+ All Categories
Home > Documents > PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

Date post: 13-Jul-2016
Category:
Upload: badar-shahbaz
View: 48 times
Download: 5 times
Share this document with a friend
Description:
PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN
18
1 PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN 1. Cities are drivers of economy whereas Public Transport is lifeline of urban life and city development. Mass Transit is neglected in a number of mega cities of developing countries, resulting in extreme congestion, long commuting times, choking air pollution and deadly traffic accidents. Prevalence of individual transport results in huge economic losses. 2. World over, governments assume the primary responsibility of solving the above problems through infrastructure development projects and urban mass transit schemes as these become the primary factors in development of national economy and maintenance of order in mega cities. 3. In order to address the ever increasing traffic and resultant congestion in Lahore, studies conducted in the 1990s by the Government of Punjab, identified the need for mass transit to meet future public transport demands and recommended Ferozepur Road as the priority corridor. Despite various attempts, no project could come on ground. Transport Department, Government of the Punjab commissioned MVA Asia Ltd to undertake a Feasibility Study of a Rapid Mass Transit System (RMTS) for Lahore in 2005-06 which covered the development of a Long Term RMTS network for Lahore and the feasibility of the priority Green Line, based on identification of potential mass transit corridors, followed by a broad assessment of patronage and engineering constraints in those corridors. The order of priority for implementing these lines was then determined based primarily on forecast passenger demand in the following order of priority:- Green Line Ferozepur Road/Mall Road/Ravi Road/Shahdara. (Gajju Matta To Shahdra; Completed; 27 Km length) Orange Line Raiwind Road/Multan Road/Macloed Road/ Railway Station/GT Road (Ali Town to Dera Gujjran ; 27.1 km Length) Blue Line Township/Gulberg Boulevard/Jail Road Purple Line Bhatti Gate/Allama Iqbal Road/Airport 4. The study conducted by MVA Asia Ltd included their recommendations on Green Line. They also undertook the Feasibility Study of the Orange Line (LRMTS) in October 2006 which was completed in 2007.
Transcript
Page 1: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

1

PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

1. Cities are drivers of economy whereas Public Transport is lifeline of urban life

and city development. Mass Transit is neglected in a number of mega cities of

developing countries, resulting in extreme congestion, long commuting times,

choking air pollution and deadly traffic accidents. Prevalence of individual

transport results in huge economic losses.

2. World over, governments assume the primary responsibility of solving the above

problems through infrastructure development projects and urban mass transit

schemes as these become the primary factors in development of national

economy and maintenance of order in mega cities.

3. In order to address the ever increasing traffic and resultant congestion in Lahore,

studies conducted in the 1990s by the Government of Punjab, identified the need

for mass transit to meet future public transport demands and recommended

Ferozepur Road as the priority corridor. Despite various attempts, no project

could come on ground. Transport Department, Government of the Punjab

commissioned MVA Asia Ltd to undertake a Feasibility Study of a Rapid Mass

Transit System (RMTS) for Lahore in 2005-06 which covered the development

of a Long Term RMTS network for Lahore and the feasibility of the priority Green

Line, based on identification of potential mass transit corridors, followed by a

broad assessment of patronage and engineering constraints in those corridors.

The order of priority for implementing these lines was then determined based

primarily on forecast passenger demand in the following order of priority:-

Green Line – Ferozepur Road/Mall Road/Ravi Road/Shahdara. (Gajju Matta

To Shahdra; Completed; 27 Km length)

Orange Line – Raiwind Road/Multan Road/Macloed Road/ Railway Station/GT

Road (Ali Town to Dera Gujjran ; 27.1 km Length)

Blue Line – Township/Gulberg Boulevard/Jail Road

Purple Line – Bhatti Gate/Allama Iqbal Road/Airport

4. The study conducted by MVA Asia Ltd included their recommendations on Green

Line. They also undertook the Feasibility Study of the Orange Line (LRMTS) in

October 2006 which was completed in 2007.

Page 2: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

2

5. According to Feasibility Study, the Green line Metro Train project was estimated

to cost USD 2.4 Billion. The Asian Development Bank expressed willingness to

finance approximately USD 1 Billion of its cost but no loan agreement was

signed. USD 1 Billion was expected to be raised through private sector financing

which also did not mature and was later found non-feasible. The Government of

Punjab through LTC negotiated and signed an agreement in China for Green

Line project at a cost of USD 1.7 Billion on 22.04.2011. However, the project

could not go through because the Sovereign Guarantee from the Federal

Government was not committed.

6. The Green line project was finally executed by the Punjab Government in 2012-

13 as Bus Rapid Transit System, with a total cost of USD 300 Million and is

presently serving the public in a big way. Average daily ridership of Green Line

on a working day is over 150, 000 Passengers per day. It is clarified that the ADB

never committed any funding for Orange Line project.

7. In 2014, the seven years old feasibility study was updated by NESPAK on

directions of Punjab Mass Transit Authority. NESPAK proposed following two

options:

Option-1: Mall Road in cut & cover section and viaduct in other reaches.

Option-2: Viaduct in entire length of the project

8. Considering various factors like high cost involved in tunnel boring / its

maintenance cost, cost of land acquisition, number of displaced/affected persons

and impact on heritage buildings etc. Option-1 with 1.72 km underground and

25.4 km elevated track was adopted.

9. The alignment of Lahore Orange Line is based on rigorous traffic engineering

modelling and parameters, including:

Origin-Destination Surveys (ODS)

Traffic Count Surveys (TCS)

Rider-ship Surveys (RS)

The alignment will:

Achieve maximum rider-ship

Minimize the land acquisition

Have no adverse effect on the historical buildings

10. Other salient features of Lahore Orange Line Metro Train project are as follows:

Page 3: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

3

Stations = 26 (Elevated = 24; Underground = 2)

Rolling Stock = 27 Train sets (One train-set comprises of 5 cars)

Ridership = Approximately 245,000 per day (estimated for first year of

operation)

Route = Ali Town to Dera Gujran

Stations location:

Sr.No. Name Of Station Sr.No. Name Of Station

1 Dera Gujran 14 Chauburgi

2 Islampark 15 Gulshan-I-Ravi

3 Salmatpura 16 Samanabad

4 Mahmood Booti 17 Yateem Khana / Bund road

5 Pakistan Mint 18 Scheme Morr / Salahuddin Road

6 Shalamar Garden 19 Shahnoor

7 Baghbanpura 20 Sabzazar

8 UET 21 Awan Town

9 Sultanpura 22 Wahdat Road

10 Railway Station 23 Hanjarwal

11 Lakshami 24 Canal View

12 Central station 25 Thokar Niaz Baig

13 Anarkali Station 26 Ali Town

11. To initiate Orange Line Metro Train Project, an open international tender was

floated on 29.01.2014 in Financing + EPC mode. Pre-bid conference was held

on 18.02.2014, which was attended by representatives of 11 foreign and 5 local

companies. On Bid submission date i.e. 21.04.2014 only two Chinese companies

namely CR-NORINCO JV and SINORAIL JV furnished their bids.

12. In the meeting of the President of Pakistan with Chinese Premier held on

19.02.2014 in Beijing, the Chinese Premier decided to fund the Orange Line

project with the condition that Chinese Enterprises will execute the project using

Chinese Equipment. He also declared it as a Chinese gift to Pakistan.

13. The International Tender was cancelled on May 12, 2014. An Inter-Governmental

Framework Agreement was signed on 22.05.2014 providing that Orange line

shall be fully designed, constructed and supervised by Chinese Enterprises

(which is a norm in all bilateral funding agreements). The Framework Agreement

Page 4: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

4

also inter alia required initiation of negotiations on Commercial Contract of

Orange Line.

14. Under instructions of the Chief Minister, on 26.05.2014, a reference was made

through EAD to the Chinese Government requesting for their concurrence that

selection of Chinese Enterprise may be done through an open competitive

bidding restricted to China.

15. On 30.05.2014 the Chinese Government informed that for projects using

Preferential Buyer’s Credit, the China Chamber of Commerce and Import and

Export of Machinery and Electronic Products (CCCME) shall provide a shortlist

of Enterprises (no more than three). The Pakistani proprietor shall tender from

this shortlist. In the history of China-Pakistan bilateral concessional lending,

Orange Line is the first project in which tendering process was followed. It is

pertinent to mention that Government to Government Agreements are exempted

from the operation of PPRA Rules. On 02.06.2014 a detailed Eligibility Criteria

and required evidence of bidder’s capability, experience and financial capacity

was sent to the Chinese side for recommending eligible Chinese Contractors.

16. On 24.06.2014, the CCCME recommended the same companies i.e. CR-

NORINCO JV and SINORAIL JV who had earlier participated in the international

tender for Orange Line project. On 24.06.2014, bids were invited from these two

companies. Technical bids of the bidders were opened on 18.07.2014. Financial

bids of the bidders were opened on 04.08.2014 after M/s NESPAK and CCCC

(A Chinese Consultant) declared them technically compliant. CR-NORINCO

emerged as lowest bidder with bid price of USD 2.139 Billion. Breakup of final

Contract Price is as follows:-

i. Contract Price of Civil Works= USD 531,681,818

ii. Contract Price of Consultancy Services = USD 24,000,000

iii. Contract Price of E&M Works (inclusive of 6% Withholding/Income Tax)

= USD 922,500,000

iv. Sub-total (a to c) = USD 1,478,181,818

v. Contingencies (only in case of unforeseen increase in work) = USD

147,818,182

vi. Total Price = USD 1,626,000,000

The final price of USD 1,478 Million is around 661 Million dollar less than the

bid price

Page 5: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

5

17. Chinese side agreed to sublet Civil Works of the project to Pakistan side resulting

in significant savings, which is again an unprecedented achievement. Significant

economies / price reductions achieved in E&M Work’s price. Effective

negotiations yielded project cost savings of approximately USD 660,818,182/-

with unprecedented support of the Chinese Government and gracious flexibility

shown by CR-NORINCO. Further, transparent tendering process of Civil Works

carried out by LDA yielded additional saving of PKR 5.97 Billion.

18. Cost of Orange Line is quite competitive when compared with similar projects

around the globe. Cost comparison of some of metros in the world on Per Km

basis is as below:

a) Orange line

i) Core project cost USD 1,478 M= USD 54.50 M per Km

ii) Core cost + Contingencies USD 1626 M= USD 59.95 M per Km

b) Mumbai (Completed in 2014) – USD 60.7 M per Km (adjusted)

c) Pune (Completion in 2018) – USD 62.21 M per Km (adjusted)

d) Jaipur (Completed in 2015) – USD 64.3 M per Km (adjusted)

e) Copenhagen (Completed in 2002) – USD 69.8 M per Km in 2002 prices

f) Jakarta (Completion in 2017) – USD 117.11 M per Km

According to latest research on the subject the per Km cost of Metro Trains

generally range between USD 50 Million and USD 100 Million.

19. Project Benefits

The Orange Line will provide important links between areas slated for new

development in the south and the major employment and education centres,

concentrated in the city centre and along the route such as UET. The benefit of

these transport links to a certain extent is reflected in improved journey times but

the actual perceived benefits of improved accessibility and flexibility is greater

than that which can be measured by journey times alone.

a. Reduction in Traffic

Reductions in Bus Flows at GT Road near University

2025 Two-way Hourly Bus Flows

Without OL With OL Reduction

Wagons 100 36 64

City Bus (Non AC) 97 8 89

Total 197 44 153

Page 6: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

6

Reductions in Bus Flows at Multan Road near Gulshan-E Ravi

2025 Two-way Hourly Bus Flows

Without OL With OL Reduction

Wagons 242 71 171

City Bus (Non AC) 61 - 61

City Bus (AC) 23 - 23

Provincial Mini Bus 4 4 -

Provincial Large Bus 179 120 59

Local Province Wagons 160 160 -

Local Province Ord 36 13 23

TOTAL 705 368 337

Total Potential Market for LRMTS (daily passengers)

Mode 2015 2025 Growth (% p.a.)

Bus and Wagon 3,411,000 4,313,000 2.4%

Car 3,073,000 4,842,000 4.7%

Motorcycle 1,732,000 2,339,000 3.1%

Rickshaw 1,266,000 1,575,000 2.2%

Total 9,482,000 13,069,000 3.2%

Results of Passenger Flow Forecast on Orange Line

Orange Line Initial Term

(2015)

Short Term

(2021)

Long Term

(2025)

Length (km) 26.2 26.2 26.2

Passenger Traffic Volume (10,000

person-time/day) 24.52 38.62 49.55

Average Travel Distance

(km/person-time) 8.1

——

8.3

Sectional Passenger Flow at Peak

Hours (10,000 person-time) 1.01 1.54

2.05

The tables show that there are considerable savings in buses with the OL in

place. The maximum saving is on Multan Road where a reduction of 337 buses

(2-way) can be achieved. Much of the saving can be attributed to the reduction

of long distance through buses – a move which also helps to provide relief for

the congested city centre area. Overall, the Orange Line is forecast to reduce the

total fleet of local buses (i.e. excluding long distance) in Lahore by 380 vehicles

(reducing total bus/wagon vehicle requirements in the city to around 3,770

vehicles).

b. Environment Benefits

Low greenhouse gas emission (e.g. chlorofluorocarbons)

Page 7: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

7

Reduction in carbon dioxide emissions as estimated through clean

development mechanism (145227.5 ton per annum pro rata – Delhi

Metro) c. Social Benefits

Reduction in congestion on the side roads

Less respiratory diseases

Reduction in accidents d. Economic benefits (Travel time + Vehicle Operating Cost Saving)

a) Ridership = Approximately 245,000 passengers/day

Direct Economic Benefits In first year of operation

Annual average over 30 years period a) Passenger Travel

Time Savings

PKR 9.29

Billion

USD 88

Million

PKR 29.5 Billion

USD 279.62

Million

b) Vehicle

Operating Costs Savings

PKR 5.62

Billion

USD 53.27

Million

PKR 9.87 Billion

USD 93.55 Million Total (a+b) PKR 14.9

Billion

USD

141.23

Million

PKR 39.38 Billion

USD 373.27

Million

b) Economic benefits of approximately Rs. 123 M per day

c) Train speed (Max) = 80 Km/h

d) Train Speed (Commercial) = 34.8 Km/h

e) End to End travel time = 45 Minutes

f) End to End present travel time = 2 to 2.5 Hours

g) Reduction in congestion on the side roads

20. Tendering

a) Open International Tender were floated on 29.01.2014 in Financing +

EPC mode. Pre-bid conference held on 18.02.2014 was attended by

representatives of 11 foreign and 5 local companies. On Bid submission

date i.e. 21.04.2014 only two Chinese companies namely CR-NORINCO

JV and SINORAIL JV furnished their bids.

b) In the meeting of the President of Pakistan with Chinese Premier held on

19.02.2014 in Beijing, the Chinese Premier decided to fund the Orange

Line project with the condition that Chinese Enterprises will execute the

project using Chinese Equipment. He also declared it as a Chinese gift

to Pakistan.

c) The International Tender was cancelled on May 12, 2014. Inter-

Governmental Framework Agreement signed on 22.05.2014 providing

that Orange line shall be fully designed, constructed and supervised by

Page 8: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

8

Chinese Enterprises. The Framework Agreement also inter alia required

initiation of negotiations on Commercial Contract of Orange Line. Under

instructions of the Chief Minister, on 26.05.2014, a reference was made

through EAD to the Chinese Government requesting for their

concurrence that selection of Chinese Enterprise may be done through

an open competitive bidding restricted to China.

d) On 30.05.2014 the Chinese Government informed that for projects using

Preferential Buyer’s Credit, the China Chamber of Commerce and Import

and Export of Machinery and Electronic Products (CCCME) shall provide

a shortlist of Enterprises (no more than three). The Pakistani proprietor

shall tender from this shortlist. In the history of China-Pakistan bilateral

concessional lending, Orange Line is the first project in which tendering

process was followed. On 02.06.2014 a detailed Eligibility Criteria and

required evidence of bidder’s capability, experience and financial

capacity was sent to the Chinese side for recommending eligible

Chinese Contractors.

e) On 24.06.2014, the CCCME recommended the same companies i.e.

CR-NORINCO JV and SINORAIL JV who participated in our

international tender for Orange Line project. On 24.06.2014, bids were

invited from these two companies. Technical bids of the bidders were

opened on 18.07.2014. Financial bids of the bidders were opened on

04.08.2014 after M/s NESPAK and CCCC declared them technically

compliant. CR-NORINCO emerged as lowest bidder with bid price of

USD 2.139 Billion. Breakup of final Contract Price:-

i) Contract Price of Civil Works= USD 531,681,818

ii) Contract Price of Consultancy Services = USD 24,000,000

iii) Contract Price of E&M Works (inclusive of 6%

Withholding/Income Tax) = USD 922,500,000

iv) Sub-total (a to c) = USD 1,478,181,818

v) Contingencies = USD 147,818,182

vi) Total Price = USD 1,626,000,000

Chinese side agreed to sublet Civil Works of the project to Pakistan side

resulting in significant savings- again an unprecedented achievement.

Significant economies / price reductions achieved in E&M Work’s price.

Effective negotiations yielded project cost savings of approximately USD

Page 9: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

9

660,818,182/- with unprecedented support of the Chinese Government

and gracious flexibility shown by CR-NORINCO. Transparent tendering

process of Civil Works carried out by LDA yielded a further saving of PKR

5.97 Billion.

21. COMPARISON OF COST BETWEEN ORANGE LINE AND OTHER WORLD’S

METRO COST

Cost comparison of some of metros in the world on Per Km basis is as

below:

Sr.# Name of Metro Cost in million USD / Km

a Orange Line

Core project cost USD 1,478 M

Core cost + Contingencies USD 1626 M

54.50

59.95

b Mumbai (Completed in 2014) 60.7 (adjusted)

c Pune (Completion in 2018) 62.21 (adjusted)

d Jaipur (Completed in 2015) 64.3 (adjusted)

e Copenhagen (Completed in 2002) 69.8 in 2002 prices

f Jakarta (Completion in 2017) 117.11

According to latest research on the subject the per Km cost of Metro Trains

generally range between USD 50 Million and USD 100 Million.

22. Resource Prioritization

Health & Education sectors are on top priority on Government’s agenda.

Sometimes, it is falsely reported that these sectors are not in the priority list of

the Government. The spending of funds during the year is governed by various

factors and also reviewed on monthly basis. Different schemes by the

Government are being carried out at different stages. New schemes in other

departments like Health and Education involved various steps which takes time

to materialize and transfer the benefits at grass root level. Sometimes delay

occur in conceiving the scheme, studies conducted for project, delays in

procurement process etc. majority of the projects are continuously funded in

many years. During planning & feasibility not huge funds are required but after

approval & research instantaneous funding is required to kick start a new project.

Keeping in view the efficiency required for a project, re-appropriation is being

Page 10: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

10

done for a project. Re-appropriation of funds is basically a need based

mechanism for project which is under direct control of Administrative Bodies &

Provincial Secretaries within a department. The purpose is to ensure the

presence of cash flow as per requirement of a certain project realizing the need

& the funds are later re-cooped after the funds for the same project are released.

Glimpse of fund allocation on Education, Health, development and non-

development from 2010 till 2016

Item 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16

Total Budget 221,381,277,771

271,566,405,822

297,318,120,628

336,112,070,843

377,570,395,938

427,787,996,265

Provincial 82,532,379,000

109,993,128,000

110,684,146,000

132,568,784,000

142,967,658,000

202,483,844,000

Education 42,845,914,000

58,244,373,000

49,830,200,000

65,408,208,000

59,244,959,000

108,137,451,000

Development 15,427,954,000

25,825,125,000

9,953,150,000

31,840,574,000

23,417,387,000

50,564,000,000

Non Development

27,417,960,000

32,419,248,000

39,877,050,000

33,567,634,000

35,827,572,000

57,573,451,000

Health 39,686,465,000

51,748,755,000

60,853,946,000

67,160,576,000

83,722,699,000

94,346,393,000

Development 16,933,053,000

18,886,825,000

21,942,875,000

21,810,747,000

31,918,844,000

30,725,000,000

Non Development

22,753,412,000

32,861,930,000

38,911,071,000

45,349,829,000

51,803,855,000

63,621,393,000

District Gov Provincial

138,848,898,771

161,573,277,822

186,633,974,628

203,543,286,843

234,602,737,938

225,304,152,265

Education 113,282,697,681

131,275,389,687

153,199,102,132

168,342,319,540

194,467,025,576

185,844,894,741

Development 3,336,673,167

1,986,745,042

2,382,904,646

4,032,109,695

7,527,512,170

2,230,439,837

Non Development

109,946,024,514

129,288,644,645

150,816,197,486

164,310,209,845

186,939,513,406

183,614,454,904

Health 25,566,201,090

30,297,888,135

33,434,872,496

35,200,967,303

40,135,712,362

39,459,257,524

Development 2,185,813,065

1,424,086,946

1,598,008,159

1,180,851,812

815,640,675

403,821,394

Non Development

23,380,388,025

28,873,801,189

31,836,864,337

34,020,115,491

39,320,071,687

39,055,436,130

Page 11: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

11

23. Environment Assessment Report

The project consultant M/s NESPAK prepared Environmental Impact

Assessment (“EIA”) report of the proposed project area as required under Punjab

Environmental Protection (Amendment) Act, 2012 of the Pakistan Environmental

Protection Act 1997 (“PEPA”).

LDA submitted the EIA Report to the Environmental Protection Agency, Punjab

(“EPA”). Public hearing regarding EIA study was conducted on June 30, 2015 at

Al-Hamra Cultural Complex, Gaddafi Stadium by EPA in which public in large

participated. EIA report was also placed before the review committee of EPA

which constitutes the leading environmentalists. The EPA approved the Project

on July 9, 2015 in accordance with the law, and after fulfilling all the legal

requirements.

The NESPAK recommended measures to mitigate any impacts, but

concomitantly concluded that the proposed project and the overall affects of the

project would be positive and would reduce the air & noise pollution in the vicinity.

24. HISTORIC BUILDINGS

Following historic buildings protected under Punjab Special Premises

(Preservation) Ordinance 1985 falls in the vicinity of project alignment:-

a) Lakshmi Building (Minimum distance from Orange Line is 10.4 meters)

b) General Post Office (G.P.O)

c) Aiwan-e-Auqaf (Shah Chiragh) Building

d) Supreme Court Registry Building

e) Mauj Darya Darbar & Mosque

Following buildings protected under Antiquities Act 1975 falls along the alignment

of Orange Line project:

1. Shalamar Garden (Minimum distance from Orange Line is 29 meters on one

end and 22.8 meters on the other end.)

2. Gulabi Bagh Gateway (Minimum distance from Orange Line is 20.9 meters)

3. Buddhu’s Tomb (Minimum distance from Orange Line is 18.1 meters)

4. Chauburji (Minimum distance from Orange Line is 15.9 meters)

5. Zeb-Un-Nisa Tomb (Minimum distance from Orange Line is 33.5 meters)

There is another old building of Saint Andrew’s church in the vicinity which is not

protected either under Punjab special premises (preservation) ordinance 1985

or Antiquities Act 1975, which will also be safeguarded.

Page 12: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

12

25. GROUND BORNE VIBRATIONS (GBV)

The project consultant NESPAK-CEC JV have taken all possible measures to

protect and preserve these national heritage sites. Special considerations have

been given in design to protect these heritage sites from any adverse effect. A

complete vibration analysis has been conducted by NESPAK for trains to be

operated with maximum operating speed less than 80 Km/hr and average

operating speed of 38-42 km/hr. According to German standards, the maximum

vibration velocity at the foundation level of the heritage structure shall be less

than 3mm/sec. The theoretical 2D FEA model of pier-ground system of light rail

train viaduct system similar to Orange line project, it is concluded that beyond a

distance of 10-12 m from the main pier of rail the ground borne vibrations (GBV)

are negligible (<0.30 mm/sec).

For historical buildings in proximity of The Mall road, Cut & Cover technique has

been adopted to protect the integrity of façade of these archaeological sites. In

order to protect these special premises from ground induced vibrations, whole

structure is bifurcated into two structural parts i.e. U shaped structure inside

Inverted U. There is an isolation/gap between these two structural components

to preclude the impact of train induced vibrations on adjacent buildings. Sand

cushion at the bottom of underground structure and mechanical dampers under

rail track will be provided as per design to further mitigate the effect of vibrations

and noise.

The elevated structure of the Orange line is very slim and sleek and will not

create any significant visual barrier. Furthermore, the Soffit level of the deck is

12m that will allow a clear view of the monument while traveling on ground.

Shifting of track 200 ft away towards populated area from these heritage sites

will only result in unnecessary displacement of hundreds of people. The Director

General, Archaeology has already issued NOC under section 22 of Antiquities

Act, 1975 & Punjab Special Premises (Preservation) Ordinance, 1985.

Page 13: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

13

26. HERITAGE SITES NEAR METRO PROJECTS IN THE WORLD

Following is the detail of the Metro Train passing in different Countries near old

historical buildings.

Sr.No Country City

Historical Place Construction Date

Distance from Metro

1

India

Bangalore Vidhana Soudha 1952-56

25 m ( just beside boundary wall)

2 Karnataka High Court 1881 50 m

3

Chennai

Madras Law College 1891 Just beside boundary wall

4 Ripon Building 1913 Just beside boundary wall

5 Victoria Public Hall 1890 Just beside boundary wall

6

Jaipur Hawa Mahal 1799 40 m

7 Rojgareshwar Mahadev & Khastran Mahadev Temple (200 Years old)

200 years old Demolished

8 Hyderabad Moazzam Jahi Market 1935 41 m

9 Dehli Karol Bagh Temple 1931 10 m

10 U.S.A New York

Bell Laboratories, Manhattan

1929 Between the building (1934-80) 46 years

11 Italy Rome Colosseum 70-80 AD 12.48 m

12 Greece

Athens

Temple of Hephaestus

415 BC 55 m

Stoa of Attalos 138 BC, Re-const 1952

Just beside boundary wall

13 France Paris

Pont de Bir-Hakelm Bridge (between Two old buildings)

1904 6 m (over the Bridge)

14 Germany

Berlin Bode Museum 1797 18.47 m

15 Oberbaum Brucke Bridge

1732 0 m (over the Bridge)

16

Cologne Deutz Abbey

1003 (re-const 1970)

82.17 m

17 Hahnen Gate

13th Century 25.40 m

18 Malaysia

Kualalumpur

Jamek Masjid 1907 24 m

19 Austria

Vienna

Hofburg Palace 13th Century 150 m

20 NHM Wien 1784 108 m

21 Palace of Justice 1881 8 m

22 Parliament Building 1883 71 m

23 Secession 1897 45 m

24 Theatermuseum 17th Century 135 m

Page 14: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

14

27. NO NEGATIVE VISUAL IMPACT

The elevated structure of the Orange line is very slim and sleek and will not

create significant visual barrier. Furthermore, the Soffit level of the deck is 12m

that will allow a clear view of the monument while traveling on ground. Maximum

permissible sharp turning radius and curves adopted near these monuments to

ensure maximum possible distance with no adverse effect and keeping land

acquisition/displacement of general public at minimum. Shifting of track 200 ft

away towards populated area from these heritage sites will only result in

unnecessary displacement of hundreds of people.

The Orange Line Metro Train project is being constructed in conformity with the

Antiquities Act, 1975 and the Punjab Special Premises (Preservation) Ordinance,

1985. As per requirement of Law, a formal request for issuance of NOC was

made to Director General, Archaeology. After detailed deliberations and long

correspondence, Archaeology Department of Government of Punjab agreed with

the stance of LDA that there would be no adverse effect on heritage sites due to

this train. Consequently Director General, Archaeology issued NOC under

section 22 of Antiquities Act, 1975 & Punjab Special Premises (Preservation)

Ordinance, 1985.

28. Land Acquisition and Resettlement

a) LDA started procedure under Land Acquisition Act, 1894 (“Act”) to acquire

the land required for the project, a preliminary Notice under Section 4 of the

Act was issued for lands likely to be required for the project. Notice under

Section 5 of the Act was issued seeking objections from the public, public

hearing was conducted on 30.11.2015. After complying with the procedure

under the Land Acquisition Act, 1894, a Notification No. SR/7120 dated

14.12.2015 under Section 6 of the Act was issued by the office of the

Commissioner, Lahore Division, Lahore. The Collector then issued notices

under section 9 of the act ibid which was served upon the individuals

whereby objection/claims with respect to compensation and measurements

made under section 8 for the land to be acquired were invited and a public

hearing was also conducted. After inquiring into the objections the Land

Acquisition Collector announced the award.

Page 15: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

15

b) The land price was assessed by District Price Assessment Committee

(DPAC). An Independent Evaluator, approved from State Bank of Pakistan,

was also approached to assess the market price of land. In this project, land

compensation price is almost twice as compared to that of Metro Bus System

completed in 2012. General public have been benefitted with 15%

Compulsory Acquisition charges for the acquired land. 100% amount of

Structural Assessment as Disturbance Allowance and Business Allowance

has been paid to the affectees.

c) A certain section of affectees which did not have ownership documents

since they have been in possession of the building/land for more than 50

years has also been considered by a committee constituted on the directions

of Chief Minister for amicable settlement of these kind of issues.

i. Bangali Building:

Evacuee Trust Property Board property, 95 families were given lump sum

compensation @ Rs. 1 million per family from special grant of Chief

Minister.

ii. Maharaja Building:

Government of Punjab property through Chief Settlement Commissioner,

58 families were given a lump sum compensation @ Rs. 1 million per

family from special grant of Chief Minister.

iii. Evacuee Trust Building (Geeta Bhawan) near Lakshami Chowk:

ETPB property, 30 residences and 7 shops were affected. ETPB and the

occupants to decide the compensation package.

iv. Institute for disadvantaged children (school near Jain Mandir):

ETPB property, lump sum amount of Rs. 1 Million was granted to the

school as shifting allowance, from special grant of Chief Minister. The

Committee also recommended to reconstruct the dismantled portion of

the Institute after completion of the Project.

v. Postal Flats:

LDA will reconstruct the dismantled portion of postal flats after completion

of the Project. The committee also requested to Post Master General to

provide the occupants of the affected portion of flats, a handsome amount

of money equal to the house requisition as per scale wise rate of federal

government so that they can have a reasonable rented apartment in the

vicinity during construction period (Approximately 1 year). It is worth to

Page 16: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

16

mention that out of 76 occupants that are being effected, 60 occupants

are in service while 16 occupants are illegal. It is further recommended

that a lump sum amount of Rs. 0.1 Million per flat may be given as shifting

allowance to the effected occupants from special grant of Chief Minister.

vi. Parachute Colony near Railway station:

Katchi Abadi on Railway land, comprising18 houses. A lump sum grant

of Rs. 1 Million per family as compensation from special grant of Chief

Minister on compassionate grounds was recommended (however, the

case is in court of law).

vii. Lahore Khas Residential area (Kapoor Thalla House, Katcha Lake

Road, Jain Mandir, Edward Road etc):

The occupants without proper land ownership documents will get a

compensation package out of CM special grant at a lump sum rate of Rs.

2.5 million per marla for the residential area and of Rs. 3.5 million per

marla for commercial area.

viii. Qazal Bash Trust properties at Lakshmi Station:

The Qazalbash Waqf area measuring 10 Kanal 13 Marla 013 Sft is

required for the project. Since the matter is sub-judice, it was proposed

that further deliberations may be done for mutual settlement between

the Trust and the occupants for deciding share of both parties in the

compensation package.

The GoPb has taken every step to ensure minimum nuisance to the public largely

in lieu of Land Acquisition for the project and allocated Historic Package of 20

Billion Rupees for affectees. In addition to it, Grant in Aid of Rupees 1.6 Billion

for those having deficient title documents was given.

29. Lahore without project.

Lahore, the provincial capital of Punjab, second largest city of Pakistan with a

population of about 11 million is the 16th most populace city in the world. The

city’s population has been growing at an annual growth rate of about 3%. The

rapidly growing population coupled with extremely high motorized (registered

vehicles increased by double between 2001 and 2008) has resulted in chronic

traffic congestion, caused mainly by a) lack of adequate public traffic system and

b) inefficient and poor conditions of existing transport system.

Page 17: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

17

Transportation system in Lahore is in a state of crisis. If the issue is not

addressed with proper engineering solution based on the studies referred above,

extreme congestion, long commute times, choking air pollution, deadly traffic

accidents and inadequate public transport will remain fate of Lahore. Billions of

Rupees in economic productivity are lost due to congestion. Air and noise

pollution severely impact health and quality of life. Transportation is thus one of

the most significant contributors to climate change, accounting for 25 % of global

emissions in absence of effective mass transit schemes.

30. Damages arising out of delay in project.

Total contract price of civil works (A)

555,681,818 USD

Rate of liquidated damages for delay (B)

0.02 % of A (per day)

Liquidated Damages (C) (0.02/100)x 555,681,818 =111,136.4 USD/day =11.64 million PKR/day (@104.7/USD)

Max. Liquidated Damages @10% of A

55.57 million USD = 5818.18 million Pkr

local contractor idling charges 21 million PKR per day

Accumulative damages PKR 51 million per day for any delay

31. Repercussions for Stoppage of Project Execution:

a. The Chinese assistance of approximately USD 45 Billion earmarked for

portfolio of CPEC projects may be jeopardized.

b. Even though the Orange Line project is not a part of CPEC, it is being treated

as a model for implementation of early harvest projects of the CPEC by

China.

c. The whole gamut Pakistan-China Economic relationship can be subjected to

serious setback.

d. It may send a wrong signal to all of Pakistan’s other bilateral and multilateral

donors.

e. Commitment Charges of approximately USD 5 Million will be imposed on

Government of Pakistan annually.

f. Dispute in connection with the Loan Agreement, if not resolved through

friendly consultation, shall be referred to China International Economic and

Trade Arbitration Commission (CIETAC) for arbitration.

g. Liquidated damages for delay in Civil Works completion will be payable by

PMA @0.02 % per day of the Contract price of Civil Works up to a maximum

of 10 % under the Commercial Contract. (page 422 of paper book ;

commercial contract sub clause 9.3; delay in completion)

Page 18: PROJECT BRIEF OF LAHORE ORANGE LINE METRO TRAIN

18

32. Who is opposing and Why?

A limited group of rich and privileged people who have the hobby to criticise every

development project and have no interest in public transport. Same group which

opposed and delayed the canal widening project and signal free projects, and

caused loss of crores of rupees are again objecting the public sector project

which will benefit a common man. Political opponents who are afraid of

Government popularity in case the project becomes successfully operational in

time are also opposing the project.


Recommended