Performing Arts Complex Progress and Status
Transcript
Page 1: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Performing Arts Complex

Progress and Status

Page 2: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Progression

Page 3: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Theatre Stage

6.25.2013•COMPANY SWITCHES INSTALLED•A/V CABLE INSTALLED•THEATRICAL CABLE INSTALLED

7.17.2013•ORCHESTRA LIFT IS OPERATIONAL•STAGE FLOOR INSTALLATION IN PROGRESS•COILING FIRE DOOR AT BACK OF STAGE INSTALLED

Page 4: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Theatre Seating Area

•6.25.13•DRYWALL COMPLETE•TAPE, BED AND FLOAT COMPLETE•FIRST COAT OF PAINT INSTALLED•KNEE WALL ROUGH IN COMPLETE

•7.17.2013•WOOD PANELS AT PROSCENIUM WALL COMPLETE•TAPE, BED AND PAINT ONGOING AT KNEE WALLS

Page 5: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Recital Hall Seating Area

6.25.2013•WALL HAVE BEEN PAINTED•WOOD PANELS AT EAST AND WEST WALL COMPLETE

7.17.2013•CURRENTLY INSTALLING PERFORATED WALL PANELS•KNEE WALL TAPE, BED AND PAINT ONGOING•EUROSPAN ACOUSTICAL PANEL TRACK INSTALLED

Page 6: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Recital Hall Lobby6/25/13•DRYWALL COMPLETE •TAPE, BED AND PAINT COMPLETE •REVEALS AT THE WALL PANELS ONGOING

7.17.2013•FIXTURE INSTALLATION ONGOING•WOOD PANEL INSTALLATION ONGOING

Page 7: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Theatre Lobby6.25.2013•DRYWALL COMPLETE•TAPE & BED RADIUS WALL COMPLETE•PRIME PAINT AT BALCONY LEVEL•GLASS RAIL VERTICAL POSTS INSTALLED

•7.17.2013•LEVEL 5 FLOAT AND PRIMER COMPLETE•WOOD PANEL INSTALLATION AT THEATER LEVEL ONGOING•CEILINGS COMPLETE AT STAIR A & B•TERRAZZO ONGOING AT STAIR B

Page 8: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Women’s Restroom - 1096.25.2013• TERRAZZO COMPLETE

7.17.2013

•LIGHT FIXTURES INSTALLED •WALL COVERINGS INSTALLED •CONCRETE LAVS INSTALLED

Page 9: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Southeast Elevation

6.25.2013•FACE BRICK AND CAST STONE COMPLETE AT ELEVATOR TOWER•FACE BRICK AND CAST STONE COMPLETE AT THE PAVILION•PLASTER SOFFIT AT THE EAST ARCADE COMPLETE

7.17.2013•PLANTERS AT EAST ENTRY INSTALLED•MONUMENT STAIRS INSTALLED AT EAST ENTRY•MOON STREET SUB GRADE COMPLETE WEST SIDE.•CURB, GUTTER AND BUS LANE INSTALLED ON WEST SIDE OF MOON]

Page 10: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Northeast Elevation6.25.2013•ENTRY PLASTER NEARLY COMPLETE•MOON STREET GRADE WORK 90% COMPLETE•CONTECH DETENTION UNIT ONGOING

7.17.2013•CONTECH DETENTION UNIT NEARLY COMPLETE •INSTALLATION OF REVISED SUB GRADE ON EAST SIDE OF MOON ONGOING

Page 11: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Northwest Elevation

6.25.2013•PAVERS COMPLETE AT NORTH ARCADE•PLASTER AT THE MANSARD ROOF COMPLETE•ALUMINUM TRELLIS COMPLETE

7.17.2013LIGHT POLES INSTALLED AND OPERATINGTREE INSTALLATION ONGOING

Page 12: Progress and Status. 6.25.2013 COMPANY SWITCHES INSTALLED A/V CABLE INSTALLED THEATRICAL CABLE INSTALLED 7.17.2013 ORCHESTRA LIFT IS OPERATIONAL STAGE.

Southwest Elevation

6.25.13•PAVER INSTALLATION ONGOING•RIBBON CURB FOR PAVERS COMPLETE

7.17.2013SOUND DOOR INSTALLATION ONGOINGTREE INSTALLATION ONGOING