ON TARGET
Dollars = $3.74 million
Injuries = 210
Average = $17,820.62 per occurrence
Average = 5 per month
Project BULLSEYESTF – Impact
Financials provided via Risxfacs – July 1, 2006 to May 1, 2010
ON TARGET
Project BULLSEYESTF – Cause Map Solutions
Communication
TrainingHazard recognition
Checklist/commentsCoaching
SelfPeer
Observing10 minute topicsInternal Processes
Loading practicesRouting changesInspection/Maintenance
Customer Connect
FeedbackPotential HazardsCleaningDesignWork thru marketing/sales
Company Focus
Incentive/MotivationSafety vs. Productivity
ON TARGET
Project BULLSEYESTF – Projected Reductions
20% reduction in STF injuries
Avg. 4 injuries per month
$213,847
1,257,926 cases
11,034 stops
1,055 routes
25% reduction in STF injuries
Avg. 3 injuries per month
$427,695
2,515,852 cases
22,068 stops
2,110 routes