+ All Categories
Home > Documents > Progress Report from ET-CTS (Expert Team on WIS-GTS Communication Techniques and Structure) Doc. 4.3...

Progress Report from ET-CTS (Expert Team on WIS-GTS Communication Techniques and Structure) Doc. 4.3...

Date post: 11-Dec-2015
Category:
Upload: teagan-spittle
View: 214 times
Download: 0 times
Share this document with a friend
Popular Tags:
15
Progress Report Progress Report from ET-CTS from ET-CTS (Expert Team on WIS-GTS Communication Techniques and (Expert Team on WIS-GTS Communication Techniques and Structure) Structure) Doc. 4.3 (1) Presentation version Doc. 4.3 (1) Presentation version ICG-WIS-6 (Seoul, 22-26 February 2010) Hiroyuki ICHIJO (Co-chair of ET-CTS) Please consider our Earth environment before printing
Transcript

Progress ReportProgress Report from ET-CTS from ET-CTS(Expert Team on WIS-GTS Communication Techniques and (Expert Team on WIS-GTS Communication Techniques and

Structure)Structure)

Doc. 4.3 (1) Presentation versionDoc. 4.3 (1) Presentation version

ICG-WIS-6 (Seoul, 22-26 February 2010) Hiroyuki ICHIJO (Co-chair of ET-CTS)

Please consider our Earth environment before printing

ET-CTS Membership and Key DeliverablesET-CTS Membership and Key Deliverables

Co-chairsHiroyuki ICHIJORemy GIRAUD

7 Core MembersRA I : 1, RA II : 1, RA III : 1

RA IV : 2, RA V : 1, RA VI : 1

20 Associate ExpertsRA I : 4, RA II : 4, RA III : 1

RA IV : 1, RA V : 3, RA VI : 5RAs II & VI (Russia) : 2

Confirm arrangements for consolidation of two IMTN clouds (migration of the current “cloud 1” to the RMDCN)

[Target : Oct 2009]

Guidance on “push” & “pull” technologies for use in WIS, including recommendations on handling of high priority information to support hazard warning

[Target : May 2010]

Publication for consultation on recommendations for changes to TCP/IP practices, including advice on adoption of IPv6

[Target : Jun 2010]

Guidance on administrative and contractual aspects of data communication services for WIS implementation

[Target : Jul 2010]

20 Task Groups20 Task Groups

Key DeliverablesKey Deliverables

Tentative ScheduleTentative Schedule

mid-March 2010: Distribution of drafts developed by task groups within ET-CTS

late April 2010 : Physical meeting of ET-CTS and review of the drafts

May 2010 : Pre-coordination with other OPAG-ISS teams

May to July 2010 : Finalize the ET-CTS report including Recommendations

July 2010 : Submission of the report to ICT-ISS and ICG-WIS

after CBS-ext.2010 : Start of another working cycle with refined TORs

Progress of Prioritized TasksProgress of Prioritized Tasks

Consolidation of two IMTN Consolidation of two IMTN cloudsclouds

Migration process forming WIS core network

IMTNcloud I

IMTNWIS core

network

IMTNcloud II

IMTN

Exeter

SofiaMelbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Network INetwork I

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New DelhiMoscow

Network IINetwork II

Exeter

SofiaMelbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Network INetwork I

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New DelhiMoscow

Network IINetwork II

Consolidation was completed in Nov 2009

Exeter

Sofia

Melbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New Delhi

IMTN cloud

Moscow

RA I

RA II

RA III

RA IV

RA V

RA VI

Exeter

Sofia

Melbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New Delhi

IMTN cloud

Moscow

RA I

RA II

RA III

RA IV

RA V

RA VI

Exeter

Sofia

Melbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New Delhi

IMTN cloud

Moscow

RA I

RA II

RA III

RA IV

RA V

RA VI

Exeter

Sofia

Melbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New Delhi

IMTN cloud

Moscow

RA I

RA II

RA III

RA IV

RA V

RA VI

Exeter

Sofia

Melbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New Delhi

IMTN cloud

Moscow

RA I

RA II

RA III

RA IV

RA V

RA VI

Exeter

Sofia

Melbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New Delhi

IMTN cloud

Moscow

RA I

RA II

RA III

RA IV

RA V

RA VI

Exeter

Sofia

Melbourne

Buenos Aires

TokyoBeijing

Nairobi

Washington

Jeddah

Prague

Toulouse

Dakar Algiers

Offenbach

Brasilia

Cairo

New Delhi

IMTN cloud

Moscow

RA I

RA II

RA III

RA IV

RA V

RA VI

Study of GISC network requirementsStudy of GISC network requirements

Background #1 The Improved MTN (IMTN) is currently operating on a single

coordinated Multi-Protocol Label Switching (MPLS) network. MPLS provides any-to-any connectivity at network level. Since a WIS core network will be established on the IMTN, it is easy to realize the full-mesh topology for synchronization among GISCs.

To minimize duplicated traffic, multicast-oriented architecture on IPv6 is desirable for synchronization. However it is premature at the moment. The current IMTN is on unicast based MPLS. Thus it is expected that traffic on the WIS core network handled by GISCs will considerably increase.

Network capacity of each GISC will have to be expanded in collaboration with others.

GISC

Unicast-oriented network

GISC GISC GISC

Responsibility Area

GISC

Multicast-oriented network

GISC GISC GISC

Responsibility Area

Multicast group

Duplicatedtransmissio

n

Study of GISC network requirementsStudy of GISC network requirements

Background #2 The Appropriate maximum number of GISCs has come up for

discussion repeatedly since the initial stage called as FWIS:

[Extraction from the final report of CBS-ext.02, Annex IV]Several (perhaps four to 10) centres would serve as GISCs. Each

GISC would have a defined area of responsibility. GISCs would usually be located within or closely associated with a centre running a global data assimilation system or having some other global commitment, such as a WMC.

[Extraction from ET-CTS outcome reported to ICG-WIS-3 in 2006]Correlation between the number of GISCs and reasonableness of

full-mesh topology of a WIS core network: From the practical and relative evaluation, the full-mesh can be

appropriate on the assumption that the number of GISCs would be less than 7 inclusive. In case of more GISCs, the full-mesh should be avoided.

However 13 GISCs candidates have been identified as of the end of Nov 2009.

Study of GISC network requirementsStudy of GISC network requirements

Main task To consider required GISC bandwidth on the core network considering not only bulk but also peak traffic

To study smooth evolution process in gradual participation of operational GISCs

Additional task on a possible basis To study further to clarify the appropriate maximum number of GISCs from the practical view of network bandwidth requirements

Study of GISC network requirementsStudy of GISC network requirements

Progress The task group devised an unbalanced model of full-meshed

topology to find out required GISC bandwidth practically. It is to simulate unbalanced conditions between incoming and outgoing traffic, considering the pragmatic case of different data volumes from individual responsible areas.

The group developed a convenient tool for trial calculation for the bandwidth based on the unbalanced model. It is able to calculate the required bandwidth corresponding to total daily traffic for global exchange, adjusting realistic parameters.

Practical required bandwidth will be estimated as long as the daily volume is accurately estimated. It is expected that ET-OI will estimate the daily volumes at present and in five years.

Regarding the maximum number of GISCs, the group will challenge the issue to find an appropriate number from the practical view in the process of the study on the required bandwidth.

Study of GISC network requirementsStudy of GISC network requirements

Architecture and flows

GISC #1

GISC #2

GISC #3GISC #4

GISC #5

GISC #6

GISC #7

AMDCN : Area Meteorological Data Communication Networks

Study of GISC network requirementsStudy of GISC network requirements

Balanced model (Example case of 4 GISCs, total volume of 8GB)

WIS core network

(Full-meshed topology)

Responsible area #1

AMDCN #1

GISC #1

2GB Responsible area #2

AMDCN #2

GISC #2

2GB

Responsible area #3

AMDCN #3

GISC #3

2GB Responsible area #4

AMDCN #4

GISC #4

2GB

2GB2GB2GB

2GB

2GB2GB

Incomingdaily

volume

Outgoingdaily

volume

Necessaryport speed

GISC #1 6 GB 6 GB

Bandwidthappropriatefor 6GB/day

GISC #2 ditto ditto ditto

GISC #3 ditto ditto ditto

GISC #4 ditto ditto ditto

Study of GISC network requirementsStudy of GISC network requirements

Unbalanced model (Example case of 4 GISCs, total volume of 8GB)

Incomingdaily

volume

Outgoingdaily

volume

Necessaryport speed

GISC #1 3 GB 15 GB

Bandwidthappropriatefor 15GB/day

GISC #2 7 GB 3 GB

Bandwidthappropriatefor 7GB/day

GISC #3 ditto ditto ditto

GISC #4 ditto ditto ditto

WIS core network

(Full-meshed topology)

Responsible area #1

AMDCN #1

GISC #1

5GB Responsible area #2

AMDCN #2

GISC #2

1GB

Responsible area #3

AMDCN #3

GISC #3

Responsible area #4

AMDCN #4

GISC #4

1GB1GB

1GB1GB

1GB5GB5GB5GB

1GB1GB1GB5GB

1GB

1GB

Investigation of blog technologiesInvestigation of blog technologies

Progress Japan (JMA) has been investigating usability of blog-based

technologies for notification of priority messages and also GISC synchronization of global data/products in cooperation with Brazil (INPE) and China (CMA).

The following items have already been tested and the empirical outcome was reported at the ET-WISC meeting (2-5 Feb 2010).(1) File synchronization like podcast using a pull-based

protocol for getting web feed of Atom and RSS(2) Notification of priority messages using a push-based

protocol of the Atom Publishing Protocol (AtomPub) for posting blog

Investigation of blog technologiesInvestigation of blog technologies

Empirical outcome(1) Blog technologies are not appropriate for “WIS part A” because

it would be difficult to introduce sharply new technologies into the existing GTS. Also the blog technologies would be not necessarily appropriate for GISC synchronization.

(2) On the other hand, they are very useful for “WIS Part B”. (3) The following usage are desirable:

Data providers provide users with data on a near-real-time basis over the Internet;

Data providers provide users with data at intervals over the Internet;

Data providers receive a priority message from the GTS, and then post it to their blog server on the Internet;

Timely delivery service can also be implemented by "pull" mechanism using the file synchronization of blog technologies.

Development of a list of synchronization protocols among GISCsDevelopment of a list of synchronization protocols among GISCs

ET-CTS will develop a list of protocols for GISC synchronization considering requirements from ET-WISC.


Recommended