Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands [email protected]
Transcript
Page 1: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

Project Management

InitiationMinder Chen, Ph.D.

CSU Channel [email protected]

Page 2: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 2 © Minder Chen, 2012-2015

Project Boundaries

Page 3: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 3 © Minder Chen, 2012-2015

Project Management Process Interactions

Page 4: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 4 © Minder Chen, 2012-2015

Project Charter• Develop Project Charter is the

process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

• The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.

Page 5: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 5 © Minder Chen, 2012-2015

Develop Project Charter: Inputs, Tools & Techniques, and Outputs

Page 6: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 6 © Minder Chen, 2012-2015

Facilitation Techniques

Facilitation techniques have broad application within project management processes and are used to guide the development of the project management plan. Brainstorming, conflict resolution, problem solving, and meeting management are key techniques used by facilitators to help teams and individuals achieve agreement to accomplish project activities.

Page 7: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 7 © Minder Chen, 2012-2015

Data Flow Diagrams Used in PMBOK5

Page 8: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 8 © Minder Chen, 2012-2015

Develop Project Charter Data Flow Diagram

Page 9: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 9 © Minder Chen, 2012-2015

Project Charter

Page 10: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 10 © Minder Chen, 2012-2015

SOW• The statement of work (SOW) is a narrative

description of products or services to be delivered by the project.

• For internal projects, the project initiator or sponsor provides the statement of work based on business needs, product, or service requirements.

• For external projects, the statement of work can be received from the customer as part of a bid document, for example, request for proposal, request for information, request for bid (quotation), or as part of a contract.

A request for information (RFI) is a standard business process whose purpose is to collect written information about the capabilities of various suppliers. Normally it follows a format that can be used for comparative purposes.

Page 11: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 11 © Minder Chen, 2012-2015

Business Case and Contract

• The business case or similar document provides the necessary information from a business standpoint to determine whether or not the project is worth the required investment.

• A contract is an input if the project is being done for an external customer.

Page 12: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 12 © Minder Chen, 2012-2015

Project Charter Output• Project purpose or justification,

• Measurable project objectives and related success criteria,

• High-level requirements,

• Assumptions and constraints,

• High-level project description and boundaries,

• High-level risks,

• Summary milestone schedule,

• Summary budget,

• Stakeholder list,

• Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project),

• Assigned project manager, responsibility, and authority level, and

• Name and authority of the sponsor or other person(s) authorizing the project charter.

Page 13: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 13 © Minder Chen, 2012-2015

Identify Stakeholders

Project Stakeholder Management includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution. Stakeholder management also focuses on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, managing conflicting interests and fostering appropriate stakeholder engagement in project decisions and activities. Stakeholder satisfaction should be managed as a key project objective.

Page 14: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 14 © Minder Chen, 2012-2015

Project Stakeholders• Stakeholders are persons or organizations (e.g.,

customers, sponsors, the performing organization, or the public), who are actively involved in the project or whose interests may be positively or negatively affected by the performance or completion of the project.

• Stakeholders may also exert influence over the project, its deliverables, and the project team members.

• The project management team must identify both internal and external stakeholders in order to determine the project requirements and expectations of all parties involved.

• Furthermore, the project manager must manage the influence of the various stakeholders in relation to the project requirements to ensure a successful outcome.

Page 15: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 15 © Minder Chen, 2012-2015

Project Stakeholders

• Positive stakeholders are those who would normally benefit from a successful outcome from the project, while negative stakeholders are those who see negative outcomes from the project’s success.

• Negative stakeholders are often overlooked by the project team at the risk of failing to bring their projects to a successful end.

Shake hands and kiss babies as necessary and grease the wheels of the bureaucratic machine so that your project has the smoothest ride possible.

Page 16: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 16 © Minder Chen, 2012-2015

Project Stakeholders

Source: PMBOK 5, p. 31

Page 17: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 17 © Minder Chen, 2012-2015

Project Stakeholder Management

Page 18: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 18 © Minder Chen, 2012-2015

Project Stakeholder Management

Page 19: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 19 © Minder Chen, 2012-2015

Identify Stakeholders

Page 20: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 20 © Minder Chen, 2012-2015

Example Power/Interest Grid with Stakeholders

Page 21: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 21 © Minder Chen, 2012-2015

The Engagement Level of the Stakeholders • Unaware. Unaware of project and potential impacts.

• Resistant. Aware of project and potential impacts and resistant to change.

• Neutral. Aware of project yet neither supportive nor resistant.

• Supportive. Aware of project and potential impacts and supportive to change.

• Leading. Aware of project and potential impacts and actively engaged in ensuring the project is a success.

C indicates the current engagement; D indicates the desired engagement

Stakeholders Engagement Assessment Matrix

Page 22: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 22 © Minder Chen, 2012-2015

Page 23: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 23 © Minder Chen, 2012-2015

Interpersonal Skills and Management Skills The project manager applies interpersonal skills to manage stakeholders’ expectations.

•Building trust,

•Resolving conflict,

•Active listening, and

•Overcoming resistance to change.

The project manager applies management skills to coordinate and harmonize the group toward accomplishing the project objectives.

•Facilitate consensus toward project objectives,

•Influence people to support the project,

•Negotiate agreements to satisfy the project needs, and

•Modify organizational behavior to accept the project outcomes.

Page 24: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 24 © Minder Chen, 2012-2015

A Typical Project Outline

Page 25: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 25 © Minder Chen, 2012-2015

Reward-Risk Matrix for Selecting Projects

Source: Paul Roberts, Guide to Project Management, 2007

Page 26: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 26 © Minder Chen, 2012-2015

Customer’s Bill of Right (for Software Project)

1. To set objectives for the project and have them followed.

2. To know how long the software project will take and how much it will cost.

3. To decide which features are in and which are out of the software.

4. To make reasonable changes to requirements throughout the course of the project and to know the costs of making those changes.

5. To know the project's status clearly and confidently

6. To be apprised regularly of risks that could affect cost, schedule, or quality, and to be provided with options for addressing potential problems.

7. To have ready access to project deliverables throughout the project.

Steve McConnell, Software Project Survival Guide, Microsoft Press, 1998.

Page 27: Project Management Initiation Minder Chen, Ph.D. CSU Channel Islands Minder.chen@csuci.edu.

PM: Initiation - 27 © Minder Chen, 2012-2015

Project Team’s Bill of Right1. To know the project objectives and to clarify priorities.

2. To know in detail what product I'm supposed to build and to clarify the product definition if it is unclear.

3. To have ready access to the customer, manager, marketer, or other person responsible for making decisions about the software's functionality.

4. To work each phase of the project in a technically responsible way, especially to not be forced to start coding too early in the project.

5. To approve effort and schedule estimates for any work that the team will be asked to perform. This includes the right to provide only the kinds of cost and schedule estimates that are theoretically possible at each stage of the project; to take the time needed to create meaningful estimates; and to revise estimates whenever the project's requirements change.

6. To have my project's status reported accurately to customers and upper management.

7. To work in a productive environment free from frequent interruptions and distractions, especially during critical parts of the project.