Date post: | 12-Apr-2018 |
Category: |
Documents |
Upload: | luksi-damanik |
View: | 213 times |
Download: | 0 times |
of 82
7/21/2019 Project Management Kr
1/82
ProjectManagement
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 -0 1
7/21/2019 Project Management Kr
2/82
What is a Project?
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 -0 2
Project
An interrelated
set ofactivities witha denitestarting andending point,which resultsin a unique
outcome for a
7/21/2019 Project Management Kr
3/82
What is ProjectManagement?
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 03
ProjectManagement
A s!stemi"ed,phasedapproach to
dening,organi"ing,planning,
monitoring,
7/21/2019 Project Management Kr
4/82
#ening and $rgani"ingProjects
#ening the %cope and $&jectives
%electing the Project Managerand 'eam
(ecogni"ing $rgani"ational%tructure
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 -0
7/21/2019 Project Management Kr
5/82
Planning Projects
#ening the Wor) *rea)down
%tructure
#iagramming the networ)
#eveloping the schedule
Anal!"ing cost+timetrade+os
Assessing ris)s
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 -0 !
7/21/2019 Project Management Kr
6/82
Wor) *rea)down%tructure
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 -0"
Wor) *rea)down %tructure
A statement of all the wor) that
has to &e completed
Activit!
'he smallest unit of wor) eortconsuming &oth time andresources that can &e planned
and controlled
7/21/2019 Project Management Kr
7/82
Copyright 2013 Pearson Education, Inc. Publishing asPrentice Hall.
Purchase and deliver equipment
Construct hospital
#evelop information s!stem
-nstall medical equipment
'rain nurses and support sta
Wor) *rea)down%tructure
%elect administration sta
%ite selection and surve!
%elect medical equipment
Prepare nal construction plans
*ring utilities to site
-nterview applicantsfor
nursing and support
$rgani"ing and %ite PreparationPh!sical .acilities and -nfrastructure/evel 0
/evel 1
/evel 2
(elocation of %t ohn3s 4ospital
02 -0#
7/21/2019 Project Management Kr
8/82
#iagramming the5etwor) Program 6valuation and (eview
'echnique 7P6('8
Critical Path Method 7CPM8
Activit!+on+5ode approach
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 0$
7/21/2019 Project Management Kr
9/82
6sta&lishing Precedence (elationships
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 0%
Precedence(elationships#etermining thesequence for
underta)ingactivities
7/21/2019 Project Management Kr
10/82
69ample 20
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 10
7/21/2019 Project Management Kr
11/82
.inish%tart
A
B
C
D
E
F
G
H
I
J
K
A:
*:CA#*6
*.A;C4#-
ImmediatePredecessor
69ample 20
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 11
7/21/2019 Project Management Kr
12/82
The following information is known ao!t a "ro#ect
Draw the network diagram for this "ro#ect
Acti$it% Acti$it% Time &da%s'Immediate
Predecessor&s'
A ( )
B * A
C + A
D + B, C
E + D
F - EG . E
Application 20
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 12
7/21/2019 Project Management Kr
13/82
Finish
G.
F-
E+
D+
Acti$it% Acti$it% Time &da%s'Immediate
Predecessor&s'
A ( )
B * A
C + A
D + B, C
E + DF - E
G . E
B*
C+
/tart A(
Application 20
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 13
7/21/2019 Project Management Kr
14/82
#eveloping the %chedule
Path
'he sequence of activities&etween a project3s start andnish
Critical Path &
'he sequence of activities&etween a start and nish thatta)es the longest time to
completeCopyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - 1
7/21/2019 Project Management Kr
15/82
#eveloping the %chedule
6arliest start time 76%8 + the latestearliest nish time of an! immediatel!preceding activities
6arliest nish time 76.8 + the earlieststart time plus its estimated duration6. = 6% > t /atest nish time 7/.8 the earliest of thelatest start times of an! of theimmediatel! following activities
/atest start time 7/%8 + the latest nishtime minus its estimated duration /% =/. t
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 1!
Activit! %lac) + the ma9imum length oftime an activit! can &e dela!ed withoutdela!ing the entire project
/.+6. or /%+6%
7/21/2019 Project Management Kr
16/82
#eveloping the %chedule
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 1"
0atest finish
time
0atest start time
Acti$it%
D!ration
Earliest start timeEarliest finish time
1
*
2*
2+
A
2*
7/21/2019 Project Management Kr
17/82
.inish%tart
A
B
C
D
E
F
G
H
I
J
K
Path 'ime 7w)s8
A+-+< @@A+.+< 2A+C+;++< B*+#+4++< BD*+6++< E@
Paths are thesequence ofactivities &etween a
project3s start andnish3
69ample 22
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 1#
7/21/2019 Project Management Kr
18/82
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 1$
'
B
C
01
(
@F
)
E
H
E1
*
D
+
01
E
2E
I
0F
.inish%tart
A
02
01
1
6arliest start time
02
6arliest nish time
1 D
D@@
D 0D 0D FD
22 F02 22
FD B@
02 2
02 22 B@ BD
69ample
22
7/21/2019 Project Management Kr
19/82
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 1%
69ample
22'
B
C
01
(
@F
)
E
H
E1
*
D
+
01
E
2E
I
0F
.inish%tart
02
01
1 D
D @@
D 0D 0D FD
22 F02 22
FD B@
02 2
02 22 B@ BD1 02
'he Critical
Path ta)es BDwee)s
7/21/2019 Project Management Kr
20/82
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 20
'
"
C10
(
3!
)
H
0
*
%
+
10
E
2
I
1!
.inish%tart
12
10
1 D
D @@
D 0D0D FD
22 F02 22
FD B@
02 2
02 22 B@ BD1 02
EB@
F@ B@
FD B@
2E FD
0D FD
@FFD
0E 2E
D 0D
2 0E
1 D
B@ BD
69ample22
/atest start time
/atest nish time
7/21/2019 Project Management Kr
21/82
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 21
'
B
C
01
(
@F
)
E
H
E1
*
D
+
01
E
2E
I
0F
.inish%tart
02
01
1D
D @@
D 0D0D FD
22 F02 22
FD B@
02 2
02 22 B@ BD1 02
E B@
F@ B@
FD B@
2E FD
0D FD
@F FD
0E 2E
D 0D
2 0E
1 D
B@ BD
69ample
22
% =1
% =2
% =2B
% =1
% =@B
% =2
% =2
% =E0
% =1
% =1
% =1
7/21/2019 Project Management Kr
22/82
#eveloping a %chedule
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 22
;antt chart
7/21/2019 Project Management Kr
23/82
Application 22
Calculate the four times for each activit! in order todetermine the critical path and project duration forthe diagram in Application Pro&lem 0
Activit
!
#uratio
n
6arliest %tart
76%8
/atest%tart
7/%8
6arliest.inish
76.8
/atest.inish
7/.8
%lac)7/%+
6%8
$n theCritica
l Path?A 1 1 1+1=1 Ges
* 2
C E
# E
6 E
. @
; F
critical path is AC#6; with a project duration of 2E da!s
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 23
7/21/2019 Project Management Kr
24/82
Calculate the four times for each activit! in order todetermine the critical path and project duration
Activit
!
#uratio
n
6arliest %tart
76%8
/atest%tart
7/%8
6arliest.inish
76.8
/atest.inish
7/.8
%lac)7/%+
6%8
$n theCritica
l Path?A 1 1 1+1=1 Ges
* 2
C E
# E
6 E
. @
; F
( 4 4 22 45(6* 7o
( ( 22 22 (5(61 8es
24 *2 ** *+ *25246* 7o24 24 *+ *+ 2452461 8es
22 22 2. 2. 2252261 8es
2. 2. 24 24 2.52.61 8es
Application 22
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 2
7/21/2019 Project Management Kr
25/82
Application 22
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 2!
itical path is AC#6; with a project duration of 2E
/tart FinishA(
B*
C+
D+
E+
F-
G.
7/21/2019 Project Management Kr
26/82
Anal!"ing Cost+'ime'rade+$s
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 2"
Project Crashing%hortening 7ore9pediting8 some
activities within aproject to reduceoverall projectcompletion time
Project Costs #irect Costs -ndirect Costs Penalt! Costs
7/21/2019 Project Management Kr
27/82
Anal!"ing Cost+'ime'rade+$s
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 2#
Project Costs
5ormal time75'8 is thetime necessar! to
complete an activit!under normalconditions
5ormal cost75C8 is theactivit! cost associated
with the normal time Crash time7C'8 is the
shortest possi&le timeto complete an activit!
Crash cost7CC8 is theactivit! cost associated
Cost to crash perperiod =
CC 5C5' C'
7/21/2019 Project Management Kr
28/82
Copyright 2013 Pearson Education, Inc. Publishing asPrentice Hall.
Cost+'ime (elationships
/inear cost assumption
111 :
111 :
B111 :
F111 :
E111 :
@111 :
1 :
#irectcost7dollars8
H H H H H HF B D 01 00
'ime 7wee)s8
Crash cost 7CC8
5ormal cost 75C8
7Crash time8 75ormal time8
6stimated costsfor a 2+wee)reduction, from01 wee)s to wee)s
F211
.igure 2B 02 - 2$
7/21/2019 Project Management Kr
29/82
Anal!"ing Cost+'ime'rade+$s#etermining the Minimum Cost %cheduleI
0 #etermine the project3s critical path7s8
2 .ind the activit! or activities on the criticalpath7s8 with the lowest cost of crashing per wee)
@ (educe the time for this activit! untilJa -t cannot &e further reduced or
&Kntil another path &ecomes critical, or
c 'he increase in direct costs e9ceeds the savingsthat result from shortening the project 7whichlowers indirect costs8
E (epeat this procedure until the increase in directcosts is larger than the savings generated &!shortening the project
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 2%
7/21/2019 Project Management Kr
30/82
69ample 2@
DI9ECT C:/T A7D TI;E DATA F:9 THE /T3 J:H7im!mTime9ed!ction &week'
Cost ofCrashing "er?eek &='
A 2*=2*,111
22=2-,111
2 2,111
B 4.1,111
( @+,111 * (,111
C 21 +,111 . (,111 . @11
D 212@,111
*1,111 * *,111
E *+
2*1,111
2+
*11,111
21 ,111
F 2121,111
@ 2@,111 + 2,.11
G -..11,111
*..-1,111
21 -,111
H +12,*11,111
-.2,*@1,111
. 2*,111
I 2.+1,111
21 .*,.11 . *,.11Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 30
7/21/2019 Project Management Kr
31/82
69ample 2@
#etermine the minimum+cost schedule forthe %t ohn3s 4ospital project
Project completion time =BD wee)s
Project cost = L2,B2E,111
#irect = L0,DD2,111
-ndirect = BD7L,1118 = LFF2,111
Penalt! = 7BD BF87L21,1118 = L1,111
AIK -- weeks
AFK * weeks
ACGJK @( weeks
BDHJK @4 weeks
BEJK +- weeksCopyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 31
7/21/2019 Project Management Kr
32/82
69ample 2@
%'A;6 0%tep 0 'he critical path is *#4
7/21/2019 Project Management Kr
33/82
69ample 2@
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 33
.inish
7/21/2019 Project Management Kr
34/82
69ample 2@
%'A;6 2%tep 0'he critical path is still *#4
7/21/2019 Project Management Kr
35/82
69ample 2@
.inish
7/21/2019 Project Management Kr
36/82
69ample 2@
%'A;6 @%tep 0.'he critical paths are *#4
7/21/2019 Project Management Kr
37/82
69ample 2@
.inish
7/21/2019 Project Management Kr
38/82
69ample 2@
%'A;6 E%tep 0'he critical paths are still *#4
7/21/2019 Project Management Kr
39/82
69ample 2@
.inish
7/21/2019 Project Management Kr
40/82
69ample 2@/tage Crash
Acti$it%Time9ed!ction&weeks'
9es!ltingCriticalPath&s'
Pro#ectD!ration&weeks'
Pro#ectDirectCosts,0ast Trial&=111'
CrashCostAdded&=111'
TotalIndirectCosts&=111'
TotalPenalt%Costs&=111'
TotalPro#ectCosts&=111'
1 ) ) B5D5H5J5K
@4 2,44*31)
..*31131
*,@*+31
2 J - B5D5H5J5K @@ 2,44*31 -31 .*31 *131 *,.+-31
* D * B5D5H5J5K
A5C5G5J5K
@+ 2,44.31+31
.2*31131
*,.2231
- K 2 B5D5H5J5K
A5C5G5J5K
@- 2,44431+31
.1+31131
*,.1(31
+ B, C * B5D5H5J5K
A5C5G5J5K
@2 *,11-312.3*
+31131
*,.1@3*
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 0
7/21/2019 Project Management Kr
41/82
-ndirect project costs = L2F1 per da!Penalt! cost = L011 per da! past da! 0E
Project Activit! and Cost #ata
Activit!
5ormal'ime7da!s8
5ormalCost7L8
Crash'ime7da!s8
CrashCost7L8
-mmediatePredecessor7s8
A F0,111
E0,211
:
* F 11 @2,111
:
C 2 B11 0D11
A, *
# @0,F11
22,111
*
6 F D11 @ C, #
Application 2@
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall
02 - 1
7/21/2019 Project Management Kr
42/82
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - 2
13
19
F
2
15
21
13
13
G
3
16
16
5
5
D
3
8
8
8
8
E
5
13
13
5
6
C
2
7
8
0
0
B
5
5
5
0
1
A
5
5
6
Start
ES
LS
ID
DUR
EF
LF
16
16
H
5
21
21
Finish
Application 2@
7/21/2019 Project Management Kr
43/82
Project Activit! and Cost #ataActivit
! Crash CostO#a!Ma9imum Crash 'ime
7da!s8
A 211 0
* B11 2
C @11 0
# F11 0
6 0F1 2
. 011 0
; 1 14 211 25ormal 'otal Costs =
'otal -ndirect Costs =Penalt! Cost ='otal Project Costs =
L,F11L2F1 per da! 20 da!s = LF,2F1
L011 per da! da!s = L11L0@,EF1
Application 2@
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - 3
7/21/2019 Project Management Kr
44/82
/te" 2 The critical "ath is , and the "ro#ectd!ration is BDEGH*2 da%s3
/te" * Acti$it% E on the critical "ath has the lowest cost ofcrashing &=2.1 "er da%'3 7ote that acti$it% G cannot ecrashed3
/te" - 9ed!ce the time &crashing * da%s will red!ce the"ro#ect d!ration to 24 da%s' and re5calc!late costs
7ormal Costs 0ast Trial 6Crash Cost Added 6Total Indirect Costs 6
Penalt% Cost 6Total Pro#ect Cost 6
=(,.11=2.1 * da%s 6 =-11=*.1 "er da% 24 da%s 6 =+,(.1
=211 "er da% . da%s 6 =.11=2-,1.1
Application 2@
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 -
7/21/2019 Project Management Kr
45/82
/te" + 9e"eat !ntil direct costs greater than sa$ings
&ste" *' Acti$it% H on the critical "ath has the ne>t lowest costof crashing &=*11 "er da%'3
&ste" -' 9ed!ce the time &crashing * da%s will red!ce the"ro#ect d!ration to 2( da%s' and re5calc!late costs
Costs 0ast Trial 6Crash Cost Added 6Total Indirect Costs 6Penalt% Cost 6
Total Pro#ect Cost 6
=(,.11 =-11 &the added crash costs' 6 =(,11=*11 * da%s 6 =+11
=*.1 "er da% 2( da%s 6 =+,*.1=211 "er da% - da%s 6 =-11
=2*,(.1
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !
Application 2@
7/21/2019 Project Management Kr
46/82
&ste" +' 9e"eat
&ste" *' Acti$it% D on the critical "ath has the ne>t lowestcrashing cost &=.11 "er da%'3
&ste" -' 9ed!ce the time &crashing 2 da% will red!ce the "ro#ectd!ration to 2@ da%s' and re5calc!late costs
Costs 0ast Trial 6Crash Cost Added 6Total Indirect Costs 6Penalt% Cost 6
Total Pro#ect Cost 6
=(,11 =+11 &the added crash costs' 6 =,*11=.11 2 da% 6 =.11
=*.1 "er da% 2@ da%s 6 =+,111=211 "er da% * da%s 6 =*11
=2*,411 which is greater than the last trial3Hence we sto" the crashing "rocess3
Application 2@
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - "
7/21/2019 Project Management Kr
47/82
The recommended com"letion date is da% 2(3
'ri
al
CrashActivi
t!
(esulting
Critical
Paths
(eduction
7da!s8
Project
#uration
7da!s8
Costs
/ast
'rial
Crash
CostAdde
d
'otal-ndire
ct
Costs
'otalPenalt!
Cost
s
'otalProjec
t
Costs
1 :*+#+6+
;+4: 20
L,F11
:LF,2F
1L11
L0@,EF1
0 6*+#+6+
;+42 0D
L,F11
L@11LE,F
1LF11
L0@,1F1
2 4*+#+6+
;+4
2 0L,
11
LE11LE,2F
1
L@11L02,
F1F!rther red!ctions will cost more than the sa$ingsin indirect costs and "enalties3
The critical "ath is B D E G H and thed!ration is 2( da%s3
Application 2@
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - #
7/21/2019 Project Management Kr
48/82
Assessing (is)s
(is)+management Plans %trategic .it
%erviceOProduct Attri&utes
Project 'eam Capa&ilit!
$perations
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - $
7/21/2019 Project Management Kr
49/82
Assessing (is)s
%tatistical Anal!sis
$ptimistic time 7a8
Most li)el! time 7m8
Pessimistic time 7b8
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - %
7/21/2019 Project Management Kr
50/82
%tatistical Anal!sis
a m b;ean
Time
Beta distri!tion
a m b
;eanTime
- -
Area !nder c!r$eetween aand bis 443(+
7ormal distri!tion
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !0
7/21/2019 Project Management Kr
51/82
%tatistical Anal!sis
'he mean of the &eta distri&utioncan &e estimated &!
te6 a +m b
@
'he variance of the &etadistri&ution for each activit! is
*6 b a@
*
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !1
7/21/2019 Project Management Kr
52/82
69ample 2E
%uppose that the project team hasarrived at the following timeestimates for activit! * 7site selection
and surve!8 of the %t ohn3s 4ospitalprojectI
a= wee)s, m= wee)s, and b= 0Fwee)s
a Calculate the e9pected time andvariance for activit! *
& Calculate the e9pected time andvariance for the other activities inthe project
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !2
7/21/2019 Project Management Kr
53/82
69ample 2E
a 'he e9pected time for activit! * is
'he variance for activit! * is
te6 6 6 4 weeks( +&' 2.
@
.+
@
*6 6 6 23(2. (@
*
@
*
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !3
7/21/2019 Project Management Kr
54/82
69ample 2E
&'he following ta&le shows the e9pectedactivit! times and variances for thisproject Time Estimates &week' Acti$it% /tatistics
Acti$it%:"timistic
&a';ost 0ikel%
&m'Pessimistic
&b'E>"ected Time
&te'ariance
&2'
A 22 2* 2- 2* 1322B ( 2. 4 23(
C . 21 2. 21 *3(
D 4 2@ 21 23(
E 2+ *. -1 *+ (322
F @ 4 2 21 +311G *. -@ +2 -. (322
H -. +1 +. +1 *3(
I 21 2- * 2. 4311
J 2 * 2. + .3++
K . @ ( @ 1322Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !
7/21/2019 Project Management Kr
55/82
Application 2E
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !!
'he director ofcontinuingeducation at*lue&ird
Kniversit! justapproved theplanning for asales training
seminar 4eradministrativeassistantidentied thevarious activitiesthat must &e
7/21/2019 Project Management Kr
56/82
Application 2E
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !"
/tart
A
B
C
D
FinishE
F
G J
H
I
'he 5etwor)#iagram isI
7/21/2019 Project Management Kr
57/82
Acti$it%Immediate
Predecessor&s':"timistic
&a'
;ost0ikel%
&m'Pessimistic
&'E>"ectedTime &t'
ariance&'
A ) . (
B ) @ 2*
C ) - + .
D A 22 2( *.
E B 21 2*
F C, E - + .
G D + 4
H F . ( 4
he *lue&ird Kniversit! sales training seminar activitilate the means and variances for each activit!
Application 2E
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !#
7/21/2019 Project Management Kr
58/82
Acti$it%Immediate
Predecessor&s':"timistic
&a'
;ost0ikel%
&m'Pessimistic
&'E>"ectedTime &t'
ariance&'
A ) . (
B ) @ 2*
C ) - + .
D A 22 2( *.
E B 21 2*
F C, E - + .
G D + 4
H F . ( 4
he *lue&ird Kniversit! sales training seminar activitilate the means and variances for each activit!
@3- 13*.
3-- 2311
+311 1322
2(3--.3++
21311 13++
+311 1322
(3.1 13@4
(311 13++
223.1*3*.
+311 1311
Application 2E
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !$
7/21/2019 Project Management Kr
59/82
Anal!"ing Pro&a&ilities
TE6 6E>"ected acti$it% times
on the critical "ath
;ean of normaldistri!tion
*ecause the activit! times areindependent
p26 &ariances of acti$ities on the critical "ath'
z6T TE
p
Ksing the z+transformation
where
T6 d!e date for the "ro#ect
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - !%
*ecause the central limit theorem can &eapplied, the mean of the distri&ution is theearliest e9pected nish time for the project
7/21/2019 Project Management Kr
60/82
69ample 2F
Calculate the pro&a&ilit! that %tohn3s 4ospital will &ecomeoperational in 2 wee)s, using 7a8 thecritical path and 7&8 path AC;
7/21/2019 Project Management Kr
61/82
69ample 2F
Ksing the 5ormal #istri&ution appendi9,we nd a value of 11 'hus thepro&a&ilit! is a&out 10 the length ofpath *#4< will &e no greater than
2 wee)s 0ength ofcritical"ath
Proailit%of meeting
the sched!leis 131(
7ormal distri!tion;ean 6 @4 weeks 6 -3+. weeks
Proailit% ofe>ceeding (*weeks is
1324**
Pro#ect d!ration &weeks'
@4 (*
*ecause this isthe critical path,there is a 0Dpercentpro&a&ilit! thatthe project willta)e longer than2 wee)s
Copyright 2013 Pearson Education, Inc. publishing asPrentice Hall 02 - "1
7/21/2019 Project Management Kr
62/82
69ample 2F
& 'he sum of the e9pected activit!times on path AC;< is Bwee)s and that 2= 100 > 2 >
00 > FEE > 100 = 0FFF 'he z+value is
23*(-34+
.
2.3..
@((*==
=z
'he pro&a&ilit! is a&out 1D1that the length of path AC;