+ All Categories
Home > Business > Project Management 101: Communication is 90% of the Job

Project Management 101: Communication is 90% of the Job

Date post: 15-Jul-2015
Category:
Upload: beth-fischi-pmp
View: 599 times
Download: 3 times
Share this document with a friend
Popular Tags:
28
PROJECT MANAGEMENT 101: COMMUNICATION IS 90% OF THE JOB Beth Fischi Alcatel-Lucent Motive Customer Experience Solutions [email protected] 2015
Transcript
Page 2: Project Management 101: Communication is 90% of the Job

Introduction

Beth Fischi

• Technical communicator ~17 years

• Sr. Technical Publications Manager

• Project Management Professional (PMP)

• Certified ScrumMaster (CSM)

Page 3: Project Management 101: Communication is 90% of the Job

What we’ll cover today

• High-level overview of project management

• Best practices for common project issues

• Info on project management certification

• Q&A

Page 4: Project Management 101: Communication is 90% of the Job

WHY

NOT

JUST

WING

IT?

(There’s not enough time to plan anyway, right?)

Page 5: Project Management 101: Communication is 90% of the Job

Wasted

time

Page 6: Project Management 101: Communication is 90% of the Job

Lost money

Page 7: Project Management 101: Communication is 90% of the Job

Missed

opportunity

Page 8: Project Management 101: Communication is 90% of the Job

Death marches

Page 9: Project Management 101: Communication is 90% of the Job

Ruined

reputations

Yours, your coworkers,

your company.

Page 10: Project Management 101: Communication is 90% of the Job

A

t

t

r

i

t

i

o

n

Page 11: Project Management 101: Communication is 90% of the Job

Constant

interruptions

by your

boss

Page 12: Project Management 101: Communication is 90% of the Job

Why risk it?

Page 13: Project Management 101: Communication is 90% of the Job

Project Management –

the art of not winging it.

Page 14: Project Management 101: Communication is 90% of the Job

What project management is NOT

• The mere use of processes, tools,

techniques

• Using Microsoft Project to create a

schedule and then watch it unfold

like a precious rosebud

• Whipping underlings

• Making team members crazy:

• “What percent done are you?”

• “What about now?”…

• “What about now?”…

Page 15: Project Management 101: Communication is 90% of the Job

What project management IS

• The art of applying a consistent, defined framework and body of

knowledge (BOK) to a project to ensure its requirements are met

• The ability and experience to tailor the approach to the project

• Working in concert with your team, stakeholders, sponsors

• 90% communication

As defined by the Project Management Institute (PMI):

The application of knowledge, skills and techniques to execute

projects effectively and efficiently. It’s a strategic competency for

organizations, enabling them to tie project results to business goals

— and thus, better compete in their markets.

Page 16: Project Management 101: Communication is 90% of the Job

PM and communications

90% of PM is

communication…

sound familiar?

As a

communicator,

you’ve got this!

Communication = Increased project success!

Right audience /

stake-holders

Right time

Right information

Page 17: Project Management 101: Communication is 90% of the Job

PM Body of Knowledge (PMBOK®)

• Defined by PMI’s PMBOK®

Guide

• Process-based, described

in terms of inputs, tools &

techniques, and outputs

• Includes:

• Framework

• Process groups

• Knowledge areas

• 47 processes

Page 18: Project Management 101: Communication is 90% of the Job

Framework highlights

• Project: Temporary & unique (not routine operation)

• Triple constraints… and more complex models

Customer Satisfaction

Page 19: Project Management 101: Communication is 90% of the Job

Process groups

Similar to:

• Start

• Plan

• Do

• Check & Act

• End

Page 20: Project Management 101: Communication is 90% of the Job

Knowledge areas

Stakeholder

Management

Page 21: Project Management 101: Communication is 90% of the Job

Best practices for common issues

Some takeaways from PMP study that overlap with

concerns we have as technical communicators:

• Estimating tasks better

• Resolving competing requirements

• Preventing disagreements over deliverables

• Dealing with conflict

• Influencing people

• Handling project changes

Our focus

today

Page 22: Project Management 101: Communication is 90% of the Job

Estimating tasks better (1/3)

• Example: My doc task took 10 days longer than planned

because <fill in usual reason>.

• Best practice:

• If possible, the person doing the work does the estimation.

• The estimator:

• Undertakes reasonable effort to understand and clarify requirements.

• Clarifies how refined the estimate must be.

• Records risks and assumptions made when estimating.

• Does not pad the task or include calendar time yet. Start with pure work

effort. (Reserves will be added later.)

• Uses the same units (hours, days, etc.) throughout.

• Can involve team members (communicate!) whenever feasible to get

other expert opinion – but ultimately the person doing the work should

decide.

TIME MANAGEMENT

My dog ate my

laptop

Page 23: Project Management 101: Communication is 90% of the Job

Estimating tasks better (2/3)

• When uncertain of task estimates, you can use one of the three-point estimating techniques:

• Triangular Distribution (Simple Average):

• Simple average of Pessimistic + Optimistic + Most Likely estimates

• Gives equal weight to all estimates

• Beta Distribution (Weighted Average):

• Weighted average of Pessimistic + Optimistic + Most Likely estimates

• Use when you want to give more weight to a type of estimate. Here, the “most likely” estimate is given the most weight, but you can modify this formula

TIME MANAGEMENT

Estimate key

P = Pessimistic

M = Most likely

O = Optimistic

(P+M+O) / 3

(P+4M+O) / 6

Page 24: Project Management 101: Communication is 90% of the Job

Estimating tasks better (3/3)

• To estimate risk, use Beta Activity Standard Deviation:

• Shows possible range for the estimate = potential variance for the task

= i.e., the larger the number, the riskier the activity

• Compare result of activities; work with project manager / leader to give

ones with larger numbers (higher risk) more reserves

• Reasons to work with PM before adding reserves:

1. PM needs to know risks to project and, as project integrator, standardizes

how reserves are created across team

2. Otherwise, team members arbitrarily determine padding

3. PM will love you and appreciate your assistance!

TIME MANAGEMENT

Estimate key

P = Pessimistic

O = Optimistic

(P-O) / 6

Page 25: Project Management 101: Communication is 90% of the Job

PMI and PMP

• The Project Management Institute (PMI) = not-for-profit association

for the project, program, and portfolio management profession

• About 700K members and 590K PM practitioners

• Standards for project management are the most widely recognized worldwide

• Requirements to become a Project Management Professional (PMP):

• Experience in PM: 4500 hours w/Bachelor’s or 7500 hours w/high school

diploma

• Professional PM education: 35 hours

• Approval to sit for the PMP certification exam: Application ($129 +$10 initial

fee; students $32) + exam fee (US $405 if PMI member)

• Pass exam: 4 hours, 200 questions

• Tips to move forward (see handout)

• For more info: www.pmi.org

Page 26: Project Management 101: Communication is 90% of the Job

Closing

• Reasons not to wing it

• What PM is and is not

• Role of communications in PM

• The PMBOK, including framework, process

groups, knowledge areas

• A best practice in time management

• Some information on how to get your PMP

certification

Page 27: Project Management 101: Communication is 90% of the Job

Q&A

Page 28: Project Management 101: Communication is 90% of the Job

Credits

• Slide 14: Photo credit: U.S. Signal Corps / Wikimedia Commons / Public

Domain – Stalin 1943.

• Slide 15: See: http://www.pmi.org/About-Us/About-Us-What-is-Project-

Management.aspx

• Slide 18:

• Image credit (left): Mapto / Wikimedia Commons / Public Domain

• Image credit (right): Recreated from Rita Mulcahey’s PMP Exam Prep, 8th

edition

• Slide 19: Image credit: Department of Veterans Affairs, Office of Information

and Technology / Wikimedia Commons / Public Domain

• Slide 20: Image credit: Department of Veterans Affairs, Office of Information

and Technology / Wikimedia Commons / Public Domain (with added

“Stakeholder Management” to bring image up to PMBOK® 5th edition)

• “PMI”, the PMI logo, “PMP”, the PMP logo, “PMBOK”, “PgMP”, “Project

Management Journal”, “PM Network”, and the PMI Today logo are registered

marks of Project Management Institute, Inc.


Recommended