+ All Categories

Project

Date post: 21-Nov-2014
Category:
Upload: notycolleen
View: 600 times
Download: 3 times
Share this document with a friend
Popular Tags:
105
Executive Summary 1
Transcript
Page 1: Project

Executive Summary

1

Page 2: Project

This project is done for the partial fulfilment of my curriculum of BBA (2008-2010)

at Ideal Institute of Management and Technology, Indraprastha University.

The training was conducted in KRIBHCO, Noida. Starting with the company profilr

i.e. introduction of KRIBHCO, its mission, vision, objectives, performance highlights

etc. Then there is an overview of the project tropic i.e. Training and Development &

Training and development programme in KRIBHCO.

A simple random technique is used for sampling. The sampling frame consists of the

employees working in the organisation. For the collection of primary data, a

questionnaire is made and secondary data is also collected from the HR folder of the

organisation.

The objective is to know how training and development process is carried out in

KRIBHCO. The final conclusion is that training and development is important for any

organisation.

2

Page 3: Project

INDEX

3

Page 4: Project

TOPIC PAGE NO.

Company Profile 5-25

Theoretical Presentation of the Topic 26-45

Research and Methodology 46-48

Analysis and Interpretation of Data 49-65

Findings, Suggestions, Conclusion and Limitations

66-70

Annexure 71-74

Bibliography 75-76

4

Page 5: Project

COMPANYPROFILE

5

Page 6: Project

Salient Features of Kribhco

17th April, 1980 : kribhco was incorporated

5th February, 1982 : Foundation stone laid at Hazira(Gujrat)

November, 1985 : Urea production started

May, 1991 : Seed production started

August, 1995 : Bio-Fertilizers production started

July, 2005 : OMIFCO started commercial production And 50% marketing of produced urea in India by KRIBHCO.

July, 2008 : Acquisition of Shahjahanpur fertilizer complex

Plant Capacity Day Annum

Ammonia

Urea

2*1520 MT

4*1310 MT

1003200 MT

1729200 MT

Project cost of Hajaria : Rs. 890 crore

6

Page 7: Project

Introduction of KRIBHCO

Krishak Bharati Cooperative Limited (KRIBHCO), a premier Cooperative Society for manufacture of fertilizer, registered under Multi-State Cooperative Societies Act–1985, was promoted by the Govt. of India, IFFCO, NCDC and other agricultural Cooperative societies spread all over the country.

KRIBHCO has setup a Fertilizer Complex to manufacture Urea, Ammonia & Bio-fertilizers at Hazira in the State of Gujarat, on the bank of river Tapti,  15 Kms from Surat city  on Surat – Hazira State Highway.

7

Page 8: Project

KRIBHCO plant at Hazaria.

Late Smt. Indira Gandhi, former Prime Minister of India laid the Foundation Stone on February 5, 1982.

The trial production commenced from November, 1985 and within a very short time of 3 months, the commercial production commenced from March 01, 1986.  Since then, it has excelled in performance in all areas of its operations.

Hazira Fertiliser Complex has 2 Streams of Ammonia Plant and 4 Streams of Urea Plant. Annual re-assessed capacity for Urea and Ammonia is 1.729 million MT and 1.003 million MT respectively, the total Project cost was Rs. 890 crores as against the estimated cost of Rs. 957 crores. This shows a saving of Rs. 67 crores (approximately 7%) in Capital Cost of the Project.

Ammonia plant

8

Page 9: Project

Urea plant

Bio fertilizer plant of 100 MT per year capacity was commissioned at Hazira in August, 1995.  KRIBHCO has also completed the installation of an expansion of the Bio-Fertiliser plant with an additional capacity of 150 MT and the same was commissioned in December, 1998.

Ten Seed Processing Plants are also in operation in various states.

9

Page 10: Project

MISSION

To act as a catalyst to agricultural and rural development by selecting, financing and managing projects that are both socially desirable and commercially profitable.

VISION

To be a  world  class  organization  that represents the farmer community and maximizes returns to them  through specialization  in  agricultural  inputs   and  products  and  other  diversified   businesses   that   maximize  stakeholder  value.

10

Page 11: Project

OBJECTIVES

To strengthen Cooperative System. To enhance the  urea installed capacity, maintaining  its market share.

To ensure optimum utilisation of existing plant and   machinery.

To diversify into other core sectors like power, port, infrastructure, rural retail etc.

Transfer of technology for modern farming and improving farmer’s livelihood.

To educate and train farmers, provide free testing facilities for soil nutrients and irrigation water.

Sustainable rural development through Gramin Vikas Trust.

11

Page 12: Project

PERFORMANCE HIGHLIGHTS

Highest Total Fertilizers Sales(Previous best was 37.76 lakh MT of urea during 2008-2009)

40.51 lakh MT

Highest Imported Fertilizers Handled(Previous best was 10.45 lakh MT during 2006-2007)

12.12 lakh MT

Highest Seed Sales(Previous best sales was 1.96 lakh Qtls during 2008-2009)

2.22 lakh Qtls

Highest KBSKs Turnover(Previous best was Rs. 63.14 crore during 2008-2009)

Rs. 74.97 crore

Highest Operational Profit of Traded Products(Previous best was Rs. 3.80 crores during 2008-2009)

43.31 crores

Highest Daily Urea Production on 13.11.2009(Previous best was 5564 on 28.10.2009)

5638 MT

Highest Daily Ammonia Production on 28.12.2009(Previous best was 3433 MT on 25.12.2009)

3452 MT

Highest Monthly Ammonia Production in December, 2009(Previous best was 104444 MT in October, 2009)

104740 MT

Highest Monthly Urea Production in December, 2009(Previous best was 166960 MT in October, 2009)

167901 MT

12

Page 13: Project

PRODUCTION PERFORMANCE

Urea & Ammonia at Hazaria Plant:-

During the year 2009-10, KRIBHCO produced 17.80 lakh MT of urea and 11.10 lakh MT of ammonia which corresponds to capacity utilization of 102.94% and 110.65% respectively. KRIBHCO also produce 3556.7 thousand NM argon .

Seed Multiplication Programme and Marketing of Hybrid Seed:-

Seed is the basic and most critical input for sustainable agriculture. KRIBHCO continues to produce certified seeds of Cereals (Paddy, Wheat, Barley and Maize), Pulses (Gram, Pea, Arhar, Moong, Lentil), Oilseeds (Soyabean, Mustard, and Castor) and Fodder (Guar) at its ten most modern Seed Processing Plants located at Abohar (Punjab), Aligarh (UP), Deaws (MP), Gajraula (UP), Himatnagar (Gujrat), Hissar (Haryana), Jangipur (UP), Moth (UP), Kota (Rajasthan) and Shahjahanpur (UP). The total production capacity of these plants is 1.90 lakh quintals per annum. The society is planning to establish four more modern seed processing Plants in the states of UP (Gorakhpur and bulandshahr), Punjab (Ludhiana) and Rajasthan (Hanumangarh). During 2009-2010, the society sold 2.22 lakh quintals of certified seed of various crops and varities which contribute 1.02% in the national seed availability. The society plans to produce 3.45 lakh quintals of seed during 2010-2011.

Considering the high potential of Hybrid seed to improve plant vigour and increased yield, KRIBHCO plans to market Hybrid seeds if major crops i.e. 2 lakh packets of BT Cotton, 20,000 quintals of hybrid Paddy and 3,000 quintals of hybrid maize through KRIBHCO Marketing network.

Bio-Fertilizers:-

Bio-Fertilizers are the low cost source of plant nutrients, eco-friendly and have supplementary role with chemical fertilizers. KRIBHCO has been producing and marketing five bacterial strains of Bio-fertilizers i.e. Rhizobium, Azotobacter, Acetobacter, Azospirilum and PSM (Phosphate Solubilising Micro-Organism) in three plants at Hazira (Gujrat), Lanjha (Maharashtra), and Varaasi (UP) with combined capacity of 550 MT. During the year 2009-10, KRIBHCO Produced 953 MT and sold 922 MT of Bio-fertilizers, which is ever highest.

13

Page 14: Project

MARKETING ACTIVITIES

The society has made notable achievements in marketing fronts, establishing sales records for five consecutive years. The society recorded sales of 18.11 lakh MT of KRIBHCO urea during the year.

Apart from marketing its own products, society also markets Kribhco branded urea produced by its joint venture subsidiary KRIBHCO Shyam Fertilizer Ltd (KSFL) and granulated urea provided by its international joint venture company Oman India Fertilizer Company (OMIFCO). Sales of KSFL urea touched 8.88 lakh MT and granulated urea of OMIFCO 10.77 lakh MT during 2008-09, thus recording a total urea sale by society of 37.76 lakh MT.

Society’s products are sold through numerous cooperative/institutional distribution channels, Apex federation as well as direct sale to Village Level Socities/Nodal points in many states throughout the country such as Uttar Pradesh, Uttrakhand, Punjab, Haryana, Gujrat, Madhya Pradesh, Rajasthan, Maharashtra, Andhra Pradesh, Karnataka, Tamil Nadu, Pudducherry, Kerla, Bihar, Jharkhand, Orissa, Chattisgarh and West Bengal.

14

Page 15: Project

INVESTMENTS MADE BY KRIBHCO

Oman India Fertilizer company (OMIFCO):-

KRIBHCO is one of the sponsors of Oman India Fertilizer Company(OMIFCO) with equity investment of US$ 69.5 million (Equivalent to INR 328.53 crore) representing 25% of paid up equity capital of OMIFCO. OMIFCO has a capacity of 16.52 lakh MTPA of granular urea and 11.9 lakh MTPA of ammonia. A highly skilled workforce from KRIBHCO is participating directly in operation and maintenance of the project under a “Personal Supply Agreement”.

OMIFCO has produced 20.8 lakh MT urea, at a capacity utilization of 122% during the financial year 2008-09. KRIBHCO is handling and marketing 50% of the urea produced by OMIFCO.

KRIBHCO Shyam Fertilizers Limited (KSFL):-

Shahjahanpur Fertilizer Complex acquired by KRIBHCO through its Joint Venture Company “KRIBHCO Shyam Fertilizers Limited (KSFL)” in 2006, has annual production capacity of 8.64 lakh MT of KRIBHCO branded urea. KRIBHCO has 85% equity with entire management control of the company and marketing rights of entire produce. During the year 2008-2009, 8.88 lakh MT of KSFL urea was sold by the society. The company achieved the date of zero inventory and zero dues as on 31.03.09, a unique achievement in fertilizer sector.

Gujrat State Energy Generation Limited (GSEG):-

Gujrat State Energy Generation Limited(GSEG) is a joint venture company with Gujrat State Petroleum Corporation Limited (GSPCL), other Gujrat Government companies KRIBHCO and GAIL (India) Ltd. The society has invested Rs. 80.68 crore towards equity of GSEG. GSEG is operating a 156 MW natural gas based combined cycle power plant at Mora, district Surat, Gujrat. GSEG is implementing 350 MW expansion project at a cost of Rs. 1160 crore.

KRIBHCO Infrastructure Limited (KRIL):-

KRIBHCO has incorporated a wholly owned subsidiary under the name of KRIBHCO Infrastructure Limited (KRIL) for undertaking Logistics Business and other infrastructure project. Action has been initiated for setting up of Inland Container Depot (ICD)/Container Freight Station (CFS) at Hazira and other locations.

KRIL has entered into a join venture with Continental Warehousing Corporation Limited (CWCL), a NDR group of companies to set up Rail linked ICD/CFS at various location in the country. Presently ICD are being planned at Ahmadabad, Hyderabad, Ludhiana, Mumbai and Panipat.

15

Page 16: Project

Urvarak Videsh Limited (UVL):-

UVL is a joint venture company set up by KRIBHCO, National Fertilizers Limited and Rashtriya Chemicals & Fertilizers Limited with equal equity participation. UVL has been mandated by GOI to take necessary step for revival of Barauni Unit of Hindustan Fertilizers Corporation Limited. Various pre-project activities are being carried out by UVL to explore the possibilities to set up a new state of the art of Ammonia-Urea plant at Barauni.

Project under implementation:-

Revamp of existing Ammonia Urea Fertilizer Complex-

KRIBHCO is implementing the revamp project at Hazira to increase the Plant capacity alongwith possible energy reduction at an estimated cost of 1301 crore. The revamp of the plant would enhance the capacity of existing Ammonia Plants from 10.03 lakh MTPA to 12.47 lakh MTPA and Urea Plants from 17.29 lakh MTPA to 21.95 lakh MTPA. The production from the revamped Plant is expected during the last quarter of 2011.

Jetty at Hazira (Surat)

KRIBHCO has initiated revival of its jetty at Hazira and has signed license agreement with GMB for operations as private jetty for own as well as third party clean cargo. Jetty has competitive advantage of rail/road link for faster evacuation.

Project under consideration:-

Hazira Fertilizer Phase II-

The society tends to set up an additional stream of Ammonia-Urea plant at its existing fertilizer complex at Hazira, Surat. Society is in the process of discussion with gas supply agencies to get desired quantity of gas for the project. Suitable deciscion would be taken after availability of natural gas/RLNG on long terms basis is firmed up.

16

Page 17: Project

GRAMIN VIKAS TRUST

Empowering rural communities

Promoted Gramin Vikas Trust (GVT), an independent legal entity,as a non profit, rural development trust. The trust is operating in Madhya Pradesh, Rajasthan, Gujrat in western India and Orissa, Jharkhand, Chhattisgarh abd West Bengal in the Eastern India.

The Trust has been a pioneer in the field of collaborative research in agriculture with academic institutions and communities as partners. It has developed close links with Government of India, Stae Governments, NGOs, Research Institutions and international organizations. Partnerships are ongoing with EU and CAZS, Bangor University, UK.

GVT through its watershed projects has brought nearly 34,000 hectares area for treatment and covered nearly 69,000 households in the targeted areas. The trust has been piloting 5 agriculture innovation projects funded under NAIP. Establishing 14 Homestead Farming projects (WADI) through funding by NABARD for generating income. The Trust is providing skill up-gradation training to tribal migrants in order to up-grade their existing capacity for increased earnings. A fully equipped and residential National Livelihood Resource Institute (NLRI) at Ratlam (M.P.) is also established for educating farmers.

17

Page 18: Project

FINANCIALS AT A GLANCE

Net Worth:-

Net Worth (sometimes called net liabilities) is the total assets minus total outside liabilities of an individual or a company.The Net Worth of Kribhco has increased in the year 2009-2010. It has increased from Rs. 2549.42 crore in 2008-2009 to Rs. 2697.13 crore in 2009-2010.

Sources of income:-

Income sources explain the basic ways of earning money and about multiple sources of income. Sources of income of Kribhco can be explained from the following chart:-

18

Page 19: Project

19

Page 20: Project

Financial Performance:-

The society has achieved excellent financial results for the financial year 2009-2010.It has Pre-Tax Profit of Rs. 252.77 crore during the year and Profit after Tax is Rs. 228.17 crore.

Dividend:-

The Board of Directors of the society have recommended for the sixth consecutive year, the maximum permissible dividend of 20% on the paid-up share capital. The proposed dividend is paid on pro-rata basis to the eligible shareholders whose names stood in Membership Register of the society as on March 31, 2010. Accordingly, the amount of proposed dividend outgo will be Rs. 77.67 crore.

20

Page 21: Project

CORPORATE SOCIAL RESPONSIBILITY

Krishak Bharati Coopertive Limited (KRIBHCO) is the world’s premier fertilizer producing cooperative having outstanding track record to its credit in all spheres of its activities. KRIBHCO has fully imbibed the cooperative philosophy and has made sustained efforts towards promoting the cause of modern agriculture and agriculture cooperatives in the country.

Having its genesis in farmers’ cooperatives, social development and humane facets have always been of prime focus in its growth and philosophy – an organisation which owes its existence to the farmers, by the farmers and for the farmers of this great country.

SERVICES TO COOPERATIVES AND FARMERS

The Society since inception has made vigorous efforts towards the development of farm technologies and other welfare schemes for upliftment of the farming community. Over 1600 programmes on crop seminars, farmers meetings, block demonstration, field days, Kisan Melas, farmers visit, agriculture campaigns health checkup campaigns, veterinary health check up camps and income generation programmes etc. have been conducted which have benefitted about 2.5 lac farmers across the country.

Around 400 programmes on cooperative conference, workshops and state consultative committee meetings have been organized with a view to strengthen the cooperative system.

A variety of facilities like farm implements, furniture, technical assistance towards improvement in godown facilities etc. are being provided to the economically weaker societies.

Around 50,000 soil and water samples have been tested and recommendations made available to the farmers to improve and enhance their produce.

Krishak Parivar Sangams have been organized in 14 states on the theme dry land farming and farm technology.

KRIBHCO has established Krishi Paramarsh Kendra at its corporate office for facilitating farmers in providing information and advise on micro nutrients soil testing, soil improvement, latest farm technology through internet and also KRIBHCO Kisan Helpline.

SEED MULTIPLICATION PROGRAMME

21

Page 22: Project

With a view to provide quality certified seeds of main crops to the farmers, KRIBHCO has established most modern seed processing plants situated in 9 states. From a modest production of 2,982 Qtls of quality seeds in 1991-92, KRIBHCO today provides 1.54 lakh Qtls of the quality seeds to the farmers annually.

CORPORATE GOVERNANCE

Ethical business conduct has been the endeavour of the society for being a responsible corporate citizen. This is achieved by society through-

Inculcating financial propriety. Adhering to national policy and objectives.

Maintaining discipline in financial reporting standards.

Striving to support a competitive environment.

Providing proactive actions in achieving the goals set by the Government of India.

Commitment for preserving environment.

Availability of quality products to the farmers of the nation.

Adhering to regulatory compliance mechanism.

22

Page 23: Project

ENVIRONMENT POLICY

KRIBHCO has ever been eco-friendly and has always cared for the preservation and improvement in the environment.

More than Rs.19 Crores has been spent on Pollution control systems, most of which has been on in-built systems to control the pollutants at source.

Quality of gaseous and liquid effluents is continuously monitored and is maintained better than the standards prescribed by pollution Control Boards.

KRIBHCO has gone way ahead  in  terms of water conservation by gradual reduction in water consumption and by implementing various effluent treatment and recycling schemes.

The discharge of the effluent is ZERO due to evaporation from effluent ponds. KRIBHCO has also developed an extensive green belt in and around the plant

and township by planting more than 3 lakh trees and around 100 acres of lush green lawns.

23

Page 24: Project

MILESTONES/RECORDS

Winning Fresh Bouquets Year After YearA saga of glorious "Firsts" from day one

One of the World's largest and most modern fertiliser plants in the Cooperative sector.

First to achieve A record capacity utilisation in the first year of commercial production - 93.5% and 97.4% for Ammonia and Urea plants.

First in the country to achieve highest net profit of Rs. 126.80 Crores in the year 1987-88 by any fertilizer organisation.

Has achieved 30 Million of Urea production on 15.08.2004 milestone within a short period of 18.7 years from commecement of production.

Has achieved 30 Million tonnes of Ammonia production on 19.03.2006 within a period of 20.3 years from commencement of production.

AWARDS & HONOURS

INDIRA GANDHI RAJBHASHA First Prize for the year 2007-2008 by Official language Department, Ministry of Home Affairs, Government of India.

Society was conferred “FAI Award” on “Production, Promotion and Marketing of Bio-fertilizers” for 2009. By Hon’ble Union Minister of Chemicals & Fertilizers Shri M.K. Alagiri.

NPC Productivity Award (Agriculture) 2006-2007 for “Second Best Productivity Performance of Bio-fertilizer” has been to KRIBHCO in 2009.

Awarded “Sarvotam Stall Puruskar-2010” on farm technology transfer at national level Krichi Vigyan Mela in Pusa, New Delhi.

“In-house Magazine-Kribhco News” was awarded 3rd prize by Public Relation Society of India in December’09.

First Prize (RCF Award in Production & technology) for “Best Article” published in Fai’s Indian Journal of Fertilizers was awarded to an executive.

“Shriram Award in Marketing” was awarded to two executives for their paper published in Fai’s Indian Journal of Fertilizers” on Agri-business.

24

Page 25: Project

SWOT Analysis of KRIBHCO

STRENGTH

• Ready market through cooperatives, as they are also the stakeholders. 

• Manpower that is experienced and qualified.

• KRIBHCO have high turnover. 

• Adequate financial resources. 

• Harmonious industrial relations.

• Proven technology and product quality. 

• Consistently good performance and the availability of substantial reserves. 

• Professional management 

• A good corporate image.

WEAKNESS

• Single product line and single plant at single location. 

OPPORTUNITIES

• Buoyant product demand.

• Growth prospectus bright for immediate future.

• Liberal economy policies. 

25

Page 26: Project

• Scope of joint venture. 

• Prospect for diversification

THREATS

• Inadequate availability of raw material.

• Development of substitute products.

26

Page 27: Project

Theoretical Presentation of the

Topic

27

Page 28: Project

INTRODUCTION OF TRAINING & DEVELOPMENT

TRAINING AND DEVELOPMENT is a subsystem of an organization. It ensures that randomness is reduced and learning or behavioral change takes place in structured format.

TRAINING AND DEVELOPMENT DEFINED

It is concerned with the structure and delivery of acquisition of knowledge to improve the efficiency and effectiveness of organization. It is concerned with improving the existing skills and exploring the potential skills of the individual i.e. upgrading the employees’ skills and extending their knowledge. Therefore, training is a key to optimizing utilization human intellectual technological and entrepreneurial skills

Training and Development referred to as:

Acquisition and sharpening of employees capabilities that is required to perform various obligations, tasks and functions.

Developing the employee’s capabilities so that they may be able to discover their potential and exploit them to full their own and organizational development purpose.

Developing an organizational culture where superior-subordinate relationship, team work, and collaboration among different sub units are strong and contribute to organizational wealth, dynamism and pride to the employees.

Development defined

It helps the individual handle future responsibilities, with less emphasis on present job duties.

Introduction of training

It is a learning process that involves the acquisition of knowledge, sharpening of skills, concepts, rules, or changing of attitudes and behaviors to enhance the performance of employees.

NEED FOR TRAINING AND DEVELOPMENT

1) Job Requirements – Employees selected for a job might lack the qualifications required to perform the job effectively. New and inexperienced employees require detailed instructions for effective performance on-the-job. In some cases, the past experience, attitudes and behaviour patterns of experienced personnel might be inappropriate to the new organisation. New

28

Page 29: Project

employees need to provide orientation training to make them familiar with the job and the organization.

2) Technological changes – Technology is changing very fast. Now automation and mechanisation are being increasingly applied in offices and service sector. Increasing use of fast changing techniques requires training into new technology. For instance, staff in public sector bank are being trained due to computerization of banking operations. No organization can take advantage of latest technology without well-trained personnel. New job require new skills. Thus both old and new employees require training.

3) Organizational viability – In order to survive and grow, an organization must continually adapt itself to the changing environment. With increasing economic liberalization and globalization in India, business firms are experiencing expansion, growth and diversification. In order to face international competition, the firms must upgrade their capabilities. Existing employees need refresher training to keep them abreast of new knowledge. Training programmes foster the initiative and creativity of employees and help to prevent obsolescence of skills. An organization can build up a second line of command through training in order to meet its future needs for human resources. Trained staff is the most valuable asset of a company.

4) Internal mobility – Training becomes necessary when an employee moves from one job to another due to promotion and transfer. Employees choosen for higher level jobs need to be trained before they are asked to perform the higher responsibilities. Training is widely used to prepare employees for higher level jobs.

Thus there is an ever present need for training people so that new and changed techniques may be taken advantage and improvements in old methods are effected. Need for training has increased due to growing complexity of jobs, increasing professionalisation of management, growing uncertainties in the environment, global competition, growing aspirations, vast untaped human potential, ever-increasing gap between plans and results and sub-optimal performance levels.

INPUTS IN TRAINING AND DEVELOPMENT

Any training and development programme must contain inputs which enable the participants to gain skills, learn theoretical concepts and help acquire vision to look into the distant future.

Skills: Training is imparting skills to employees. A worker needs skills to operate machines, and use other equipments with least damage and scrap. This is a basic skill without which the operator will not be able to function. Employees, particularly supervisors and executives, need interpersonal skills.

Education: The purpose of education is to teach theoretical concepts and develop sense of reasoning and judgment.

29

Page 30: Project

Development: It is less skill-oriented but stresses on knowledge. Knowledge about business environment, management principles and techniques, human relations, specific industry analysis is useful for better management of a company.

Ethics: There is need for imparting greater ethical orientation to a training and development programme. Ethical attitude help managements make better decisions which are in the interests of the public, the employees and in the long term-the company itself.

Attitudinal Changes: Attitude represents feelings and beliefs of individuals towards others. Attitude affects motivation, satisfaction and job commitment. Negative attitude need to be converting into positive attitude. Attitude must be changed so that employees feel committed to the organization, are motivated for better performance, and derive satisfaction from their jobs and the work environment.

Decision making and problem solving skills: It focus on methods and techniques for making organization decision-making and solving work related problems.

TRAINING AND DEVELOPMENT OBJECTIVES    

The principal objective of training and development division is to make sure the availability of a skilled and willing workforce to an organization. In addition to that, there are four other objectives: Individual, Organizational, Functional, and Societal.  

Individual objectives – help employees in achieving their personal goals, which in turn, enhances the individual contribution to an organization.  

Organizational Objectives – assist the organization with its primary objective by bringing individual effectiveness.  

Functional Objectives – maintain the department’s contribution at a level suitable to the organization’s needs.

Societal Objectives – ensure that an organization is ethically and socially responsible to the needs and challenges of the society.

IMPORTANCE OF TRAINING AND DEVELOPMENT  

It helps to develop human intellect and an overall personality of the employees.   • Productivity – Training and Development helps in increasing the productivity of the employees that helps the organization further to achieve its long-term goal. 

30

Page 31: Project

 • Team spirit – Training and Development helps in inculcating the sense of team work, team spirit, and inter-team collaborations. It helps in inculcating the zeal to learn within the employees.  

• Organization Culture – Training and Development helps to develop and improve the organizational health culture and effectiveness. It helps in creating the learning culture within the organization.   

• Organization Climate – Training and Development helps building the positive perception and feeling about the organization. The employees get these feelings from leaders, subordinates, and peers.  

• Quality – Training and Development helps in improving upon the quality of work and work-life.

• Healthy work-environment – Training and Development helps in creating the healthy working environment. It helps to build good employee, relationship so that individual goals aligns with organizational goal.  

• Health and Safety – Training and Development helps in improving the health and safety of the organization thus preventing obsolescence.

• Morale – Training and Development helps in improving the morale of the work force. 

• Image – Training and Development helps in creating a better corporate image. 

• Profitability – Training and Development leads to improved profitability and more positive attitudes towards profit orientation. 

• Training and Development aids in organizational development i.e. Organization gets more effective decision making and problem solving. It helps in understanding and carrying out organizational policies  

• Training and Development helps in developing leadership skills, motivation, loyalty, better attitudes, and other aspects that successful workers and managers usually display.

• Optimum Utilization of Human Resources – Training and Development helps in optimizing the utilization of human resource that further helps the employee to achieve the organizational goals as well as their individual goals.  

• Development of Human Resources – Training and Development helps to provide an opportunity and broad structure for the development of human resources’ technical and behavioral skills in an organization. It also helps the employees in attaining personal growth.

31

Page 32: Project

Development of skills of employees – Training and Development helps in increasing the job knowledge and skills of employees at each level. It helps to expand the horizons of human intellect and an overall personality of the employee.

PROCESS OF TRAINING

TRAINING NEED ANALYSIS (TNA)/TRAINING NEED IDENTIFICATION (TNI)

An analysis of training need is an essential requirement to the design of effective training. The purpose of training need analysis is to determine whether there is a gap between what is required for effective performance and present level of performance.

Training Need arises at three levels:

Organizational level

Individual level

32

TRAINING EVALUATION

TRAINING NEED ANALYSIS

TRAINING

DESIGN

TRAINING IMPLEMENTA

TION

TRAININGPROCESS

Page 33: Project

Operational level

Corporate need and training need are interdependent because the organization performance ultimately depends on the performance of its individual employee and its subgroup.

Organizational level – Training need analysis at organizational level focuses on strategic planning, business need, and goals. It starts with the assessment of internal environment of the organization such as, procedures, structures, policies, strengths, and weaknesses and external environment such as opportunities and threats. After doing the SWOT analysis, weaknesses can be dealt with the training interventions, while strengths can further be strengthened with continued training. Threats can be reduced by identifying the areas where training is required. And, opportunities can be exploited by balancing it against costs. For this approach to be successful, the HR department of the company requires to be involved in strategic planning. In this planning, HR develops strategies to be sure that the employees in the organization have the required Knowledge, Skills, and Attributes (KSAs) based on the future KSAs requirements at each level.

Individual level – Training need analysis at individual level focuses on each and every individual in the organization. At this level, the organization checks whether an employee is performing at desired level or the performance is below expectation. If the difference between the expected performance and actual performance comes out to be positive, then certainly there is a need of training. However, individual competence can also be linked to individual need. The methods that are used to analyze the individual need are:

• Appraisal and performance review

• Peer appraisal

33

Page 34: Project

• Competency assessments

• Subordinate appraisal

• Client feedback

• Customer feedback

• Self-assessment or self-appraisal

Operational level – Training Need analysis at operational level focuses on the work that is being assigned to the employees. The job analyst gathers the information on whether the job is clearly understood by an employee or not. He gathers this information through technical interview, observation, psychological test; questionnaires asking the closed ended as well as open ended questions, etc. Today, jobs are dynamic and keep changing over the time. Employees need to prepare for these changes. The job analyst also gathers information on the tasks needs to be done plus the tasks that will be required in the future. Based on the information collected, training Need analysis (TNA) is done.

TRAINING-DESIGN

The design of the training program can be undertaken only when a clear training objective has been produced. The training objective clears what goal has to be achieved by the end of training program i.e. what the trainees are expected to be able to do at the end of their training. Training objectives assist trainers to design the training program.

The trainer – Before starting a training program, a trainer analyzes his technical, interpersonal, judgmental skills in order to deliver quality content to trainers. 

The trainees – A good training design requires close scrutiny of the trainees and their profiles. Age, experience, needs and expectations of the trainees are some of the important factors that affect training design.

Cost of training – It is one of the most important considerations in designing a training programme. A training programme involves cost of different types. These may be in the form of direct expenses incurred in training, cost of training material to be provided, arrangement of physical facilities and refreshment, etc. Besides these expenses the organization has to bear indirect cost in the form of loss of production during training period. Ideally, a training programme must be able to generate more revenues than the cost involved. 

Training climate – A good training climate comprises of ambience, tone, feelings, positive perception for training program, etc. Therefore, when the climate is favorable nothing goes wrong but when the climate is unfavorable, almost everything goes wrong

34

Page 35: Project

Trainees’ learning style – the learning style, age, experience, educational background of trainees must be kept in mind in order to get the right pitch to the design of the program. 

Training strategies – Once the training objective has been identified, the trainer translates it into specific training areas and modules. The trainer prepares the priority list of about what must be included, what could be included. 

Training topics – After formulating a strategy, trainer decides upon the content to be delivered. Trainers break the content into headings, topics, ad modules. These topics and modules are then classified into information, knowledge, skills, and attitudes.   Sequence the contents – Contents are then sequenced in a following manner: 

• From simple to complex 

• Topics are arranged in terms of their relative importance 

• From known to unknown 

• From specific to general 

• Dependent relationship 

Training tactics – Once the objectives and the strategy of the training program becomes clear, trainer comes in the position to select most appropriate tactics or methods or techniques. The method selection depends on the following factors: 

• Trainees’ background 

• Time allocated 

• Style preference of trainer 

• Level of competence of trainer 

• Availability of facilities and resources, etc 

Support facilities – IT can be segregated into printed and audio visual. The various requirements in a training program are white boards, flip charts, markers, etc. 

Constraints – The various constraints that lay in the trainers mind are: 

• Time 

35

Page 36: Project

• Accommodation, facilities and their availability 

• Furnishings and equipments 

• Budget 

• Design of the training, etc

TRAINING IMPLEMENTATION

To put training program into effect according to definite plan or procedure is called training implementation. Training implementation is the hardest part of the system because one wrong step can lead to the failure of whole training program. Even the best training program will fail due to one wrong action. Training implementation can be segregated into:

• Practical administrative arrangements

• Carrying out of the training

Once the staff, course, content, equipments, topics are ready, the training is implemented. Completing training design does not mean that the work is done because implementation

phase requires continual adjusting, redesigning, and refining. Preparation is the most important factor to taste the success. Therefore, following are the factors that are kept in mind while implementing training program:

The trainer – The trainer need to be prepared mentally before the delivery of content. Trainer prepares materials and activities well in advance. The trainer also set grounds before meeting with participants by making sure that he is comfortable with course content and is flexible in his approach.

Physical set-up – Good physical set up is pre-requisite for effective and successful training program because it makes the first impression on participants. Classrooms should not be very small or big but as nearly square as possible. This will bring people together both physically and psychologically. Also, right amount of space should be allocated to every participant.

Establishing rapport with participants – There are various ways by which a trainer can establish good rapport with trainees by:

• Greeting participants – simple way to ease those initial tense moments

• Encouraging informal conversation

36

Page 37: Project

• Remembering their first name

• Pairing up the learners and have them familiarized with one another

• Listening carefully to trainees’ comments and opinions

• Telling the learners by what name the trainer wants to be addressed

• Getting to class before the arrival of learners

• Starting the class promptly at the scheduled time

• Using familiar examples

• Varying his instructional techniques

• Using the alternate approach if one seems to bog down

Reviewing the agenda – At the beginning of the training program it is very important to review the program objective. The trainer must tell the participants the goal of the program, what is expected out of trainers to do at the end of the program, and how the program will run. The following information needs to be included:

• Kinds of training activities

• Schedule

• Setting group norms

• Housekeeping arrangements

• Flow of the program

• Handling problematic situations

Methods and techniques of training:

1) On-the-job Training –

In this method the trainee is placed on a regular job and taught the skills necessary to perform it. The trainee learns under the guidance and supervision of the superior or an instructor. The trainee learns under the guidance of the superior or an instructor. The

37

Page 38: Project

trainee learns by observing and handling the job. Therefore, it is called learning by doing.

Several methods are used to provide on-the-job training, e.g. coaching, job rotation, committee assignments etc. a popular form of on-the-job training is Job Instruction Training or step by step learning. It is widely used in United States to prepare supervisors. It is appropriate for acquisition or improvement of motor skills and routine and repetitive operations. The JIT involves the following steps:

a) Preparing the trainee for instruction. This involves putting the trainee at ease, securing his interest and attention, stressing the importance of the job, etc.

b) Presenting the job operations or instructions in terms of what the trainee is required to do. The trainee is put at work site and each step of the job is explained to him clearly.

c) Applying and trying out the instructions to judge how far the trainee has understood the instructions.

d) Following up the training to identify and correct the deficiencies, if any.

JIT method provides immediate feedback, permits quick corrections of errors and provides extra patience when required. But it needs skilled trainers and preparation in advance.

2) Off-the-Job Training –

Under this method, the trainee learns outside the job and devotes whole time on learning. The main techniques used in off-the-job training are given below:

a) Vestibule training- In this method, a training centre called vestibule is set up and actual job conditions are duplicated or simulated in it. Expert trainers are employed to provide training with the help of equipment and machines which are identical with those in use at the workplace.

b) Apprenticeship Training- In this method, theoretical instruction and practical learning are provided to trainees in training institutes. In India, the government has established Industrial Training Institutes(ITIs) for this purpose. Under the Apprenticeship Act, 1962 employers in specified industries are required to train the prescribed number of persons in ‘designated trades’. The aim is to develop all-round craftsmen. Generally, a stipend is paid during the training period. Thus, it is an “earn when you learn” scheme.

c) Classroom training- Under this method, training is provided in company classrooms or in educational institutions. Lectures, case studies group discussions, and audio visual aids are used to explain knowledge and skills to the trainees. Classroom training is suitable for teaching concepts and problem-solving skills. It is also useful for orientations and safety training programmes. Some companies maintain their own training institutes or schools. Special training courses are designed, e.g., management courses for foremen, computer course for typists, etc. Courses in retraining and upgrading may also be conducted. Small firms depend on outside schools and courses.

38

Page 39: Project

d) Internship training- it is a joint programme of training in which educational institutions and business firms cooperate. Selected candidates carry on regular studies for the prescribed period. They also work in some factory or office to acquire practical knowledge and skills. The method helps to provide a good balance between theory and practice. But it involves a long-time period due to slow process. This method of training is used in professional work, e.g. MBBS, CA, ICWA, Company Secretaries etc.

TRAINING EVALUATION

The process of examining a training program is called training evaluation. Training evaluation checks whether training has had the desired effect. Training evaluation ensures that whether candidates are able to implement their learning in their respective workplaces, or to the regular work routines.

Purposes of Training Evaluation

The five main purposes of training evaluation are:

Feedback: It helps in giving feedback to the candidates by defining the objectives and linking it to learning outcomes.

Research: It helps in ascertaining the relationship between acquired knowledge, transfer of knowledge at the work place, and training.

Control: It helps in controlling the training program because if the training is not effective, then it can be dealt with accordingly.

Power games: At times, the top management (higher authoritative employee) uses the evaluative data to manipulate it for their own benefits.

39

Page 40: Project

Intervention: It helps in determining that whether the actual outcomes are aligned with the expected outcomes.

Functions of evaluation :

There are basically two functions of evaluation:

1) Qualitative evaluations is an assessment process how well did we do?2) Quantitative evaluation is an assessment process that answers the question

How much did we do?

Principles of Training Evaluation :

Training need should be identified and reviewed concurrently with the business and personal development plan process.

a) Evaluation must be continuous.

b) Evaluation must be specific.

c) Evaluation must be based on objective methods and standards.

d) There should be correlation to the needs of the business and the individual.

e) Organizational, group and individual level training need should be identified and

evaluated.

f) Techniques of evaluation should be appropriate.

g) The evaluation function should be in place before the training takes place.

h) The outcome of evaluation should be used to inform the business and training

process.

Need of evaluation of Training:

Training cost can be significant in any business. Most organizations are prepared to incur these cost because they expect that their business to benefit from employees development and progress. Whether business has benefited can be assessed by evaluation training.

There are basically four parties involved in evaluating the result of any training.

Trainer, Trainee, Training and Development department and Line Manager.

40

Page 41: Project

The Trainee wants to confirm that the course has met personal expectations and satisfied any learning objectives set by the T & D department at the beginning of the programme.

The Trainer concern is to ensure that the training that has been provided is effective or not.

Training and Development want to know whether the course has made the best use of the resources available.

The Line manager will be seeking reassurance that the time hat trainee has spent in attending training results in to value and how deficiency in knowledge and skill redressed.

The problem for many organizations is not so much why training should be evaluated

but how. Most of the organizations overlook evaluation because financial benefits are

difficult to describe in concrete terms.

The process of evaluation is central to its effectiveness and helps to ensure that:

Whether training budget is well spent

To judge the performance of employee as individual and team.

To establish culture of continuous learning and improvement.

Process of training evaluation

Before Training: The learner’s skills and knowledge are assessed before the training program. During the start of training, candidates generally perceive it as a waste of resources because at most of the times candidates are unaware of the objectives and learning outcomes of the program. Once aware, they are asked to give their opinions on the methods used and whether those methods confirm to the candidates preferences and learning style

During Training: It is the phase at which instruction is started. This phase usually consist of short tests at regular intervals.

After Training: It is the phase when learner’s skills and knowledge are assessed again to measure the effectiveness of the training. This phase is designed to determine whether training has had the desired effect at individual department and organizational levels. There are various evaluation techniques for this phase.

Techniques of evaluation

The various methods of training evaluation are:

41

Page 42: Project

• Observation

• Questionnaire

• Interview

• Self diaries

• Self recording of specific incidents

What to evaluate/level of evaluation

Donald Kirkpatrick developed four level models to assess training effectiveness. According to him evaluation always begins with level first and should move through other levels in sequence.

Reaction Level: The purpose is to measure the individual reaction to the training activity. The benefit of Reaction level evaluation is to improve Training and Development activity efficiency and effectiveness.

Learning Level: The basic purpose is to measure the learning transfer achieved by the training and development activity. Another purpose is to determine

to what extent the individual increased their knowledge, skills and changed their attitudes by applying quantitative or qualitative assessment methods

Behaviour Level: The basic purpose is to measure changes in behavior of the individual as a result of the training and development activity and how well the enhancement of knowledge, skill, attitudes has prepared than for their role.

Result Level: The purpose is to measure the contribution of training and development to the achievement of the business/operational goals.

42

Page 43: Project

Training and development in KRIBHCO

Organisations become dynamic and grow through zeal, calibre and vision of their Human Resources. A healthy climate of trust in organisation is essential for developing Human Resources. KRIBHCO has always considered development of Human Resources as its not most important responsibility because this alone ensures the well being and growth of the organisation. Training and development activities of society form a part of continuous process in integrating the organisational needs and the needs of individuals. “Willingness to change” for betterment is the pre-requisite for moving towards excellence. Objectives of Human Resource Development

The objectives of HRD are to-

1) Ensure selection and induction of personnel of the requisite calibre, temperament and integrity.

2) Adopt training, job rotation and motivational practices to enable employees to achieve their full potential and make their best contributions to corporate success and family welfare.

3) Develop the employees as a total person.4) Promote work culture based on:

a) Dedication to pursuit of excellence.b) Achieving goals within normative time and cost.c) Individual and group initiative.d) Personal integrity.e) Self reliance.f) Self awareness.g) Service before self.h) Multi-cooperation and team spirit; andi) Concern for individual as a human being.

Objectives of Training

To orient the employees to the needs of the society and provide opportunities for them to improve their performance on the job:-

1) To minimise the gap between learning new development2) To equip the participants with requisite ability so that they can work with

minimum supervision.3) To enable employees to update their knowledge and increase the level of

performance on their present job assignment as well as channelise their inherent potential, in order to make him a holistic person.

4) To foster initiative, self confidence and to overcome manpower obsolescence occurring due to age, temperament, lack of motivation or inability of person to adapt to changes.

5) To impart training to new entrants to enable them to take up their assignment effectively.

43

Page 44: Project

6) To create an environment of “we feeling” and enhance accountability of people.

Identification of training needs

A committee has been constituted at head office for identification and assessment of training needs of each employee posted at HO/CMO/SMOs. On the basis of specific recommendations of Head of Departments the committee would nominate employees for various seminar/training programmes/conferences etc, either in India or abroad to meet the development needs.

In house training programmes

After identification of the training needs of employees and keeping in view the requirements of the society, the in house Training Programmes, faculties are drawn from within the organisation and from outside also.

The infrastructure facilities for in-house training programmes at plant, surat include:

1) An auditorium with a capacity of 500 persons.2) Two air conditioned lecture halls to accommodate 50 persons each.3) Full-fledged library.

The infrastructure facilities for in-house training programmes at Head Office, Noida include:

1) “Padam Shri Pothan Multi-Purposes Auditorium” having a capacity to accommodate 300 persons. The auditorium is furnished with state-of-art equipments to organize talks/lectures/seminar and various culture programmes.

2) An air conditioned conference hall with capacity to accommodate upto 25 persons. The hall is well furnished and equipped for organising Training Programmes, Talks/Lectures within the office premises from time to time.

Training programmes are conducted keeping in view the needs of the society. Efforts are made to avail sponsorship from organisation like ILO, ICA, British Council, IMF, EEC etc.

Submission of training report

After attending the training programme the employees are required to submit within a week’s time a brief report about the training highlighting its usefulness. Employees deputed for foreign training are required to give a presentation about their experiences.

Induction training

New appointees are imported induction training covering KRIBHCO’s aim, objectives and achievements, work culture, office procedures and job responsibilities.

44

Page 45: Project

Normally internal faculty is drawn for such training. New appointees are put on job only after necessary induction training.Similarly, special programmes are being designed for the employees who are being promoted to officer category in the recent past.

Honorarium

Employees who are required to be associated as Internal Faculty in In-house training programmes/seminars etc are paid Honorarium, as decided by the management from time to time.

Training schemes

Graduate Engineer/Management Training Schemes.

Degree holders in chemical, Mechanical, Electrical Engineering, Instrumentation, Computer technology are required on all India basis.

They are given intensive training for a period of 1 and half years in their respective specialised field after brief induction and orientation in the general areas of operation of KRIBHCO. They are subsequently assessed for absorption in KRIBHCO subject to vacancy and suitability.

Operator/Technician Training Scheme (B.sc/DIP/ITI)

The management selects Science Graduates, Diploma Holders in Engineering Branches and certificate holders in various ITI trades on the basis of their performance in written test, personal interview and medical fitness. The focus is “on the job Training” and shouldering responsibility. The duration of training is two years and three years in respect of Diploma/B.sc and ITI respectively. After satisfactory completion of training, they are offered absorption in KRIBHCO services, subject to vacancies.

Vocational training

On the request from educational institutions, facilities of Vocational/Summer training are provided to the students sponsored, to enable them to have the practical experience.

Society Training Scheme

Trainees may be inducted and considered for placement in regular grades after successful completion of training period. Number of trainees to be recruited in each discipline/trade will be determined on the basis of Man Power Planning/expansion requirements of the society from time to time categories in which trainees may be inducted are as under:

45

Page 46: Project

S.No Discipline Qualification

Training PeriodLimit

Maximum

Age limit

Design on absorption

1 Engg. Mgt. Services-1

Engg. Graduate 1 ½ yrs 25 yrs Asst. Engr.

2 Engg. Suborn

Engg. Dip. Holders

2 yrs 23 yrs Opts/Tech.

3 Mgt. services

MBAs from IIMs

Ahmedabad, Bangalore, Calcutta & Lucknow.

- - To be included as Jr. Manager in Gr. G2

4 Pers. & IR PG Dip. Business Mgt.

with specialisation Personnel/IR from XLRI, Jamshedpur

1 yr 24 yr Jr. Manager in Gr. H

5 Agri. Graduate Trainees

B.Sc Agri with 1st class

1 ½ yrs 25 yrs Field Rep.

6 Commercial Subordinate

Services

MBA with 55% marks other

than IIMS/XLRI

2 yrs 25 yrs Asstt. Gr. I

7 Admm. Subordinate

services

Master degree in social work with min 55% marks/ PG Dip

in PM/IR/Social welfare/

DSW/LSW/DLL from

recognised institution

2 yrs 25 yrs Asstt. Gr. I

8 Jr. Commercial

Services

Graduate 1 yr 25 yrs Clerk

46

Page 47: Project

RESEARCH METHODOLOGY

47

Page 48: Project

DATA COLLECTION

Data collection is a term used to describe a process of preparing and

collecting business data.

There are two methods of data collection which are discussed below:

DATA COLLECTION

PRIMARY DATA SECONDARY DATA

PRIMARY DATA

In primary data collection, you collect the data yourself using methods such as

interviews and questionnaires. The key point here is that the data you collect is unique

to you and your research and, until you publish, no one else has access to it.

I have tried to collect the data using methods such as questionnaires. It is done to get

the real scenario and to get the original data of present.

DATA COLLECTION TECHNIQUE

Questionnaire:

Questionnaire are a popular means of collecting data, but are difficult to design and

often require many rewrites before an acceptable questionnaire is produced. The

features included in questionnaire are:

Theme and covering letter

Instruction for completion

Types of questions

Length

SAMPLING METHODOLOGY

Sampling technique:

48

Page 49: Project

Initially, a rough draft was prepared keeping in mind the objective of the research. A

pilot study was done in order to know the accuracy of the questionnaire. The final

questionnaire was arrived only after certain important changes were done. Thus my

sampling came out to be judgmental and continent.

Sampling Unit:

The respondents who were asked to fill out questionnaires are the sampling units. These comprise of employees of KRIBHCO.

Sampling Size: 16

SECONDARY DATA

All methods of data collection can supply quantitative data (numbers, statistics or

financial) or qualitative data (usually words or text). Quantitative data may often be

presented in tabular or graphical form. Secondary data is data that has already been

collected by someone else for a different purpose to yours. Secondary research (also

known as desk research) involves the summary or collection of existing research

rather than primary research.

The data required was provided by the HR of KRIBHCO that helped me to complete

my project properly.

Need of using secondary data

1. Data is of use in the collection of primary data.

2. They are one of the cheapest and easiest means of access to information.

3. Secondary data may actually provided enough information to resolve the problem

being investigated.

Limitation of secondary data

1. May be outdated.

2. May not be very accurate.

3. Collection for some other purpose.

49

Page 50: Project

Analysis & Interpretation of

Primary data

50

Page 51: Project

ANALYSIS OF PRIMARY DATA

1. What do you understand by training?

Learning 0Enhancement of knowledge, skill &attitude 7Sharing information 1All of the above 8

ANALYSIS

The above result shows that most of the employees of KRIBHCO from HR are well aware of the definition, inputs and purpose of the training program. They are self motivated to attend such training program as it will result in their skill enhancement & improving their interpersonal skill.

51

Page 52: Project

2. Training is must for enhancing productivity and performance.

Completely agree 10Partially agree 6Disagree 0Unsure 0

ANALYSIS:

The above result shows that mostly all the KRIBHCO are well aware of the role and

importance of the training. It means somewhere their productivity and performance has

been improved after the training program attended by them and it helped them to achieve

their goal.

52

Page 53: Project

3. (i). Have you attended any training program in the last 01 year?

Yes 10No 6

ANALYSIS:

56% respondents have attended training program in the last 01 year. It means

KRIBHCO provides time to time training to its employees and it is continous process.

But it should also provide timely training to its other employees also.

53

Page 54: Project

(ii). If yes, which module of soft skill development training?

Personality and positive attitude 3Business communication 0Team building and leadership 2Stress management and work-life balance 0Business etiquettes and corporate grooming 1All of above 4

ANALYSIS:

Only 40% employees of KRIBHCO have attended all the soft skill modules of

training. Instead all the employees should be given training regarding all the modules

of training.

54

Page 55: Project

4. (i). After the training, have you given feedback of it?

Yes 13No 3

ANALYSIS:

81% respondent had given feedback after attending the training. It means most of the

respondents are well aware of the importance of giving feedback. They know that

their feedback is very important to identify the effectiveness and valuation of training

program.

55

Page 56: Project

(ii). If yes, through which method?

Questionnaire 7Interview 5Supplement test 0Any other 1(discussion)

ANALYSIS:

The above result shows that the questionnaire is the most popular method of evaluating

the training program and other methods are not very much in practice in KRIBHCO.

But since there are various other methods of evaluation of training program like

interviews, supplement test, self diaries& observation so it should also implement the

other methods also to identify effectiveness and valuation of the training program.

56

Page 57: Project

5. Which method of training feedback according to you is more appropriate?

Observation 7Questionnaire 3Interviews 5Self diaries 0Supplement test 1

ANALYSIS:

I. KRIBHCO, mostly use the questionnaire to get the feedback of trainees but only

19% respondents are in favor of questionnaire because in it there is a possibility of

getting inaccurate data..

II. On the other side 31% respondents feel that interview is the appropriate method of

evaluating the training program because it is more flexible method, and in this they

can get the opportunity for clarification and the most important thing is that in the

interview, personal interaction is also possible.

57

Page 58: Project

III. 44% respondents are in favor of observation. They think that observation is the

most appropriate method of evaluating the training program because this is non-

threatening and is excellent way to measure the behavioral changes.

IV. Beside this, 6% are in favor of supplement test and no one is in the favor of self

diaries.

58

Page 59: Project

6.(i). Do you think that the feedback can evaluate the training

effectiveness?

Yes 16No 0

ANALYSIS:

100% respondents think that the feedback can evaluate the training effectiveness. It

means that employees of KRIBHCO are well aware of the importance of taking

feedback after the training.

59

Page 60: Project

(ii).If yes, how can the post training feedbacks can help the participants?

Improve job performance 2An aid to future planning 2Motivate to do better 5All of the above 7None 0

ANALYSIS:

43% respondent feel that the post training feedback can help the participants to improve

their job performance, is an aid to future planning and can motivate to do better. It

means that they are benefited by giving feedback of the training, attended by them.

60

Page 61: Project

7. Post training evaluation focus on result rather than on the effort expended in conducting training.

Completely agree 10Partially agree 6Disagree 0Unsure 0

ANALYSIS:

62% respondents are completely agree and 38% respondents are partially agree with the

statement that post training evaluation focus on result rather than on the effort expended

in conducting training program. It means that all the respondent are well aware of the

purpose and objective of the post training evaluation.

61

Page 62: Project

8. What should be the approach of post training evaluation?

Trainer centered 2Trainee centered 1Subject centered 9All of the above 4

ANALYSIS:

I. 57% respondents feel that the approach of post training evaluation should be subject

centered and 13% respondent also feel that it should be trainer, trainee and subject

centered.

II. 13% respondents are in favor of trainee centered approach and 17% respondents are

in favor of trainer centered approach.

It means that the evaluation procedure should be implemented concerning the subject

matter only.

62

Page 63: Project

9. What should be the ideal time to evaluate the training?

Immediate after training 12After 15 days 1After 1 month 2Can’t say 1

ANALYSIS:

75% respondent feel that training should be evaluated immediate after training after

training. . 13% feel that ideal time to evaluate the training is after 1 month and 6% are

unsure. 6% feel that it should be after 15 days.

Since each respondent had attended different training program. So the ideal time of

evaluation of training depends on types of training. It could be vary for different

training.

63

Page 64: Project

10. Should the training evaluation procedure reviewed and revised periodically?

Yes 15No 1Can’t say 0

ANALYSIS:

94% respondents feel that the post training evaluation procedure should be reviewed

and revised periodically. It means that it has to be a continuous process and be taken

regularly by the Reporting manager of the participants.

Still 6% feel that the post training evaluation procedure should not be reviewed and

revised periodically. It means they are satisfied with the post training evaluation

procedure, followed by KRIBHCO.

64

Page 65: Project

11. Is the whole feedback exercise after the training worth the time, money and effort?

Yes 12No 2Can’t say 2

ANALYSIS:

74% respondents feel that the whole feedback exercise worth the time, money and

effort and 13% respondent are not agree with this. It means that feedback exercise is

valuable and worthful for the participant to achieve their personal goal as well as for

the organization.

Still 13% are unsure about it.

65

Page 66: Project

12. The post training feedback can be used:

To identify the effectiveness and valuation of training program 5To identify the ROI(return on investment) 0To identify the need of retraining 0To provide the points to improve the training 2All of above 9

ANALYSIS:

56% respondents feels that post training feedback can be used to identify the

effectiveness and valuation of training program, to identify the ROI, to identify the

need of retraining and to provide the points to improve the training. And others are

also aware of the importance of post training feedback.

66

Page 67: Project

Findings, Suggestions, Conclusion

&Limitations

67

Page 68: Project

KEY FINDINGS

Mostly all the employees of KRIBHCO are well aware of the role and

importance of the training They are self motivated to attend such training

program as it will result in their skill enhancement & improving their

interpersonal skill.

KRIBHCO provides time to time training to its and it is continuous process.

Questionnaire is the most popular mean of evaluating the training program in

KRIBHCO.

Most of the employees of KRIBHCO feel that observation is the most

appropriate method of evaluating the training program.

Post training evaluation focus on result rather than on the effort expended in

conducting the training and it worth the time, money and effort.

Most of the participants are benefitted by giving feedback after attended the

training. It motivated them to do better, helped them to increase their job

performance and is an aid to future planning.

In KRIBHCO, post training evaluation is used to identify the effectiveness and

valuation of training program, to identify the ROI (return on investment), to

identify the need of retraining and to provide the points to improve the

training.

68

Page 69: Project

SUGGESTIONS AND

RECOMMENDATIONS

The management must commit itself to allocate major resources and adequate

time to training.

Ensure that a comprehensive and systematic approach to training exists, and

training and retraining are done at all levels on a continuous and ongoing

basis.

Ensure that timely training is provided to all the employees.

Besides questionnaire other methods of post training evaluation should also be

used like interviews, self diaries, observation and supplement test.

The evaluation procedure must be implemented concerning trainer, trainee and

subject.

All the employees should be given training regarding all the modules of

training.

69

Page 70: Project

CONCLUSION

Professional competence describes the Area- knowledge, expertise and skill relevant

for performing excellently within a specific functional department. This competence

insures that knowledge is both present and used within a firm for the welfare of its

stake-holders. To develop this competence regular Training and Development is

required

Therefore, Training initiatives and programs have become a priority for Human

Resources. As business markets change due to an increase in technology initiatives,

companies need to spend more time and money on training employees. In today’s

business climate employee development is important for success and organizations

are investing more in their employees training and development needs.

Training evaluation is the important part of training process. It provides the feedback

and helps the employees for improvement at the level of individual performance and

in the strategy formulation for training and development. Training evaluation can be

used to identify the effectiveness and valuation of training programme, to identify the

ROI (return on investment), to identify the need of retraining and to provide the points

to improve the training.

70

Page 71: Project

LIMITATION OF THE STUDY

1. The time period of the study was only two six weeks which may provide a

deceptive picture in comparison of the study based on long run.

2. KRIBHCO, Noida provides only soft skill development training. So skill based

training is still unsolved.

3. The study is based only on secondary & primary data so lack of keen observations

and interactions were also the limiting factors in the proper conclusion of the

study.

71

Page 72: Project

ANNEXURE

72

Page 73: Project

QUESTIONNAIRE

Dear Madam/Sir,

I am a BBA student. As a part of my curriculum I am undergoing summer training in KRIBHCO. Please give your views/opinions in the space given below about the training and development in KRIBHCO. The information provided by you will be kept highly confidential & will be used by me strictly for analysis only.

1) What do you understand by training?

a) Learning b) Enhancement of knowledge, skill and aptitudec) Sharing informationd) All of above

2) Training is must for enhancing productivity and performance.

a) Completely agreeb) Partially agreec) Disagreed) Unsure

3) (i) Have you attended any training programme in the last 01 year?a) Yesb) No

(ii) If yes ,which module of soft skill development training?

a) Personality and positive attitudeb) Business communicationc) Team building and leadershipd) Stress management and work-life balancee) Business etiquettes and corporate groomingf) All of aboveg) If any other please specify ___________________________

4) (i) After the training ,have you given feedback of it?

a) Yesb) No

(ii) If yes, through which method?(can select more than one)

a) Questionnaireb) Interviewc) Supplement testd) If any other please specify _______________

73

Page 74: Project

5) Which method of post training feedback according to you is more appropriate?

a) Observationb) Questionnairec) Interviewsd) Self diariese) Supplement test

6) (i) Do you think that the feedback can evaluate the training effectiveness?a) Yesb) No

(ii) If yes, how can the post training feedbacks can help the participants?(can select more than one)

a) Improve job performanceb) An aid to future planningc) Motivate to do betterd) All of the abovee) None

7) Post training evaluation focus on result rather than on the effort expended in conducting training.

a) Completely agreeb) Partially agreec) Disagreed) Unsure

8) What should be the approach of the post training evaluation?(can select more than one)

a) Trainer centeredb) Trainee centeredc) Subject Centeredd) All of the above

9) What should be the ideal time to evaluate the training?

a) Immediate after trainingb) After 15 daysc) After 1 monthd) Cant say

10) Should the post training evaluation procedure reviewed and revised periodically?

74

Page 75: Project

a) Yes b) Noc) Cant say

11) Is the whole feedback exercise after the training worth the time, money and Effort ?

a) Yes b) Noc) Cant say

12) The post training feedbacks can be used:

a) To identify the effectiveness and valuation of the training programmeb) To identify the ROI( return on investment)c) To identify the need of retrainingd) To provide the points to improve the traininge) All of above

13) Suggestion for improving the post training feedback procedure exists in KRIBHCO. (If any)

75

Page 76: Project

BIBLIOGRAPHY

76

Page 77: Project

BIBLIOGRAPHY

1. BOOKS/MAGAZINES:

Human Resource Management by C.B. Gupta.

2. WEBSITES:

http://www.kribhco.net

http://traininganddevelopment.naukrihub.com

www.google.com

77


Recommended