step by step guide for progress analysis is SAP PS projects with SKF
14
Generated by Jive on 2015-03-01+01:00 1 Progress Analysis with SKF in PS This document is to briefly explain the way progress of a project/wbs in terms of POC is calculated when planning is performed based on SKF. There is no detail business scenario as this document is mainly to see the steps involved in using the SKF to check the progress of a project. 1. Create SKF Transactions : KK01/02/03 Here, the SKF category 'Fixed Value' is used. Usually Fixed value is used when the SKF does not change very often, as in the case of number of employees, area etc. The rest of the document will consider the fixed value type of SKF. 2. POC customizing Transaction : SPRO PS customzing path for progress analysis
Transcript
  • Generated by Jive on 2015-03-01+01:001

    Progress Analysis with SKF in PS

    This document is to briefly explain the way progress of a project/wbs in terms of POC is calculatedwhen planning is performed based on SKF. There is no detail business scenario as this document ismainly to see the steps involved in using the SKF to check the progress of a project.

    1. Create SKF

    Transactions : KK01/02/03

    Here, the SKF category 'Fixed Value' is used. Usually Fixed value is used when the SKF does not change veryoften, as in the case of number of employees, area etc. The rest of the document will consider the fixed valuetype of SKF.

    2. POC customizing

    Transaction : SPRO

    PS customzing path for progress analysis

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:002

    Maintain Progress Version

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:003

    Define Measurement method

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:004

    Details of Measurement method definition

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:005

    3. Cj20n : Progress on WBS

    Progress version : 132 The planned and actual measurement method :MEG_QUANT defined above. The WBS is released and saved.

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:006

    Here, both the planned and actual measurement method has been taken as : MEG_QUANT.

    4. Posting Planned and Actual SKF

    Planning SKF on WBS

    If the SKF is defined is a Fixed category, then the value of the key figure entered in one monthwill be used for the remainder of the fiscal year.If the SKF is defined as a Total category, then the value of the key figure entered in one monthwill be used in one particular month and not the following ones.

    In our case SKF - 1304 is Fixed value.

    Transactions to plan & distribute SKF values on WBS: CJS2/ CJS3. SKF can be planned in CJ20n also on activities & WBS. Transactions to plan & distribute SKF values on network: CJK2/ CJK3.

    The below snap shots will show the Planning of SKF on WBS via CJS2

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:007

    In CJ20n, the dates tab will have dates which will show the period for which the SKF was planned.

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:008

    Posting actual SKF on WBS

    Transaction for posting actual SKF values for WBS is KB31N

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:009

    5. Progress Calulation and analysis

    Run transaction CNE1 for calculating project progress

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:0010

    Run Transaction CNE5 for checking the POC for the project

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:0011

    Calculations:

    Period 7 8 9 10 11 12

    PLAN 100 100

    ACTUAL 50 50 50 50 50 50

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:0012

    POC = Planned/Actual Quantity * 100 Overall Planned Quantity

    POC Actual = 50/100 * 100 = 50. POC Planned = 100/100 * 100 = 100

    6. Reporting SKF Data

    Transaction for displaying SKF data both planned & actual is S_ALR_87013548

    On running this standard SAP report

  • Progress Analysis with SKF in PS

    Generated by Jive on 2015-03-01+01:0013

    The actual and planned SKF values above are the average values across all the periods.

    Actual = 50+50+50+50+50+50 / 12 = 300 /12 = 25.Planned = 100+ 100 /12 = 200/12 = 16.6667

    On drilling down

    Hope the document will provide an insight into the SKF and progress functionality and how it works in PS. Ihave mentioned below a few importanat notes which have the recent corrections in the SKF area in PS.