    GASCO - RUWAIS TRAINS 1&2 HP & LP FLARES

    PROJECT DOCUMENT CONTROL PROCEDURE

    GASCO Document No. 5631-PRC-00-AA-8001

    Dhabi Nortech Project No. P-GAS-0213

    REV DATE PAGES DESCRIPTION BY CHECKDISC

    APPROVE

    EM

    APPROVE

    3RD

    PARTY

    APPROVE

    DM or MD

    APPROVE

    A1 14/08/2015 13 Issued for Comment SSL BND SSL KSN BND

    A2 08/10/2015 13Updated Re-Issued for

    CommentSSL BND SSL KSN BND

  • 7/24/2019 Project Document Control Procedure

    2/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 2of 13

    Table of Contents

    INTRODUCTION 3

    1. GENERAL 33. ELECTRONIC DOCUMENT MANAGEMENT SYSTEM (EDMS) 34. PROJECT & DOCUMENT NUMBERING & REVISION CONTROL 45. DOCUMENT FORMAT 85.1 Drawings 85.2 Documents 85.3 Document Revision Control 8

    6. MASTER DOCUMENT REGISTER (MDR) 97. DOCUMENTATION ISSUE, TRACKING & STORAGE 97.1 Documentation Issue 97.2 Tracking 97.3 Documents for Review by Client 97.4 Control of Comments from Client/Dhabi Nortech 108. CLIENT / SUPPLIER DOCUMENTATION 108.1 Client Documents 108.2 Supplier Documents 109. CORRESPONDENCE 119.1 Emails 11

    9.2 Letters 1110. DISTRIBUTION 1211. PROJECT REPORTING 13

  • 7/24/2019 Project Document Control Procedure

    3/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 3of 13

    INTRODUCTION

    The procedure has been produced for use on the GASCO Ruwais Trains 1&2 HP & LPFlares. Project specific requirements are in line with those requested by the customer.

    1. GENERAL

    The objective of this procedure is to ensure that all documents, correspondence anddeliverables (hereafter collectively named as documents), prepared, received and sent byDhabi Nortech are recorded, distributed and filed in an efficient and controlled andtraceable manner.

    2. DEFINITIONS

    Documents: In the context of this procedure applies to all documents such asspecifications, calculations, reports, minutes of meetings and all design drawings.

    The EDMS implemented through ProArc is the system or tool adopted by Dhabi Nortech forthe numbering, control and management of all documentation. ProArc will be managed bythe Dhabi NortechDocument Control Manager (DCM).

    CRS - Comment Resolution SheetDCC - Document Control CentreDCM - Document Control ManagerDM - Delivery ManagerEDMS - Electronic Document Management SystemEM - Engineering Manager

    MDR - Master Document ListSDR - Supplier Document List

    3. ELECTRONIC DOCUMENT MANAGEMENT SYSTEM (EDMS)

    All Dhabi Nortech project documents will be stored on the ProArc EDMS; DCC will beresponsible for allocating document numbers by using a document profile within ProArc.The document profile will store the native file and PDF of the document that has beenissued. All documents can be retrieved by searching for documents by number, title & byusing other fields in the profile.

  • 7/24/2019 Project Document Control Procedure

    4/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 4of 13

    4. PROJECT & DOCUMENT NUMBERING & REVISION CONTROL

    A unique numbering system is used for filling and recovery of all documents as described in

    Client document ORTPP-PR-003.

    Example: 5631-PRC-07-BD-1001

    4 DIGITs (Max) - Sequential Number

    1 DIGIT (Max) - Document SizeSee Table C

    1 DIGIT (Max)DisciplineSee Table B

    2 DIGITs (Max) - Plant No.See Table A

    3 DIGITs (Max)Document TypeSee Table D

    4 DIGITs (Max) - Project No.

    Table A Plant Location

    Code Plant

    00 General

    05 Ruwais

    07 Utilities

    Table B Discipline/Engineering

    Letter Discipline Code

    A General

    B Process

    C Civil & Structural

    D Static Equipment

    E Energy Packages

    F Furnaces

    G Packages

    J InstrumentationL Piping

    M Mechanical

    N Insulation

    Q Foundations

    P Electrical

    R Buildings

    S Site Improvement

    T Telecommunications

    W Welding & Metallurgy

    X Painting

    Y HSE

    Z Marine

  • 7/24/2019 Project Document Control Procedure

    5/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 5of 13

    Table C Document Format

    Code Original Paper Size

    A A4

    B A3

    C A2D A1

    E A0

    Table D Document Types

    Commercial/Contract Documents

    Document Code Document Type

    CBE Commercial Bid Evaluation

    PEP Project Execution Plan

    REP Report

    SCH Schedule

    Project Documents

    Document Code Document TypeAUR Audit Report

    AUR Audit Report

    BIS Bid Appraisal Summary

    BID Bid Evaluation

    CSS Cost & Schedule Summary

    OPR Operating Procedure

    PCN Project Change Notice

    PCS Project Cost Summary

    RKM Risk Management

    STA Statement

    General Documents

    Document Code Document Type

    ANA Analysis

    APP Application

    ASS Assessment

    ATR Action Tracker

    BLS Bid List

    BOD Basis of Design

    BOM Bill of Materials

    CAC Calculation

    CEP Contract Execution Plan

    CRE Concession request

    CRT Commissioning Report

    CTR Cost Time Resource

    DAB Data BookDAS Data Sheet

    DCN Design Change Notice

    DDM Document Distribution Matrix

    DOC Declaration of Conformity

    DRF Deviation Request

    DTN Document Transmittal

    EAF External Audit Form

    EML Email

    ENQ Enquiry

    ENS Environmental Statement

    ERA Environmental Risk Assessment

    EST EstimateEVA Evaluation

    EWN Early Warning Notice

  • 7/24/2019 Project Document Control Procedure

    6/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 6of 13

    FAX Fax

    FDS Functional Design Specification

    FOR Forms

    IAF Internal Audit Form

    IDX Index Register or List

    INT Interface DocumentIOM Installation, Operating & Maintenance Manual (IOM)

    ITP Inspection & Test Plan

    ITT Invitation to Tender

    LST List

    LTR Letter

    MAN Manual

    MAT Matrix

    MOM Minutes of Meeting

    MRB Manufacturing Record Book

    MTO Material Take-off

    NCR Non-Conformance Report

    NOT Notification

    PCP Project Control ProcedurePCS Project Cost Summary

    PDP Project Delivery Plan

    PFS Performance Standard

    PHI Philosophy

    PLD Project Plan Deviation

    POL Policy

    PQP Project Quality Plan

    PRC Procedure

    PRG Programme

    PRL Proposal

    PSC Project S Curve

    PUR Purchase OrderQAM Quality Assurance Manual

    QPN Quality Plan

    QRY Project/Technical Query

    QUA Qualification

    REG Register

    REQ Requisitions

    RNS Risk Notification Sheet

    RQT Request

    RTA Recommendation to Award

    SDS Supplier Data Schedule

    SEP Service Execution Plan

    SII Site Instruction

    SPA Spares Listing

    SPE Specification

    SOW Scope of Work

    STD Standard

    STU Study

    TBE Technical Bid Evaluation

    TCO Technical & Commercial Offer

    TNN Technical Note

    TOR Terms of Reference

    TPR Test Procedure

    VAR Variation Order

    VOR Variation Order Request

    WCS Weight Control SheetWIS Work Instruction

  • 7/24/2019 Project Document Control Procedure

    7/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 7of 13

    WKP Workpack

    WPS Welding Procedure Specification

    TechnicalDocuments

    Document Code Document Type

    ADD Addendum

    ASY AssemblyBLD Block Diagrams

    CAU Cause & Effect Diagram

    CCR Change Request

    CDD Circuit Diagram

    CER Certification Record

    CRD Cable & Routing Record

    CSA Cross Section Area

    DTL Detail Drawing

    ELD Equipment Layout

    ELV ElevationFAB Fabrication

    FLD Flow Diagram

    GEN General Arrangement

    HAZ Hazardous Area Classification

    HMB Heat & Mass Balance

    HOK Hook-up Diagram

    IND Interconnection Diagram

    INS Installation Drawing

    ISO Isometric

    LAY Layout

    LDI Logic Diagram

    LID Line Diagram

    LOD Loop Diagrams

    PAL Panel Layouts

    PED Penetration Details

    PFD Process Flow Diagram

    PID Piping & Instrumentation Diagrams

    PIS Pipe Support

    PPL Plot Plan

    SCE Schematic

    SKE Sketch

    SLD Single Line Diagram

    TER Termination Diagram

    UFD Utility Flow Diagram

    WDD Wiring Diagram

  • 7/24/2019 Project Document Control Procedure

    8/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 8of 13

    Sequential Number

    The serial numbers shall be:1001 (to 1999)Flow Sheets, P&ID, Plot Plans

    2001 (to 2999)Piping Layout, Isometrics, Supports3001 (to 3999)Equipment Related4001 (to 4999)Civil Related5001 (to 5999)Instrument Related6001 (to 6999)Electrical Related7001 (to 7999)Rotating Equipment Movables8001 (to 8999)General Documents, HSE (now included)

    5. DOCUMENT FORMAT

    Standard templates shall be used for all documents, drawings data sheets, specifications,calculations and reports. Standard templates shall be held within discipline specific folders

    within the Dhabi Nortech Quality Management System at G:\QA\05-Standard Documents.

    All documents other than drawings shall have a front sheet which is formatted inaccordance with OP-SD- 001 Standard Document Template.

    All documents shall be in the English language

    All documents, except drawings, shall be supplied in a searchable PDF format

    5.1 Drawings

    New drawings will be prepared using the appropriate CAD system; an appropriate templatewill be selected for drawings and will be saved in the relevant document profile on ProArc.Client document numbers will also be added within the Dhabi Nortech drawing templatewhere applicable.

    5.2 Documents

    All documents will be saved in the relevant document profile on ProArc. Client documentnumbers will also be added within the Dhabi Nortech drawing template where applicable.

    5.3 Document Revision Control

    Where Dhabi Nortech apply their own revision control system the following shall apply.

    All Preliminary / For Information status documents shall be identified by revision P1, andthen further revisions shall be identified by P2, P3 onwards.

    All For Approval status documents shall be identified by revision A1, and then furtherrevisions shall be identified by revision A2, A3 onwards.

    All Issued for Design / Enquiry status documents shall be identified by revision B1 andthen further revisions shall be identified by revision B2, B3 onwards.

    All Issued for Construction / For Use status documents shall be identified by revision C1and then further revisions shall be identified by revision C2, C3 onwards.

    All As Built status documents shall be identified by revision Z1, and then further revisions

  • 7/24/2019 Project Document Control Procedure

    9/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 9of 13

    shall be identified by revision Z2, Z3 onwards.

    All Cancelled status documents shall be identified by revision XX, with CANCELLEDclearly marked across the document.

    Changed information

    When a drawing is changed, a revision cloud / bubble with the revision number inside (in atriangle) shall be shown alongside each change. As the drawing progresses, i.e.Preliminary through Design, Enquiry and Construction, existing revision clouds / bubblesshall be removed at each update to show a clean drawing.

    When changing a document, all changes should be referenced on the document front sheet/ drawing title block to show the current revision of the document. Revision numbering willbe as follows:

    REV DATE PAGES DESCRIPTION

    A1,B1,C1 etc. RevDate Pageseffected Description of change

    6. MASTER DOCUMENT REGISTER (MDR)

    It will be the responsibility of DCC to ensure the MDR is maintained and updated throughthe life of the project. DCC will reserve document numbers & add Client documentnumbers in ProArc, delivery dates will be set against the document number to trackprogress in accordance with Client document SVP(P)-PR-027

    7. DOCUMENTATION ISSUE, TRACKING & STORAGE

    7.1 Documentation Issue

    Release of Documents to Client

    Final issue of documents shall be transmitted to the Client only after review and sign-off byEM. The extent and format of such documentation will be advised by the client.

    Issue and Distribution

    The distribution of documents to Client, Suppliers and & third parties will be as noted on thetransmittal with the reason for issue included; ProArc will maintain records of all documentsthat have been issued.

    7.2 Tracking

    When documents are issued to a receiver outside Dhabi Nortech, DCC will be responsiblefor checking receipt of the transmittal. Signed Transmittals will be stored in ProArc by DCC.

    DCC will be responsible for expediting turnaround of documents on internal squadcheck/workflow. Progress of document production and review is monitored using ProArc.

    7.3 Documents for Review by Client

    Documents requiring comment / approval by Client or other external authority will be agreedduring the Project Kick-off meeting. Documents will be issued with a Transmittal and returnby dates will be recorded on the document profile. The standard timescale will be 10

  • 7/24/2019 Project Document Control Procedure

    10/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 10of 13

    working days, however this may vary depending on agreed timescales with Client. Theturnaround times will be indicated by the DM on the issue request. DM/DCC will expedite alloutstanding documents from clients and record all received comments in the documentprofile on ProArc.

    7.4 Control of Comments from Client/Dhabi Nortech

    Documents, when issued for review to Client, will be accompanied by a CRS, this will becompleted by the DCC and will be included in the transmittal to the Client. The CRS iscompleted by the Client and returned to Dhabi Nortech for resolution.

    8. CLIENT / SUPPLIER DOCUMENTATION

    The numbering, review and control of client and vendor documentation is as follows.

    8.1 Client Documents

    Client documents will be received by DCC and they will be logged in ProArc in the relevantproject. DCC will include the client number in the client number field on the documentprofile. DC will notify the Project team that new documents have been received by sendingan email link with the details.

    8.2 Supplier Documents

    The supplier will provide a supplier document register (SDR) listing documents withexpected dates of issue. DC will reserve document profiles in ProArc and include dates forexpediting and add client document numbers if required. The client numbers will be given tothe supplier for inclusion on the documents.

    a. Numbering

    Supplier documents will be received by DCC and then logged in ProArc in the relevantproject. DCC will include the supplier document number in the supplier documentnumber field on the document profile.

    Any special requirements for supplier document format will be identified at the Kick Offmeeting.

    b. Location Of Documents

    All supplier documents will be stored by DCC on ProArc in the relevant project; thesewill be searchable by document number and title. New revisions will supersede the

    previous version and will be filed in the same document profile.

    Supplier Documentation Review

    DCC creates workflow as per supplier document distribution matrix Reviewerchecks documents by viewing on ProArc

    Reviewer closes workflow

    DM receives workflow and reviews all comments made

    DCC receive notification workflow is complete

    DCC issue documents to vendor indicating status

    Completed reviews will be confirmed with a document status code:-

    1Accepted

  • 7/24/2019 Project Document Control Procedure

    11/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 11of 13

    2Accepted with Comments incorporate Revise & Resubmit

    3Not Accepted. Revise & Resubmit

    4For Information

    These will be shown on the document profile and Transmittal.

    9. CORRESPONDENCE

    The circulation and distribution of emails, letters and transmittals will be as noted in 10.1below. Any technical discussion with the client must be addressed to the clientsrepresentative raising the issue (using the email reply all function) and ensure that theDM/EM/DCC is copied in any response.

    Where this is a new discussion raised by Dhabi Nortech then they should be addressed, inthe first instance, with the persons noted below in table 10.1.

    The subject line of all emails/transmittals should follow the clients requested format; e.g.5631 (FEED) : (letter/email/transmittal reference): (subject of message)

    For clarity, and in accordance with OP-SEP-001, Do Not change subject in any email trail.

    9.1 Emails

    Emails must include the project number (and/or transmittal reference) and subject in thesubject field, a project mailbox has been created in outlook Public Folders. All emailsshould be filed in the relevant month for archiving.

    9.2 Letters

    Letters issued to the Client must be issued with a sequential Correspondence Number.

  • 7/24/2019 Project Document Control Procedure

    12/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 12of 13

    10. DISTRIBUTION

    10.1From Dhabi Nortech to Client

    CorrespondenceType

    Mean of Communication Recipients

    Contractual Matters Letters/Fax To: PX2Cc: PC, PCP, PX2/M1

    Project Documents(Except contractualmatters)

    Letters/Fax/Transmittals2 Hard copies

    To: PX2Cc: PX2/M1

    E-mail To: PX2/M1Cc: PX2, PX-3/P-SEC0, PX1/S1

    Day to day technical E-mail To: PX-3/P-SEC0Cc: PX2, PX2/M1

    Circulation Legend

    Designation Name Email Address

    PX Hasan Mohamad Al Ali

    Vice President, Projects Ruwais

    [email protected]

    PC Mahmoud A. Yousef Al HosaniVice President, Project Controls

    [email protected]

    PCP Bharat MehtaProjects Procurement &Contracting Department Head

    [email protected]

    PX2 Joseph GeraldSr. Project Manager (Ruwais)

    [email protected]

    PX2/M1 Assaad AbdallahProjectManager

    [email protected]

    PX-3/P-SCE0 Abdelsayed BotrossSr. Construction Engineer

    [email protected]

    PX1/S1 Sikander Ali

    Office Administrator #

    [email protected]

    PCC/P-SPAS7 Saravanan AmarnathPlanning**

    [email protected]

    # copied on all project emails (not contractual)** copied on planning related emails only

  • 7/24/2019 Project Document Control Procedure

    13/13

    Abu Dhabi Gas Industries Ltd Document No. 5631-PRC-00-AA-8001GASCO Rev A1Project Document Control Procedure

    OP-SD-001-A3 Page 13of 13

    10.2From Client to Dhabi Nortech

    Correspondence Type Mean ofCommunication

    Recipients

    Contractual Matters Letters/Fax To: DM

    Cc: EM, MDProject Documents (Exceptcontractual matters)

    Letters/Fax/Transmittals To: DMCc: DCC

    E-mail To: DMCc: DCC

    Day to day technical E-mail To: DMCc: DCC, EM and relevant TechnicalLead Engineer below

    Circulation Legend

    Designation Name Email Address

    DM Brian NewbouldDelivery Manager

    [email protected]

    MD Bryan BunnManaging

    Director

    [email protected]

    EM Keith StephensonEngineering Manager

    [email protected]

    SWE Steve WakeCivil & StructuralTechnical Lead Engineer

    [email protected]

    CCY Craig CowleyE I & C Technical LeadEngineer

    [email protected]

    AOE Anthony ORourkePiping Technical Lead

    [email protected]

    SSN Shaheeb ShanMechanical Technical

    Lead

    [email protected]

    SDN Steve DoneganProcess Technical Lead

    [email protected]

    Document Control Centre (DCC) to be included in all project related emails (not contractual)[email protected]

    11. PROJECT REPORTING

    The following reports will be produced from ProArc:

    Document status

    Documents awaiting Client Approval

    Documents Approved by Client

    Master Document Register (MDR)

    Supplier document status

    Supplier Document Register (SDR)

    The above will be supplied to GASCO on request along with any additional reportingrequested by GASCO