+ All Categories
Home > Documents > Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Date post: 30-Mar-2015
Category:
Upload: myra-hocking
View: 215 times
Download: 0 times
Share this document with a friend
Popular Tags:
24
Progress update John Moore John Moore Ian Marr Ian Marr CEO, NYnet CEO, NYnet Project Project Manager Manager NYCC/NYnet NYCC/NYnet
Transcript
Page 1: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Progress updateJohn Moore John Moore Ian MarrIan MarrCEO, NYnet CEO, NYnet Project Project Manager Manager NYCC/NYnetNYCC/NYnet

Page 2: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Areas we will cover• Why are we doing this?• BT rollout• Demand stimulation• Business support• Communications and partnerships• Community broadband• Lessons learnt to date• Challenges to come• What the next few months look like

Page 3: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Reminder of our Vision

Access to high-quality broadbandfor

100% of North Yorkshireby

2017

Page 4: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Problem is ..• Failed market• Digital divide• User frustrationOvercome with ..• Local expertise• UK and EU funding, although State

Aid brings risks

Page 5: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

BT Rollout• Key contract terms

100% access to min 2Mbps 90% access to min 25Mbps Completion by end 2014

• Mostly FTTC• Some FTTP and satellite

Page 6: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

BT Rollout• Headlines

90+ of 690 cabinets completed

20,000+ of 142,000 total premises now able to access superfast speeds

Page 7: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Demand stimulation• Team established• Promoting cabinet upgrades and

community schemes• Not ISP specific• Booklet produced

Page 8: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Demand stimulation• Targeted activity• Nationally, superfast broadband

take-up is 16% after 2 years • SFNY are already getting 8% after

200 days• Our local target is to exceed20%

Page 9: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Business Support (£3M)• Targets– 550 businesses to get 12hrs

support– new jobs created– superfast broadband take-up by

SMEs– increase in GVA

Page 10: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Business Support (£3M)• Intro is through breakfast session• Leading to, eg, cloud computing, social

media and digital marketing master classes. • Plus 1:1 support and a £££ incentive.• For more information: – call: 0845 002 0021 – email: [email protected]

Page 11: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Communications and Partnerships• Website– Postcode searcher– Enquiry email– Community schemes– Business support

• Also …

Page 12: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Communications and Partnerships• Partner briefings – inc public meetings

• Newletters• Press releases• Events

Page 13: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Community broadband• Continuing to support existing

schemes• First ‘Framework’ competition

close to release• Will help inform 10% strategy

Page 14: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Community broadband• 10% options (all likely to require

additional £££’s)•More fibre by BT•Community Wireless•Other technologies (eg satellite)

Page 15: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Lessons learnt to date

• State aid/procurement is complex• BT approach works, but has issues– laws of physics– quality of pre-existing (voice)

networks– split communities/business parks

Page 16: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Lessons learnt to date

• Very wide spectrum of public awareness and understanding• Thirst for Business Support• Demand stimulation boosts take-

up

Page 17: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Challenges to come

• Ensuring BT complete + on time• Outcome of first ‘Framework’

competition• 10% areas– Funding– Technology options

• Meeting public expectations

Page 18: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Next few months• BT will bring a further 600

cabinets on line and lift the total premises passed to 142,000• Complete first ‘Framework’ • Do the next one• Continue to lobby for more funds

Page 19: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Links and ContactsUseful links;SFNY website

www.superfastnorthyorkshire.com

Contacts;Ian Marr [email protected] John Moore [email protected]

Page 20: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

Questions?Questions?

Page 21: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

The basics - FTTC

Fibre to the Cabinet

Page 22: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

The basics - FTTP

Fibre to the Premises

Page 23: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

The basics - CISP

Community Internet Service Provider

Page 24: Progress update John Moore Ian Marr CEO, NYnet Project Manager NYCC/NYnet.

The basics - Satellite

Satellite Internet Service Provider


Recommended