By CHHIENG Pich, Director, DICO National Project Director, TDSP Director, EIF-NIU Progress Update on Trade SWAp , TDSP and EIF
Transcript
Page 1: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

By CHHIENG Pich,Director, DICONational Project Director, TDSPDirector, EIF-NIU

Progress Update on Trade SWAp, TDSP and EIF

Page 2: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

1. Progress Update on TDSP

2. Progress Update on EIF

3. EU Funding Program 2014-2020

4. Seeking SSC approval on revised

budget of GDCE and TTRI projects

Page 3: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

1. Project Development Objectives (PDOs): TDSP will contribute to increase the Royal Government of Cambodia's efficiency in formulating and implementing effective trade policies.

2. Multi-Donor Trust Fund : EU, DANIDA & UNIDO3. Trust Fund Manager : World Bank4. Executing Agency : DICO/MoC5. Board approval date : 07 Jan 20096. Effective date : 09 Mar 20097. Duration : 5 years (until 31 Mar 2012)8. Original budget : US$12,350,0009. Additional budget : US$3,100,00010. First extension : 31 Jan 2014 (22 months)11. Second extension : 31 Mar 2015 (14 months)12. Third extension : 14 Aug 2016 (17 months)13. WB Implementation Support Mission : 27 Oct – 27 Nov 201414. Next Implementation Support Mission: mid Sep 2015

Page 4: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

No Identified Projects # Projects

1. Total project under TDSP 29

2. Projects completed and closed 12

3. Ongoing projects 15

• Projects will be completed and closed by Mar 2015 Implementing Agency Capacity Enhancement Program (RSA) – (completed) Reviewing commercial laws (DNLC) – (completed) Support drafting E-commerce Law (DLAD) – (completed) Rules of Origin (DMUL) – (completed) MoC Core HR Function (DoP) – (completed) Strengthen Capacity of ISC (ISC-MIH) – (completed) Support to G-PSF (CCC) – (completed) Better Quality of Fish and Fishery Products (FiA-MAFF) – (completed)

8

• Projects will be completed and closed by Aug 2016 ASYCUDA World System (GDCE-MEF), ICT Master Plan – Automation of Certificate of Origin (MoC), Automation of Business Registration (BRD), Automation of SPS Certificate (GDA-MAFF), Trade Training and Research Institute (TTRI-MoC), Drafts of Rice Standards – Certification Schemes for Rice (Accreditation System) (ISC-MIH), Development of a stronger National system for IP generation, protection, administration

and enforcement (DIPR), Support for the Arbitration Council and Dispute Resolution in Cambodia Strengthening the Operational Capacity of the National Commercial Arbitration Centre

9

Page 5: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

Cumulative Expenditure $10,799,666

(70%)

Funds Required for DICO Operations & including various consultants

$1,069,955(7%)

Balance Commitment under all MOUs including GDA, TTRI, ACF, NCAC & ICT but excluding the closed

projects $ 3,580,379 (23%)

TDSP Funds PositionAs of 30th June 2015

(Unaudited - Expressed in Percentage of the Total Grant Amount of US$ 15.450 million)

• We have $4,650,334 to spend in the next 14 months,

• We need to spend $332,167 each month,• Or $930,067 each quarter

Page 6: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

TDSP FundActual Disbursement against Projected Disbursement by Quarter, 2004/2015

As of 30 Jun 2015

0

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

Q2/2014 Q3/2014 Q4/2014 Q1/2015 Q2/2015

593,715 592,966

798,281

551,935

400,259361,490

482,675

653,425

586,610

262,511

Disbursement Projection Actual Disbursement

61%

81%

82%

106%

65%

Page 7: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

TDSP FundDisbursement by Year, As of 30th June 2015

(Expressed in Percentage of the Total Grant Amount of US$ 15.450 million)

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

2009 2010 2011 2012 2013 2014 2015

116,584615,558

1,674,943

2,751,160

2,087,570

2,704,645

849,121

17.5%

5.5%4%

0.75 %

10.8%

17.8%

13.5%

NOTE: *. Cumulative Disbursement = USD 10,799,666**. Cumulative Disbursement as a Percentage of Total Grant = 70%

Page 8: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1,600,000

Q3/2015 Q4/2015 Q1/2016 Q2/2016 Q3/2016

1,076,144

864,387

1,460,262

703,375546,166

TDSP FundFuture Disbursement Projection by Quarter (2015/2016)

Estimated Disbursements of Grant Balance – US$ 4,650,334

Page 9: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.
Page 10: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

EIF Tier 1 (Phase I and II)

1. Starting date: Feb 2010

2. Closing date: Mar 2016

3. Net amount of Phase 1: 709,900

4. Total amount of Phase 2: 584,000

5. Total amount (P1+P2): 1,293,900

6. Total fund received (P1+P2): 1,174,606

7. Total fund disbursed: 1,071,770

EIF Tier 2 (CEDEP I and II)

1. Start date: Jul 2012

2. Closing date: Mar 2016

3. Total fund received: 225,000

4. Total fund disbursed: 91,226

As of June 30, 2015 (CEDEP I – US$ 84,090 and CEDEP II – US$ 7,136)

Page 11: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

-

10,000

20,000

30,000

40,000

50,000

60,000

Q 1/2014 Q 2/2014 Q 3/2014 Q 4/2014 Q 1/2015 Q 2/2015

57,166 57,618

22,381

49,173

37,517 43,825

As of June 30, 2015

Page 12: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

-

50,000

100,000

150,000

200,000

250,000

300,000

350,000

2010 2011 2012 2013 2014 2015

12,844

192,991

313,290 284,826

186,475

81,342

As of June 30, 2015 – Total Disbursement – US$ 1,071,770 or 83%

Page 13: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

-

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

High Value Silk/ITC Milled Rice/IFC M&E/DICO

$ 793,335 or 79 % (As of Apr 20, 2015)

$ 297,365 or 27 %(As of Mar 31, 2014) $ 84,090 or 29%

(As of Jun 30, 2015)

Total Expenditure for all components was $1,174,790 or 49%

Page 14: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

-

50,000

100,000

150,000

200,000

250,000

300,000

Cassava/UNDPMarine FisheriesProducts/UNIDO ACAC/Shift 360

M&E/DICO

$ 82,778 or 8%(As of Jul 31, 2015)

$ 253,185 or 26% (As of Jun 30, 2015)

0%$ 7,136 or 2%

(As of Jun 30,2015)

Total Expenditure for all components was $343,099 or 10.4%

Page 15: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

EU Funding Program (MIP)Multi-Annual Indicative Program 2014-2020

Fund for Bilateral: EUR 410 million Fund for Regional: EUR 50 million

• Focus sectors:• Agriculture/national resources management: 144m• Education/skill: 140m• Governance and Administration: 120m• Support measure: 6m

• Three expected results: Improved business enabling environment for the agriculture

and NRM related sectors, through the improvement of existing national capacities, policies and regulations which support the development of sustainable agricultural and forestry use and commercialisation, stimulate innovation and private sector investment, and ensure protection of natural resources.

Strengthened value chains, including increased productivity, processing efficiency, improved product quality and increased market competitiveness in domestic and export markets that result in increased rural incomes and employment creation.

Empowered local communities to participate in the conservation and management of agriculture and natural resources including sustainable forest management (FLEGT) through the improvement of national and sub-national capacities, regulations and law enforcement.

• Identification mission: May-Jun 2015• Formulation mission: Q4 2015• Programs to start by early 2017

• Focus Areas: support the ASEAN Economic Integration beyond 2015:

Support improvements in customs, transit, standards, services, investment, food safety, IPR.

Narrowing the development gaps in the public administrations of CMLVs

Further integration into the global economy of ASEAN Member States

Euro 35 million for ASEAN Secretariat Euro 15 million for Cambodia, Laos PDR and Myanmar Will include regional programs (ECAP IV, ARISE) and national

envelopes (Cambodia)

• Identification mission: finalised in January 2015• Evaluation and Formulation mission: 22-26th June 2015 • Programs to start: Q4 2016 • Exploring new modalities for implementation, building on what has

been achieved, more RGC ownership.

• Any project must be based on Rectangular Strategy, NSDP, CTIS, IDP• This program will approve by EU Parliament in Sep 2015

Page 16: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

The 1st Mission took place (Mar 29 - Apr 11, 2015), Debriefing of the 1st mission findings organized on 10 April 2015, Preliminary list of possible additional TA needs has been prepared

and shared with key stakeholders during the debriefing meeting, Inception Report submitted to MoC/DICO on 19 April 2015, List of the Ten Clusters was endorsed by 21st SSC Meeting on 03

Jun 2015, and prioritized by MoC Management on 24 Jun 2015 (MoC Weekly Meeting),

The second mission is to coincide with EU mission, which is tentatively scheduled in early Oct 2015,

Page 17: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

1. Trade Policy, Sector Policy, Legal and Regulatory Reform: Formulate Trade Policy in view of AEC, RCEP, TPP and erosion of preferences including RoOs; develop sector policies (e.g. cassava, fish, rubber, others); identify sector-specific NTMs; implement the Government’s 2012-2015 Work Program on Legal Reform, including key reforms identified in the Trade SWAp Road Map 2014-2018.

2. Trade Facilitation and Transport Logistics: Establish the NSW including automation of trade related documents; respond to the Bali Agreement on Trade Facilitation; develop, adopt, implement a national transportation logistics plan; improve cross-border transit agreements; improve and enforce road transport regulations; encourage modernization of road transport fleet.

3. SPS and Other Quality Systems for Trade: Complete key legal reforms in SPS; develop capacity of key agencies not only in Phnom Penh but in field offices as well especially in areas of surveillance and inspections; promote a culture of SPS including through encouraging agro exporters to adopt SPS standards required by importing markets, develop various quality systems to support export sectors (e.g. rubber, silk.)

4. Private Sector Structuring: Strengthen sector associations and private sector in rice, cassava, fisheries, rubber, and hospitality including ability of sectors to articulate positions and engage government through G-PSF or other venues; strengthen and promote branding through sector-specific collective marks, GIs, Quality Seals, other means as well as through “Made in Cambodia” branding; strengthen export promotion capacity including through capacity building in sector associations.

5. Development of Inclusive Value Chains: Build capacity of priority export sectors identified by Government in the Trade SWAp Road Map 2014, including in light manufacturing, agro-processing, rubber and tourism.

6. Trade Mainstreaming and Management of Aid for Trade: Continue to build capacity for monitoring and communicating Trade SWAp as a program instead of a collection of projects; continue to mobilize and coordinate AFT support; strengthen capacity of MoC and other line ministries to participate in SWAp; improve fiduciary management of AFT projects using different disbursement modalities. Deepen trade build trade-related training and research capacity in Government;

7. Skills for Exports: Address the lack of skilled technical personnel as a result of the absence of a robust TVET structure is a serious bottleneck in Cambodia’s ability to move up value chains; address the lack of well-trained engineers (mechanical, structural, agricultural, chemical, biologist, etc.); strengthen collective bargaining environment and dispute resolution mechanisms.

8. Investment Environment, Integration in Regional Value Chains, Backward Linkages: Complete supportive legal framework including encouraging development/deepening of backward linkages in garment, bicycles, footwear, hospitality (horticulture); diversify investment in regional and global value chains beyond garment, footwear and bicycles; develop investment promotion capacity including at provincial level.

9. Rural Development for Exports including Extension Services, Cooperatives Development, Surveillance Services: Develop structured value chains between farmers and semi-agro-processors or agro-processors through farmers groups, cooperatives, contract farming arrangements, etc; strengthen quality of seeds, seedling, and other plantings;

10. Access to Finance: Address the lack of access to working capital and trade finance especially for SMEs and other small producers/exporters as it is a significant constraint to export development.

Page 18: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

Seeking Endorsement from SSC

1. Trade Training and Research Institute (TTRI/MoC) E-Learning E-Library

2. ASYCUDA World System Project (GDCE/MEF) Data Center Connection and expertise SoClass License

Page 19: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

1. Trade Training and Research Institute (TTRI/MoC)

1. Subject: Requests for budget increase 2. Justification:

– TTRI through TDSP will develop 16 training curriculums, these resources will make bigger impact if accessible through E-learning system (similar case for WTO training resources).

• E-learning will benefit to MOC & PDoCs staff, students, and entrepreneurs.

– TTRI/MoC will be equipped with physical books and electronic resources (E-library).

3. Request:– Request additional budget in amount of $175,000 for the

project implementation (Revised total budget: $675,000)

Page 20: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

2. ASYCUDA World System Project (GDCE)1. Subject: Requests for additional budget for Data Center and

continuation of some components. 2. Justification:

– ASYCUDA project is rated high satisfactory under TDSP. This project is very important to improve LPI. Project to continue until June 2016, extension of IT support and WAN/Internet connection are needed;

– Geographical expansion (51 sites currently) and many new feature functions of AWS require upgrading the capacity of Data Center (including Data Recovery Storage);

– While UNCTAD updating the software, SoClass license must be upgraded also.

3. Request:– Request additional budget in amount of $320,000 for implementing

Data Center and cost-extension activities (Revised total budget: $1,931,058 ).

Page 21: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.

រកសងពាណជ�កម�

នាយកដ� នសហរ�តបត�ករអន�រជាត

ឣ‍សយដ‌� ន: ឡ�តេលខ ១៩-៦១ វ�ថរកសងពាណជ�កម�

(១១៣េប), ភមទកថ‌� , សង‌� តទកថ‌� , ខណ� ែសនសខ,

រ‌ជធានភ�េពញ ១២១០២

ទរសព�/ទរសារៈ ០២៣-៨៦៦-០៧៤

Email: [email protected]

www.moc.gov.kh | www.moc.gov.kh/tradeswap

Ministry of CommerceDepartment of International Cooperation

Lot 19-61, MoC Road (113B)Phum Teuk Thla, Sangkat Teuk ThlaKhan Sen Sok, Phnom Penh 12102

Cambodia

Tel/Fax: 023-866-074

Email: [email protected]

www.moc.gov.kh | www.moc.gov.kh/tradeswap

Page 22: Progress Update on Trade SWAp, TDSP and EIF · Progress Update on Trade SWAp, TDSP and EIF. 1. Progress Update on TDSP 2. Progress Update on EIF 3. EU Funding Program 2014-2020 4.