    FEMA Benefit-Cost Analysis

    Re-engineering (BCAR)

    Project Cost Guidance Methodology Report

    Version 4.5

    May 2009

  • 8/4/2019 Project Cost Guidance

    2/87

  • 8/4/2019 Project Cost Guidance

    3/87

    i

    Table of Contents

    Purpose.....................................................................................................................................................1 Introduction: Problem Statement..............................................................................................................1Recommendations: Proposed Methodology to Address Problem Statement ............................................. 2Section 1: Cost Estimating Methodology Programming and User Overview............................................. 4

    Step 1: Developing an Estimate of Pre-Construction Costs.......................................................................8Step 2: Developing an Estimate of Construction Costs ............................................................................. 8Step 3: Developing an Estimate of Ancillary Costs....................................................................................9Step 4: Developing an Estimate of Annual Maintenance Costs............................................................... 10

    Step 5: Adjusting Your Estimate to Account for Project Timing .............................................................. 10Step 6: Review and Confirmation of the Estimate .................................................................................. 12

    Section 2 Provide Specific Guidance......................................................................................................14Section 3 Benefit-Cost Analysis Handout Tool ....................................................................................... 15Conclusions: Reasons for Selection of Proposed Methodology ................................................................ 16APPENDIX A: Mitigation Strategy Flow Charts.......................................................................................... 17

    APPENDIX B: Sample Estimates................................................................................................................34APPENDIX C: Cost Estimating Storyboard................................................................................................ 67Sample BCA Tool Cost Estimating Screenshot .......................................................................................... 68APPENDIX D: Scope Builder Checklists ..................................................................................................... 69

    Tables

    Table 1. Proposed Hazard Mitigation Project Types ................................................................................. 2Table 2. Recommended Proxy Values ...................................................................................................... 9

  • 8/4/2019 Project Cost Guidance

    4/87

    ii

  • 8/4/2019 Project Cost Guidance

    5/87

    1

    Purpose

    This Benefit-Cost Analysis Re-engineering (BCAR) report is provided for use by the Federal Emergency

    Management Agency (FEMA) Technical Advisory Group (TAG) to review and approve the recommended

    methodology to provide project cost guidance for the FEMA benefit-cost analysis (BCA) modules. The

    methodology report is part of a larger effort to re-engineer the FEMA BCA methods, modules, guidance,

    and training to improve the BCA process.

    Introduction: Problem Statement

    The BCA modules were developed to calculate project benefits and project costs as part of the effort to

    evaluate the cost-effectiveness of proposed hazard mitigation projects. However, since project benefits

    are more difficult to determine than project costs, the FEMA BCA modules and guidance devote most of

    their efforts to estimating and documenting project benefits. As a result, there is little guidance

    provided on how to properly and completely estimate and document project costs used in the BCAmodules. For this reason, many applicants submit BCAs with project costs that are incomplete,

    inaccurate, or poorly documented.

    In response to this problem, FEMA Headquarters has requested that additional guidance be provided to

    assist applicants with the preparation of complete and well-documented project costs as part of the

    BCAR initiative. Specifically, additional guidance was requested on the following five project cost

    estimate issues:

    1. What hard construction and ancillary costs related to a variety of mitigation project types are

    acceptable?

    2. Should contingencies and allowances for change orders be accounted for in project cost

    estimates?

    3. What are the acceptable sources of data for the mitigation project cost estimates?

    4. What is an appropriate level of detail to be included in a mitigation project cost estimate?

    5. Can we provide helpful hints and defined values to help the grant applicant develop complete

    and accurate cost estimates?

    At present, the inclusion of contingencies and allowances for change orders is not being considered by

    the mitigation directorate; these items are more relevant to FEMAs Public Assistance Program, and are

    not applicable to the majority of mitigation projects being considered.

    Specifically, the URS BCA team has been asked to address 16 specific mitigation project cases comprised

    of five hazards (flood, wind, earthquake, landslide, and wildfire) and two to five project types per

    hazard, including structural and non-structural mitigation alternatives, as shown in Table 1. While the

    estimating methodology is applicable to additional hazards and project types, sample scope items,

  • 8/4/2019 Project Cost Guidance

    6/87

    2

    estimating flowcharts, and sample estimates are only provided for the 16 specific mitigation project

    cases shown in Table 1. Any project types that do not fit into the 16 defined types shall be defined as

    other.

    Table 1. Proposed Hazard Mitigation Project Types

    Hazard Mitigation Project Type

    Flood Acquisition

    Elevation

    Relocation

    Wet and dry floodproofing/floodwalls

    Drainage structures (culverts, storm drains, etc.)

    Wind A combination of strengthening load path members and connections and addingshutters/impact-resistant glazing

    Tornado safe roomsEarthquake Strengthen structural elements

    Anchor/brace non-structural elementsLandslide Retaining structures (gabions, piles, mechanically stabilized earth systems, etc.)

    Toe erosion armoring

    Surface/subsurface drainage improvements

    Bio-engineered surface erosion protection

    Fire Vegetation control (including fire breaks around critical facilities/roads)

    Fire-resistant roofing

    Fire suppression

    Recommendations: Proposed Methodology to Address Problem

    Statement

    To address the problem of inadequate project cost estimates as well as the project cost estimate issues

    raised by the BCAR initiative, the URS BCA team proposes the following methodology to provide

    expanded cost estimating guidance:

    Our efforts focused on three main areas:

    1. Guidance on how to develop a complete estimate is presented in the 16 hazard/mitigation

    project type flow charts and sample estimates provided in Appendices A and B. These flowcharts and sample estimates are further supported by definitions and references contained in

    the help area of the BCAR tool.

    2. An overall estimating approach that walks the users through a six step process designed to help

    account for construction and non-construction related costs associated with a mitigation

    project. This process is defined and outlined in the storyboard presented in Appendix C.

  • 8/4/2019 Project Cost Guidance

    7/87

    3

    3. A Scope Builder Checklist is designed for reference by Applicants/subapplicants prior to their use

    of the BCA cost estimating tool. This Handout will provide guidance to assist in the preparation

    of an effective scope of work and will assist the preparer in the identification and collection of

    the cost information needed to use the BCA module. The Checklists are provided in Appendix D.

  • 8/4/2019 Project Cost Guidance

    8/87

    4

    Section 1: Cost Estimating Methodology Programming and User

    Overview

    The critical part of developing an accurate cost estimate is having a defined scope of work that itemizes

    the specific work elements (tasks) that will be accomplished as part of the mitigation project. Once

    these specific work elements are defined they can be translated into work element descriptions for

    which quantities and unit prices can be estimated. The flow charts, sample estimates, and scope builder

    tables provided in Appendices A, B, and D offer guidance and suggestions as to typical work elements

    associated with the various mitigation measures. Those resources are not intended to be all inclusive,

    and each mitigation project may have different and unique elements that must be included in the scope

    of work and cost estimate.

    An estimate can be developed in a variety of ways, but most estimates fall into the following categories:

    1. Published unit price information for defined work elements can be obtained from commercialestimating sources such as RS Means and Marshall & Swift. This information is copyrighted and

    users typically purchase the right to use their information. Note that these published cost

    sources are regularly updated and if the estimate is prepared using old unit price information,

    the estimate should be updated to reflect current pricing.

    2. Historical Costs for completing the similar projects can be obtained from local contractors,

    building officials, State hazard mitigation officers, and project owners. Note that these historical

    costs should be escalated to ensure current pricing.

    3. Contractor Bids or estimates for completing a specific scope of work or project are typically

    completed at the time of the bid and account for inflation over the course of the project.

    The accuracy of each of these estimates will vary according to the level of detail in the scope of work

    and work elements to be estimated. Preliminary estimates are applicable for initial project screening or

    scoping, but detailed costs estimates should be used when submitting project applications for funding

    approvals.

    The cost estimating portion of the BCA methodology shall use a step by step process of simple inquiries,

    dynamic help screens, and input boxes to walk users through the six steps associated with developing a

    complete cost estimate for their mitigation project. This six-step process outlined below follows the

    users selection of a hazard and mitigation strategy and consists of:

    1. Developing an estimate of pre-construction or non-construction costs

    2. Developing an estimate of construction costs

    3. Developing an estimate of ancillary costs

    4. Developing an estimate of annual maintenance costs

  • 8/4/2019 Project Cost Guidance

    9/87

    5

    5. Adjusting the estimate to account for project timing and currency of the data used in the

    estimate

    6. Reviewing and confirming the cost estimate

    At any time during this process users can input a previously completed estimate, an explanation of their

    estimating approach, and their estimate file (spreadsheet). Each step in that process is explained and

    illustrated in the following paragraphs. Prior to entering the cost estimation portion of the BCAR tool,

    users will have chosen a hazard mitigation strategy and defined a mitigation project type for a specific

    structure. The initial cost estimation screen will pre-populate the project and structure names and the

    mitigation option will be displayed for reference. At this point users will be asked to:

    verify the projects useful life in years;

    verify that a detailed scope of work has been developed; and

    answer whether or not a detailed cost estimate has already been developed for the project.

    Depending on the answers to the above questions, users will be prompted to input a completed

    estimate, explanation/justification, and upload their file or they will be directed to the estimating tool.

    This process is presented in screen shot CE1 of the BCAR cost estimating storyboard shown in Appendix

    C. As noted in screen shots CE2 and CE3 of the storyboard, if a completed estimate is input (rather than

    built), users will be queried to ensure that the estimate includes applicable construction markups and

    that it reflects current pricing. If it does not include those items, users will be led through a process of

    adding them to their previously completed estimate.

    Once users have selected the option of developing a detailed cost estimate, they will follow the six-step

    process outlined above as they develop their project cost estimate.

  • 8/4/2019 Project Cost Guidance

    10/87

    8

    Step 1: Developing an Estimate of Pre-Construction Costs

    In this section, users will be asked to develop an estimate of all pre-construction costs associated with

    the mitigation project. Pre-construction costs are also called non-construction costs and may include

    those non-construction costs an owner incurs in the planning, permitting, and management of a

    mitigation project.

    For example, pre-construction costs for an acquisition project may include the costs for propertysurveys, property appraisal fees, transaction and legal fees, the cost to purchase property and

    improvements, and the cost of professional services needed for environmental or engineering

    assessments and/or managing the process.

    This process is presented in screen shot CE2a of the BCAR cost estimating storyboard shown in Appendix

    C. As noted in the two screen shots, users can enter a lump sum amount (if a completed estimate is

    available) or they can use the cost tool to develop their estimate by building on the pre-populated cells.

    In all cases, flexibility is built into the cost estimating tool to allow users to input specific work elements

    that are applicable to their mitigation project rather than use the default line items that were developed

    for each of the 16 mitigation project types.

    Within the cost estimating tool, the column format is consistent across all six steps. Each template has a

    description of the work element, followed by a box to check the source of the unit pricing used (i.e.,

    published data, historical data, or contractor data), the quantity and unit associated with each work

    element, the unit cost of the work and a task cost, which is the product of the quantity and the unit cost.

    Additional rows can be added to introduce work elements that were not included in the default format.

    Step 2: Developing an Estimate of Construction Costs

    In this section, users will be asked to develop an estimate of all hard construction costs associated

    with the mitigation project. Hard construction costs are costs associated with the actual physical

    altering of the property or structure. In the acquisition example, costs associated with site demolitionmight include the removal of hazardous materials, general demolition activities, well and septic

    abandonment, utility disconnections, and utility removals.

    This process is presented in screen shot CE2b of the BCAR cost estimating storyboard shown in Appendix

    C. As noted in the two screen shots, users can enter a lump sum amount (if a completed estimate is

    available) or they can use the cost tool to develop their estimate by building on the pre-populated cells.

    In all cases, flexibility is built into the cost estimating tool to allow users to input specific work elements

    that are applicable to their mitigation project rather than use the default line items that were developed

    for each of the 16 mitigation project types.

    Within the cost estimating tool, the column format is consistent across all six steps. Each template has a

    description of the work element, followed by a box to check the source of the unit pricing used (i.e.,

    published data, historical data, or contractor data), the quantity and unit associated with each work

    element, the unit cost of the work and a task cost, which is the product of the quantity and the unit cost.

    Additional rows can be added to introduce work elements that were not included in the default format.

  • 8/4/2019 Project Cost Guidance

    11/87

    9

    Step 3: Developing an Estimate of Ancillary Costs

    Once users input a detailed construction cost estimate, they will be queried to ensure that all general

    construction and ancillary costs have been accounted for. Specifically, users will be asked if their unit

    prices/costs have accounted for any of the following cost elements:

    A/E Costs associated with project design and construction administration

    General Contractor costs for general requirements and general conditions

    General Contractor costs for overhead and profit

    Project management costs associated with executing the project

    Permit fees, testing costs, and plan approval fees

    Mobilization and Demobilization costs

    Depending upon the answer to each of the above questions, users will be asked to include those costs in

    their estimate. This can be accomplished in two ways. First, users can revisit their pre-construction andconstruction costs and add a line item for the ancillary costs not previously included. Alternatively, they

    can use industry standard proxy values as shown below in Table 2. These specific value ranges are

    referenced using RS Means construction cost data as a resource. However, other national cost data

    sources have similar values.

    Table 2. Recommended Proxy Values

    Cost Element Proxy Value

    Mobilization and Demobilization 3% of the hard

    construction cost

    Construction General Conditions and Requirements (i.e.,

    costs associated with a general contractors field supervision

    costs and job site costs, such as temporary services and

    utilities, safety and security measures, quality control, and

    administrative submittals)

    10% of the hard

    construction cost

    General Contractor Overhead Costs, Insurance Costs and

    Payment/Performance Bond Costs, and Profit

    10-20% of the hard

    construction cost

    Architectural and Engineering Services to cover the cost of

    basic design and inspection services normally associated with

    a construction project, such as preliminary engineering

    analysis, preliminary design, final design, and construction

    inspection.

    10% of the hard

    construction cost

    Project Management costs to cover the applicant costs to

    manage the project during the evaluation, design, permitting,

    coordination, and construction phases

    4% of the hard

    construction cost

  • 8/4/2019 Project Cost Guidance

    12/87

    10

    This process is presented in the BCA Tool screen shot shown in Appendix C. As noted in the screen shots,

    the users can select a proxy value that will be included in the mitigation project estimate.

    Step 4: Developing an Estimate of Annual Maintenance Costs

    The cost of maintaining mitigation measures is often not accounted for in mitigation cost estimates. If

    maintenance is required for the proper and effective implementation of the mitigation measure, it

    should be included in the cost estimate. In this section, the users will be asked to develop an estimate of

    the annual maintenance costs necessary for the proper and effective implementation of the mitigation

    project and to identify the number of years maintenance will be required (which is typically the project

    useful life). The software will then calculate the present worth of the annual maintenance costs and add

    that value to the project cost. This process is presented in screen shot CE3 of the BCAR cost estimating

    storyboard shown in Appendix C.

    Step 5: Adjusting Your Estimate to Account for Project Timing

    In this section, the users will be asked if the estimate reflects current prices. Price currency is a function

    of two separate issues. First, was the estimate prepared using current pricing data and second, was the

    estimate escalated to the midpoint of construction to account for anticipated inflation in labor,

    materials, and equipment over the term of the construction project.

    With regard to the current pricing question, historical data must be escalated to todays values and

    published data may vary based on the date of the published source. With regard to the issue of inflation

    over the course of a project, the issue is the length of time between when the estimate was developed

    and the start/completion of construction. Estimates are typically escalated to the midpoint of

    construction to account for the inflation that will occur over the project lifecycle (design, bidding, and

    construction).

    As noted in screen CE3 of the storyboard (Appendix C), users will be asked if their estimate reflects

    current prices and if not, they will be asked to input information on the type of construction project, the

    cost basis year, the construction start year and the construction end year. The software will calculate

    the escalation according to the methodology described in the following paragraphs.

    The escalation is based on a computed 5-year annual building construction escalation rate for each

    FEMA Region based on Engineering News RecordBuilding Cost Index for cities within each region. The

    5-year average annual escalation used in this step is based on index values from December 2002 to

    December 2007. The recommended escalation factors are provided in the following table.

  • 8/4/2019 Project Cost Guidance

    13/87

    11

    FEMA Region(s)2002 - 2007 Average Annual

    Escalation Rate

    1 6.4%

    2 3.9%

    3 5.0%4 and 10 4.3%

    5 4.4%

    6 and 9 4.9%7 5.4%

    8 5.2%

    We recommend that the escalation factors be used to escalate cost data from the date of its source to

    the anticipated mid-point of construction of the proposed project. Escalation can be calculated using the

    formula:

    EC = PC*(1+E)N

    Where EC = Escalated cost

    PC = Present cost

    E = Escalation rate

    N = Estimated number of years from data date of date source to midpoint of

    construction

    Project schedules must indicate reasonable periods for project design, bid and contract award and

    construction. Cost data should be escalated to the estimated mid-point of construction. The mid-point

    of construction is calculated as the time for design, bid and contract award plus one-half the

    construction period. Based on the precision of the data, including proposed project schedules, we

    recommend that times to mid-point of construction be rounded upward to the next full year for

    escalation purposes

    Project schedules should be developed by experienced project and construction professionals. However,

    a general guide to estimating project timelines as a function of project construction cost is provided on

    the following table.

    15,000$ 2 Months35,000$ 4 Months

    125,000$ 2 Months

    200,000$ 3 Months

    350,000$ 4 Months500,000$ 6 Months

    $500,000 to $1 Million$1 to $5 million

    $5 million

    Construction Estimate

    Fee < $50,000Fee > $50,000

    Ramp-up and close-

    out timeDesign

    Design & Construction Monthly ExpenditureRate Assumptions

  • 8/4/2019 Project Cost Guidance

    14/87

    12

    Example 1: A proposed drainage mitigation project located in FEMA Region 3 is identical to a project

    completed by the applicant in 2005. The proposed project is scheduled for completion by the end of

    2010. The project cost in 2005 was $300,000 plus $30,000 design and construction inspection fees.

    Estimated Schedule:

    Design fee approx. $30,000

    Design time = ($30,000/$15,000 per month) + 2 months = 4 months

    Construction cost = $300,000

    Construction time = ($300,000/125,000) + 2 months = 4.4 months

    Time to mid-point of construction = 4 months design + (4.4 months construction/2) = 6.2months. Round up to 1 year from start of design.

    Escalated Project Cost

    Estimated project start data January 2009

    Escalation period = (Estimated start date + Time to midpoint of construction) Datasource year

    (2009 + 1) 2005 = 5 years

    EC = ($330,000)*(1+0.05) 5

    EC = $421,173

    Example 2: The $1,750,000 construction cost estimate for a proposed relocation in FEMA Region 6 is

    based on 2008 published construction cost data. The estimated design and construction inspection fee is

    $175,000. The project is expected to be completed in 2011.

    Estimated Schedule

    Design fee $175,000

    Design time = ($175,000/$35,000 per month) + 4 months = 9 months

    Construction cost = $1,750,000

    Construction time = ($1,750,000/$350,000 per month) + 4 months = 9 months

    Time to midpoint of construction = 9 months design + (9 months construction/2) = 13.5months. Use 2 years from start of design.

    Escalated Project Cost

    Estimated project start January 2009

    Escalation period = (Estimated start date + Time to midpoint of construction) Datasource year

    (2009 + 2) 2008 = 3 years

    EC = (1,925,000)*(1+0.049)3

    EC = $2,222,067

    Step 6: Review and Confirmation of the Estimate

    Finally, users will be required to certify that their cost estimate is complete and includes all costs

    associated with the mitigation project scope of work. Queries should require the users to be instructed

    to:

    Compare each item in the cost estimate with the scope of work to make certain that all work

    necessary to complete the project has been included

  • 8/4/2019 Project Cost Guidance

    15/87

    13

    Review the unit and quantity of each item to confirm accuracy of the total costs

    Assure that items that have been presented as lump sums are appropriate and cannot be readily

    broken into units, and

    Accept the following certification language by checking a box and entering the preparers name:

    Information provided in this section has been reviewed and found to be complete.

    The information represents a full and complete description of the components of the

    project scope of work and associated costs.

  • 8/4/2019 Project Cost Guidance

    16/87

    14

    Section 2 Provide Specific Guidance

    The flow charts provided in Appendix A lead the estimator through specific steps in developing a cost

    estimate that is consistent with the scope of work, transparent, and contains only the appropriate lump

    sum items. To assist the estimator in developing a complete and comprehensive cost estimate, the

    following specific guidance will be provided within the cost portion of the BCAR effort.

    Estimating process flow charts: Appendix A provides 16 cost estimation process flow charts that

    detail the general steps required in developing reliable estimates, and offer specific suggestions for

    each hazard and mitigation combination identified in Table 1. These estimating process flow charts

    are designed to be referenced in Step 1 of the cost estimating process, and provide users with a

    road map for developing a valid cost estimate.

    See Figures 1-16 in Appendix A.

    Sample estimate template: A sample cost estimate will be prepared for each of the 16 hazard

    mitigation project types covered in Table 1. These estimates are designed to be referenced duringeach step of the cost estimating process, providing the users with a typical approach to developing a

    valid cost estimate. It is important to note that these estimates are only samples, and each

    mitigation project may have different descriptions of the items of work, different quantities,

    different units, and different unit costs based on each projects specific scope of work.

    Estimating helpful hints: Dynamic help features will be available to guide the users through the

    software and define terms and processes associated with each step in the process. Examples of

    these helpful hints are shown in the layout of the main cost estimation screen shown in Appendix A.

  • 8/4/2019 Project Cost Guidance

    17/87

    15

    Section 3 Benefit-Cost Analysis Handout Tool

    The Benefit Cost Analysis (BCA) Handout is designed for reference by Applicants and subapplicants prior

    to their use of the BCA tool. This Handout will provide guidance to assist in the preparation of an

    effective scope of work and will assist the preparer in the identification and collection of the cost

    information needed to use the BCA module. This handout will consist of the following elements and willbe developed once the software is beta tested:

    1. Overview of the BCA Tool

    2. Scope Builder checklists for each of the 16 mitigation project types covered in the estimating

    module. These checklists will provide an itemized breakdown of the primary work tasks and

    subtasks and are provided in Appendix D. (To be finalized after the tool structure is completed.)

    3. Estimating Flow Charts for each of the 16 mitigation project types as provided in Appendix A

    4. Sample Cost Estimates for each of the 16 mitigation project types as provided in Appendix B

  • 8/4/2019 Project Cost Guidance

    18/87

    16

    Conclusions: Reasons for Selection of Proposed Methodology

    In conclusion, the URS BCA team recommends the proposed methodology because it provides a simple,

    straightforward approach to supplying comprehensive cost estimate guidance for a wide range of

    hazard mitigation projects. The proposed methodology does not require recreating, linking, or updating

    any existing cost estimating tools or products. Instead, users will be referred to those tools/productswhere applicable, and would be expected to learn tools or purchase products to address shortcomings

    in their project cost estimates, as illustrated in the flow charts. This will simplify programming, reduce

    development costs, and avoid licensing issues with firms that have proprietary estimating products.

    Specifically, the proposed methodology addresses the five project cost estimate issues identified earlier

    as follows:

    Provides guidance on what hard construction and ancillary costs should be included for a variety of

    mitigation project types

    Does not include contingencies or allowances for change orders

    Reinforces to the users that historical cost data is as useful as standard cost estimating references

    Provides guidance on an appropriate level of detail to be included in a mitigation project cost

    estimate

    Provides helpful hints, reference values, and sample cost estimates to guide the user through the

    cost estimating process

  • 8/4/2019 Project Cost Guidance

    19/87

    17

    APPENDIX A: Mitigation Strategy Flow Charts

  • 8/4/2019 Project Cost Guidance

    20/87

    18

    Flood

    Flood-Proofing

    Step 1Preconstruction Cost

    Non-construction costs for planning,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Site Topographic Surveyo Feasibility Studieso Materials Evaluations

    Ancillary Cos

    Mobil

    Const

    condit Gene

    A/E s

    docum

    Estima

    Adjus

    Rev

    A-1 Cost Estimate

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Flood Proofing

    Wet Flood Proofing Dry Flood Proofing

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

  • 8/4/2019 Project Cost Guidance

    21/87

    Flood

    Relocation

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o New Site Phase I EnvironmentalSite Assessment

    o Site Purchas New Locationso Property Surveyo Transaction Closing Fees

    Step 2

    Construction Costs (Develop hard costs toexecute the project)

    Identify All Work Elementso Site Acquisitiono Transport Facilityo Foundation Constructiono Site Improvements and

    Infrastructureo Old Site Restoration

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Co

    Mobi

    Cons

    cond

    Gene

    A/E sdocu

    Estima

    Adjus

    Re

    A-2 Cost Esti

    R

  • 8/4/2019 Project Cost Guidance

    22/87

    Flood

    Drainage

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listed below)o Hydrology Studieso Environmental Assessmento Compliance Studies

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Site Acquisitiono Demolitiono Site Restorationo Site Maintenanceo Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using appropriate

    units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Cos

    Mobiliz

    Constr

    conditi

    Gener

    A/E se

    docum

    Estimat

    Adjust

    Re

    A-3 Cost Estimate

  • 8/4/2019 Project Cost Guidance

    23/87

    Flood

    Elevation

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Site Topographic surveyo Existing Floor Elevation Certification

    Survey

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elements

    o Elevate Facilityo Foundation Constructiono Utilities Adjustmentso Building Accesso Site Restorationo Professional Feeso Demolition of Existing Facilityo Construction of New Facilityo Site Restorationo Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo

    Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Costs (AIn

    Mobilizatio

    Constructi

    conditions

    General C A/E servic

    document

    Estimate A

    Adjust Est&

    Review

    A-4 Cost Esti

  • 8/4/2019 Project Cost Guidance

    24/87

    Flood

    Acquisition

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Property Surveyso Appraisal Feeso Property Purchaseo Transaction Closin Fees

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Site Acquisitiono Demolitiono Site Restorationo Site Maintenanceo Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Cos

    Mobiliz

    Constrconditi

    Gener

    A/E se

    docum

    Es

    Ad

    A-5 Cost Esti

    A

  • 8/4/2019 Project Cost Guidance

    25/87

  • 8/4/2019 Project Cost Guidance

    26/87

    Earthquake

    Strengthen Structural Elements

    Step 1Preconstruction Cost

    Non-construction costs for lannin , desi n,

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Work Area Preparationo Reinforce Facilityo Strengthen Structural Memberso Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Co

    Mob

    Cons

    cond

    Gene

    A/E s

    docu

    Esti

    Adj

    R

    A-7 Cost Estimate Process Earthquake-

    Strengthen Structural Elements

  • 8/4/2019 Project Cost Guidance

    27/87

    Wildfire

    Vegetative Control

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Erosion/Environmental Studyo Property Survey

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Vegetative Control (Fuel Reduction)o Fire Breakso Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Cos

    Mobiliz

    Constr

    conditi

    Gener

    A/E se

    docum

    Estima

    Adjus

    Re

    A-8 Cost Estimate Pr

    Vegetative

  • 8/4/2019 Project Cost Guidance

    28/87

    Wildfire

    Fire Resistant Exterior

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Appraisers Feeso Property Survey

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Roofingo Walls

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Cos

    Mobiliz

    Constr

    conditi

    Gener

    A/E se

    docum

    Estima

    Adjus

    Re

    A-9 Cost Estimate Process Wildf

    Resistant Exterior

  • 8/4/2019 Project Cost Guidance

    29/87

  • 8/4/2019 Project Cost Guidance

    30/87

    Wind

    Strengthen Load Path Elements/Shutters

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Feasibility Studyo Structural Assessment Of Existing

    Structural Systemo Feasibility Analysis Of Alternatives

    Step 2

    Construction Costs (Develop hard costs toexecute the project)

    Identify All Work Elementso Temporary Relocation Costso Strengthen Structural Memberso Strengthen Load Path Connectionso Strengthen Building Openingso Impact Resistant Glazingo Install Shutterso Reengineer Ancillary Equipment

    Connectionso Selective Demolitiono Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo Current Bidso

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Cos

    Mobiliz

    Constr

    conditi

    Gener

    A/E se

    docum

    Estimat

    Adjust

    Rev

    A-11 Cost Estimate Pro

    Strengthen Load Path Ele

  • 8/4/2019 Project Cost Guidance

    31/87

    Wind

    Tornado Shelter

    Step 1

    Preconstruction Cost Non-construction costs for planning, design,

    permitting, and managing mitigation projects Typical Preconstruction Activities (listed

    below)o Site Acquisitiono Inspection Feeso Property Survey

    Step 2Construction Costs (Develop hard costs to

    execute the project) Identify All Work Elements

    o Strengthen Designated ShelterAreas

    o Provide Emergency Accesso Retrofit Services For Emergency

    Useo Site Acquisitiono New Constructiono Site Improvementso Professional Fees

    Identify Cost Data Sources

    o Published vs. Historicalo Current Bidso

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Cos

    Mobiliz

    Constr

    conditi

    Gener

    A/E se

    docum

    Estimat

    Adjust

    Rev

    A-12 Cost Estimate P

    Sh

  • 8/4/2019 Project Cost Guidance

    32/87

    Landslide

    Slope Drainage Improvements

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Site Surveyo Geotechnical Boringso Environmental Assessment and

    Compliance Studies

    Step 2Construction Costs (Develop hard costs to

    execute the project) Identify All Work Elements

    o Gradingo Install Channel Liningo Outlet Structureso Dimensionso Professional Feeso Excavationo Drain Installationo Ancillary Structureso Dimensionso Professional Services

    Identify Cost Data Sourceso Published vs. Historicalo Current Bidso

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Costs

    Mobiliza

    Constru

    conditio

    Genera

    A/E ser

    docume

    Estimate A

    Adjust Es

    Review

    A-13 Cost Estimate Process Landsl

    Slope Drainage Improvements

  • 8/4/2019 Project Cost Guidance

    33/87

    Landslide

    Bio-Engineered Slope Stabilization

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Environmental Assessment andCompliance Reviews

    o Agricultural Assessmento Geotechnical Studieso Typographic Surveys

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Site Gradingo Bio-Engineered Slope Protectiono Dimensionso Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Cos

    Mobiliz

    Constr

    conditi

    Gener

    A/E se

    docum

    Estimat

    Adjust E

    Revie

    A-14 Cost Estimate Process Landslide-

    Bio-Engineered Slope Stabilization

  • 8/4/2019 Project Cost Guidance

    34/87

    Landslide

    Toe Armoring

    Step 1Preconstruction Cost

    Non-construction costs for planning, design,permitting, and managing mitigation projects

    Typical Preconstruction Activities (listedbelow)

    o Hydrology/Hydraulic Studieso Environmental Assessment and

    Compliances Studieso Geotechnical Studies

    Step 2Construction Costs (Develop hard costs to

    execute the project)

    Identify All Work Elementso Surface Water (if required)o Armoring Approacho Site Gradingo Professional Fees

    Identify Cost Data Sourceso Published vs. Historicalo Current Bids

    Develop Cost Estimateo Itemize cost elements using

    appropriate units of measurement

    o Limit lump sums to less than 20% of

    Task line items

    Ancillary Costs (Ad

    In T Mobilization

    Construction

    conditions/re

    General Con

    A/E services

    documents

    Estimate Annu

    Adjust Estima

    & Da

    Review an

    A-15 Cost Estimate Proc

    Armor

  • 8/4/2019 Project Cost Guidance

    35/87

  • 8/4/2019 Project Cost Guidance

    36/87

    34

    APPENDIX B: Sample Estimates

  • 8/4/2019 Project Cost Guidance

    37/87

    35

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant City of Lowland, GAProject Title Lowland Civic Center FloodproofingPreparer:

    HAZARD: FloodMITIGATION STRATEGY Floodproofing

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    $

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $

    Excavating, trench or continuous footing, commonearth, 3/8 C.Y. excavator, 1' to 4' deep, excludessheeting or dewatering

    260.00 B.C.Y. $7.55 $1,963

    Excavating, trench or continuous footing, commonearth, trim sides and bottom for concrete pours,

    excludes sheeting or dewatering

    5,700.00 S.F. $0.81 $4,617

    Structural concrete, in place, continuous stripfooting, 36" wide x 12" deep, includes forms(4uses), reinforcing steel, and finishing

    130.00 C.Y. $255.00 $33,150

    Curing, burlap, 12 oz., 4 uses assumed 23.00 C.S.F. $28.50 $656

    Structural concrete, in place, grade wall, 12" thickx 8' high, includes forms(4 uses), reinforcing steel,and finishing

    65.00 C.Y. $375.00 $24,375

    Backfill, light soil, by hand, no compaction 65.00 L.C.Y. $27.00 $1,755

    Backfill, 6" layers, compaction in layers, handtamp

    65.00 E.C.Y. $18.50 $1,203

    Anchor bolt, J-type, plain steel, 1/2" dia x 18" L,incl nut & washer

    300.00 Ea. $18.15 $5,445

    Column base plates, structural, heavy, 100-tonproject, over 150 lb each, A992 steel, shopfabricated, incl shop primer

    900.00 Lb. $2.07 $1,863

    Precast wall panel, exposed aggregate,uninsulated, low rise, 8' x 8' x 4" thick, 3000 psi

    5,700.00 S.F. $33.00 $188,100

    Precast column, small, rectangular to 12' high.,3000 psi, includes material only

    600.00 L.F. $113.00 $67,800

    Waterstop, fittings, rubber, flat, dumbbell or centerbulb, flat cross, 3/8" thick x 9" wide

    60.00 Ea. $68.50 $4,110

    Caulking & Sealants, backer rod, polyethylene,1/4" dia

    1,200.00 L.F. $1.12 $1,344

    Caulking & Sealants, acrylic latex caulk, white,1/2" x 1/2", in place

    1,200.00 L.F. $2.40 $2,880

    Self-raising flood gate @ pedestrian entrance 1.00 Ea. $13,250.00 $13,250

    Self-raising flood gate @ vehicle entrance 1 Ea. $41,700.00 $41,700

    $-

    2Construction

    (Specify Phases)

    Construction Subtotal $394,210

  • 8/4/2019 Project Cost Guidance

    38/87

    36

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Insurance and Bonds 1 LS 3.5% $13,797

    Site supervision and contract requirements 1 LS 10% $40,801

    G.C. overhead & profit 1 LS 28% $125,666

    Permits and Review Fees 1 LS 0.5% $2,872

    Construction -General

    General Construction Phase Subtotal $183,137

    Preparation of construction documents 1 LS 10% $57,735

    Applicant Cost to Manage Design 1 LS 2% $11,547

    Applicant Cost to Manage Construction 1 LS 4% $23,094

    3

    Applicant Costs

    Applicant Cost Subtotal $92,375

    Maintenance $-

    $-

    $-4 Maintenance

    Annual Maintenance Subtotal $-

    5 Escalation Escalation (to mid-point of construction) 12 Months 0.42% $28,890

    Pre-construction subtotal $-

    Construction subtotal $394,210

    General Construction Phase Subtotal $183,137

    Applicant Cost Subtotal $92,375

    Annual Maintenance Subtotal $-

    6Estimate Review& Confirmation

    Escalation Subtotal $28,890

    PROJECT TOTAL $698,613

  • 8/4/2019 Project Cost Guidance

    39/87

    37

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Riverside Township, PAProject Title Township Office Building RelocationPreparer: H. Waters

    HAZARD: Flood

    MITIGATION STRATEGY RelocationEstimating

    StepProject Phase Description Quantity Unit Unit Cost Task Cost

    Pre-purchase Phase I Environmental SiteAssessment

    1 Ea. $2,500.00 $2,500

    Site purchase - new location 3 Acres $25,000 $75,000

    Property boundary survey 1500 LF $2 $2,370

    Legal Fees 1 LS $1,500 $1,500

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $81,370

    Building demolition, small buildings or singlebuildings, masonry, elevated slabs, includes 20 milehaul, excludes salvage, foundation demolition ordump fees

    100,000 C.F. $0.29 $29,000

    Rubbish handling, loading & trucking, chute loaded,including 2 mile haul, cost to be added to demolitioncost.

    1,300 C.Y. $45.50 $59,150

    Dump charges, typical urban city, buildingconstruction materials, includes tipping fees only

    1,400 Ton $90.00 $126,000

    Seeding, wildflower, 0.10 lb. per M.S.F., tractorspreader

    40 M.S.F. $17.35 $694

    A Substructure $-

    Standard Foundations 8,000 SF $2.40 $19,200

    Slab on Grade 8,000 SF $4.45 $35,600

    Basement Excavation 8,000 SF $0.24 $1,920

    Basement Walls 8,000 SF $3.33 $26,640

    B Shell $-

    Roof Construction 8,000 SF $6.25 $50,000

    Exterior Walls 8,000 SF $8.56 $68,480

    Exterior Windows 8,000 SF $4.76 $38,080

    Exterior Doors 8,000 SF $0.81 $6,480

    Roof Coverings 8,000 SF $2.88 $23,040C Interiors 8,000 SF $-

    Partitions 8,000 SF $4.05 $32,400

    Interior Doors 8,000 SF $2.60 $20,800

    Fittings 8,000 SF $0.48 $3,840

    Wall Finishes 8,000 SF $1.26 $10,080

    Floor Finishes 8,000 SF $7.00 $56,000

    Ceiling Finishes 8,000 SF $4.71 $37,680

    2Construction

    (Specify Phases)

    D Services $-

    Plumbing Fixtures 8,000 SF $5.26 $42,080

    Domestic Water Distribution 8,000 SF $1.40 $11,200

    Rain Water Drainage 8,000 SF $0.89 $7,120

    Terminal & Package Units 8,000 SF $7.94 $63,520

    Sprinklers8,000 SF

    $2.40$19,200

    Electrical Service/Distribution 8,000 SF $2.33 $18,640

    Lighting and Branch Wiring 8,000 SF $9.00 $72,000

    Communications and Security 8,000 SF $2.40 $19,200

    Other Electrical Systems 8,000 SF $0.13 $1,040

    E Equipment & Furnishings $-

    Other Equipment 8,000 SF $2.08 $16,640

    Parking lot, 60 degree angle parking, 3" bituminouspaving, 6" gravel base 50 Car $965.01 $48,251

    2 Construction(SpecifyPhases)

    Concrete sidewalk, 4" thick, 4" gravel base, 5' wide 150 L.F. $24.71 $3,706

  • 8/4/2019 Project Cost Guidance

    40/87

    38

    $-

    Construction Subtotal $967,680

  • 8/4/2019 Project Cost Guidance

    41/87

    39

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Insurance and Bonds 1 LS 3.5% $33,869

    Site supervision and contract requirements 1 LS 10% $100,155

    G.C. overhead & profit 1 LS 28% $308,477

    Permits and Review Fees 1 LS 0.5% $7,458

    Construction -General

    General Construction Phase Subtotal $449,959

    Preparation of construction documents 1 LS 10% $141,764

    Applicant Cost to Manage Design 1 LS 2% $28,353

    Applicant Cost to Manage Construction 1 LS 4% $56,706

    3

    Applicant Costs

    Applicant Cost Subtotal $226,822

    Maintenance $-

    $-

    $-4 Maintenance

    Annual Maintenance Subtotal $-

    5 Escalation Escalation (to mid-point of construction) 19 Months 0.42% $112,320

    Pre-construction subtotal $81,370

    Construction subtotal $967,680

    General Construction Phase Subtotal $449,959

    Applicant Cost Subtotal $226,822

    Annual Maintenance Subtotal $-

    6Estimate Review &

    Confirmation

    Escalation Subtotal $112,320

    PROJECT TOTAL $1,838,151

  • 8/4/2019 Project Cost Guidance

    42/87

    40

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Palisades County, New Jersey Dept. of RoadsProject Title Hill Bench Road StabilizationPreparer: N. Wetfoot

    HAZARD: LandslideMITIGATION STRATEGY Drainage Improvements

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Site survey 1 LS $5,000.00 $5,000

    Geotechnical Borings 1 LS $27,500.00 $27,500

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $32,500

    Minor site demolition, patio/carport, bituminous, to6" thick, with hand held air equipment, excludeshauling

    1,000 S.F. $1.29 $1,290

    Demo guard rail, corrugated steel 600 L.F. $2.38 $1,428

    Demo guard rail, wood posts 75 Ea. $5.95 $446

    Rubbish handling, loading & trucking, machineloading truck, includes 2 mile haul, cost to beadded to demolition cost.

    20 C.Y. $18.30 $366

    Rubbish handling, up to 8 C.Y. truck, loading &trucking, haul, per mile, includes 2 mile haul, costto be added to demolition cost.

    100 C.Y. $0.81 $81

    Dump charges, typical urban city, reclamationstation, usual charge, includes tipping fees only 30 Ton $104.50 $3,135

    Excavating, trench or continuous footing, commonearth, 1/2 C.Y. excavator, 1' to 4' deep, excludessheeting or dewatering

    80 B.C.Y. $5.65 $452

    Excavating, trench or continuous footing, commonearth, 1/2 C.Y. excavator, 4' to 6' deep, excludessheeting or dewatering

    50 B.C.Y. $5.65 $283

    Drainage geotextiles, fabric, laid in trench,polypropylene, ideal conditions 450 S.Y. $1.90 $855

    Bedding, for pipe and conduit, crushed orscreened bank run gravel, excludes compaction 500 L.C.Y. $36.00 $18,000

    Corrugated plastic tubing, perforated or plain, inrolls, 8" diameter, excludes excavation and backfill 500 L.F. $10.30 $5,150

    Piping, HDPE, butt fusion joints, 40' lengths, 24"diameter, SDR 21 50 L.F. $116.00 $5,800

    Excavating, trench backfill, 1 C.Y. bucket, minimalhaul, front end loader, wheel mounted, excludesdewatering

    30 L.C.Y. $2.17 $65

    2Construction

    (Specify Phases)

    Asphaltic concrete pavement, for highways andlarge paved areas, pavement replacement overtrench, 6" thick, for paving projects 300 tons orless add for trucking

    125 S.Y. $61.99 $7,748

  • 8/4/2019 Project Cost Guidance

    43/87

    41

    EstimatingStep Project Phase Description Quantity Unit Unit Cost Task Cost

    Manholes, concrete, precast, 4' I.D., 6' deep,excludes base, excavation, backfill, frame andcover

    2 Ea. $1,799.87 $3,600

    Manhole steps, heavyweight cast iron, 8" x 9" 4 Ea. $38.00 $152

    Catch basins, frames and covers, cast iron, heavytraffic, 24" diameter, 400 lb., excludes footing,excavation, and backfill

    2 Ea. $469.97 $940

    Fine grade, slopes, steep, gentle, finish grading 200 S.Y. $0.20 $40

    Soil stabilization, geotextile fabric, woven, heavyduty, 600 lb. tensile strength

    200 S.Y. $2.34 $468

    Rip-rap, random, broken stone, 18" minimumthickness, machine placed for slope protection, notgrouted

    200 S.Y. $84.00 $16,799

    Guide/Guard rail, corrugated steel, galvanized steelposts, install wrap around end section 2 Ea. $165.00 $330

    Guide/Guard rail, corrugated steel, galvanized steelposts, install metal guide/guard rail, double face,steel posts 6' - 3" O.C., W6x8 posts

    600 L.F. $32.50 $19,500

    2Construction(Specify

    Phases)

    Construction Subtotal $86,928

    Insurance and Bonds 1 LS 3.5% $3,042Site supervision and contract requirements 1 LS 10% $8,997

    G.C. overhead & profit 1 LS 28% $27,711

    Permits and Review Fees 1 LS 0.5% $796

    Construction -General

    General Construction Phase Subtotal $40,546

    Preparation of construction documents 1 LS 10% $12,747

    Applicant Cost to Manage Design 1 LS 2% $2,549

    Applicant Cost to Manage Construction 1 4% $5,099

    3

    Applicant Costs

    Applicant Cost Subtotal $20,396

    Maintenance $

    $

    $4 Maintenance

    Annual Maintenance Subtotal $

    5 Escalation Escalation (to mid-point of construction) 9 Months 0.33% $3,729

    Pre-construction subtotal $32,500

    Construction subtotal $86,928

    General Construction Phase Subtotal $40,546

    Applicant Cost Subtotal $20,396

    Annual Maintenance Subtotal $

    6Estimate Review &

    Confirmation

    Escalation Maintenance Subtotal $3,729

    PROJECT TOTAL $184,100

  • 8/4/2019 Project Cost Guidance

    44/87

    42

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Lowland, MSProject Title Elevate Town Hall BuildingPreparer: P. Riser

    HAZARD: FloodMITIGATION STRATEGY Elevation

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    $

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $

    Selective demolition- wood frame, includesloading and 5 mile haul to dump

    2,500.00 C.Y. $17.75 $44,375

    Demolition, concrete slab on grade, reinforced, 5,400.00 S.F. $5.95 $32,130

    Footings and foundations demolition, removeconcrete footing, 2' thick, 3' wide

    510.00 L.F. $22.00 $11,220

    Selective demolition, timber piles, up to 14",diameter

    900.00 V.L.F. $9.30 $8,370

    Dump charges, typical urban city, buildingconstruction materials, includes tipping fees only

    150.00 Ton $90.00 $13,500

    Bulk Asbestos Removal, remove VAT from floorby hand, incl. disp. and tools

    4,800.00 S.F. $1.83 $8,784

    Waste Packaging, Handling & Disposal,containerize bagged material in drums, per 3 CFdrum

    25.00 Ea. $12.40 $310

    Waste Packaging, Handling & Disposal, collectand bag bulk material, by hand, 3 CF

    25.00 Ea. $11.85 $296

    Asbestos contaminated waste Packaging,Handling & Disposal, disposal charges,

    5.00 C.Y. $175.00 $875

    Decontamination Containment Area Demolition &Cleanup, fine clean exposed substrate, wet wipesubstrate

    4,800.00 S.F. $0.88 $4,224

    Excavating, grade beams 100.00 B.C.Y. $6.65 $665

    Piles, concrete, precast, prestressed; 10" square, 1,900.00 V.L.F. $19.55 $37,145

    Piles, mobilization, 1 1,900.00 V.L.F. $1.68 $3,192

    Structural concrete, in place, grade beams 100.00 C.Y. $249.00 $24,900

    Structural concrete, in place, handicap accessramp, railing both sides, 5' wide, 120.00 L.F. $650.00 $78,000

    Cast-in-place concrete beam and slab, 75 PSFsuperimposed load 5,400.00 S.F. $17.95 $96,930

    Wood roof, truss, 4/12 slope, 24" O.C., 44' to 60'span

    5,400.00 S.F. $6.26 $33,794

    Wood siding, 2"x6" studs 24"OC, insulated wall,1" x 4" vertical T&G redwood 3,024.00 S.F. $11.30 $34,165

    2Construction

    (Specify Phases)

    Windows, aluminum, projecting, insulated glass,4'-5" x 5'-3" 57.00 Ea. $622.95 $35,508

  • 8/4/2019 Project Cost Guidance

    45/87

    43

    EstimatingStep Project Phase Description Quantity Unit Unit Cost Task Cost

    Door, aluminum & glass, with transom, narrowstile, double door, hardware, 6'-0" x 10'-0"opening

    1.00 Opng. $2,221.21 $2,221

    Door, steel 18 gauge, hollow metal, 1 door with

    frame, no label, 3'-0" x 7'-0" opening 2.00 Opng. $1,073.67 $2,147

    Asphalt roofing, strip shingles, premiumlaminated, multi-layered, Class A, 4" slope, 260-300 lbs/SQ

    5,700.00 S.F. $2.14 $12,181

    Flashing, aluminum, no backing sides, .019" 360.00 S.F. $3.88 $1,397

    Gravel stop, aluminum, extruded, 4", mill finish,.050" thick 360.00 L.F. $8.85 $3,186

    Wood partition, 5/8" fire rated gypsum boardface, 5/8" fire rated gypsum board base, 2x4 @16", 5/8" fire rated gypsum board opposite face,no insulation

    2,700.00 S.F. $4.99 $13,469

    1/2" fire rated gypsum board, taped & fi nished,painted on metal furring 3,024.00 S.F. $3.85 $11,644

    Door, single leaf, wood frame, 3'-0" x 7'-0" x 1-3/8", birch, solid core 27.00 Opng. $521.02 $14,067

    Toilet partitions, cubicles, ceiling hung, plasticlaminate 6.00 Unit $874.28 $5,246

    Painting, interior on plaster and drywall, walls &ceilings, roller work, primer & 2 coats 4,860.00 S.F. $0.71 $3,450

    Ceramic tile, thin set, 4-1/4" x 4-1/4" 540.00 S.F. $6.26 $3,381

    Carpet tile, nylon, fusion bonded, 18" x 18" or24" x 24", 35 oz 3,780.00 S.F. $4.47 $16,899

    Terrazzo, maximum 810.00 S.F. $22.79 $18,462

    Vinyl, composition tile, maximum 810.00 S.F. $3.11 $2,518

    Acoustic ceilings, 3/4" mineral fiber, 12" x 12"tile, concealed 2" bar & channel grid, suspendedsupport

    5,400.00 S.F. $4.71 $25,433

    Water closet, vitreous china, bowl only with flushvalve, wall hung 6.00 Ea. $1,465.48 $8,793

    Urinal, vitreous china, wall hung 3.00 Ea. $1,055.95 $3,168

    Lavatory w/trim, vanity top, PE on CI, 19" x 16"oval

    6.00 Ea. $956.20 $5,737

    Kitchen sink w/trim, countertop, PE on CI, 24" x21", single bowl 1.00 Ea. $1,006.87 $1,007

    Service sink w/trim, PE on CI, corner floor, 28" x28", w/rim guard 3.00 Ea. $1,813.30 $5,440

    Water cooler, electric, wall hung, 8.2 GPH 2.00 Ea. $1,131.71 $2,263

    2Construction(Specify

    Phases)

    Water cooler, electric, wall hung, wheelchairtype, 7.5 GPH 1.00 Ea. $2,013.13 $2,013

  • 8/4/2019 Project Cost Guidance

    46/87

    44

    EstimatingStep Project Phase Description Quantity Unit Unit Cost Task Cost

    Gas fired water heater, commercial, 100< F rise, 95MBH input, 86 GPH

    2.00 Ea. $5,601.54 $11,203

    Roof drain, CI, soil, single hub, 4" diam, 10' high 3.00 Ea. $1,502.62 $4,508

    Roof drain, CI, soil, single hub, 4" diam, for eachadditional foot add

    95.00 Ea. $27.81 $2,642

    Rooftop, single zone, air conditioner, offices,

    10,000 SF, 31.67 ton5,400.00 S.F. $7.94 $42,885

    Wet pipe sprinkler systems, steel, light hazard, 1floor, 10,000 SF

    5,400.00 S.F. $2.40 $12,960

    Service installation, includes breakers, metering,20' conduit & wire, 3 phase, 4 wire, 120/208 V, 400A

    1.00 Ea. $6,623.60 $6,624

    Feeder installation 600 V, including RGS conduitand XHHW wire, 400 A

    50.00 L.F. $94.48 $4,724

    Switchgear installation, incl switchboard, panels &circuit breaker, 400 A

    1.00 Ea. $7,251.83 $7,252

    Receptacles incl plate, box, conduit, wi re, 16.5 per1000 SF, 2.0 watts per SF

    5,292.00 S.F. $3.14 $16,619

    Wall switches, 1.0 per 1000 SF 5,400.00 S.F. $0.25 $1,350

    Miscellaneous power, 1.2 watts 5,400.00 S.F. $0.29 $1,566

    Central air conditioning power, 6 watts 5,076.00 S.F. $0.91 $4,619

    Fluorescent fixtures recess mounted in ceiling, 2watt per SF, 40 FC, 10 fixtures per 1000 SF

    5,400.00 S.F. $4.52 $24,408

    Communication and alarm systems, includesoutlets, boxes, conduit and wire, fire detectionsystems, 25 detectors

    1.00 Ea. $3,073.06 $3,073

    Generator sets, w/battery, charger, muffler andtransfer switch, gas/gasoline operated, 3 phase, 4wire, 277/480 V, 15 kW

    1.00 kW $689.36 $689

    Directory boards, plastic, glass covered, 36" x 48" 1.00 Ea. $1,375.27 $1,375Detection Systems, heat detector, smoke detector,ceiling type, excl. wires & conduit

    8.00 Ea. $171.03 $1,368

    Emergency light units, nickel cadmium batteryoperated, twin sealed beam light, 25 W, 6 V each

    8.00 Ea. $769.77 $6,158

    Bituminous roadway, two lanes, 3-1/2" thickpavement, 3" thick gravel base, 24' wide

    100.00 L.F.$91.00

    $9,100

    2Construction

    (Specify Phases)

    Parking lot, 90 degree angle parking, 3" bituminouspaving, 6" gravel base

    25.00 Car$965.00

    $24,125

    Bituminous sidewalk, 1" thick paving, 4" gravelbase, 5' width

    200.00 L.F.$7.00

    $1,400

    Septic system, 2000 gal tank, 6' high precast pit,2@6'-6" diameter, 50 feet from building

    1.00 Ea. $10,628.46 $10,628

    $$$

    2 Construction(Specify Phases)

    Construction Subtotal $831,785

    Insurance and Bonds 1 LS 3.5% $29,112

    Site supervision and contract requirements 1 LS 10% $86,090

    G.C. overhead & profit 1 LS 28% $265,156

    Permits and Review Fees 1 LS 0.5% $6,061

    Construction -General

    General Construction Phase Subtotal $386,419

    Preparation of construction documents 1 LS 10% $121,820

    3

    Applicant CostsApplicant Cost to Manage Design 1 LS 2% $24,364

    Maintenance $

    $

    $4 Maintenance

    Annual Maintenance Subtotal $

    5 Escalation Escalation (to midpoint of construction) 14 Months 0.36% $ 61,056

    Pre-construction subtotal $

    Construction subtotal $831,785

    General Construction Phase Subtotal $386,419

    Applicant Cost Subtotal $194,913

    Annual Maintenance Subtotal $

    6Estimate Review& Confirmation

    Escalation Subtotal $ 61,056

    PROJECT TOTAL $1,474,173

  • 8/4/2019 Project Cost Guidance

    47/87

    45

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Shaking Heights, CA Fire DepartmentProject Title Heavy Equipment Storage StabilizationPreparer: 0

    HAZARD: EarthquakeMITIGATION STRATEGY Anchor Non-structural Component

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Remove equipment from storage shelves andremove shelves to storage

    160 Hrs. $28.75 $4,600

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $4,600

    Walls and partitions demolition, brick wall, 4" thick 280 S.F. $2.13 $596

    Rubbish handling, 100' haul, load, haul to chute anddumping into chute, cost to be added to demolitioncost.

    5 C.Y. $46.00 $230

    Dump charges, typical urban city, buildingconstruction materials, includes tipping fees only 7 Ton $90.00 $630

    Rubbish handling, up to 8 C.Y. truck, loading &

    trucking, haul, per mile, includes 2 mile haul, cost tobe added to demolition cost.

    50 C.Y. $0.83 $42

    Channel framing, structural steel, field fabricated,C4x5.4, incl cutting & welding 160 L.F. $34.49 $5,518

    Acoustical slotted concrete masonry unit (CMU),partition, 2000 psi, 4" thick, NRC .65 type A-1,includes mortar, excludes scaffolding, horizontalreinforcing, vertical reinforcing and grout

    280 S.F. $10.40 $2,912

    Concrete masonry unit (CMU), high strength, hollow,5000 psi, 4" x 8" x 16", includes mortar andhorizontal joint reinforcing every other course,excludes scaffolding, grout and vertical reinforcing

    280 S.F. $7.35 $2,058

    #3 and #4 reinforcing steel bars, placed vertically,ASTM A615 1,000 Lb. $1.90 $1,900

    $

    2Construction

    (Specify Phases)

    Construction Subtotal $13,886

    Insurance and Bonds 1 LS 3.5% $486

    Site supervision and contract requirements 1 LS 10% $1,437

    G.C. overhead & profit 1 LS 28% $4,427

    Permits and Review Fees 1 LS 0.5% $124

    Construction -General

    General Construction Phase Subtotal $6,474

    Preparation of construction documents 1 LS 10% $2,036

    Applicant Cost to Manage Design 1 LS 2% $407

    Applicant Cost to Manage Construction 1 LS 4% $814

    3

    Applicant Costs

    Applicant Cost Subtotal $3,258

    Maintenance $

    $

    $4 Maintenance

    Annual Maintenance Subtotal $

    5 Escalation Escalation (to mid-point of construction) 9 Months 0.41% $748Pre-construction subtotal $4,600

    Construction subtotal $13,886

    General Construction Phase Subtotal $6,474

    Applicant Cost Subtotal $3,258

    Annual Maintenance Subtotal $

    6Estimate Review& Confirmation

    Escalation Subtotal $748

    PROJECT TOTAL $28,966

  • 8/4/2019 Project Cost Guidance

    48/87

    46

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Shaking Dunes, SCProject Title Earthquake Retrofit of Public Work BuildingPreparer: J. E. Orler

    HAZARD: EarthquakeMITIGATION STRATEGY Strengthen Structural Elements

    Estimating Step Project Phase Description Quantity Unit Unit Cost Task Cost

    $

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $

    Office systems furniture, cubicle, selectivedemolition

    14,400 S.F. $0.25 $3,600

    Ceiling demolition, suspended ceiling, mineral fiber,on suspension system, remove

    4,080 S.F. $0.64 $2,611

    Walls and partitions demolition, drywall, nailed 5,000 S.F. $0.38 $1,900

    Walls and partitions demolition, metal or woodstuds, finish two sides, plywood

    300 S.F. $2.60 $780

    Rubbish handling, 100' haul, load, haul to chuteand dumping into chute, cost to be added todemolition cost.

    75 C.Y. $46.00 $3,450

    Rubbish handling, dumpster, 30 C.Y., 10 toncapacity, weekly rental, includes one dump perweek, cost to be added to demolition cost.

    1 Week $990.00 $990

    Temporary floor protection, exterior plywood, 2uses, 1/2" thick

    10,800 S.F. $0.91 $9,828

    Steel plate, structural, for connections & stiffeners,1/2" T, shop fabricated, incl shop primer

    600 S.F. $23.00 $13,800

    Welding, structural steel, in field, cleaning &welding plates/bars/rods to existingbeams/columns/trusses

    750 L.F. $66.00 $49,500

    Gypsum wallboard, on walls, standard,w/compound skim coat (level 5 finish), 1/2" thick

    5,300 S.F. $1.70 $9,010

    2Construction

    (Specify Phases)

    Suspended Acoustic Ceiling Tiles, fiberglassboards, film faced, 2' x 2' or 2' x 4' x 5/8" thick

    4,080 S.F. $1.43 $5,834

    Paints & Coatings, walls & ceilings, interior,concrete, drywall or plaster, oil base, 2 coats,smooth finish, roller

    10,000 S.F. $0.65 $6,500

    Flooring demolition, remove temporary floorprotection

    10,800 S.F. $0.81 $8,748

    Systems furniture, replace secretarial work station,minimum

    3 Ea. $3,075.00 $9,225

    Systems furniture, replace management workstation, minimum

    10 Ea. $3,500.00 $35,000

    Systems furniture, replace executive work station,minimum

    2 Ea. $7,800.00 $15,600

    $

    2Construction(Specify

    Phases)

    Construction Subtotal $176,377

  • 8/4/2019 Project Cost Guidance

    49/87

    47

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Insurance and Bonds 1 LS 3.5% $6,173

    Site supervision and contract requirements 1 LS 10% $18,255

    G.C. overhead & profit 1 LS 28% $56,225

    Permits and Review Fees 0 LS 0.5% $

    Construction -General

    General Construction Phase Subtotal $80,653

    Preparation of construction documents 1 LS 10% $25,703

    Applicant Cost to Manage Design 1 LS 2% $5,141

    Applicant Cost to Manage Construction 1 LS 4% $10,281

    3

    Applicant Costs

    Applicant Cost Subtotal $41,125

    Maintenance $

    $

    $4 Maintenance

    Annual Maintenance Subtotal $

    5 Escalation Escalation (to mid-point of construction) 10 Months 0.36% $9,202

    Pre-construction subtotal $

    Construction subtotal $176,377

    General Construction Phase Subtotal $80,653

    Applicant Cost Subtotal $41,125

    Annual Maintenance Subtotal $

    6Estimate Review& Confirmation

    Escalation Subtotal $9,202

    PROJECT TOTAL $307,357

  • 8/4/2019 Project Cost Guidance

    50/87

    48

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Weeville, COProject Title West Trail High School Landscaping ImprovementsPreparer: S. Bear

    HAZARD: WildfireMITIGATION STRATEGY Vegetation Control

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    $

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $

    Site clearing trees, with 335 H.P. dozer, to 24"diameter

    25 Ea. $20.50 $513

    Selective clearing, brush, medium clearing, to 4"diameter, with dozer and brush rake, excludesremoval offsite

    2.2 Acre $239.00 $526

    Grub stumps, with 335 H.P. dozer, to 36" diameter 125 Ea. $10.65 $1,331Tree pruning, 36" caliper, aerial lift equipment 100 Ea. $608.00 $60,800

    Ground covers, vines and climbing plants, phloxsubulata, (Moss Phlox, Creeping Phlox), B&B, zone4, 1 gallon

    150 Ea. $4.73 $710

    Deciduous trees, oak, B & B, 2-1/2"-3" caliper, inprepared beds

    10 Ea. $640.00 $6,400

    Loam or topsoil, up to 200' radius, remove andstockpile on site, spread from pile to rough finishgrade, by hand

    1,200 E.C.Y. $25.50 $30,600

    Lawn bed preparation, rake topsoil, site materials,adverse conditions, harley rock rake

    45 M.S.F. $205.00 $9,225

    Lawn bed preparation, root raking and loading,municipal, no boulders

    50 M.S.F. $7.15 $358

    Lawn bed preparation, spread conditioned topsoil,6" deep, by hand

    550 S.Y. $8.45 $4,648

    Mulch, filter fabric weed barrier 550 S.Y. $1.38 $759

    Mulch, stone mulch, ceramic chips, deluxe, handspread

    550 S.Y. $15.40 $8,470

    $

    $

    $

    2Construction

    (Specify Phases)

    Construction Subtotal $124,338

    Insurance and Bonds 1 LS 3.5% $4,352

    Site supervision and contract requirements 1 LS 10% $12,869

    G.C. overhead & profit 0 LS 28% $

    Permits and Review Fees 0 LS 0.5% $

    Construction -General

    General Construction Phase Subtotal $17,221

    Preparation of construction documents 1 LS 10% $14,156

    Applicant Cost to Manage Design 1 LS 2% $2,831

    Applicant Cost to Manage Construction 1 LS 4% $5,662

    3

    Applicant Costs

    Applicant Cost Subtotal $22,649

  • 8/4/2019 Project Cost Guidance

    51/87

    49

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Maintenance $

    Site maintenance, general site work maintenance,clearing brush, by hand - quarterly 2,200 S.Y. $1.28 $2,816

    Site maintenance, flower bed maintenance, weedmulched bed - quarterly 20 M.S.F. $17.90 $358

    $

    4 Maintenance

    Annual Maintenance Subtotal $3,174

    5 Escalation Escalation (to mid-point of construction) 9 Months 0.43% $5,517

    Pre-construction subtotal $

    Construction subtotal $124,338

    General Construction Phase Subtotal $17,221

    Applicant Cost Subtotal $22,649

    Annual Maintenance Subtotal $3,174

    6Estimate Review& Confirmation

    Escalation Subtotal $5,517

    PROJECT TOTAL $172,899

  • 8/4/2019 Project Cost Guidance

    52/87

    50

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Upland County, CA Library DistrictProject Title Middle County Library RenovationPreparer: C. Pasquel

    HAZARD: WildfireMITIGATION STRATEGY Fire Resistant Exterior Materials

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    $

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $

    Siding demolition, wood, boards, vertical 5,000 S.F. $0.90 $4,501

    Insulation removal, rigid board 15,000 B.F. $0.10 $1,500

    Roofing and siding demolition, shingles, wood 12,000 S.F. $0.83 $9,960

    Brick veneer wall, standard face, 2x4 studs @ 16"back-up, running bond

    5,400 S.F. $20.75 $112,059

    Slate roofing, shingles, 3/16" thick, 4" min slope,8.0 PSF

    12,000 S.F. $6.98 $83,760

    Insulation, rigid, roof deck, polyisocyanurate,2#/CF, 3.5" thick, R25

    12,000 S.F. $2.55 $30,590

    $

    $

    2Construction

    (Specify Phases)

    Construction Subtotal $242,370

    Insurance and Bonds 1 LS 3.5% $8,483

    Site supervision and contract requirements 0 LS 10% $

    G.C. overhead & profit 0 LS 28% $

    Permits and Review Fees 1 LS 0.5% $1,254

    Construction -General

    General Construction Phase Subtotal $9,737

    Preparation of construction documents 1 LS 10% $25,211

    Applicant Cost to Manage Design 1 LS 2% $5,042

    Applicant Cost to Manage Construction 1 LS 4% $10,084

    3

    Applicant Costs

    Applicant Cost Subtotal $40,337

    Maintenance $

    $

    $4 Maintenance

    Annual Maintenance Subtotal $

    5 Escalation Escalation (to mid-point of construction) 12 Months 0.41% $12,343

    Pre-construction subtotal $

    Construction subtotal $242,370

    General Construction Phase Subtotal $9,737

    Applicant Cost Subtotal $40,337

    Annual maintenance Subtotal $

    6Estimate Review& Confirmation

    Escalation Subtotal $12,343

    PROJECT TOTAL $304,788

  • 8/4/2019 Project Cost Guidance

    53/87

    51

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Sedge County, FloridaProject Title Emergency Wildfire Suppression Water StoragePreparer: T. Bear

    HAZARD: Wildfire

    MITIGATION STRATEGY SuppressionEstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Land acquisition 1.5 Acres $3,500.00 $5,250

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $5,250

    Clear and grub, cut & chip, light trees, to 6"diameter

    1.00 Acre $3,475.00 $3,475

    Stripping and stockpiling, topsoil, sandy loam,adverse conditions, 200 H.P. dozer 450.00 C.Y. $1.51 $680

    Fine grade, fine grade for slab on grade, machine 3,400.00 S.Y. $1.32 $4,488

    Fill, from stockpile, 130 H.P., 2-1/2 C.Y., 300'haul, spread fill, with front-end loader, excludescompaction

    1,150.00 L.C.Y. $2.60 $2,990

    Compaction, riding, vibrating roller, 3 passes, 6"lifts

    1,150.00 E.C.Y. $0.49 $564

    Backfill, structural, common earth, 80 H.P. dozer,50' haul, excludes compaction 800.00 L.C.Y. $1.06 $848

    Compaction, riding, vibrating roller, 2 passes, 6"lifts

    800.00 E.C.Y. $0.37 $296

    Storage Tanks, vinyl coated fabric pillow type,freestanding, 50,000 gallons, excl. supportingembankment

    1.00 Ea. $31,400.00 $31,400

    Aggregate base course, for roadways and largepaved areas, alternate method to figure basecourse, crushed stone, compacted, 3/4", 6" deep

    270.00 E.C.Y. $43.50 $11,745

    Chain link fence, industrial, galvanized steel, 6 ga.wire, 2-1/2" posts @ 10' OC, 8' high, includesexcavation

    570.00 L.F. $44.00 $25,080

    Chain link fence, double swing gates, 6' high, 20'opening 2.00 Opng. $1,675.00 $3,350

    2Construction

    (Specify Phases)

    Construction Subtotal $84,915

    Insurance and Bonds 1 LS 3.5% $2,972

    Site supervision and contract requirements 1 LS 10% $8,789

    G.C. overhead & profit 1 LS 28% $27,069

    Permits and Review Fees 1 LS 0.5% $645

    Construction -General

    General Construction Phase Subtotal $39,475

    Preparation of construction documents 1 LS 10% $12,439

    Applicant Cost to Manage Design 1 LS 2% $2,488

    Applicant Cost to Manage Construction 1 4% $4,976Applicant Costs

    Applicant Cost Subtotal $19,902

  • 8/4/2019 Project Cost Guidance

    54/87

    52

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Maintenance $

    $

    Labor for weed control: Laborer 2 days/month 192 Hrs. $31.76 $6,0984 Maintenance

    Annual Maintenance Subtotal $6,098

    5 Escalation Escalation (to mid-point of construction) 11 Months 0.42% $5,706

    Pre-construction subtotal $5,250

    Construction subtotal $84,915

    General Construction Phase Subtotal $39,475

    Applicant Cost Subtotal $19,902

    Annual Maintenance Subtotal $6,098

    6Estimate Review& Confirmation

    Escalation Subtotal $5,706

    PROJECT TOTAL $161,346

  • 8/4/2019 Project Cost Guidance

    55/87

    53

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Seawinds, TexasProject Title Town Hall StrengtheningPreparer: Norman Storm

    HAZARD: Wind

    MITIGATION STRATEGYRoof and Load Path Strengthening and

    Shutters

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    $

    $

    Relocation costs: moving expenses $

    Relocation costs: rental assistance $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $

    Roof Reinforcement $

    Light Framing, average for all light framing 1 M.B.F. $1,599.94 $1,600

    Labor productivity for restricted work space forcrew of two carpenters

    3 Days $1,009.60 $3,029

    Load Path Reinforcement

    Ceiling demolition, drywall, furred and nailed,remove

    3,820 S.F. $1.00 $3,819

    Walls and partitions demolition, drywall, nailed 2,300 S.F. $0.40 $925

    Selective demolition, rubbish handling, dumpster,30 C.Y., 10 ton capacity, weekly rental, includesone dump per week, cost to be added todemolition cost.

    4 Week $990.00 $3,960

    Selective demolition, rubbish handling, 100' haul,load, haul to chute and dumping into chute, cost tobe added to demolition cost.

    10 C.Y. $48.50 $485

    Timber Connectors, joist & beam hangers,galvanized, 18 gauge, for 2" x 6" to 2" x 10" joist

    560 Ea. $4.14 $2,318

    Timber Connectors, split rings, twist straps, 18gauge, 12" x 1-1/4"

    570 Ea. $7.30 $4,162

    Concrete impact drilling, for anchors, 3/8" dia, in

    concrete or brick walls and floors, incl bit & layout,excl anchor, for each additional inch of depth, add

    160 Ea. $1.51 $242

    Anchor, expansion shield, zinc, 3/8" dia x 1-1/2" L,single, in concrete, brick or stone, excl layout &drilling

    160 Ea. $8.05 $1,288

    Gypsum wallboard, on beams, columns, or soffits,w/compound skim coat (level 5 finish), 1/2" thick

    3,820 S.F. $2.24 $8,557

    2Construction

    (Specify Phases)

    Paints & Coatings, walls & ceilings, interior,concrete, drywall or plaster, oil base, 3 coats,smooth finish, roller

    3,820 S.F. $0.88 $3,362

  • 8/4/2019 Project Cost Guidance

    56/87

    54

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Ceiling Suspension System, class A, 15/16" T bar,2' x 4" grid

    2,300 S.F. $1.21 $2,783

    Exterior Shutters, polystyrene, solid raised panel,16" wide x 80" long

    72 Pr. $129.01 $9,288

    Door hardware, hinges, full mortise, averagefrequency, steel base, USP, 6" x 6"

    144 Pr. $85.80 $12,355

    Concrete impact drilling, for anchors, 1/4" dia, inconcrete or brick walls and floors, incl bit & layout,excl anchor, for each additional inch of depth, add

    576 Ea. $1.20 $691

    Anchor, expansion shield, zinc, 1/4" dia x 1-5/16" L,single, in concrete, brick or stone, excl layout &drilling

    576 Ea. $6.90 $3,975

    $

    $

    $

    $

    $

    2Construction(Specify

    Phases)

    Construction Subtotal $62,839

    Insurance and Bonds 1 LS 3.5% $2,199

    Site supervision and contract requirements 1 LS 10% $6,504

    G.C. overhead & profit 1 LS 28% $20,032

    Permits and Review Fees 0 LS 0.5% $

    Construction -General

    General Construction Phase Subtotal $28,735

    Preparation of construction documents 1 LS 10% $9,157

    Applicant Cost to Manage Design 1 LS 2% $1,831

    Applicant Cost to Manage Construction 1 LS 4% $3,663

    3

    Applicant Costs

    Applicant Cost Subtotal $14,652

    Maintenance $

    $

    $4 Maintenance

    Annual Maintenance Subtotal $

    5 Escalation Escalation (to mid-point of construction) 11 Months 0.41% $4,110

    Pre-construction subtotal $

    Construction subtotal $62,839

    General Construction Phase Subtotal $28,735

    Applicant Cost Subtotal $14,652

    Annual Maintenance Subtotal $

    6Estimate Review &

    Confirmation

    Escalation Subtotal $4,110

    PROJECT TOTAL $110,335

  • 8/4/2019 Project Cost Guidance

    57/87

    55

    BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Prairieland Texas School BoardProject Title Flattop Elementary School Tornado Safe roomPreparer: B. Eddy

    HAZARD: WindMITIGATION STRATEGY Tornado Safe Room

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    $

    $

    $

    $

    1Pre-Construction

    (Specify)

    Pre-construction subtotal $

    Strip footing, concrete, reinforced, 180 L.F. $38.55 $6,939

    Foundation wall, CIP, 180 L.F. $60.35 $10,863

    Slab on grade, 6" thick, light industrial, reinforced 900 S.F. $6.76 $6,084

    Concrete block (CMU) wall, regular weight, solid,double wythe, reinforced and grouted

    1,200 S.F. $17.80 $21,360

    Concrete block (CMU) partition, regular weight,solid, 6" thick, no finish

    300 S.F. $7.75 $2,325

    Exterior Door, steel 18 gauge, hollow metal, 1door with frame, "A" label, 3'-0" x 7'-0" opening

    2 Opng. $1,740.00 $3,480

    Metal door/metal frame, flush, composite, 18 gafull panel, 3'-0" x 6'-8", KD drywall frame, 4-7/8"

    2 Ea. $870.00 $1,740

    Interior Door frames, steel channels with anchorsand bar stops, 8" channel@ 11.5 lb/LF, 6' x 8'door, weighs 275 lb

    1 Ea. $655.55 $656

    Interior Doors, commercial, steel, flush, full panel,hollow core, 18 ga., 3'-0" x 6'-8" x 1-3/4" thick

    2 Ea. $360.00 $720

    Painting, masonry or concrete, latex, brushwork,primer & 2 coats

    1,500 S.F. $1.75 $2,625

    Roof, steel joists, on bearing walls 900 S.F. $3.34 $3,006

    Insulation, rigid, roof deck, fiberboard, highdensity, 3'x4' sheets, 1-1/2" thick, R3.8

    900 S.F. $1.26 $1,134

    Roofing, coal tar pitch, gravel, coated glass fiberbase sheet, 3 plies glass fiber felt (Type IV),mopped, on nailable deck

    900 S.F. $3.10 $2,790

    Switchgear installation, incl switchboard, panels &circuit breaker, 400 A

    1 Ea. $7,250.00 $7,250

    Receptacles and wall switches, 600 SF, 10receptacles

    900 S.F. $3.17 $2,853

    Receptacles and wall switches, 600 SF, 2switches

    900 S.F. $0.76 $684

    2Construction

    (Specify Phases)

    Urinal, vitreous china, wall hung 2 Ea. $1,185.00 $2,370

  • 8/4/2019 Project Cost Guidance

    58/87

    56

    EstimatingStep

    Project Phase Description Quantity Unit Unit Cost Task Cost

    Water closets, battery mount, wall hung, side byside, first closet

    1 Ea. $1,720.00 $1,720

    Water closets, battery mount, wall hung, side by

    side, each additional water closet, add

    5 Ea. $1,615.00 $8,075

    Lavatories, battery mount, side by side, firstlavatory

    1 Ea. $1,540.00 $1,540

    Lavatories, battery mount, side by side, eachadditional lavatory, add

    3 Ea. $1,245.00 $,735

    Heat pump, thru-the-wall, supplemental electricheat, cabinet, louver, 1-1/2 ton

    2 Ea. $3,205.00 $6,410

    Partitions, toilet, cubicles, ceiling hung, paintedmetal

    6 Ea. $705.00 $4,230

    Partitions, toilet, cubicles, floor & ceiling anchored,incl. 52" grab bars, for handicap units, add

    2 Ea. $330.00 $660

    $

    2Construction

    (Specify Phases)

    Construction Subtotal $103,249

    Insurance and Bonds 1 LS 3.5% $3,614

    Site supervision and contract requirements 1 LS 10% $10,686

    G.C. overhead & profit 1 LS 28% $32,914

    Permits and Review Fees 0 LS 0.5% $

    Construction -General

    General Construction Phase Subtotal $47,213

    Preparation of construction documents 1 LS 10% $15,046

    Applicant Cost to Manage Design 1 LS 2% $3,009

    Applicant Cost to Manage Construction 1 LS 4% $6,018

    3

    Applicant Costs

    Applicant Cost Subtotal $24,074

    Maintenance $

    $

    $4 Maintenance

    Annual Maintenance Subtotal $

    5 Escalation Escalation (to mid-point of construction) 11 months 0.41% $6,753


Recommended