+ All Categories
Home > Documents > PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA...

PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA...

Date post: 27-Apr-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
15
HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO POWER PROJECT By James Baanabe Commissioner Energy Department Ministry of Energy and Mineral Development, Uganda.
Transcript
Page 1: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

HYDRO POWER AFRICA

Johannesburg South Africa

28 July 2009

PROGRESS ON THE CONSTRUCTION OF THE

BUJAGALI HYDRO POWER PROJECT

By James Baanabe

Commissioner Energy Department

Ministry of Energy and Mineral Development, Uganda.

Page 2: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Project Location

Page 3: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Background

• The Project Promoter is the Government of (GoU)

• The project was originally under development by AES

between 1994 and 2003.

• However, faced by a myriad of problems, AES officially

withdrew from the project in August 2003.

• Bujagali Energy Limited (BEL) was selected sponsor in May

2005. The Shareholders are:

• Affiliates of Industrial Promotion Services/AKFED,

• Sithe Global Power (USA) and Government of Uganda (GoU)..

It is sponsored by industrial promotion Services (Kenya)

Limited and SG Bujagali Holdings Ltd, an affiliate of sithe

Global Power, LLC (USA).

Page 4: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

The Project

• The Bujagali Hydropower Project is a 250-

MW power ((5X50MW) hydroelectric

development on the Nile River, 8 km

downstream from Victoria Nile River.

• The project is an Independent Power Project

(IPP) premised on a Build, Own and Transfer

(BOT).

• The project went through extensive

economic, social and environmental due

diligence.

Page 5: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

The Project Cont’d

• BEL will sell electricity to UETCL under a 30-

year Power Purchase Agreement (PPA).

• UETCL’s payment obligation under the PPA is

guaranteed by the Government of Uganda

(GOU) through a government guarantee.

• The PPA is backed by a 30-year

Implementation Agreement that includes a

GoU sovereign guarantee and enhanced by a

liquidity facility arrangement.

Page 6: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

The Project Cont’d

• Salini of Italy is the EPC contract for the project who

was procured through international competitive

bidding.

• The ‘levelised’ tariffs over 30 years is about US¢6-6.5

per kwh.

• The tariffs will however reach about US¢11 per unit

during debt repayment.

• Bujagali will replace thermal generation that currently

costs US¢25-31 per kilowatt-hour.

• Construction started in 2007 and construction period

initially 44 months. Fist unit to provide power in Mid

2011.

Page 7: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Project Financing• Bujagali will be project financed on a non-recourse basis at a leverage of

more than a 75:25 debt to equity ratio.

• Government of Uganda’s contributions include intellectual property, land

and other assets that were received from AES and passed on to BEL.

Financiers

(MIGA provided insurance guarantee cover for Sithe equity)

Institution(s) Amount

International Finance Corporation US 130m

European Investment Bank ₤100m

African Development Bank US$110

FMO US$73m

Proparco / AFD US$73m

DEG/Kfw US$45m

Commercial Banks Barclays/ABSA and Standard Chartered.

US$115m

Page 8: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Why the Bujagali Project?

• Demand for power is high

– Inadequate generation capacity

Expensive thermal plants in operation till Bujagali is on line.

– The growth in GDP has been affected by inadequate

power supply.

– Growing demand of about 8% annually.

• Support economic growth & reduce poverty

– Least cost power option

– Reduce tariffs

• Affordable tariffs

• Sustainable

– Reduced subsidies

– Job creation

Page 9: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Project Progress as of June 2009

• Civil works approximately 35 % complete. Power house permanent

works are several months (4-6 months) behind schedule.

• Electro mechanical works progressing according to schedule-

Alstom sub-contractor of electromechanical shows progress as

follows:

– Engineering 91%

– Procurement 75%

– Manufacturing 45%

– Transport 20%

– Overall Project 60

– Switchyard approximately 5%

Transmission Line: First 5 km of T- Line was completed . Foundation

works are ongoing in several Sections of the T- Line. Two sections

of the T-Line still have issues of compensation to be resolved.

Page 10: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Regional Power Trade

• To enhance energy security in the region, there are

plans Under Nile Basin Initiative (NBI) and the Nile

Equatorial Lakes Subsidiary Action Plan ( NELSAP) to

promote regional power trade.

• Main obstacles have been: lack of interconnections

and inadequate power supply. With the construction

of Bujagali and other power projects regional power

trade will be possible.

• Regional Projects under the East African Power

Master plan:

• Uganda-Kenya (220kV, 230km),

• Uganda-Tanzania ((220kV, 510km); and

• Uganda-Rwanda (132kV, 230km).

Page 11: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Existing and planned interconnections

DRC

ZAMBIA

ETHIOPIA

Page 12: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Erection Bay And Gravity Dam Progress as of 02.06.2009

Page 13: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Units 3, 4 & 5 Progress – View From D/S

Page 14: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Gated Spillway – Slabs SBS1, SBS4 & SBS2

A ground condition ( schist ) traverses the path of the spill discharge. Work on this section

was temporarily stopped pending suitable design solution. Three options are available for

consideration .

Page 15: PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO … · 2019-09-02 · HYDRO POWER AFRICA Johannesburg South Africa 28 July 2009 PROGRESS ON THE CONSTRUCTION OF THE BUJAGALI HYDRO

Left Stepped Embankment Dam Construction Progress.

Progress was delayed by slide requiring change of excavation

design , method statement and grouting.

Total Excavation to date = 129,253m3.

Excavation to new design completed after October

2008 landslide.

Jet Grouting Works in progress


Recommended