc, have been cleaned out.

    e) Inspect the earthing arrangements, including earthing connections, inside the

    connection boxes.

    f) Inspect the paint finish, paying particular attention to externally located equipment.

    Any damaged areas shall be made good.

    g) Inspect the weatherproofing and bolting of the connection boxes. Weatherproofing

    should not be dependent upon the application of paint, tape or plastic compounds.

    h) Ensure that the appropriate requirements of the procedure for the apparatus for use inHazardous areas are carried out, if applicable.

    i) Note the size, type and rating of all fuses and protective devices. Compare with the

    values stated on the approved drawings.

    6.13.2 Test Certificates

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E010 (MOD.ELE.FTC.011).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    27/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 27 di 59

    6.14 Earthing

    6.14.1 Installation Completion

    a) Compare the earth connection type and size with the Schedule.

    b) Where conductors have been terminated using crimped connections, ensure that the

    correct size and type of crimping lug has been used.

    c) Ensure all connections are tight and greased.

    d) In the case of instrument earths, refer to installation specification.

    e) Ensure that buried conductors and earth rods are located in accordance with the design.

    f) Ensure that conductors installed without protection are sheathed (yellow/green).

    g) Ensure that the continuity of the protective conductors (PE), equipotential conductors

    and other conductors which form part of the earthing system has been verified.

    h) Ensure that conductors rising from the floor or ground are protected by means of a

    conduit section.

    i) Ensure that buried joints of conductors are protected against damp with a bitumen orsimilar mixture.

    j) Ensure that earthing and equipotential connections are provided for machines, panels,

    equipment, components and structures, including those outside the electrical

    installation, as anticipated in the design and in accordance with reference codes.

    k) Ensure that down conductors and other apparatus relevant to lightning protection

    system comply with the design.

    l) Ensure that transformer neutrals are correctly earthed.

    m) Ensure that earthing of concrete reinforcing bars has been carried out, if required bythe design.

    n) Ensure that terminals and earth bus-bars are correctly installed.

    o) Ensure that protective conductors (PE) and earthing conductors are sized in relation to

    the design and are correctly fixed and protected.

    p) Ensure that metal sheaths and cable armouring are earthed.

    q) Ensure that protection against corrosion has been provided and is complete or made

    good where necessary.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    28/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 28 di 59

    6.14.2 Mechanical Completion Certification Testing

    a) Measurement of grounding grid resistance (RE):

    - The measurements shall be carried out before the start-up of the plant and

    subsequently wit a periodicity dictated by regulations.

    b) Measurement of step and touch voltages (US and UT):

    The measurement of step and touch voltages is not necessary if the ground potential

    rise (UE: maximum electrical potential that a grounding grid may attain relative to a

    distant grounding point assumed to be at the potential or remote earth. This voltage

    (GPR) is equal to the maximum grid current (IE) times the grounding grid resistance

    (RE)), measured and/or calculated, does not exceed the maximum allowable values of

    step and touch voltages;

    c) Measurement of earth fault loop impedance (ZS):

    The measurement of earth fault loop impedance shall be taken into account in TN

    systems. The measurements aim to establish if the protection device against indirect

    contacts (carried out by means of automatic breaking of the circuit), operates

    correctly.

    The relationship to be met is the following:

    IaU0/ZS; ZSU0/Ia

    Where:

    - U0: rated voltage between the system phase and earth (V);- Ia: current causing the tripping of the protection device within the times indicated

    in the applicable standards (A);

    - ZS: impedance of fault loop ();

    The situations that can occur are the following:

    - The protection device is a residual current relay: the relationship is alwaysrespected;

    - The protection device are fuses, circuit-breaker or other overcurrent protectiondevices: the relationship should be verified;

    When the above mentioned relationship is not verified, it is necessary proceed by:- increasing the cross section of phase conductor and protective conductor (PE);

    - replaying, if possible, the protection device (circuit-breaker, overcurrent release of

    circuit-breaker, fuses, etc);

    - inserting a residual current protection device;

    6.14.3 Mechanical Completion Certification Testing and Test Certificate

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E011 (MOD.ELE.FTC.012).

    Tests shall be recorded on form MOD-ELE-FTC-015 and 016.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    29/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 29 di 59

    6.15 Electrical Heaters

    6.15.1 Installation Completion

    a) Ensure that the equipment meets the Area Classification and Specification

    requirements.

    b) Ensure that the equipment identification is correctly shown.

    c) Ensure that the heater is free from damage and the paintwork is correct.

    d) Ensure that the cables are supported correctly, glands are made off correctly and spare

    entries are plugged.

    e) Ensure that flanges are undamaged and that seals and gaskets are correctly fitted.

    f) Inspect the earthing for mechanical and electrical continuity. Refer to

    earthing/bonding procedure.

    g) Inspect the terminal box of the heater for neatness of connections and general good

    workmanship.

    h) All equipment in hazardous areas should be inspected in accordance with the

    requirements of the procedure for the apparatus for use in hazardous areas.

    6.15.2 Mechanical Completion certification testing

    a) Confirm all cable certification is complete.

    b) Measure insulation resistance of heater.

    c) Check the earth continuity of the heater.

    6.15.3 Test Certificates

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E012 (MOD.ELE.FTC.013).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    30/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 30 di 59

    6.16 Electrical Equipment & Device (Local Panel - Push Button - Power Socket)

    6.16.1 Installation and Mechanical Completion

    a) Ensure that the equipment meets the area classification and specification requirements.

    b) Note the nameplate of the devices and compare with those given on the approved

    drawings.

    c) Ensure that the enclosure IP rating meets specification requirements.

    d) Inspect for correct alignment, level, tightness of foundation bolts and fixing in general.

    e) Ensure that the equipment is free from damage and that the paintwork is correct.

    f) Ensure that cables are supported correctly, glands are installed correctly, spare entries

    are plugged, flanges are undamaged and seals and gaskets are correctly fitted.

    g) Ensure that all panel doors and gland plates are bonded to the panel structure.

    h) Inspect the earthing for mechanical and electrical continuity. Refer to earth procedure.

    i) Ensure that all terminal shrouds are correctly fitted.

    j) Ensure that all ferrules and crimps are correct and that all internal wiring is neatly

    fitted.

    l) Inspect the inside of the panel for cleanliness.

    m) Ensure that door locking arrangements are correct.

    n) Ensure that access is satisfactory.

    o) All equipment in hazardous areas should be inspected in accordance with the

    requirements of the relevant procedure.

    p) Ensure that all equipment are securely fixed to the ground (if applicable).

    q) Ensure that the base-plate is correctly executed (if applicable).

    r) Ensure that the position is as specified in the design.

    s) Ensure that covers have been installed as indicated in the drawings.

    t) Ensure that there are not obvious damages to switches and they operate correctly.

    u) Ensure that instrument glasses and warning lamp covers are not broken.

    v) Ensure that warning lamp covers are of the correct colour.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    31/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 31 di 59

    w) Ensure that boxes are complete with all bolts and are securely closed.

    x) Ensure that plugs fit properly and mechanical interlocks operate correctly

    6.16.2 Test Certificates

    a) Installation Completion and Mechanical Completion shall be recorded on Forms

    CL-E013 (MOD.ELE.FTC.014).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    32/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 32 di 59

    6.17 Junction Box

    6.17.1 Installation and Mechanical Completion

    a) Ensure that the equipment meets the area classification and specification requirements.

    b) Note the nameplate of the devices and compare with those given on the approved

    drawings.

    c) Ensure that the enclosure IP rating meets specification requirements.

    d) Ensure that the junction box location is correct.

    e) Ensure that the junction box is adequately supported and identified.

    f) Ensure that the terminal type, size, fixing and identification are correct.

    g) Ensure that the earthing, internal and external, is correct.

    h) Ensure that the glands and accessories are correctly fitted and that unused cable entries

    are plugged.

    i) Ensure that grease and gaskets are correctly installed, as required.

    j) Ensure that the box is correctly sealed.

    k) For hazardous area installation, procedure for apparatus for use in hazardous areas

    must be followed.

    6.17.2 Test Certificates

    a) There are no specific standard forms for recording that the requirements of this

    procedure have been implemented, however, form CL-E013 (MOD.ELE.FTC.014)

    may require endorsement to show that the requirements of these procedures have beencomplied with.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    33/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 33 di 59

    6.18 ELECTRICAL SUBSTATIONS, HV SWITCHYARDS, TELEPHONEEXCHANGES, BATTERY ROOMS, ETC

    6.18.1 Installation Completion

    a) Ensure that doors and hatches close properly, are provided with keys and, from the

    inside, can be opened using the handle or crash-bar only as anticipated in the design.

    b) Ensure that fencing and boundary limits for keeping persons away from equipment

    installed outdoors (e.g. transformers) are correctly installed.

    c) Ensure that glass panels are not broken.

    d) Ensure that ventilation openings are not blocked off and are fitted with gratings and

    insect nets.

    e) Ensure that the artificial ventilation system in the panel room and/or battery room

    operates correctly.

    f) Ensure that the layout of panels and equipment meets requirements as regards working

    and safety space, as anticipated in the design.

    g) Ensure that all parts of civil works are complete and comply with the design. The floor

    slope is correct and the drain pit is clean.

    h) Ensure that the floor and walls of the battery room are coated and/or painted with

    acid-resistant paint (where necessary). The floor slope is correct and the drain pit is

    clean. The floor is fitted with insulating footboards.

    i) Ensure that the lighting system and socket outlets are correctly executed.

    j) Ensure that the earthing system is complete.

    k) Ensure that the floor is fitted with insulating footboards, where necessary.

    l) Ensure that canopies are installed on transformers if anticipated in the design.

    m) Ensure that fencing and boundary limits for keeping unauthorized persons away are

    correctly installed and connected to the earthing system (where necessary).

    n) Ensure that protection against corrosion is provided and is complete or made good

    where necessary.

    o) Ensure that rooms are clean.

    p) Ensure that warning labels are fixed to access doors, fencing of transformer bays,

    battery room door, etc.

    q) Ensure that a set of electrical diagrams is available for whoever must operate the

    electrical plant. The one line diagram is correctly displayed and updated.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    34/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 34 di 59

    r) Ensure that first-aid equipment and fire-extinguishers are suitably positioned andavailable for whoever must operate and maintain the plant. Selectors with automatic

    extinction prearrangement and relevant signalling are correctly installed and operative.

    s) Ensure that energy tripping pushbutton, if any, is operative and clearly identified.

    6.18.2 Mechanical Completion Certification Testing

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E014 (MOD.ELE.FTC.017).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    35/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 35 di 59

    6.19 CHATODIC PROTECTION SYSTEM.

    6.19.1 Installation Completion

    a) Ensure that control panels are clean and there are no foreign bodies or dust in them.

    b) Ensure that there is no obvious damage to mounted instruments and equipment.

    c) Ensure that protection devices are set in accordance with the design value.

    d) Ensure that doors close properly and are supplied with keys.

    e) Ensure that cables and conductors are correctly installed. Conductors of the protection

    circuit are correctly connected.

    f) Ensure that holes which are not used but which are anticipated for future equipment

    and cable inlets are plugged.

    g) Ensure that measuring points are correctly positioned in accordance with design and

    properly installed.

    h) Ensure that measuring points are correctly numbered.

    i) Ensure that characteristics of the anodes and reference electrodes for the measurements

    are as anticipated in the design.

    j) Ensure that the number and location, both plan and depth-wise, of the anodes and

    reference electrode are as indicated in the design.

    k) Ensure that characteristics of the anodic bed (material surrounding the anodes) are as

    laid down in the design.

    l) Ensure that the ground of the anode has been compacted and is not subject to future

    settlement.

    m) Ensure that passive protections against corrosion are provided; these are in complete

    execution and do not present faults when restored, if required (painting, thermoplastic

    sheaths).

    n) Ensure that dielectric joints are correctly positioned and are adequate for the utilization

    (operating temperature, isolating and conducting fluids etc.)

    o) Ensure that the field connections are properly executed, the connections through bolts

    and brazing are protected against corrosion (stainless steel bolts, bituminous or

    thermoplastic insulations for buried joints).

    p) Ensure that the current absorbed by the protection system is compatible with that ofproject design in relation to the adopted protection system: CV constant potential

    supply constant current CC CV constant potential with base current Ib.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    36/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 36 di 59

    q) Ensure that protective overloads dischargers of insulation joints and those towardsearth are correctly positioned and adequate to the installation site.

    r) Ensure that cathodic protection system does not present interferences with other

    protected structures and earthing system.

    6.19.2 Mechanical Completion Certification Testing

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E015 (MOD.ELE.FTC.018).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    37/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 37 di 59

    6.20 CABLE TRAY & RACK.

    6.20.1 Installation Completion

    a) Ensure that the equipment meets the area classification and specification requirements,

    where applicable.

    b) Ensure the mechanical integrity of all components.

    c) Inspect the paint finish for damage. Any damaged areas shall be repainted.

    d) Inspect the equipment assembly for alignment, level, etc.

    e) Inspect the earthing for mechanical and electrical continuity.

    6.20.2 Mechanical Completion Certification Testing

    a) Installation Completion and Mechanical Completion shall be recorded on form

    CL-E016 (MOD.ELE.FTC.019).

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    38/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 38 di 59

    6.21 Apparatus for Use in Hazardous Areas

    6.21.1 Installation Completion

    The following is a general inspection guide for all types of equipment used in hazardous

    areas or specified accordingly and installed in non-hazardous areas.

    The particular requirements for special equipment used in these locations will be listed

    individually and should be read in conjunction with hazardous area classification data

    sheet.

    a) Ensure that the apparatus is appropriate to the area classification, the surface

    temperature class is correct, the apparatus group is correct and that any special

    conditions on the certificate have been followed.

    b) Ensure that there are no unauthorised modifications and that it carries correct circuit

    identification.

    c) Ensure that all bolts, glands and stoppers are tight and that the condition of the

    enclosure gaskets is satisfactory.

    d) Inspect the interior of the equipment for dust or dirt accumulation and ensure that all

    electrical connections are tight. A check should also be made that the electrical

    protection is adequate for the drive rating where applicable.

    e) Inspect the equipment earthing for security and tightness.

    f) Ensure that there is not damage to any cables and that the equipment is adequately

    protected against corrosion, weather, vibration and other adverse factors.

    g) Ensure that the lamp rating and type are correct.

    h) Where guards are used, ensure that they are correctly located and that motor fans and

    couplings are not rubbing.

    i) The following additional checks are required on special equipment as listed (whereapplicable):

    (i) Ex'd', Flameproof Enclosure

    Ensure that:

    - Obstructions in the vicinity of the equipment do not impair the efficient operation

    of the flame-path.

    - All gaps are correct and free from damage, corrosion, dirt and paint.

    - The machined surface may be protected with one of the approved greases.

    - All conduit runs are tight and free from corrosion.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    39/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 39 di 59

    (ii) Ex'e', Increased Safety

    - A seal must be provided between the gland and the enclosure by means of a

    sealing washer.

    - Unused cable entries should be closed with plugs to maintain as a minimum, the

    same IP rating as the enclosure, using a tool for insertion and removal.

    (iii) Ex'n'

    - Any unused cable entries shall be closed with plugs that maintain the degree of

    protection of the enclosure.

    (iv) Ex'i', Intrinsically Safe

    - All installation should be inspected to ensure that any cable screens are earthed in

    accordance with the relevant standard drawing.

    - All diode safety barrier installations should be inspected to ensure that the correct

    type of barriers have been fitted and that they remain firmly fixed to the barrier

    earth bar.

    - Boxes containing diode safety barriers and junction boxes should be inspected to

    ensure that they do not contain wiring other than that specified in the

    documentation for the intrinsically safe system.

    - All installations should be inspected to ensure that relays and similar devices

    which act as safety barriers between circuits have not become damaged be

    repeated operation or vibration in a way which reduces the segregation afforded.

    - The earth path resistance must be measured.

    - Ensure Ex'i' earth system is segregated from other earthing systems.

    (v) Ex'p', Pressurised or Purged

    - The purge medium is from an uncontaminated source.

    - Any filters are clean and accessible.

    - The purge system shall be thoroughly checked to ensure that the purge pressure,

    cycle times, interlocks, lock out sequence, etc. are correct.

    (vi) General

    The particular earthing requirements of any of the above equipment must be

    clarified with reference to the specific Code of Practice for the equipment. It is

    also recommended that where there is any ambiguity in the interpretation of the

    requirements, reference should be made to the relevant Code of Practice.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    40/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 40 di 59

    6.21.2 Mechanical Completion Certification Testing

    The diversity of equipment and special components which are contained in a particular

    type of apparatus does not permit a generalisation of the testing required to demonstrate

    suitability for service in a hazardous area. Special requirements for testing may be

    contained in the standard or specific Code for the equipment and this should be compiled

    with prior to final energisation of the circuit.

    Supplier manuals shall be examined to ensure that electrical components and equipment

    have been certified in compliance with appropriate code, National Standards and that

    relevant certificates are available.

    Such certificates must also be examined to determine whether the validity of the

    certificate is subject to specific installation instructions and further testing afterinstallation, e.g. testing of cables for intrinsically safe apparatus.

    6.21.3 Test Certificates

    There is no specific standard for recording that the requirements of the Procedure have

    been implemented; forms should be used to record the results of any checking and testing

    required by the Standard and Code certificate to demonstrate suitability for use in a

    hazardous area.

    The forms, however, make reference to this Procedure and require endorsement to signify

    that the equipment and the standard of installation is suitable for use in hazardous areas.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    41/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 41 di 59

    7. PRE-COMMISSIONING REQUIREMENTS

    7.1 General

    This section covers the general responsibilities of the electrical contractor during Pre-

    commissioning of electrical equipment.

    a) All work shall be executed in strict accordance with project specifications and the

    approved drawings. The written approval of the COMPANY is required for any

    deviations by the CONTRACTOR from specifications.

    b) The CONTRACTOR shall bring to the attention of the COMPANY any areas of thisspecification which conflicts with or does not meet safe and acceptable electrical

    practices.

    c) The CONTRACTOR shall be responsible for the protection and security of all

    equipment during all stages of checkout and commissioning.

    d) The CONTRACTOR shall not perform any electrical equipment or system tests that

    would either void warranties or damage equipment.

    7.2 Conduct of Tests

    a) Written programmes for commissioning electrical equipment shall be developed by

    the CONTRACTOR.

    b) The Pre-commissioning program shall detail the final tests to be conducted on all

    electrical equipment after the checkout program is complete. The Pre-commissioning

    program shall demonstrate the proper operation of the complete electrical system.

    c) All checkout and Pre-commissioning may be witnessed by the COMPANY.

    d) Pre-commissioning tests may be conducted concurrently with Mechanical

    Completion.

    e) The CONTRACTOR shall submit a full test dossier to the COMPANY at completion

    of Pre- commissioning.

    f) After the checkout and Pre-commissioning program has been completed and accepted

    by the COMPANY, the CONTRACTOR shall be responsible for leaving the

    equipment in a safe and operable condition. All covers, doors, and access plates shall

    be properly fastened. All wiring shall be complete and all jumpers used in testing shall

    be removed. Some items may be left energised, on agreement with COMPANY.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    42/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 42 di 59

    7.3 Safety

    a) General Safety Precautions

    The consequences of shock or burn from electrical systems are serious. Work on

    electrical equipment shall, therefore, be performed only when the equipment is de-

    energised, and by qualified personnel, and who fully understand the electrical system

    of the project.

    One-line diagrams shall be available at all times. All feeding equipment and circuits

    shall be tagged-out and locked-out. The test/check operatives own key or lock shall

    form part of the lock-out procedure.

    The CONTRACTOR shall be completely responsible for the safety of his own

    operatives, and other personnel, at all times.

    All equipment such as bus bars, circuit breakers, and motor shall be properly grounded

    before any testing or other work is initiated.

    b) Equipment Isolation

    All equipment shall be physically disconnected from its power source to prevent

    accidental injury to personnel resulting from inadvertent re-energisation. Equipment

    isolation is necessary to ensure that voltages applied to the equipment under test are

    not allowed to back-feed into power transformers, generators, and associated upstream

    synchronizing and control circuits. The consequences of back-feeding voltages include

    danger to personnel and damage to equipment. A lock-out procedure will be

    developed.

    c) Medium Voltage Testing

    While any high or medium voltage testing is being conducted, the CONTRACTOR

    shall ensure that the test area is properly guarded to prevent unauthorized entry and

    that DANGER notices are posted adjacent to, and at all access ways to the test area

    during the period of the test.

    All cables must be discharged both before and after applying any test voltage. Any

    associated cables not being tested shall be grounded during the test, e.g., other phase

    conductors of a three-phase circuit.

    Temporary conductors used for test purposes shall not be sized less than the rating of

    the circuit under test.

    d) Portable Electrical Equipment

    Unless portable electrical equipment is double insulated or connected to ground fault

    interrupters, the equipment shall be grounded using flexible supply cable that

    incorporates a ground continuity conductor.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    43/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 43 di 59

    7.4 Generators

    7.4.1 Pre-Commissioning Certification Testing

    a) Check that all factory checks and tests have been completed as par specification

    requirement.

    b) Check that all original of suppliers checks list and test records are available.

    c) Ensure that all cables and/or bus ducts have been certified in accordance with the

    Cable and/or bus ducts Test Procedures.

    d) Verify that incoming circuit breaker has been tested in accordance with therequirements of Electrical Procedure.

    e) Short and earth all semi-conductors and carry out insulation resistance checks on the

    exciter field. Remove shorts and earths after test.

    f) Measure the status phase-to-frame insulation resistance. After separating the windings

    at the star point, measure the insulation resistance between windings. Reconnect the

    windings on completion of test.

    g) Measure the polarization index of the generator carried out by supplier (only if

    original certification records are not available from the manufacturer).

    h) Measure the insulation resistance of the anti-condensation heater.

    i) Remove earth strap on driven end of generator and measure non-driven end bearing

    pedestal insulation. Replace driven end earth strap on completion of test.

    j) Test the circuit continuity of temperature protection devices. Insulation resistance tests

    shall not be carried out on thermistors.

    k) Confirm that torque of generator lubrication and cooling systems are operational.

    l) Confirm that generator lubrication and cooling systems are operational.

    m) Ensure that all protection and metering has been tested in accordance with the

    requirements of the specification and relevant procedures.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    44/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 44 di 59

    7.4.2 Test Certificates

    a) Pre-commissioning certification testing shall be recorded on Form RS-E001

    (MOD.ELE.FTC.020).

    b) Any certificates generated by the requirements of electrical procedures (i.e. protection

    relay etc.) shall be attached to Form RS-E001 (MOD.ELE.FTC.020) for inclusion in

    the system test dossier.

    c) Supplier test sheets shall be attached to Form RS-E001 (MOD.ELE.FTC.020) for

    inclusion in the system test dossier.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    45/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 45 di 59

    7.5 Power Transformers

    7.5.1 Pre-Commissioning Certification Testing

    a) Check that all factory checks and tests have been completed as par specification

    requirement.

    b) Check that all original of suppliers checks list and test records are available.

    c) Test the alarm and trip circuits.

    d) Ensure that all cables have been certified in accordance the relevant procedures.

    e) Ensure adequate separation distances on high voltage cable connection chamber andterminations are as per Supplier's drawing.

    f) Inspect tightness of bus-bar connections plus bracing from secondary winding to bus-

    bars of switchgear.

    g) Measure the phase-to-phase and phase-to-earth insulation resistance for auxiliary

    circuits and both the MV and LV windings. The table below gives the test voltages

    and minimum acceptable values of insulation resistance.

    TRANSFORMER

    WINDING

    VOLTAGE

    (V)

    TEST

    VOLTAGE

    (V)

    MIN INSULATION

    RESISTANCE

    (M)

    - Up to 1 kV

    - Up to 4.6 kV

    - Above 4.6 kV

    1000 Vdc

    2500 Vdc

    5000 Vdc

    10

    150

    200

    h) Carry out a power frequency voltage (pressure test) between the MV and LV

    windings. The test should be carried out for one minute between each winding withthe core and tank earthed.

    Alternatively, a dc pressure test may be applied. Duration of this test shall be fifteen

    (15) minutes.

    The test voltages to be applied are given in the table below.

    TRANSFORMER

    WINDING

    VOLTAGE

    (V)

    TEST

    VOLTAGE

    AC

    (V)

    MIN INSULATION

    RESISTANCE

    (M)

    U 5000 10000

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    46/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 46 di 59

    NOTE: Hi-pot test shall be carried out by supplier (only if original certification

    records are not available from the manufacturer).

    i) Carry out the required testing of any protection and/or meter circuitry with cables and

    bus ducts disconnected and in accordance with Supplier's commissioning instructions.

    j) Check phase rotation of transformer secondary windings.

    k) Check the operation of cooling fans (if fitted).

    7.5.2 Pre-Commissioning Certification Testing

    a) Pre-commissioning certification testing shall be recorded on Forms RS-E002(MOD.ELE.FTC.021).

    b) All supplementary certificates should be attached to Forms RS-E002

    (MOD.ELE.FTC.021) for filing in the System Test Dossier.

    c) Supplier test sheets shall be attached to Form RS-E002 (MOD.ELE.FTC.021) for

    inclusion in the system test dossier.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    47/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 47 di 59

    7.6 NEUTRAL EARTHING RESISTORS

    7.6.1 Pre-Commissioning Certification Testing

    a) Check that all factory checks and tests have been completed as par specification

    requirement.

    b) Check that all original of suppliers checks list and test records are available.

    c) Ensure all cable certification is complete as per relevants procedures.

    d) Measure the insulation resistance of the resistor to earth with incoming and outgoing

    connections disconnected. Measure the value of neutral earthing resistor with resistor

    in cold state. Using temperature coefficient calculate resistance for temperature stated

    on the nameplate. Compare calculated and design resistance.

    e) Measure resistance of frame earth path.

    f) Test the anti-condensation heater and circuits, where fitted.

    g) If current transformers have been fitted, check that Supplier test certificates and

    magnetising curves are available.

    h) Measure the equipment earth path resistance at the main earthing terminal to the

    general earth system.

    i) Upon completion of tests, reconnect the incoming and outgoing cables.

    7.6.2 Test Certificates

    a) Pre-commissioning certification testing shall be recorded on Forms RS-E011

    (MOD.ELE.FTC.031).

    b) Any supporting current transformer certificates should be attached to the

    relevant protection certificate.

    c) Supplier test sheets shall be attached to Form RS-E011 (MOD.ELE.FTC.031) for

    inclusion in the system test dossier.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    48/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 48 di 59

    7.7 MV & LV Motors

    7.7.1 Pre-Commissioning Certification Testing

    a) Check that all factory checks and tests have been completed as par specification

    requirement.

    b) Check that all original of suppliers checks list and test records are available.

    c) Ensure that all cables have been certified in accordance with the Cable Test

    Procedures. Check the phase sequence and polarity of all connections.

    d) Measure the insulation resistance phase-to-phase if the windings can be separated andphase-to-earth. If the windings require drying out, reference shall be made to the

    guidance notes and typical drying out curves as detailed in Vendor's Instructions.

    MOTOR

    VOLTAGE

    (V)

    TEST

    VOLTAGE

    (V)

    MIN INSULATION

    RESISTANCE

    (M)

    - Up to 1 kV

    - Up to 4.6 kV

    - Above 4.6 kV

    1000 Vdc

    2500 Vdc

    5000 Vdc

    10

    150

    200

    e) Measure insulation resistance of anti-condensation heater (if fitted).

    f) Check motor cooling and lubrication.

    g) If special motor protection devices (e.g. thermocouples) have been fitted, test their

    circuit continuity. (Insulation resistance tests should not be carried out acrossthermistor terminals or thermistor control units).

    h) Verify that the starter cubicle has been tested in accordance with relevant Procedures

    (SWITCHGEAR).

    i) Verify that the water cooling, pressurization and purge systems have been tested and

    are available (if applicable).

    j) Where applicable , remove earth strap on drive end of motor and measure non-drive

    end pedestal bearing insulation. If satisfactory, refit drive end earth strap.

    k) Confirm that torque of motor terminations conforms to Supplier's Specifications.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    49/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 49 di 59

    l) Have the coupling broken to separate the motor from the driven unit or the belts

    removed from the belt-driven equipment. Ensure that the motor rotates freely and therotor end play is within tolerance.

    m) Start the motor to determine the direction of rotation and compare this with the

    required rotation of the driven unit.

    n) Run the motor for about 30 minutes and check the bearings for undue temperature

    rise. Check for vibration. Tabulate results after 30 minutes to confirm temperature

    stabilizes. On DC motors check for armature sparking (if fitted).

    o) Measure and record the line current of the free running motor (at no load).

    7.7.2 Test Certificates

    a) Pre-commissioning certification testing shall be recorded on Forms RS-E003

    (MOD.ELE.FTC.022).

    b) Supplier test sheets shall be attached to Form RS-E003 (MOD.ELE.FTC.022) for

    inclusion in the system test dossier.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    50/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 50 di 59

    7.8 MV & LV Switchgear and Bus-bars

    7.8.1 Pre-Commissioning Certification Testing

    a) Check that all factory checks and tests have been completed as par specification

    requirement.

    b) Check that all original of suppliers checks list and test records are available.

    c) Check for correct voltage of trip/close supplies.

    d) Prove correct operation of all mechanical and electrical interlocks (incoming feeder,

    outgoing feeder, all MCC cubicle, etc.).

    e) Energise switchboard and check for correct bus-bar phase rotation.

    7.8.2 Circuit Breakers Pre-Commissioning

    a) Check that all factory checks and tests have been completed as par specification

    requirement.

    b) Check that all original of suppliers checks list and test records are available.

    c) Ensure manual trip and close is functional.

    d) Ensure electrical trip and close is functional.

    e) Ensure earthing switch is functional (if fitted).

    f) Ensure that the appropriate requirements of Procedure for apparatus for use in

    hazardous areas have been complied with, if applicable.

    g) Carry out insulation resistance tests before and after pressure test with circuit breaker

    both open and closed.

    h) Carry out pressure tests as detailed on relevant Procedure and Supplier's instruction.

    i) Control Circuits - The following checks shall be undertaken.

    Check electrical closing and tripping from the following locations:

    - local to breaker;

    - local station;

    - remote station (discrepancy switches);

    - closing from dead bar and auto synchronizer contacts;

    - tripping from protection trip relay.

    Check control circuit operation for closing and tripping. Where coils are short-time

    rated, check the isolating contacts for operation.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    51/59

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    52/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 52 di 59

    b) Check that all original of suppliers checks list and test records are available.

    c) Measure the insulation resistance through the closed isolator (phase to phase and all

    phases to earth).

    d) Carry out required testing of any protection and/or meter circuitry in accordance with

    the requirements of specifications and relevant procedures.

    7.8.5 Testing of Protection Circuits

    The following equipments may require testing of protection and/or meter circuitry by

    means of primary and/or secondary injection:- Switchgear & Bus-bars

    - Circuit Breakers

    - Contactor Starter

    - Fuse Switches

    - Power Transformers

    - Panels/Consoles

    - Generator

    Owing to both the variety of schemes and the diverse types of relays in use, no attempt

    has been made to produce a standard Testing Procedure.

    The following commissioning tests must be carried out in accordance with the relevant

    manufacturers commissioning documentation and with reference to the project "Power

    System Design - Protection Co-ordination Study documents", specification data sheet,

    etc.

    1) Check that all factory checks and tests have been completed as par specification

    requirement.

    2) Check that all original of suppliers checks list and test records are available.

    3) Individual items of protection have not been damaged by transport and handling.

    This is proved by Secondary injection Tests.

    4) The correct items have been connected together, e.g. the correct set of Current

    Transformers have been connected to a given set of relay. This is provided by Primary

    Injection Tests.

    5) All connections, panel wiring and intertrips are correct. This is provided by Function

    Tests.

    6) The correct settings and/or adjustments have been applied according to therequirements of the specification, data sheet and Protection Co-ordination Study.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    53/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 53 di 59

    7.8.6 Voltmeter & Ammeter Testing

    a) Check that each individual items have not been damaged by transport and handling.

    7.8.7 Test Certificates

    a) Pre-commissioning certification testing shall be recorded on Form RS-E004

    (MOD.ELE.FTC.023).

    b) Any certificates generated by the requirements of electrical procedures (i.e. protection

    relay etc.) shall be attached to Form RS-E004 (MOD.ELE.FTC.023) for inclusion in

    the system test dossier.

    c) Supplier test sheets shall be attached to Form RS-E004 (MOD.ELE.FTC.023) for

    inclusion in the system test dossier.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    54/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 54 di 59

    7.9 DC Supply System UPS & Battery Charger and Batteries

    7.9.1 Pre-Commissioning Certification Testing

    a) Check that all factory checks and tests have been completed as par specification

    requirement.

    b) Check that all original of suppliers checks list and test records are available.

    c) Measure the voltage at the terminal of each cell and compare with the recommended

    values. Record the results and ensure that a copy of the Check List remains with the

    batteries.

    d) When all inspection and tests have been carried out, the batteries may be given their

    initial charge. This shall be carried out under the supervision of the Supplier's

    representative on site. The boost and float charge rates should be noted.

    Under NO CIRCUMSTANCES WHATSOEVER are sealed cells to be boost charged.

    e) Check the operation of all alarms.

    f) Measure the level of output voltage ripple on load and check in the Supplier's data that

    this is within tolerance.

    g) Check the operation of ESD trip and battery circuit breaker.

    h) Carry out battery discharge test using a Procedure acceptable to the Supplier and

    record the results, including decay graphs, on test sheets (care must be taken not to

    damage batteries by excessive discharging).

    i) Switch on the inverter and record the frequency, input and output voltage and

    current.

    j) Transfer the load from the inverters via the static switch to mains by pass and from

    mains by pass back to the inverters via the static switch.

    7.9.2 Test Certificates

    a) Pre-commissioning certification testing shall be recorded on Forms RS-E005,

    RS-E006 and RS-E012 (MOD.ELE.FTC.024, 25 and 32).

    b) Any certificates generated by the requirements of electrical procedures (i.e. protection

    relay etc.) shall be attached to Forms RS-E005, RS-E006 and RS-E012

    (MOD.ELE.FTC.024, 25 and 32) for inclusion in the system test dossier.

    c) Supplier test sheets shall be attached to Forms RS-E005, RS-E006 and RS-E012

    (MOD.ELE.FTC.024, 25 and 32) for inclusion in the system test dossier.

  • 8/10/2019 PROGRAM OF CHECKS AND TESTS FOR ELECTRICAL INSTALLATIONS

    55/59

    EniS.p.A.Exploration & Production Division

    05221 VAR.ELE.SPCRev. 4 Dec. 2004

    Sheet 55 di 59

    7.10 Lighting & Small Power Distribution System

    7.10.1 Pre-Commissioning Certification Testing

    a) Test the voltage and polarity of each socket.

    b) Check the operation of interlock on all sockets in hazardous areas.

    c) Check the voltage drop at the further point of each circuit.


Recommended