+ All Categories
Home > Documents > Project deliverables FPSO Mooring Install & Project ......projects as well as access to in-house...

Project deliverables FPSO Mooring Install & Project ......projects as well as access to in-house...

Date post: 21-Feb-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
2
FPSO Mooring Install & Replacement Project deliverables Project management Planning Engineering Design Procurement Transport mooring equipment Disconnect temporary moorings Install permanent moorings Maersk Supply Service was awarded a contract by an American oil major to deliver an integrated FPSO mooring installation and replacement solution in the Gulf of Guinea. e project was for the disconnection of a temporary FPSO mooring system and installation of the permanent replacement mooring system. Maersk Supply Service's full-scope delivery included project management, planning, engineering, design, procurement and marine execution. It also entailed the transport of mooring chains and connectors from China, and Intermoor SEPLA anchors and follower from Louisiana. Advanced Capabilities To accommodate heavy moorings equipment Maersk Maker, a 2019 new-build AHTS vessel, transported and installed nine 25 tonne SEPLA anchors using a 120 tonne follower of 4.3m diameter. e anchors were installed to 27m below seabed, while Maersk Achiever concurrently deployed 650m-long studless chains of 157mm diameter. With some of the most advanced capabilities in the industry, our AHTS and SSV vessels are designed to handle the large mooring systems of tomorrow. Increased Efficiency From two vessels working in tandem By working with Maersk Maker and Maersk Achiever in tandem, we were able to save time and reduce the number of port calls required. Together, the vessels carried and installed five SEPLA anchors and chain sets per mobilisation, as well as five sheathed spiral strand wires and chains. Tandem operations also prevented entanglement of the large chains and follower during installation in deep waters. Flexibili in Operations Applying 50 years of marine experience We approach every project from a background of over 50 years of hands-on offshore experience. As it was the first time the mooring equipment was installed at this large size, the on- and offshore project team was able to address the associated challenges, and ensure installation was completed safely and efficiently. Key facts Client: American oil major Project: FPSO mooring installation & replacement Location: Gulf of Guinea Water depth: 500m No of vessels used: 4 Project timing: April - December 2019 Operations: Mooring equipment transportation Temporary moorings disconnection Permanent moorings installation Safe performance: Zero incidents
Transcript
Page 1: Project deliverables FPSO Mooring Install & Project ......projects as well as access to in-house cost-competitive vessels with competent and experienced crew that meet the highest

FPSO Mooring Install &Replacement

Project deliverablesProject managementPlanningEngineeringDesignProcurementTransport mooring equipmentDisconnect temporary mooringsInstall permanent moorings

Maersk Supply Service was awarded a contract by anAmerican oil major to deliver an integrated FPSOmooring installation and replacement solution in theGulf of Guinea.

The project was for the disconnection of a temporary FPSO mooring system andinstallation of the permanent replacement mooring system. Maersk Supply Service'sfull-scope delivery included project management, planning, engineering, design,procurement and marine execution. It also entailed the transport of mooring chains andconnectors from China, and Intermoor SEPLA anchors and follower from Louisiana.

Advanced CapabilitiesTo accommodate heavy

moorings equipment

Maersk Maker, a 2019 new-build AHTS vessel,transported and installed nine 25 tonne SEPLA anchorsusing a 120 tonne follower of 4.3m diameter. The anchorswere installed to 27m below seabed, while MaerskAchiever concurrently deployed 650m-long studlesschains of 157mm diameter. With some of the mostadvanced capabilities in the industry, our AHTS and SSVvessels are designed to handle the large mooring systemsof tomorrow.

Increased EfficiencyFrom two vessels

working in tandem

By working with Maersk Maker and Maersk Achiever intandem, we were able to save time and reduce thenumber of port calls required. Together, the vesselscarried and installed five SEPLA anchors and chain setsper mobilisation, as well as five sheathed spiral strandwires and chains. Tandem operations also preventedentanglement of the large chains and follower duringinstallation in deep waters.

Flexibility in OperationsApplying 50 years of

marine experience

We approach every project from a background of over 50years of hands-on offshore experience. As it was the firsttime the mooring equipment was installed at this largesize, the on- and offshore project team was able toaddress the associated challenges, and ensureinstallation was completed safely and efficiently.

Key factsClient:

American oil major

Project:

FPSO mooring installation &replacement

Location:

Gulf of Guinea

Water depth:

500m

No of vessels used:

4

Project timing:

April - December 2019

Operations:

Mooring equipment transportation

Temporary moorings disconnection

Permanent moorings installation

Safety performance:

Zero incidents

Page 2: Project deliverables FPSO Mooring Install & Project ......projects as well as access to in-house cost-competitive vessels with competent and experienced crew that meet the highest

Maersk Supply Service - Provider of vessels and full service solutions to the energy sector

Maersk Supply Services is a leading provider of global offshore marineservices. We bring more than 50 years of hands-on marine experiencefrom vessel operations on a global scale, serving a broad range ofclients in the energy sector.

Our Integrated Solutions division delivers full service solutions, whichinclude scoping, planning, subcontracting and execution of marineprojects as well as access to in-house cost-competitive vessels withcompetent and experienced crew that meet the highest standards ofquality and safety.

Safe hands. Sound business.

Vessels involved in the FPSO mooring installation and replacement project:

End-to-end project management of:

Equipment procurement and transportationMooring chains and connectors mobilised from ShanghaiAnchors and follower mobilised from Louisiana

Anchor mobilisation and installationTransport and installation by Maersk Maker and Maersk AchieverInstallation using a 120 tonne follower of 4.3m diameter9x 25 tonne SEPLA anchors installed

Chain mobilisation and installationTransport and installation by Maersk Maker and Maersk Achiever6200m of 157mm chain installed in 650m-long sections4600m of sheathed spiral strand wire installedTotal 4000 tonnes of mooring equipment transported and installed

Temporary mooring system disconnection9x Omni-Max anchors recoveredMud mats and associated mooring chains of various sizes recovered

The follower at quayside

Large 25 tonne SEPLA anchors at quayside

Loading the follower onto Maersk Maker fromMaersk Achiever

2


Recommended