Progress Progress
Stage 1 Report – priority locations – Industry View (February 2010)
Stage 2 – deliverability – planning and funding (June 2010)– Engagement – Delivery Group – developers and port interests
Stage 3 – Implementation based on market focused triggers being met
Emerging Themes – locations operating as groups/clusters– timing of installation - earlier focus on some locations– importance of existing infrastructure and strengths – e.g north east
sub-sea and O&M capability
Subsea /
O&M Cluster
Turbine
manufacture,
foundations,
cables
installation
Marine
Component
manufacture,
Installation
Turbine manufacture,
foundations,
installation
Cluster Potential Roles Timing and Market Interest
Forth Tay Cluster Turbine manufacture, foundations, cables and installation
Sustained supply chain interest; early R3 sites (2014 onwards)
Moray Firth Cluster Component manufacture and Installation
Moray Firth Installation timing could be pre 2015;
Wave and Tidal role
West Coast Cluster Turbine manufacture, foundations and installation
Compete for Irish Sea, Timing of STW later (2017 onwards)
Emerging Locations for Emerging Locations for Large Manufacturing Large Manufacturing
Next StepsNext Steps
Stage 2 Report – end June
Investment and triggers for all sites
Operations and maintenance locations
Wave and Tidal needs
Triggered delivery approach and funding
Test and Demonstration Infrastructure Test and Demonstration Infrastructure
Innovation to drive down costs
Marine – EMEC
Wind – Aberdeen Offshore Test Location
Energy Technology Centre – Sub-component testing
Grid – Power Networks Demonstration Centre