Project Management 3. Project Management Plans
Transcript
Page 1: Project Management 3. Project Management Plans. Week 3.

Project Management3. Project Management Plans

Page 2: Project Management 3. Project Management Plans. Week 3.

Week 3

Page 3: Project Management 3. Project Management Plans. Week 3.

Project management plans

Page 4: Project Management 3. Project Management Plans. Week 3.

WhyWhatHowWhe

nWho

Page 5: Project Management 3. Project Management Plans. Week 3.

WhyWhatHowWhe

nWho

Why is this project happening?

Why now?

Why us?

Page 6: Project Management 3. Project Management Plans. Week 3.

WhyWhatHowWhe

nWho

What solution needs to be put in place to achieve the goals?

What work needs to happen to build the solution?

Page 7: Project Management 3. Project Management Plans. Week 3.

WhyWhatHowWhe

nWho

How do we get this solution in place?

How do we know when we’re done?

Page 8: Project Management 3. Project Management Plans. Week 3.

WhyWhatHowWhe

nWho

When do work activities happen?

What do we need to do first?

What’s last?

Page 9: Project Management 3. Project Management Plans. Week 3.

WhyWhatHowWhe

nWho

Who do we need to deliver this project successfully?

Page 10: Project Management 3. Project Management Plans. Week 3.

And what will it cost?

$

Page 11: Project Management 3. Project Management Plans. Week 3.

Course objectives

Implement IT project planning and selection techniques

Appreciate the importance of project portfolio management

Page 12: Project Management 3. Project Management Plans. Week 3.

The project management plan

Benefits of planning

What to consider in your plan

Guidelines

Reviewing a plan

Page 13: Project Management 3. Project Management Plans. Week 3.

The project management plan

Benefits of planning

What to consider in your plan

Guidelines

Reviewing a plan

Page 14: Project Management 3. Project Management Plans. Week 3.

Plans are useless. Planning is

indispensibleDwight Eisenhower

Page 15: Project Management 3. Project Management Plans. Week 3.

The project management plan

Benefits of planning

What to consider in your plan

Guidelines

Reviewing a plan

Page 16: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

Why plan?Why plan?

Page 17: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Page 18: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Guides you activities

Page 19: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Guides you activities

Makes you think ahead

Page 20: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Guides you activities

Makes you think ahead

Helps you work out who you need to hire

Page 21: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Guides you activities

Makes you think ahead

Helps you work out who you need to hire

Works out the timeline and budget

Page 22: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Guides you activities

Makes you think ahead

Helps you work out who you need to hire

Helps manage expectations

Works out the timeline and budget

Page 23: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Guides you activities

Makes you think ahead

Helps you work out who you need to hire

Helps manage expectations

Works out the timeline and budget

Helps understand the effects of changes

Page 24: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/xabier-martinez/225627841/

The PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe PlanThe Plan

Changes once you start

Guides you activities

Makes you think ahead

Helps you work out who you need to hire

Helps manage expectations

Makes sure you are doing the right thing

Works out the timeline and budget

Helps understand the effects of changes

Page 25: Project Management 3. Project Management Plans. Week 3.

The project management plan

Benefits of planning

What to consider in your plan

Guidelines

Reviewing a plan

Page 26: Project Management 3. Project Management Plans. Week 3.
Page 27: Project Management 3. Project Management Plans. Week 3.

?

Page 28: Project Management 3. Project Management Plans. Week 3.

Who will read it?

What do they need to know?

Do they come in cold?

Page 29: Project Management 3. Project Management Plans. Week 3.

What is your project going to deliver?

Scope

The work to be done = The target product

Page 30: Project Management 3. Project Management Plans. Week 3.

Hunt, B. et al. (2003). Project charter. Retrieved January 23, 2006 from http://webpages.charter.net/hafox/pm/docs/charter.doc (partial)

Page 31: Project Management 3. Project Management Plans. Week 3.

Hunt, B. et al. (2003). Hunt, B. et al. (2003). Project scope statementProject scope statement. Retrieved January 23, 2006 . Retrieved January 23, 2006 from from http://webpages.charter.net/hafox/pm/docs/scope.doc http://webpages.charter.net/hafox/pm/docs/scope.doc (partial)(partial)

Page 32: Project Management 3. Project Management Plans. Week 3.

What is your project going to deliver?

Definition

The work to be done=?= The target product

Page 33: Project Management 3. Project Management Plans. Week 3.

What is your project going to deliver?

Change control

The work to be done=?= The target product

Page 34: Project Management 3. Project Management Plans. Week 3.

What is your project going to deliver?

Value?

The work to be done=?= The target product

Page 35: Project Management 3. Project Management Plans. Week 3.

The WBS

Page 36: Project Management 3. Project Management Plans. Week 3.

The right way

The right way

The wrong way

The wrong way

Page 37: Project Management 3. Project Management Plans. Week 3.

Focus on deliverable

s

Focus on deliverable

s

Focus on processesFocus on processes

Page 38: Project Management 3. Project Management Plans. Week 3.

Align to value

Align to value

Align to process stages

Align to process stages

Page 39: Project Management 3. Project Management Plans. Week 3.

Why?Why? Why not?Why not?

Page 40: Project Management 3. Project Management Plans. Week 3.

Figure 5.2 Sample hierarchical WBS organized by phase (Schwalbe, 2006, p176)

The wrong way?

The wrong way?

Note the Layers

Note the Layers

Page 41: Project Management 3. Project Management Plans. Week 3.

Table 5.3 Table 5.3 Sample tabular WBSSample tabular WBS(Schwalbe, 2006, p176)(Schwalbe, 2006, p176)

1.0 Concept1.1 Evaluate current systems1.2 Define requirements

1.2.1 Define user requirements1.2.2 Define content requirements1.2.3 Define system requirements1.2.4 Define server owner

requirements1.3 Define specific functionality1.4 Define risks and risk management

approach1.5 Develop project plan1.6 Brief Web development team

2.0 Web Site Design3.0 Web Site Development4.0 Roll Out5.0 Support

Page 42: Project Management 3. Project Management Plans. Week 3.

http://images.google.com.au/images?hl=en&q=wbs&btnG=Search+Images&gbv=2

Page 43: Project Management 3. Project Management Plans. Week 3.

Document your assumptions

Very little knowledg

e

Complete knowledg

e

Degree of knowledge over time

Page 44: Project Management 3. Project Management Plans. Week 3.

OBS

Page 45: Project Management 3. Project Management Plans. Week 3.

Figure 9.2 Sample Project Organizational Chart(Schwalbe, 2006, p358)

Page 46: Project Management 3. Project Management Plans. Week 3.

Task 1

Task 2

Task 3

Task 4

Task 5

Task 6

Person 1 Person 2 Person 3 Person 4

Page 47: Project Management 3. Project Management Plans. Week 3.

http

://w

ww

.win

ning

with

add.

com

/org

aniz

atio

n/

Page 48: Project Management 3. Project Management Plans. Week 3.

Figure 9.6 Sample Resource Histogram (Schwalbe, 2006, p362)

Page 49: Project Management 3. Project Management Plans. Week 3.

tools

rasci(aka raci)

ram

Page 50: Project Management 3. Project Management Plans. Week 3.

http://makeitstrategic.com/index.php?blog=5&cat=18

Page 51: Project Management 3. Project Management Plans. Week 3.

r

a

s

c

i

responsible

accountable

supportive

consulted

informed

Page 52: Project Management 3. Project Management Plans. Week 3.

r

a

m

responsibility

assignment

matrix

http://www.iil.com/freeresources/downloads/UPMM_IIL_Responsibility%20Assignment%20Matrix%20(RAM).doc

Page 53: Project Management 3. Project Management Plans. Week 3.

Task 1

Task 2

Task 3

Task 4

Task 5

Task 6

Person 1 Person 2 Person 3 Person 4

R

R

R

R

R

R

Page 54: Project Management 3. Project Management Plans. Week 3.

Figure 9.4 Sample Responsibility Assignment Matrix (RAM)(Schwalbe, 2006, p360)

OBS: Organizational Breakdown Structure

WBS: Work Breakdown Structure

Page 55: Project Management 3. Project Management Plans. Week 3.

One and only one person can be accountable. Multiple people can be responsible and certainly others can be informed and consulted. Source: Glen B Alleman, (2007) Responsibility Assignment Matrix, Herding Catshttp://herdingcats.typepad.com/my_weblog/2007/02/responsibility_.html retreived 2/8/08

Page 56: Project Management 3. Project Management Plans. Week 3.

One and only one person can be accountable. Multiple people can be responsible and certainly others can be informed and consulted. Source: Glen B Alleman, (2007) Responsibility Assignment Matrix, Herding Catshttp://herdingcats.typepad.com/my_weblog/2007/02/responsibility_.html retreived 2/8/08

Page 57: Project Management 3. Project Management Plans. Week 3.

Project organisations go farther than workers and work

Page 58: Project Management 3. Project Management Plans. Week 3.

1. Project Team structure

Project Sponsor

Project ManagerCraig Brown

Working Group:• Design focus• OLA decisions and choices• Formal review & validation of

deliverables• Business input and SME access

Steering Committee:• Governance focus• Approval of project strategy &

plans• Endorsement of key OLA

decisions• Final approval of the OLA

Business case and Solution Design

• Removal of major roadblocks & prioritisation

Analysts

Testers

Designer

Change consultants

Working GroupMarketing

Product ManagementLegal

FinanceSales

Customer Service

Steering CommitteeHead of Marketing and SalesHead of Product Management

Head of Customer ServiceHead of Finance

Developers

Page 59: Project Management 3. Project Management Plans. Week 3.

Remember this?

Page 60: Project Management 3. Project Management Plans. Week 3.

You might break down the work by phases

You might break down the work by phases

Page 61: Project Management 3. Project Management Plans. Week 3.

Why?Why?

Page 62: Project Management 3. Project Management Plans. Week 3.

http://flickr.com/photos/pshan427/2382209408/

Page 63: Project Management 3. Project Management Plans. Week 3.

So now you know what needs to be done

Page 64: Project Management 3. Project Management Plans. Week 3.

So now you know what needs to be done

and who is going to do it.

Page 65: Project Management 3. Project Management Plans. Week 3.

So now you know what needs to be done

and who is going to do it.

But what about when?

Page 66: Project Management 3. Project Management Plans. Week 3.

Schedule

Page 67: Project Management 3. Project Management Plans. Week 3.

http://www.edwardtufte.com/bboard/q-and-a-fetch-msg?msg_id=000076

Page 68: Project Management 3. Project Management Plans. Week 3.

Figure 3.3 Figure 3.3 Sample network diagram (partial) Sample network diagram (partial) (Schwalbe, 2006, p211)(Schwalbe, 2006, p211)

Page 69: Project Management 3. Project Management Plans. Week 3.

Table 3.10 Sample milestone report (partial) (Schwalbe, 2006, p100)

Page 70: Project Management 3. Project Management Plans. Week 3.

Figure 3.3 Sample Gantt chart (partial) (Schwalbe, 2006, p97)

Page 71: Project Management 3. Project Management Plans. Week 3.

http://www.edwardtufte.com/bboard/q-and-a-fetch-msg?msg_id=000076

Page 72: Project Management 3. Project Management Plans. Week 3.

Scope Resource plan Schedule

Page 73: Project Management 3. Project Management Plans. Week 3.

Why What How When Who

Page 74: Project Management 3. Project Management Plans. Week 3.

And what will it cost?

$

Page 75: Project Management 3. Project Management Plans. Week 3.
Page 76: Project Management 3. Project Management Plans. Week 3.
Page 77: Project Management 3. Project Management Plans. Week 3.

Constructing a budget is easy

Sticking to it is hard.

Page 78: Project Management 3. Project Management Plans. Week 3.
Page 79: Project Management 3. Project Management Plans. Week 3.

How will you Monitor and Control the project?

Who needs to know?

Page 80: Project Management 3. Project Management Plans. Week 3.

Galloway, M. (2004). Galloway, M. (2004). Status reportStatus report. Retrieved January 23, 2006 from . Retrieved January 23, 2006 from http://web.augsburg.edu/~oie/mis376/documents/SR1.doc (partial)(partial)

Page 81: Project Management 3. Project Management Plans. Week 3.

Risk management

Degree of knowledge over time

Page 82: Project Management 3. Project Management Plans. Week 3.

BetterProjects.nethttp://www.betterprojects.net/search?q=risk+101

risks

impact

Page 83: Project Management 3. Project Management Plans. Week 3.

The project management plan

Benefits of planning

What to consider in your plan

Guidelines

Reviewing a plan

Page 84: Project Management 3. Project Management Plans. Week 3.

Six-Step Proven Path for Schedule DevelopmentRudi van den Berg, Pcubed, Inc.  http://www.pcubed.com/Solutions/SolSixStep.asp

Page 85: Project Management 3. Project Management Plans. Week 3.

The project management plan

Benefits of planning

What to consider in your plan

Guidelines

Reviewing a plan

Page 86: Project Management 3. Project Management Plans. Week 3.

htt

p:/

/thin

h1

80

8.fi

les.

word

pre

ss.c

om

/20

07

/12

/pro

jpla

n_s

am

ple

_20

05

06

10

_14

40

24

.pdf

Page 87: Project Management 3. Project Management Plans. Week 3.

BetterProjects.net

Title page pic care of cayusa & CC @ Flickrhttp://flickr.com/photos/cayusa/465106926/