+ All Categories
Home > Documents > Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water,...

Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water,...

Date post: 28-Aug-2018
Category:
Upload: hangoc
View: 214 times
Download: 0 times
Share this document with a friend
22
Issued by SATS Technical Projects Office Date: 17/05/2017 Page 1 of 22 To Supply, Deliver, Install and Commissioning of Chilled Water System at SICC2 Expansion Building Project Description & Brief The scope of this project includes the supply and installation of a chilled water system within the new expansion building at SATS Inflight Catering Centre 2. Chilled water will be used at 3 work areas: - Sterilizer Room (250 litres/min) - Meal Dishing Area (10 litres/min) Potential vendors are to submit proposal for the following: 1. Scope of work and responsibilities 2. Equipment specification of new equipment to be supplied and installed 3. Vendor is to ensure that proposed new equipment should interface and work accordingly with the existing M&E requirements, or otherwise make recommendation in the proposal 4. Depending on the proposed system by the vendor, it will include the main Electrical control panels and necessary interfaces for performance management monitor and audit trails 5. Project Management, which includes the submission of engineering drawings, approval from authorities (where necessary), submission for Safety requirements (Method Statement etc.) detail timeline, testing and commissioning as well as user and technical training 6. To provide 2 year warranty to the commissioned system 7. To provide 1 year of Maintenance Services commencing from the end of warranty period with an option to extend it each year for at least next two (2) years 8. Any proposed energy conservation measures will be a plus. 9. General layouts attached in Annex A.
Transcript
Page 1: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 1 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Project Description & Brief The scope of this project includes the supply and installation of a chilled water system within the new expansion building at SATS Inflight Catering Centre 2. Chilled water will be used at 3 work areas:

- Sterilizer Room (250 litres/min) - Meal Dishing Area (10 litres/min)

Potential vendors are to submit proposal for the following: 1. Scope of work and responsibilities 2. Equipment specification of new equipment to be supplied and installed 3. Vendor is to ensure that proposed new equipment should interface and work accordingly

with the existing M&E requirements, or otherwise make recommendation in the proposal 4. Depending on the proposed system by the vendor, it will include the main Electrical

control panels and necessary interfaces for performance management monitor and audit trails

5. Project Management, which includes the submission of engineering drawings, approval

from authorities (where necessary), submission for Safety requirements (Method Statement etc.) detail timeline, testing and commissioning as well as user and technical training

6. To provide 2 year warranty to the commissioned system

7. To provide 1 year of Maintenance Services commencing from the end of warranty period

with an option to extend it each year for at least next two (2) years

8. Any proposed energy conservation measures will be a plus.

9. General layouts attached in Annex A.

Page 2: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 2 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Evaluation Criteria The proposals will be evaluated based on the following factors (including but not limited):

Overall value; i.e. cost versus benefit to SATSCAT

Point-by-point responses to the Scope of Work

Completeness of solution

Completeness of tender submission

Ease of integration with existing system

Technical Expertise

Prior Experience

Value added services (Energy Conservation, Process Re-Engineering, reduced running cost etc.)

Completion of project within given project schedule

The evaluation process may include telephone calls to your referees (clients) to verify claims made by your company.

The short listed candidates may be asked to present their Tender Submission on-site at SATS premises. SATS will provide the necessary facilities for the presentation but all other expenses incurred by the Vendors in making the presentations will be borne by Vendors.

Page 3: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 3 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Vendor Matrix Please complete the Matrix briefly (URLs are not acceptable). Additional information can be given as an attachment and / or in the relevant parts of your tender proposal.

Category/Section Description

Corporate Information

Company’s Name and Address

Year of Incorporation

Parent Company Name and Address (if any)

Mission and Direction

Core Competencies / Business

Revenue for the 3 most current year-end periods

Net Profit for the 3 most current year-end periods

Technology / Business Partner

Contact Person’s Name, Job Title, email address, mobile

& DID contact no., fax no.

Experience

Relevant Project Experience number of years state the projects title & customer

reference (a brief description can be given as attachment)

Product Features

Estimated Market Share (Singapore)

Resources

Number of Staff in Singapore Total Technical (Consultant, Engineer, etc.) Maintenance Support

Project Management

Development Methodology Adopted

Development Model (on-site/off-shore/ hybrid)

CMM, ISO or equivalent Certification

Page 4: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 4 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Project Schedule The following schedule gives the overview guideline on the project tasks and the fixed milestone dates. Vendor is to submit project schedule base on the guidelines. These dates shall be detailed by major installation stages, sub-packages and areas in the building. Additional information can be given as an attachment and / or in the relevant parts of your tender proposal.

Task Timeline

Preliminary Design Submission (Scale 1:100) including Building and

Utilities Requirements

3 Weeks

Preliminary Equipment Details and Design Specification Submission

Review Meeting

Approval of Final Equipment Design Specification Submission 1 Week

Commence Fabrication/Construction 12 Weeks

Delivery and Installation of Equipment 6 Weeks

Permanent Power turn on 1 Week

Testing and Commissioning

Handover*

Staff Training 1 Week

Start of Full Production

Start - up support / Warranty Servicing

Final Acceptance Test

Warranty Period (1 year plus time from Start of Full Operation to Final

Acceptance)

1 Year

Page 5: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 5 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

PRICING

PRICING SUMMARY

Supply, installation & commissioning of the following items including all the necessary accessories

for the machine to operate properly (otherwise stated as described in “Technical Specification”). For

software items, the required run-time licences and development licences must be stated separately but

clearly.

The vendor must submit a fixed fee proposal. Items illustrated in the itemised pricing table are not

exhaustive. The vendor shall provide a detailed price breakdown including those that has already been

listed in the pricing table, with unit prices.

SATSCAT places high importance to running cost and energy conservation. If for any systems or

equipment there are solutions that reduces the running cost (including utilities) even if the initial cost

is higher, please quote as an option.

Options proposed by the vendor shall be quoted separately.

All prices should be quoted in Singapore Dollars (SGD)

The total contract sum is ___________________

(No Exceptions To Specifications) excl. GST

Options as proposed by vendor, purchase price is _________________

(No Exceptions To Specifications) excl. GST

Page 6: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 6 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

ITEMISED PRICING TABLE

SICC2 Chilled Water System

Item Description Qty Unit Price (S$) Total Price (S$) Remarks

1 Supply :

- Chilled Water System 1 lot

2 Factory Acceptance Testing

3 Freight Charges/Insurance/Local Transport/Handling/Site Materials, Accessories & Preliminaries

4 Installation/Testing/Commissioning

i

ii

3 Other Proposed Equipment and accessories (Please specify):

i

ii

4 Design & Engineering:

i Engineering (Drawings, Documentation, approval etc)

ii Project Management

iii Testing and commissioning

5 Training

6 Warranty (2 Years)

7 Maintenance Services :

i Year 1

ii Year 2

iii Year 3

8 Monitoring System complete with cabling and software with computer located in Technical Office 2

Page 7: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 7 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

ITEMISED PRICING TABLE

Please complete the Matrix briefly (URLs are not acceptable). Additional information can be given as an attachment and / or in the relevant parts of your tender proposal.

Optional items :

Item Description Qty Unit Price (S$) Total Price (S$) Remarks

1

2

3

All prices as quoted to be in Singapore Dollars

Page 8: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 8 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

SPARE PART ITEMISED PRICE LIST

Please complete the Matrix briefly (URLs are not acceptable). Additional information can be given as an attachment and / or in the relevant parts of your tender proposal.

Item Description Unit Price (S$) Country of Origin

1

2

3

All prices as quoted to be in Singapore Dollars

Page 9: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 9 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Technical Specifications General requirements

High degree of standard components and uniform brands/makes, reduced no. of sub-

vendors/suppliers; lower maintenance and repair cost; reduced no. of spare parts

Standard spare parts such as indication lamps, light tubes, transmission belts, electrical motors

etc. must be locally available.

Heavy duty design and execution

All machines to be fit for purpose. Vendor must ensure that the proposed equipment meet the

requirement of a high performance quality caterer.

All materials coming in contact with food must be stainless steel. As an exception food proven

plastic can be accepted.

All surfaces needing a frequent cleaning to be in stainless steel.

Design

Top side of cabinets, cupboards, splash backs, utility distribution ducts, etc. to be manufactured

with slant, where ever practicable.

Flexible installation and erection of all equipment and machines for easy exchange of

equipment location.

Fully heat insulated hot water, steam, and condensate pipes as well as water pipes (if need be);

coated with formed stainless steel sheets (non-exposed pipes inside equipment require formed

aluminium sheets only.)

Heat- and sound insulation materials to be asbestos and CFC/HCFC-free.

All switches, e-stops, knobs, sockets, door/drawer handles, cross handles of valves etc. to be

recessed and protected against damages by trolleys.

Half open lid of electric socket with plugged connection must not protrude the equipment front.

All knobs to be mechanically secured by screws or similar devices.

PCB boards/control boards, keypads etc. to be very robust.

Frame and panelling

Heavy duty frame structure

Totally constructed of stainless steel, including base frame, legs and feet, enclosed panels with

top and back sides, double-walled panels and doors, interior cavities and compartments, hoods,

ducts, etc.

Base frame, uprights, cross/longitudinal members etc. shall be reinforced by welded stainless

steel gusset plates.

Page 10: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 10 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Stand-alone equipment and machines incl. utility distribution ducts; complete enclosed body

made of stainless steel.

All sides (front, side, back, top, bottom/underside) of equipment, machines to be equipped with

easily to clean panelling. Ventilation openings to be splash-proof.

All panelling (front, side, back, top and bottom/underside panels), easily accessible and

removable; for maintenance, service and repair light-weight panels with quick locking system.

Panel element size and weight must consider that the panels will be removed and re-positioned

by one man only.

Completely enclosed, tight and sealed panelling to meet rigid hygienic requirements and for

easily cleaning.

Open ends of flue channels to be covered by louvres, wire mesh or similar means.

All cavities and hollow areas inside equipment panelling shall allow for easy inspection and

pest control, necessary inspection openings to be provided at factory and on-site before and

after equipment acceptance at no additional cost.

Rubber, plastic and flexible sealant to be heat, cold, food, oil, and detergent resistant, as well as

non-ageing, easily replaceable.

All back-side of panels to be equipped with noise absorbing liners (no wood or wooden

materials).

Protection of panelling by bumpers, please refer to section on Castors and bumpers.

Feet and equipment height

General table and working height 800 mm above finish floor.

Feet to be fastened to base frame, table top etc. by welded gusset plates.

Full clearance height between finish floor and base frame, cross/longitudinal members etc. at

least 250 mm for easily floor cleaning.

Minimum distance between two legs/feet at least 500 mm for easy floor cleaning; the location

of legs/feet can be subject to changes by client or/and system engineer at no extra cost.

In general no floor mounted equipment shall be installed.

Floor mounted equipment (if no alternatives) to be installed tight-sealed to floor surface.

Equipment installation

The tender price must include all materials, installation, function, operational and hygiene tests etc. as

well as required qualified personnel for installation, installation supervision, etc. No subsequent

charges will be accepted.

All necessary installations beyond the connection point and all installations for equipment and

machine performance, maintenance and easy faults finding must be supplied and installed by the

Equipment Vendor or his local licensed installation workers and plumbers respectively.

Page 11: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 11 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Installation and location of final connection points to meet structural requirements such as beams,

intermediate beams etc. Necessary amendment of the equipment due to installation constraints shall

be executed by the equipment vendor at no extra cost.

All installations shall be co-ordinated with all building engineers (architects, M + E engineers,

structural engineers, systems and equipment engineer)

The vendor must for his work also provide all:

Required lifting devices, mobile cranes, scaffolding, tools etc.

Unloading of all material and system components from delivery truck/container and

transport to points of installation.

Removal of all packing material from work place and site

Mechanical installation and utilities

Mechanical utilities (hot and cold water, sanitary, compressed air) will be supplied to each piece of

equipment according to vendor’s requirements. The final connection to the equipment will be

executed by the equipment vendor.

For cooking islands/utility distribution ducts the utilities will be supplied from below except gas and

electricity, which will be from above.

All necessary utility installations beyond the connection point must be supplied and installed by the

Equipment Vendor or his locally licensed installation workers and plumbers respectively. Such

installation items comprise:-

Power Supply

The electrical power will be supplied to each piece of equipment and machine according to vendor’s

requirements. One cable / one connection point per machine. The final connection to the equipment's

control cabinets and boxes will be executed and supervised by the equipment vendor and/or his local

licensed sub-contractor. All power distribution beyond the connection point as well as all control

cable distribution is the responsibility of the Equipment Vendor too.

Vendor equipment electrical isolators will be supplied and installed by others. The Equipment

Vendor will terminate the equipment cables at the electrical isolator.

For equipment located at walls the sockets/isolators are wall mounted.

Page 12: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 12 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Control cabinets

Where applicable, power connection and motor circuits are to be accommodated in control cabinets.

They contain all fuses, main switches, contactors, motor protection switches, relays, panel indication

lamps, terminal strips, auto timer, operating hour meters, fans, cooling unit, dryer, required for the

function of the system.

Each control cabinet must have an isolator, cable locks and an emergency push button. Cable entry

will be from the top or bottom of the cabinet. Access for final connection, which will be by others, is

to be provided by the vendor.

Control cabinets must have interior lighting and socket outlet as well as internal testing device for

indication lamps, etc.

The location of the control cabinets is to be shown in the proposal tender drawings to be submitted

with the proposal. Each control cabinet shall have 20% spare space for later extensions.

Each control cabinet is equipped with a suitable means for keeping the electrical drawings and layouts

located at the first opening door. Control cabinets to be at least splash proof and easy to operate.

Installation and wiring

The tender price must include all materials, installation, wiring, function tests etc.; no subsequent

charges will be accepted.

The installation comprises:

Manufacturing and installation of control cabinets, control desks, control panels, control boxes

etc.

Installation and wiring of and to all control/monitoring peripherals as well as of and to all

peripheral equipment like central monitoring panel

Installation and wiring of motors, cable ducts, cable ladders/trays and steel conduits, control

and signal cables between the system elements, the control cabinets and the control centre.

Cables and wires are to be installed in galvanised cable ducts/ladders/trays with covers or in

steel conduits to provide protection against mechanical damage

Cable duct/ladders/trays are to be provided with 20 % spare space for later installation of

additional cables.

Cables passing through firewalls and ceilings must be in accordance with regulations of fire

protection, with cable sleeves and making good and closing of openings

Marking for cables and cable ducts/ladders/trays every 10 m and next to walls and floor

openings (letters in height size at least 10 mm). Labels to be affixed with 2 screws or 2 rivets.

Page 13: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 13 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Electric cables

All cables and plugs to be of food-,oil-, heat-, cold- and detergent-resistant as well as non-

ageing materials

All electric cables are to be cut to the appropriate length. No cables on floor surface.

All mobile equipment has to be equipped with spiral cable and cable/plug holder or hook.

Cables, plugs, and installation at least splash-proof

Plug execution according to local code

Electric sockets, junction boxes etc.

All sockets, junction boxes etc. to be of food-, oil-, heat-, cold- and detergent-resistant as well

as non-ageing materials

Socket, junction box, execution etc. to be at least splash-proof

Open lids of socket with connected plug must not protrude front surface, socket to be located in

recessed areas

Socket, junction box execution etc. design according to local code

Hygiene and Food Safety

Equipment must be able to maintain records in accordance to Food Processing Safety Standards

and Hygiene Practices.

Dishwashing Equipment must ensure that washed Equipment reaches a surface temperature of

71°C/160°F for 30 seconds, and can be verified time and time again the effectiveness of

sanitization using a thermolabel (or other irreversible registering temperature indicator) that

activates at 71°C/160°F for 30 seconds.

The design of the Dishwashing Equipment must conform to the series of standards DIN 10510

& DIN 10511

Page 14: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 14 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Equipment Specifications

Chilled Water System No of units: 1

For the production of chilled water at 4 degrees celsius. Return loop will be between 25 to 30 degrees celsius.

Used to cool down packed food products and equipment.

System to be equipped with spare slots to retrofit additional compressors to increase the system capacity by another 30% in the future.

Chilled water will be required within the hot kitchen, meal dishing area, and the sterilizer room.

Chilled water to be generated adjacent to the place of usage. Compressor/condenser system will be roof located at the ground floor adjacent to the building.

System will have to be supplied with weather proof enclosures as they will be located in the open.

System shall operate at 75% of its rated capacity during peak load conditions.

Non-CFC type refrigerant to be used; to be approved for usage within food production facility by local authorities. Ammonia is not preferred.

If a multi-compressor system is recommended, isolating valves will have to be provisioned to allow compressors to be isolated and taken offline without interrupting the operation of the overall system.

System to be equipped with vibration isolators at mounting points so as to eliminate vibration transfer to the building.

System to operate well below critical speed.

Check valve to be located at compressor discharge to prevent flow reversal during shutdown.

Compressor to be equipped with separate cooling fan to ensure efficient removal of heat.

Isolation valves shall be provisioned at the condensers to allow for isolation of refrigerant.

Each compressor must be equipped with its own electrically powered oiling system

Entire system to be controlled via micro-processor with the following: 1) Compressor start/stop push button switches with indicator lights 2) Motor current control and load switch from 15 to 100% of full load current 3) Refrigerant suction and discharge temperature indicated by a LCD display

Page 15: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 15 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Price to include the following works (Additional Works)

24 months Comprehensive Warranty coverage on Parts and Labour

All wiring system and control switches must be properly laid and comply with EMA safety requirements

To conduct technical training sessions for technical staff

To conduct user training for operators and cleaners

To provide operating manual and technical/maintenance manual in hard and soft copies

To submit critical spare parts list with pricing

Pictorial step by step cleaning procedures Note: Vendor to include options/price breakdown of accessories.

Page 16: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 16 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Chilled Water System

Technical Data Projected by SATS Designed by Contractor

Peak flow rate Litres/min 260

Base flow rate Litres/min 20

Chilled Water Temperature °C 4

Water Return Temperature

°C 25 to 30

Electrical

Voltage V 400

Peak Connected load kW 150

Protection enclosure IP 66

Refrigerant type R# R404

Overall System COP - >2.5

Manufacturer

Type

Comments

Page 17: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 17 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

In addition to the above, the tender price shall include:

Integrated control cabinets and integrated electrical installation of

equipment machines. This applies to the electrical installation and wiring

between equipment/machines and remote control cabinets, too

Preparation of functional design specification documents incl. draft copies,

presentations, meetings etc.

Fire rated pipes/pipe sleeves for remote equipment and machine components

and cables at fire compartment walls and floors

Approval of all appliances, equipment, machines etc of this tender package

by local authorities inclusive fees

Final connections and associated pipe-works / electrical cables etc. between

equipment and connection points

Any necessary subsequent work, readjustments etc., necessary because of

shortcomings and defects evident from the various acceptance runs

Timely and comprehensive training and instruction of the management,

operational and maintenance personnel in advance of the integration phase

Co-ordination at all interfaces and at every point of contact to other works

to achieve the construction of a complete unified plant. In particular,

interfaces will arise between site works and the above-described scope of

work.

Participation in meetings and regular site meetings

Factory inspections

Start up attendance

Participation and attendance in feedback meetings and appraisals

Provided by others:

Concrete floor slab, finished floor surface (1 - 2 % fall)

Pipe sleeves for utility supply pipes and electric cables

M + E installations in general including installation close to the equipment

and valved for pipe services and an electrical isolator within 3 metres of the

equipment.

Page 18: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 18 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

The vendor is further required:

to submit a proposed layout in drawings at a scale of 1:100 or 1:50

to submit detail front view drawings at a scale of 1:50 or 1:25/1:20 of

equipment layout within the cooking island

to submit a detailed drawing at a scale of 1:20 showing the construction and

installation method of the utility distribution duct.

to fill in the attached technical data forms completely for all quoted

equipment and machines including alternatives and options

to submit 2 sets of original coloured equipment brochures, photographs etc.

of each piece of equipment and machine including attachment and

accessories, each brochure to be identified by the specification item-no.

SPECIAL NOTES

The functions, procedures, information and requirements provided in this document serve as a guide

for the bidding of this package. It is by no means complete.

All functions, procedures, information and requirements necessary for achieving full operational

performance for the equipment and machines but not listed in this tender document must be included

in the proposal.

To avoid any misunderstanding and dispute, the vendor must seek acceptance (i.e. acceptance

signature) for each stage/phase of the design and development process, and also during the various

stages/phases of the implementation process.

Any changes made, to accept design must be re-accepted before start of its implementation.

Page 19: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 19 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Service Levels for Warranty Period and Preventive Maintenance Services

1. WARRANTY / MAINTENANCE SUPPORT 1.1 Help Desk Telephone Service For the duration of warranty period and application maintenance services (post warranty

period), Vendor will operate from service centre located in Singapore and a helpline will be provided to SATS Catering staff. The helpline will be active for 24 hours x 7 days.

1.2 Process & Procedures

SATS Catering will provide first line support to Catering users and will carry out preliminary investigations to ascertain the nature of the problem, and having identified the problem, make a decision to call the vendor helpline to activate the vendor support with Severity Level made known to the vendor as well. Vendors will need to comply with SATSCAT incident management flow (Refer to section 4).

2. PROBLEM RESOLUTION CRITERIA 2.1 Problem Response Time

The time taken by the maintenance team to validate, confirm and acknowledge that it is an application problem.

2.2 Problem Resolution Time

The time taken by the application maintenance team to fix the problem, produce a workaround or resolution plan.

3. SERVICE LEVEL 3.1. Severity & Service Levels Table

Severity Level

Definition of Severity Level

Response time Resolution

time Office hours

After office hours

1 Affects 50% or more of the entire System. No acceptable workaround is available leading to significant business impact.

2 hour 2 hour Within 2 hours

2 Affects up to 50% of the entire System. No acceptable workaround is available leading to substantial business impact.

2 hour 2 hour Within 1

working day

3 Error in the system functionality, which does not interrupt the operational flow due to availability of an acceptable workaround.

4 hours Next working

day Within 3

working days

4 Non-critical error or a cosmetic change, which disrupts neither the functional nor operational flow.

1 working

day

Next working day

Within 10 working days

Page 20: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 20 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

4. INCIDENT MANAGEMENT Resolver Acceptance

Roles and Responsibilities 1. Allocate initial resource to assess the Incident 2. Assess the assigned Incident Severity and feedback to SATSCAT if there is any

discrepancy. Incident Resolution

Roles and Responsibilities 1. Ascertain whether there is a workaround 2. If so, apply the workaround and update status and Severity if necessary 3. If no workaround available:-

a. Ascertain whether more resources are required. If required, then assign additional resources

b. Commence work to resolve problem

Incident Closure

Roles & responsibilities

1. Contacts SATSCAT appointed personnel(s) to discuss any outstanding issues regarding

the Incident.

2. Resolves incident and updates with details of incident resolution with stated date/time of

completion. (Field Service Report)

3. SATSCAT is the only entity that can close an Incident. A closure request can be from: an intermittent problem where the problem has "gone away" Resolver who has resolved the Incident to the satisfactory of SATSCAT

Page 21: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 21 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Annex A – Level 2

Proposed location from Compressors/Condensers

Location of Chilled Water usage (up to 250 litres/min)

Page 22: Project Description & Brief - SATS · Evaluation Criteria ... Fully heat insulated hot water, steam, ... top and back sides, double-walled panels and doors, ...

Issued by SATS Technical Projects Office Date: 17/05/2017 Page 22 of 22

To Supply, Deliver, Install and Commissioning of Chilled Water

System at SICC2 Expansion Building

Annex 2 – Level 3

Location of Chilled Water usage (up to 10 litres/min)


Recommended